HomeMy WebLinkAboutFY27 - Urban Renewal Action Plan - Pole YardPOLE YARD URBAN RENEWAL DISTRICT
FY2026 ANNUAL REPORT
and FY 2027 WORK PLAN AND BUDGET
FY 2028 WORK PLAN AND BUDGET
The Purpose and Intent of the Pole Yard Urban Renewal District and Plan
The creation of the URD in the Pole Yard enables the City of Bozeman to eliminate conditions that
contribute to blight substantially impairing sound growth of the City through investments in public
infrastructure and efficient delivery of public services.
Goals of the Pole Yard Urban Renewal District Plan
GOAL 1. Promote Innovative Economic Development
Rationale: Commerce strengthens the community, opens reinvestment opportunities, enables
livable wage jobs, and supports the sound growth of the community, helping to eliminate
conditions that contribute to blight.
GOAL 2. Enable Enhanced Connectivity and Mobility
Rationale: Connecting neighborhoods through investments in multi-model transportation corridors
strengthens the fiber of the community.
GOAL 3. Invest in Efficient Delivery of Public Infrastructure
Rationale: Infrastructure is the backbone of the community. Private development typically requires
a corresponding public investment in infrastructure. Capital improvements will help achieve
economic vitality and support the delivery of public services.
GOAL 4. Foster Urban Neighborhood Coherency
Rationale: Higher concentration of development achieves greater efficiency in the delivery of public
services. Urban growth, oriented to centers of employment and activity, can reduce or eliminate
commute times, lower transportation costs and create vitality and a sense of community.
Integrated elements of growth, ensuring a cohesive neighborhood that in turn contributes to the
well-being of the entire community, will reduce geographic, as well as economic and social
isolation.
GOAL 5. Protect Public Health
Rationale: An area that includes a superfund site presents the need for increased diligence to
comply with the obligation to not exacerbate the human health contact risk or environmental
contamination.
GOAL 6. Encourage the Retention of Existing Businesses
Rationale: Urban infill development can affect the community through such things as additional
traffic and noise, particularly when the existing public systems do not meet current standards.
GOAL 7. Respect Critical Environments
Rationale: Riparian and wetland areas provide benefits to the community through such things as
filtering urban runoff, providing habitat for wildlife and flood protection.
Pole Yard Urban Renewal District (PYURD)
FY2026 Annual Report (July 1, 2025 to June 30, 2026)
Highlights of investments are documented below.
The only expenditure in FY26 were payroll costs of $6,400.
Pole Yard Urban Renewal District (PYURD)
FY2027 Work Plan (July 1, 2026 to June 30, 2027)
Personnel $34,800
This includes salaries and benefits for support staff
Contracted Services $150,000
The district requests a budget for contracted services to be responsive to opportunities
related to the design or evaluation of public infrastructure projects and development
agreements.
Other/General $2,650,200
We propose allocating the entirety of the expected increment to be responsive to
opportunities. It is likely that in FY 26 we will either support developer or city led Infrastructure
projects and development agreements. These funds could also be devoted to the design or
construction of public infrastructure that serves the District. Specifically, the vast majority of
these funds could be allocated to the construction of quiet zone improvements at the Rouse
Ave. crossing in the event the project moves forward within the Fiscal Year.
Pole Yard Urban Renewal District (PYURD)
FY2028 Work Plan (July 1, 2027 to June 30, 2028)
Personnel $36,700
This includes salaries and benefits for support staff
Contracted Services $150,000
The district requests a budget for contracted services to be responsive to opportunities
related to the design or evaluation of public infrastructure projects and development
agreements.
Other/General $572,900
We propose allocating the entirety of the expected increment to be responsive to
opportunities. It is likely that in FY 26 we will either support developer or city led Infrastructure
projects and development agreements. These funds could also be devoted to the design or
construction of public infrastructure that serves the District.