Here is Terrain's estimate for the city hall parking lot. Please let me know if you need anythingelse from us.
--
W e b s t e r R h o d e s
Estimator
p: 406.536.1706
e: estimator@terrainmt.com
w: terrainmt.com
2545 Spain Bridge Rd, Belgrade MT, 59714
Terrain, INC
2545 Spain Bridge road, Belgrade, MT, 59718
406-536-1706
estimator@terrainmt.com
EIN:85-3254226
Technical Submittal
1. Company Profile & Overview
Terrain Inc. is a locally owned and operated excavation and sitework contractor based in
Bozeman, Montana. With decades of combined industry experience, we specialize in
delivering high-quality earthwork and infrastructure solutions for municipal, commercial,
and industrial projects across Southwest Montana.
Our firm maintains a modern, well-maintained fleet of heavy equipment and a strong
safety culture committed to jobsite protection and technical precision. We are fully
registered and maintain active bonding capacity through First West to support
large-scale government contracts.
2. Technical Plan & Work Approach
Terrain Inc. utilizes a systematic approach to concrete repair and earthwork, ensuring
projects are delivered on time and in strict accordance with specifications. Our typical
work plan for infrastructure repair includes:
● Mobilization & Site Preparation: Rapid deployment of personnel and equipment
to the project site, including the establishment of erosion control and site
stabilization measures.
● Precision Excavation: Utilizing state of the art equipment and experienced staff
to deliver exceptional final product.
● Demolition & Removal: Efficient saw cutting and removal of existing concrete,
asphalt, or subgrade materials as required.
● Utility & Infrastructure Installation: Expert handling of underground utility
trenching and reinforced concrete pipe (RCP) culvert placement.
● Concrete & Site Finish: Professional fine grading, concrete placement, and
asphalt patching to restore site functionality and aesthetics.
3. Relevant Project Experience
Terrain Inc. has a proven track record of completing complex stream restoration, bank
stabilization, and municipal infrastructure projects.
4. Equipment Fleet & Resources
Our capabilities are backed by a comprehensive fleet of modern heavy equipment,
primarily comprised of CAT machinery:
●Excavators: CAT 320 DL , 320, 317, 315, 306
●Grading : CAT 140m and D3c
●Support: Loaders, Skid Steers, Mini Excavators, and Water Trucks.
5. Commitment to Safety, Quality, and Communication
Safety is a core value at Terrain Inc.. We maintain a comprehensive safety program that
includes:
●Regular operational reviews to monitor labor efficiency and productivity.
●Comprehensive insurance coverage meeting all federal and municipal
requirements.
●Onsite foreman and superintendent relay information, progress, and issues
reliably and promptly.
Description of Proposed Solution
Terrain Services will execute the Bozeman City Hall Parking Lot Replacement project through a
well-planned, phased construction approach that emphasizes safety, quality workmanship, and
minimizing disruption to City Hall operations. Our experienced crews and modern equipment
allow us to efficiently complete asphalt removal, grading, paving, and striping while maintaining
continuous access for City staff and the public.
Project Execution
The project will be completed in two phases, allowing one parking lot to remain operational
while work is performed in the other. Traffic control devices, barricades, directional signage, and
pedestrian protection measures will be installed prior to construction to safely separate the work
area from public access. Upon completion of the first phase, traffic will be shifted, and work will
proceed in the second parking lot.
Tear Out and Removal
Existing asphalt pavement will be saw-cut where required and removed using excavators and
loaders to minimize disturbance to adjacent improvements. All removed asphalt will be hauled
to an approved recycling facility for processing and reuse. Existing unsuitable materials
encountered during demolition will be removed and properly disposed of or replaced as
necessary to provide a stable foundation for the new pavement.
Grading and Base Preparation
Following demolition, the exposed aggregate base will be evaluated for condition and stability.
The parking lot subgrade will be fine graded to establish positive drainage and eliminate existing
low areas responsible for ponding. Areas requiring additional aggregate will receive imported
crushed road base meeting Montana Department of Transportation specifications or equivalent
local standards. The prepared base will be moisture conditioned as necessary and compacted
using vibratory rollers until proper density is achieved, providing a durable foundation for the
new pavement.
Asphalt Paving
Terrain Services will install a new 3-inch hot mix asphalt pavement section in accordance with
the project specifications. Asphalt will be placed using a self-propelled paving machine to
achieve a consistent mat thickness and smooth surface. Breakdown, intermediate, and finish
rolling will be performed immediately after placement using steel drum and pneumatic rollers to
achieve proper density and surface finish. All pavement joints will be carefully constructed and
sealed to maximize pavement longevity and reduce future maintenance requirements.
The existing unpaved parking area will also be prepared, graded, compacted, and paved to
match the finished elevations and adjacent asphalt surfaces.
Striping and Site Restoration
After the new asphalt has cooled and cured sufficiently, all parking stalls, ADA-compliant parking
spaces, access aisles, pedestrian walkways, directional arrows, and pavement markings will be
restriped to match the existing layout unless otherwise directed by the City. Pavement markings
will utilize high-quality traffic paint designed for durability and visibility.
The project will conclude with a comprehensive site cleanup, removal of all construction debris
and temporary traffic control devices, and a final walkthrough with City representatives to ensure
all work meets project requirements.
Materials
Terrain will furnish and install high-quality construction materials including:
●3-inch compacted hot mix asphalt pavement.
●Crushed aggregate road base where required for grading corrections and base repairs.
●Tack coat applied between existing and new asphalt surfaces and at pavement joints as
required.
●Durable traffic marking paint for parking stalls, ADA markings, pedestrian crossings, and
directional striping.
Quality Commitment
Terrain is committed to delivering a finished parking lot that provides improved drainage, a
smooth riding surface, long-term durability, and an attractive appearance. Our experienced
crews, attention to detail, and commitment to quality control ensure the project will be
completed safely, efficiently, and in accordance with the City's specifications while maintaining
access to City Hall throughout construction.
Proposed Schedule
Terrain proposes beginning construction within two weeks of receiving the Notice to
Proceed, subject to weather conditions and material availability. With our experienced paving
and excavation crews, dedicated equipment, and efficient project management, we anticipate
completing the project in 5 working days.
Proposed Construction Schedule
Day 1 – Mobilization & Phase 1 Demolition
●Mobilize personnel and equipment.
●Install traffic control, barricades, and directional signage.
●Close the East Parking Lot while maintaining full access to the West Parking Lot.
●Remove and recycle existing asphalt.
●Fine grade and compact the aggregate base.
Day 2 – Phase 1 Paving
●Install 3-inch hot mix asphalt in the East Parking Lot.
●Once paving is complete and the pavement has cooled sufficiently for traffic, reopen the
East Lot.
●Shift traffic to the newly paved East Lot.
Day 3 – Phase 2 Demolition & Base Preparation
●Close the West Parking Lot.
●Remove and recycle existing asphalt.
●Grade and compact the aggregate base.
●Prepare the site for paving.
Day 4 – Phase 2 Paving
●Install 3-inch hot mix asphalt in the West Parking Lot.
●Complete all pavement tie-ins and joints.
●Reopen the parking lot once the pavement has cooled sufficiently for traffic.
Day 5 – Striping & Final Completion
●Install all parking stall striping, ADA parking spaces, access aisles, crosswalks,
directional arrows, and pavement markings.
●Perform final cleanup and site restoration.
●Complete a final walkthrough with City representatives and address any punch list items.
Maintaining Accessible Parking
Terrain will complete the project using a two-phase construction approach, ensuring that one
parking lot remains fully operational during normal City Hall business hours at all times.
Employees and visitors will always have access to parking while work is underway in the
opposite lot.
Temporary traffic control devices, directional signage, and pedestrian routing will be installed to
safely guide vehicles and pedestrians through the site.
Our superintendent will maintain daily communication with the City's representative regarding
construction progress, traffic shifts, and any schedule adjustments resulting from weather or
unforeseen site conditions. This phased approach minimizes disruption to City Hall operations
while allowing Terrain Services to complete the project safely, efficiently, and within the
proposed five-day schedule.
List of some Current & Past Jobs:
1. Lindley Park - Addi Jadin
2. City of Bozeman Vault Toilet, Concrete & Landscape - Katherine Canter
3. Sunset Hills Cemetery - Shane Surber
4. Bozeman Public Schools (too many to list) - Matthew Stark
5. Bozeman Library Landscape Rehab - Max Zeigler
6. Bozeman Sunset Hills CMU Wall demo - Max Zeigler
7. Westlake Park - Addi Jadin
8. Farmers Market Trail - Addi Jadin
References:
1. Mathew Stark - Bozeman Public Schools
406 - 595 -1270
matthew.stark@bsd7.org
2. Shane Surbur - City of Bozeman
406 - 582 - 2904
3. Matt Parsons - Gallatin Valley Land Trust
406 - 920 - 4503
matt@gvlt.org
4. Max Zeigler - City of Bozeman
maxziegler@bozemanmt.gov
5. Jason Leep - Meadowlark Homes
406 - 539 - 0397
jasonleepnai@gmail.com
6. Matt Freese - CCS Builders
406 - 580 - 0509
matt@ccsbuilders.com
Terrain, Inc.
2545 Spain Bridge Rd
Belgrade, MT 59714
4065361707
billing@terrainmt.com
www.terrainmt.com
ADDRESS
City of Bozeman, Montana
PO Box 1230
Bozeman, MT 59771-1230
ESTIMATE #PRJ000495
DATE 07/08/2026
DATE SERVICE QTY RATE AMOUNT
EAST LOT
07/08/2026 Excavation Services
Demolition, hauling and disposal of existing
asphalt
11,000 0.90 9,900.00
Excavation Services
Grading and compaction in preparation for paving
11,000 0.31 3,410.00
Excavation Services
3" Asphalt Paving
11,000 2.95 32,450.00
Excavation Services
Removal and Reinstallation of Parking Blocks
30 85.00 2,550.00
Excavation Services
Striping - to match existing
1 1,190.00 1,190.00
WEST LOT
Excavation Services
Demolition, hauling and disposal of existing
asphalt
9,150 0.90 8,235.00
Excavation Services
Grading and compaction in preparation for paving
10,350 0.31 3,208.50
Excavation Services
3" Asphalt Paving
10,350 2.95 30,532.50
Excavation Services
Removal and Reinstallation of Parking Blocks
20 85.00 1,700.00
Excavation Services
Striping - to match existing
1 780.00 780.00
Please make checks out to Terrain, Inc
Estimator contact info:
Chris Brown
406-451-2853
TOTAL $93,956.00
Appendix A
NONDISCRIMINATION AND EQUAL PAY AFFIRMATION
____________________________________(name of entity submitting) hereby affirms it will
not discriminate on the basis of race, color, religion, creed, sex, age, marital status, national
origin, or because of actual or perceived sexual orientation, gender identity or disability and
acknowledges and understands the eventual contract will contain a provision prohibiting
discrimination as described above and this prohibition on discrimination shall apply to the
hiring and treatments or proposer’s employees and to all subcontracts.
____________________________________(name of entity submitting) hereby affirms it will
abide by the Equal Pay Act of 1963 and Section 39-3-104, MCA (the Montana Equal Pay Act).
______________________________________
[Name and title of person authorized to sign on behalf of Respondent]
Terrain Inc
Terrain Inc
Estimator / Sales