HomeMy WebLinkAbout001.01 - CONR Comment ResponsesPlan Review - Review Comments Report
Project Name: 25733 Ferguson Farm Blk 2 CONR
Workflow Started: 12/5/2025 8:43:04 AM
Report Generated: 01/12/2026 08:26 AM
REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS
1 1 Solid Waste
Russell Ward
12/16/25 12:04 PM
Changemark
Solid Waste
1. need detailed plan for refuse enclosure
2. refuse enclosure will need to be covered.
002 - C1.0 - CIVIL SITE PLAN.pdf Info Only
2 1 Addressing
Jenny Connelley
12/29/25 3:58 PM
Comment
Lot 3 Block 2 of the Ferguson Farm Subdivision has an address of 785
Boardwalk Ave. This address can be used for the main address of this
building Any additional units (if any) would be addressed once this project is
approved and the building permit needs to be obtained.
Info Only
3 1 Forestry Division
Alex Nordquest
12/31/25 2:32 PM
Changemark
Tree Pit Details
The Forestry Division recommends following Engineering's Downtown
Standards for tree pits for best results. Specs include, but not limited to:
* particular model numbers for ADA approved grates
* 48" x 48" grates & sub-frame, with 5' vertical guard
* dedicated irrigation to each tree pit
* avoiding electrical outlets or other accessories on vertical guards, which
may be removed after a few years of tree growth
003 - L 100 - LANDSCAPE CONCEPT
PLAN.pdf
Info Only
4 1 Transportation
Candace Mastel
1/6/26 2:58 PM
Comment
BMC 38.530.070 (code adopted for enforcement February 1, 2026): Adequate
bicycle parking is provided however applicant should redistribute part of the
short-term parking from the north side of the building to also service the
south entry. The long-term bicycle parking is located hidden behind the
trash dumpster location on the north side of the building, which is not ideal.
All bicycle parking should be placed in convenient locations that are easily
accessible from the shared use path along Baxter and from the parking lot.
Details/cut sheets of the short- and long-term bicycle parking should be
provided in future applications. Provide detail of bicycle racks proposed that
meet requirements of the new code.
Info Only
5 1 Parks Department
Ross Knapper
1/7/26 8:57 AM
Comment
Commercial project with no residential component. No parkland dedication
required per Sec. 38.420.010.
Info Only
6 1 Fire Department
Shane Brandhorst
1/7/26 10:15 AM
Comment
There is a proposed fire line going to the building, provide proposed
location of sprinkler riser room
Info Only
7 1 Engineering
Alicia Paz-Solis
1/7/26 11:31 AM
Changemark
ENG Label Boardwalk Ave
BMC 38.220.080.A.2.g (2) - The applicant must label Boardwalk Avenue on
the Civil Site Plat (C1.0).
002 - C1.0 - CIVIL SITE PLAN.pdf Info Only
REVIEW COMMENTS
Created in ProjectDox version 9.4.9.931
Understood, Please see the Architectural and Civil Site plans
for the location of the dumpster enclosure. Additionally,
please see Sheet SP101 for more information on the details
of the enclosure
Understood, Thank you!
Thank you, Please see the landscape plans for more details
on the tree pits.
Thank you, The applicant has relocated a few short term bike
racks to the south side of the building as requested. The long
term bike parking can not be relocated. It is located in the
most efficient spot for the project. The location is within the
required distance and is meeting the requirements of being
covered and lockable.
Thank you.
This is shown on the architectural and civil site plans.
Understood, thank you.
Plan Review - Review Comments Report
Project Name: 25733 Ferguson Farm Blk 2 CONR
Workflow Started: 12/5/2025 8:43:04 AM
Report Generated: 01/12/2026 08:26 AM
REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS
8 1 Engineering
Alicia Paz-Solis
1/7/26 11:38 AM
Changemark
ENG Sewer Service
DCS 5.2.9 - The applicant must revise the sanitary sewer plan to show the
sanitary sewer service installed perpendicular to the main.
002 - C1.0 - CIVIL SITE PLAN.pdf Info Only
9 1 Engineering
Alicia Paz-Solis
1/7/26 11:50 AM
Comment
DCS 2.1.1 - The applicant must submit plans/specifications for the proposed
fire service line through the City's ProjectDox electronic plan review system
Submittals must be stamped and signed by a Professional Engineer licensed
in the State of Montana with responsible charge of the project.
https://www.bozeman.net/services/development-center
Info Only
10 1 Engineering
Alicia Paz-Solis
1/7/26 1:57 PM
Comment
1.Water Rights and Water Adequacy. Prior to the Ferguson Farm Blk 2
site plan application being deemed adequate for review, the
applicant must describe how it intends to satisfy water adequacy
requirements in BMC 38.410.130 and meet requirements of BMC
38.220.060.A.9.a. The information provided should be compiled into
a preliminary water adequacy compliance report containing the
following:
i.A description of water rights associated with the property or
otherwise available to the applicant, and a description of
whether each respective water right is appurtenant to the
property or has been severed from the land title.
i.A description of the proposed lots for which a payment of
cash in lieu of water rights will be provided and the proposed
lots for which deferred compliance of BMC 38.410.130 will be
sought.
i.A description of the proposed lots for which non-potable
irrigation systems will be provided; the anticipated irrigation
water demand of each lot; and the water source proposed to
supply the non-potable irrigation systems.
a.If exempt wells are proposed for irrigation supply,
Info Only
Created in ProjectDox version 9.4.9.931
Understood, This design has been updated to address this
comment.
Understood, thank you.
The applicant does not have any water rights and was not
allocated any credits on the final plat. the application intends
to pay CILWR for all water usage include the landscaping
exterior to the building. A water demand calculation is
provided, please advise what this CILWR fee will be.
Plan Review - Review Comments Report
Project Name: 25733 Ferguson Farm Blk 2 CONR
Workflow Started: 12/5/2025 8:43:04 AM
Report Generated: 01/12/2026 08:26 AM
then the applicant must obtain DNRC approval of
“Form No. 602I – Notice of Intent to Appropriate
Groundwater” prior to adequacy.
a.If exempt wells authorized by DNRC under an
approved notice of intent to appropriate groundwater
are inadequate to meet the anticipated irrigation
demands and existing irrigation water rights are
associated with the property or otherwise available to
the applicant , then the applicant must:
1.Evaluate the legal elements of the water rights
to determine if a DNRC change authorization
is required to use the rights as proposed.
1.Confirm that the flowrate and volume of the
water rights are adequate to meet the
anticipated irrigation water demands.
1.Confirm that existing water conveyance
facilities can deliver the water rights from their
point of diversion to the proposed place of
use. If existing conveyance facilities are
inadequate, then provide a description of
improvements needed to deliver the water
rights to the proposed place of use.
d. Provide a copy of the following documents as attachments to
Created in ProjectDox version 9.4.9.931
Plan Review - Review Comments Report
Project Name: 25733 Ferguson Farm Blk 2 CONR
Workflow Started: 12/5/2025 8:43:04 AM
Report Generated: 01/12/2026 08:26 AM
the report:
1.
i.
a.DNRC-approved notice of intent to appropriate
groundwater.
a.Abstracts of water rights associated with the property
or otherwise available to the applicant.
a.Copies of any share certificates from a canal company,
ditch company, or water users association that are
held by the applicant.
a.The annexation agreement for the property.
a.Any existing water adequacy agreements pertinent to
the property or development.
12 1 Engineering
Alicia Paz-Solis
1/7/26 2:02 PM
Comment
BMC 38.710.050 - The applicant must provide initial peak-hour trip
estimates so transportation can confirm whether a Transportation Impact
Study (TIS) is required under the new UDC; a TIS is not anticipated.
Info Only
Created in ProjectDox version 9.4.9.931
Understood, this is provided as Appendix H.
Plan Review - Review Comments Report
Project Name: 25733 Ferguson Farm Blk 2 CONR
Workflow Started: 12/5/2025 8:43:04 AM
Report Generated: 01/12/2026 08:26 AM
REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS
13 1 Engineering
Alicia Paz-Solis
1/7/26 2:04 PM
Comment
BMC 38.410.070 and DCS 4.2 and DCS 5.2 - Water & Sewer Demand:
Prior to a determination of adequacy, the applicant must provide an estimate
of the peak-hour sanitary sewer demand as well as the average and max day
demands of domestic water usage for the proposed site development. A
professional engineer must certify the estimates.
Info Only
14 1 Engineering
Alicia Paz-Solis
1/7/26 2:34 PM
Comment
DCS 6 - Storm Drainage Design - Because the proposed building footprint
exceeds 5,000 sf, stormwater compliance is triggered. The applicant must
confirm whether the proposed building footprint was included in the original
subdivision stormwater design for the existing pond. It is was not included,
the applicant must provide additional stormwater capacity to meet the
current City of Bozeman Design and Construction Standards for the
additional impervious area.
Info Only
15 1 Engineering
Alicia Paz-Solis
1/7/26 3:22 PM
Comment
BMC 38.360.280 - The applicant must submit a completed Ditch Noticing
Checklist with the site plan application:
https://www.bozeman.net/home/showpublisheddocument/
15320/638985313385730000
Info Only
16 1 Engineering
Alicia Paz-Solis
1/7/26 3:23 PM
Comment
BMC 38.220.130.A.1 – If wetlands or watercourses are not present on or
adjacent to the subject property, a letter signed by a qualified wetlands
professional must be submitted to the city certifying there are no wetlands
or watercourses within the subject property or adjacent to the property and
describing the methods used to determine that the wetlands or watercourses
do no exist on or adjacent to the property.
https://librarystage.municode.com/mt/bozeman/ordinances/code_of_ordina
nces?nodeId=1384190
Info Only
17 1 Water Conservation
Division
Eric Neustrup
1/9/26 10:35 AM
Comment
On June 15th, 2024, Ordinance 2155 and Resolution 5586 were adopted by
the Bozeman City Commission as well as the associated City of Bozeman
Landscape and Irrigation Performance and Design Standards Manual.
Projects not deemed "adequate” by June 15, 2024 are now subject to these
new code requirements. To familiarize yourself with these requirements
please visit https://www.bozeman.net/departments/utilities/water-
conservation/new-development-standards-3620.
Info Only
Created in ProjectDox version 9.4.9.931
Please see Appendix D for the water and sewer demand
reports.
Please see Appendix D for the water and Storm Drainage
reports.
This subject property is not adjacent to any ditches. This item
appears to not be applicable to this property.
There are no wetlands located on site. Please see Appendix
H for a letter from our civil engineer certifying this fact.
Thank you. The landscape design has taken this into account
in their design.
Plan Review - Review Comments Report
Project Name: 25733 Ferguson Farm Blk 2 CONR
Workflow Started: 12/5/2025 8:43:04 AM
Report Generated: 01/12/2026 08:26 AM
REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS
18 1 Planning
Bailey Minnich
1/9/26 11:48 AM
Comment
Comments on Applicant’s Questions:
1. Section 38.260.040.C under Coverage identifies the requirements for
Commercial Open Space. The language under the header identifies it as ‘an
area that is part of a commercial project designated to be used for
pedestrian-oriented open space.’ This is further supported by C.1 Purpose,
which states under C.1.a, the area is ‘to provide pedestrian-oriented spaces
in commercial areas that enhance the employees’ and public’s opportunity
for active and passive activities...’. The proposed 2nd-floor patio space does
not appear to be for pedestrian-oriented activities and is only accessed
through the proposed office space, similar to an employee-only break room;
therefore, it does not appear the proposed patio space on the 2nd-floor
would count towards the required commercial open space. If there were an
opportunity to design the space to be located adjacent to a public lobby or
public access, allowing for both private and public usage, that may permit a
change in this determination.
2. Staff cannot find anything in the new UDC addressing the location of ADA
spaces on a site, other than within the Affordable Housing section, which
does not apply to this project. Generally, ADA compliance is reviewed by the
Building Department and they may be able to provide more information.
Info Only
19 1 Planning
Bailey Minnich
1/9/26 11:48 AM
Comment
Please be aware that the City of Bozeman has adopted new zoning
regulations, commonly referred to as the Unified Development Code or UDC.
The UDC was formally adopted by the City Commission on December 16,
2025, with an effective date beginning February 1, 2026. Planning staff
comments outlined in this Concept Review application are based on the
adopted draft UDC (December 16, 2025 version). If a formal site plan
application does not achieve adequacy under the current regulations by this
date, it would need to comply with the new standards. The Draft UDC can be
found on the city's website: https://engage.bozeman.net/udc
Info Only
20 1 Planning
Bailey Minnich
1/9/26 11:48 AM
Comment
Please make sure to show all existing easements on the site plan or civil site
plan. The plat shows a 30-ft wide utility easement and the shared parking,
drainage and access easement which is not shown on the proposed site plan.
It’s important to note those on the site plan to confirm that no portion of the
building is encroaching.
Info Only
21 1 Planning
Bailey Minnich
1/9/26 11:49 AM
Comment
The site plan shows an existing storm pond along the front property line
adjacent to Huffine Trail, however, no easement is shown on the submitted
plat. Please provide any existing easements for the storm pond, which might
have been recorded as a separate document.
Info Only
Created in ProjectDox version 9.4.9.931
1. Thank you, The applicant will proceed accordingly. All of
the open space is provided on the exterior of the building.
2. Understood, The applicant is adjusting and will utilize the
existing ada spaces located in the parking lot just off site.
Understood. The application would like this project to be
reviewed under the new code. Thank you
Understood. All easements are shown on the civil site plan
drawings.
Understood. All easements are shown on the civil site plan
drawings.
Plan Review - Review Comments Report
Project Name: 25733 Ferguson Farm Blk 2 CONR
Workflow Started: 12/5/2025 8:43:04 AM
Report Generated: 01/12/2026 08:26 AM
REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS
22 1 Planning
Bailey Minnich
1/9/26 11:49 AM
Comment
Sec. 38.220.040 B-2M Community Mixed Use. The subject property is
proposed to be zoned B-2M under the new Unified Development Code. The
applicant needs to review all standards identified under this section that
pertain to new developments within the B-2M zoning district, including both
lot standards and building standards. Staff has provided specific comments
for code sections related to critical path items.
Info Only
23 1 Planning
Bailey Minnich
1/9/26 11:49 AM
Comment
Sec. 38.220.040.A.4 Streetscape. The applicant needs to demonstrate
compliance with this section and Sec. 38.260.050 along the Huffine Lane
street frontage, including required street trees, with the formal application
submittal. Due to multiple existing easements along the front property line, it
does not appear feasible to construct the required sidewalk along the entire
front width. Additionally, after discussion with the Forestry Department, it is
not possible to install street trees within the easements. Therefore, to
demonstrate compliance, the applicant will need to request a relief to these
standards as outlined under Section 38.260.050.A.5 and explain how the
alternative design provides for safe and comfortable pedestrian traffic.
Info Only
24 1 Planning
Bailey Minnich
1/9/26 11:49 AM
Comment
Sec. 38.220.040.A.5 Setbacks. The front setbacks within the B-2M are a
minimum of 1’ and maximum of 20’. This property includes multiple
easements along the front property line adjacent to Huffine Lane, including a
public access and trail easement, which limits the placement of structures.
The definition of Setback Line per Section 38.800.200 states “that line that is
the required minimum distance from the street right-of-way or public access
easement line...that establishes the area within which structures must be
placed.” In this case, the City will measure the required minimum and
maximum setback from the edge of the public access and trail easement to
determine the buildable area.
Info Only
25 1 Planning
Bailey Minnich
1/9/26 11:49 AM
Comment
Sec. 38.220.040.A.7 Frontage. The applicant needs to demonstrate
compliance with this section and Sec. 38.260.080 regarding the percentage
of the proposed building within the required build-to zone along Huffine
Lane with the formal application submittal. While it is clear that the proposed
building is within this required zone, the application needs to provide the
proposed percentages to demonstrate compliance with the B-2M zoning
district.
Info Only
26 1 Planning
Bailey Minnich
1/9/26 11:50 AM
Comment
Sec. 38.510.060. Location and design of service areas and mechanical
equipment. The applicant must provide adequate service area and
mechanical equipment screening that meets the requirements of this section
with the formal submittal. This includes any ground, roof top, or wall
mounted mechanical equipment, utility meters, and solid waste enclosures.
Info Only
Created in ProjectDox version 9.4.9.931
Understood. Thank you.
Understood, this documentation is provided in the project
narrative under the setback section.
Understood, this documentation is provided in the project
narrative under the setback section. The building is located
10' behind the trail easement.
Understood, This documentation is provided on plan sheet
SP100
Understood, This documentation is provided on plan sheet
SP101
Plan Review - Review Comments Report
Project Name: 25733 Ferguson Farm Blk 2 CONR
Workflow Started: 12/5/2025 8:43:04 AM
Report Generated: 01/12/2026 08:26 AM
REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION STATUS
27 1 Planning
Bailey Minnich
1/9/26 11:50 AM
Comment
Sec. 38.520.040 Building massing and articulation. The applicant will need to
demonstrate compliance with 38.520.040.B Non-residential façade
articulation standards for the building. The non-residential standards require
articulation features every 60-feet maximum. Please make sure to address
which articulation features are being utilized with the formal application
submittal.
Info Only
28 1 Planning
Bailey Minnich
1/9/26 11:50 AM
Comment
Sec. 38.530.040 Number of vehicle parking spaces required. The formal
application submittal must demonstrate compliance with the required
number of parking spaces determined under this section, at the time of
project adequacy. Sec. 38.530.040.B is effective through September 30, 2026,
and Sec. 38.530.040.C is effective starting October 1, 2026. Please make sure
to use the ratio for parking spaces provided in the table. While the included
1 per 500 square feet is correct, the Personal & General Service is listed as 2
per 1000 square feet, and staff wouldn’t want the public to get confused as
to where the provided ratio is obtained.
Info Only
29 1 Planning
Bailey Minnich
1/9/26 11:50 AM
Comment
Sec. 38.530.070.A Number of bicycle parking spaces required. All site
development, not including developments qualifying for sketch plan review
per 38.740, must provide bicycle parking facilities to accommodate bicycle-
riding residents and/or employees and customers of the proposed
development. The formal application submittal must demonstrate
compliance with the required number of bicycle parking spaces, location,
and bike rack system outlined under this code section.
Info Only
30 1 Planning
Bailey Minnich
1/9/26 11:50 AM
Comment
Sec. 38.540.050. Mandatory landscaping provisions. The formal submittal
must include a compliant landscaping plan that meets the requirements of
this section, including any required screening, parking lot landscaping, street
frontage landscaping, and irrigation. Landscape plans must include the
information required by section 38.710.090.
Info Only
31 1 Planning
Bailey Minnich
1/9/26 11:51 AM
Comment
Sec. 38.560.020. Site Lighting. With the exception of street lighting, lighting is
not required. If installed, all lighting must comply with the requirements of
this division. The formal submittal must include lighting sheets that provide
adequate fixture details and photometric data necessary to review for site
lighting, entrance lighting, full cut-off, and building-mounted lighting.
Info Only
Created in ProjectDox version 9.4.9.931
Understood, Please see the setback and frontage sections of
the narrative for a description and the elevation plan sheets
for documentation of compliance.
Understood, Thank you
Understood, Please see the narrative section "bike parking"
and the cover sheet for the required calculations.
Additionally, please see the architectural site plan for more
detail on location and size. Finally, please see the landscape
detail sheet for the specification of the requested product.
Understood, Thank you. The parking lot landscaping was
installed with the subdivision. The applicant has provided
documentation for the mandatory landscaping provisions for
all new landscaping.
Please see the lighting plan sheets for more information on
the exterior lighting, cutsheets and photometric plans.