HomeMy WebLinkAbout26 - Submissions - RFP - City Hall Parking LotFrom:Zach Liley
To:Bozeman Procurement
Cc:Vale May; Cade Harris
Subject:[EXTERNAL]Bozeman City Hall Parking Lot - Proposal
Date:Thursday, July 9, 2026 1:33:40 PM
Attachments:image001.pngBid Package_Bozeman City Hall Parking Lot_CK May.pdf
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you
recognize the sender and know the content is safe.
BID ENCLOSED. PLEASE DO NOT OPEN UNTIL 2:00 PM ON July 9th, 2026.
Please see CK May Excavating’s proposal for the Bozeman City Hall Parking Lot Replacement
project enclosed. Please confirm receipt of receival. Thank you for your time!
Thanks,
Zach Liley
CK May Excavating
O: 406.388.0015
C: 406.595.9914
PROPOSAL FOR
City of Bozeman
Bozeman City Hall
Parking Lot Replacement
July 09, 2026
2.) SCOPE OF WORK
MARY & SCOPE2. SCOPE OF WORK
1.) FIRM PROFILE
1. FIRM PROFILE
July 8th, 2026
RE: Bozeman City Hall Parking Lot Replacement
Firm Profile
CK May Excavating, Inc. is pleased to submit a proposal to the City of Bozeman for the Bozeman City
Hall Parking Lot Replacement project.
CK May is a Belgrade based heavy civil and asphalt paving contractor that specializes in earthwork,
utilities, road and highway construction, and asphalt paving for both public and private clients. Our
team has successfully completed projects for municipalities, state & federal agencies, airports, and
private developers throughout Montana.
We maintain a modern fleet of equipment and utilize the latest technology including GPS machine
control and total station equipment to improve efficiency, accuracy, and quality of construction. We are
experienced in coordinating with owners, engineers, and subcontractors to minimize disruptions and
meet project deadlines.
Safety and quality are fundamental to every project that we take on. We implement strict safety
protocols and quality control procedures to ensure that potential issues are resolved before they have
impacts to cost or schedule.
CK May is well equipped with personnel, equipment, and management experience to successfully
complete the project in a timely fashion, while delivering a high-quality finished product.
2.) SCOPE OF WORK
MARY & SCOPE2. SCOPE OF WORK
2.) PROPOSED SOLUTION
2. PROPOSED SOLUTION
July 8th, 2026
RE: Bozeman City Hall Parking Lot Replacement
Proposed Solution
This project can be completed swiftly with the right equipment and an appropriately sized crew. If
awarded this project, CK May plans to supply the necessary equipment and manpower to finish this job
in less than two weeks. The work will be completed in phases, beginning with the east lot and then
moving to the west lot once the east lot is reopened to traffic. The asphalt removal process will utilize
an excavator, a wheel loader, and a mini excavator to remove and load the existing asphalt.
Immediately following asphalt removal, the existing base course will be graded and compacted to
prepare each lot for new asphalt. The new base will then be paved with a 3" section of Grade B
asphalt. At this point, the striping contractor can stripe the lot and it will be reopened to traffic once the
paint is cured. Immediately following the reopening of the east lot, the west lot will be closed and the
process repeated.
2.) SCOPE OF WORK
MARY & SCOPE2. SCOPE OF WORK
3.) PROPOSED SCHEDULE
3. PROPOSED SCHEDULE
July 8th, 2026
RE: Bozeman City Hall Parking Lot Replacement
Proposed Schedule
The project is anticipated to begin on August 24, 2026, and be completed by September 3, 2026. Work
will be phased to maintain accessible parking during City Hall's operating hours. The east lot will be
completed first while the west lot remains open for parking. Once the east lot is reopened, the west lot
will be closed and completed while the east lot remains available for parking.
Activity ID Activity Name Duration Start Finish
Bozeman City Hall Parking Lot ReplacementBozeman City Hall Parking Lot Replacement 9.0 Aug.24.26 Sep.03.26
A1000 Mobilization 1.0 Aug.24.26 Aug.24.26
A1010 Close East Lot 0.0 Aug.24.26
A1020 East Lot - Remove Existing Asphalt & Wheel Stops 1.0 Aug.24.26 Aug.25.26
A1030 East Lot - Grade & Compact Existing Base Course 1.0 Aug.25.26 Aug.26.26
A1040 East Lot - Grade B Asphat (3" Section)1.0 Aug.26.26 Aug.27.26
A1050 East Lot - Parking Stall Striping 1.0 Aug.27.26 Aug.28.26
A1060 Open East Lot 0.0 Aug.28.26
A1070 Close West Lot 0.0 Aug.28.26
A1080 West Lot - Remove Existing Asphalt & Wheel Stops 1.0 Aug.28.26 Aug.31.26
A1090 West Lot - Grade & Compact Existing Base Course 1.0 Aug.31.26 Sep.01.26
A1100 West Lot - Grade B Asphalt (3" Section)1.0 Sep.01.26 Sep.02.26
A1110 West Lot - Parking Stall Striping 1.0 Sep.02.26 Sep.03.26
A1120 Open West Lot 0.0 Sep.03.26
Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr
Aug 23 Aug 30 Sep 06
2026
Sep.03.26, Bozeman City Hall Parking Lot Replacement
Mobilization
Close East Lot
East Lot - Remove Existing Asphalt & Wheel Stops
East Lot - Grade & Compact Existing Base Course
East Lot - Grade B Asphat (3" Section)
East Lot - Parking Stall Striping
Open East Lot
Close West Lot
West Lot - Remove Existing Asphalt & Wheel Stops
West Lot - Grade & Compact Existing Base Course
West Lot - Grade B Asphalt (3" Section)
West Lot - Parking Stall Striping
Open West Lot
26082 - Bozeman City Hall Parking Lot Replacement *Order of operations & durations are subject to change*Printed: Jul.09.26
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Date Revision Checked Approved
Jul.09.26 Preliminary Schedule ZL
Page 1 of 1
2.) SCOPE OF WORK
MARY & SCOPE2. SCOPE OF WORK
4.) RECENT AND CURRENT WORK FOR
THE CITY OF BOZEMAN
4. RECENT AND CURRENT WORK FOR THE CITY OF BOZEMAN
July 8th, 2026
RE: Bozeman City Hall Parking Lot Replacement
Recent and Current Work for the City of Bozeman
CK May has a strong relationship with the City of Bozeman and has recently completed the following
projects:
• 2026 Black Lot Mill & Overlay
• Sourdough Creek Intake Improvements
• 2024 Street and Utility Improvements
• Riverside Lift Station and Force Main
• Manley Ditch Rehabilitation
• 5th Avenue Trail
2.) SCOPE OF WORK
MARY & SCOPE2. SCOPE OF WORK
5.) REFERENCES
5. REFERENCES
July 8th, 2026
RE: Bozeman City Hall Parking Lot Replacement
References
The following references are provided for recently completed project work.
Taylor Lonsdale
Transportation Engineer
City of Bozeman
tlonsdale@BOZEMAN.NET
Josh Ritchie
Maintenance Chief
Montana Dept. of Transportation
jritchie@mt.gov
Craig Walker
Project Manager Butte District
Montana Dept. of Transportation
cwalker@mt.gov
2.) SCOPE OF WORK
MARY & SCOPE2. SCOPE OF WORK
6.) PRICE PROPOSAL
6. PRICE PROPOSAL
Page 1 of 1
PROPOSAL
CK May Excavating, Inc.
P.O. Box 1426
Belgrade, MT 59714
zach@ckmayexcavating.com
Pricing Date 07/09/2026
Pricing is good for 30 days
QUOTE
TO
Max Ziegler
City of Bozeman
Facilities Assistant Superintendent
(406) 582-2439
JOB LOCATION START DATE
Bozeman City Hall Parking Lot Replacement Bozeman, MT August 2026
ITEM DESCRIPTION QUAN UNIT
101 Mobilization 1.00 LS
102 Remove & Reset Parking Bumpers 1.00 LS
103 Remove Existing Asphalt 20,150.00 SF
104 Grade & Compact Existing Base 21,350.00 SF
105 Grade B Asphalt (3" Thick) 21,350.00 SF
106 Striping 1.00 LS
Grand Total: $97,801.00
Clarifications:
Parking bumpers are to be reused
One parking lot will be closed at a time, with no access through said parking lot while work is conducted
New striping to match current layout
Exclusions:
New curb & gutter
New concrete flatwork
Landscaping
Soft/unstable subgrade replacement
Signs
Curb paint
Bollards