HomeMy WebLinkAbout007-Stormwater Permit v5 ADABOZEMAN?T
Stormwater Division
Construction Stormwater Permit
Single-Family Residential Projects
April 3, 2025
Stormwater Division
P.O. Box 1230
Bozeman, Montana 59771
(406) 582-2916
The City requires all single-family residential contractors/owners to submit this application and receive an approval letter
before initiating construction activities pursuant to Chapter 40 Article 4 of the Bozeman Municipal Code (BMC). The City's
Stormwater Division reviews, inspects, and enforces all provided information. This Permit is active once approved by the
City and considered terminated upon the contractor/owners receipt of a Certificate of Occupancy.
Section 1: Applicant Information (All Fields Must Be Completed)
OWNER: Charley Switzer Company:
Phone: (406) 580-2013 Email: pcMb3@Msn.com
Address: 5400 Penwell Bridge RoCity: Belgrade State: MT Zip code: 59714
CONTRACTOR: Kyle Gunnarson Company:Collective Works
Phone: (406) 595-7065 Email:gunnarson.ky@gmail.com
Address: 184 Buckskin Ro. Unit A City: Belgrade State: MT Zip code: 59714
Project Type (Check)VNewRemodel Addition O Demo
Project Address: 509 E Lanne St, Bozeman
Disturbance Area (square feet): 145 O
MT 59715
Start Date (MM/YYYY):Estimated Completion Date (MM/YYYY):
1.Contractor/owner agrees to install Best Management Practices (BMPs) per the example layout below before
beginning land disturbance activities and maintain throughout the entire length of the project:
INITIAL HERE: KG
- Property Boundary
Flow Line
Flow Line Flow line
House Footprint
Gravel
Flow line
Disturbed Area
Silt Fence, Foam Wattle, or
Straw Wattle Adjacent to
Road or Sidewalk ** Low to
Grade is not an approved
BMP**
City Road, Curb, and
Gutter
Flow Line
Flow Line
* Not to Scale
Section 5: Local Erosion and Sediment Control Requirements
**Refer to the City of Bozeman's Best Management Practice (BMP) Manual to select required controls.**
1. Control disturbed areas: Project boundaries require BMPs that control stormwater flowing from disturbed areas
pursuant to §40.04.360.B. BMC. Approved options:
? Silt Fence
2 Foam or Straw Wattle
? Other:.clean site
2. Mitigate tracking: Exit points require BMPs that mitigate the tracking of debris off-site onto the right-of-way
pursuant to §40.04.360.C. BMC. Approved options:
I Gravel
? Proprietary Tracking Control Product
_ Other:
3. Control concrete waste, slurry and other masonry wash waters: Concrete activities require BMPs that allow for the
capture and disposal of wastes, slurries, and wash-waters, pursuant to §40.04.360.F. BMC. Approved options:
& Reusable or Disposable Product / Dumpster
? Other:
4. Manage dewatering flows: Accumulated groundwater or stormwater discharges pumped into infrastructure or
waterways are MDEQ permitted activities and are required to meet the effluent limitations in the MDEQ
General Permit for Construction Dewatering pursuant to 40.04.360.B. BMC, Montana Clean Water Act, and Federal
Clean Water Act. Approved options:
? Land Application
Well Point
A MDEQ Construction Dewatering General Permit Coverage
Other:
Section 6: Administrative and Operational Controls
1. Contractor/Owner agrees to implement the following required administrative controls:
? Street Sweeping: Frequency: weeky
? On-site Spill Kit
? Protect on-site inlets
? Control of Construction Wastes
? Removal of Temporary BMPs Upon Project Completion
Section 7: Acknowledgment Certificate
I certify that I am the contractor/owner or an authorized agent. If acting as an authorized agent, I certify that I am
authorized to act as the contractor/owner agent regarding the property at the above-referenced address for the purpose
of filing applications for decisions, plans, or review under Chapter 40 Article 4 of the BMC and Ordinances #1763 and
#2002, and have full power and authority to perform on behalf of the contractor/owner all acts required to enable the
and maintained throughout the life of the project.
By checking this box, l acknowledge that non-compliance with this Permit, aforementioned BMC, and City Ordinances
may result in a stop work order, city withholding a certificate of occupancy, or a lien filed against the project for
unpaid costs of abatement of violations.
7/09/2025
Signature of Legally Responsible Person
Kyle Gunnarson
Printed Name
Date
Owner
Title