Loading...
HomeMy WebLinkAbout006 Concept Plan Review Comment ResponsesREF # CYCLE REVIEWED BY TYPEFILENAME DISCUSSION STATUS1 1 Solid WasteRussell Ward11/25/24 12:54 PMChangemarkSLD Waste1. no raised curbs are allowed within the 50 foot straight approach003 C1.0 - Site Plan.pdf Acknowledged. 50' straight approach does not have any raised curb within the 24' width. See Site Plan drawing. Info Only2 1 Solid WasteRussell Ward11/25/24 12:57 PMChangemarkSLD Waste1. need detailed plan for refuse enclosures 2.refuse enclosures will need to be covered003 C1.0 - Site Plan.pdf Acknowledged. Please refer to the Architectural Details, Sheet AS501 for refuse enclosure details. Info Only3 1 AddressingJenny Connelley12/4/24 8:47 AMCommentIt appears that N 14th and Oak Park Drive will need to be extended so that the buildings can be addressed off of them. Acknowledged. Oak Park Drive extends south. See Site Plan drawing. Info Only4 1 AddressingJenny Connelley12/4/24 8:50 AMCommentIt also appears that a new plat will be recorded splitting this off from the property to the south (1221 Durston Road). That will need to be done before addressing as that creates a new legal description that will be used in each of the new address records, as well as modifying the legal description of the existing building. Acknowledged. Plat will be recorded before addressing for new buildings can be finalized. Info OnlyPlan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AMREVIEW COMMENTS Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM5 1 Building DivisionKevin Bailey12/4/24 10:30 AMCommentThese comments are from the Building Division for the submitted primary plan and not a complete plan review of the project. The following comments are general items which are required to be included in the plan set application for the required building permit. At that time a complete plan review will be completed. 1. The submitted plans are required to be stamped and signed by the architect of record. 2. Provide the required geotechnical report. 3. Provide the energy design documents. 4. Submit the fire sprinkler and alarm plans to the Bozeman Fire Department for review. 5. Provide complete engineering supporting the project's design. 6. Identify the type of occupancy it is. Is it R1 or R2 by the IBC. And relate their occupancy to table 705.5 for separation distances. 7. Identify the required accessible units and their locations throughout the complex with their paths to the public ways. 8. Provide electrical load calculations for each building. 9. Provide the water and DWV sizing calculations for each building and the complex as a whole. 10. Provide a fire separation plan with all the listed assemblies, sections, how to build details and specific method for sealing penetrations in the fire partitions approved by the architect. Please pay particular attention to the tub / shower units to the fire partitions. Acknowledged. Please refer to the architectural design sheets included in this submittal.Info Only6 1 Water Conservation DivisionEric Neustrup12/6/24 8:10 AMCommentThe "City of Bozeman Landscape and Irrigation Performance and Design Standards Manual" places limits on the amount of turfgrass allowed. These limits are different based on the approval pathway selected by the applicant. See "City of Bozeman Landscape and Irrigation Performance and Design Standards Manual", Section 3.2.1 "Landscape Design Standards", "Landscape Approval Pathways"Acknowledged. Please refer to the Landscape and Irrigation Plans.Info Only7 1 Water Conservation DivisionEric Neustrup12/6/24 8:10 AMCommentAreas less than eight feet wide in any direction must be irrigated with drip irrigation, either subsurface or above ground. See "City of Bozeman Landscape and Irrigation Performance and Design Standards Manual", Section 3.3.1 “Irrigation Design Standards”, “Sprinklers/Overhead Irrigation”, 6).Acknowledged. Please refer to the Landscape and Irrigation Plans.Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM8 1 Water Conservation DivisionEric Neustrup12/6/24 8:11 AMCommentAt least 60% of the landscaped area must be covered with plants. See "City of Bozeman Landscape and Irrigation Performance and Design Standards Manual", Section 3.2.1 "Landscape Design Standards", "Landscape Area Coverage Requirements"Acknowledged. Please refer to the Landscape and Irrigation Plans.Info Only9 1 Water Conservation DivisionEric Neustrup12/6/24 8:11 AMCommentTrees must be planted at a minimum rate of 1 per 1600 square feet of landscape area. See "City of Bozeman Landscape and Irrigation Performance and Design Standards Manual", Section 3.2.1 "Landscape Design Standards", "Tree Requirements Outside of Parking Lots and Boulevards".Acknowledged. Please refer to the Landscape and Irrigation Plans.Info Only10 1 Water Conservation DivisionEric Neustrup12/6/24 8:14 AMCommentDrip irrigation must be used for all landscaped areas other than turfgrass. See "City of Bozeman Landscape and Irrigation Performance and Design Standards Manual", Section 3.3.1 "Irrigation Design Standards", "Drip Irrigation", 1).Acknowledged. Please refer to the Landscape and Irrigation Plans.Info Only11 1 Water Conservation DivisionEric Neustrup12/6/24 8:15 AMCommentLandscaped areas must have a minimum topsoil depth of 6”. See “City of Bozeman Landscape and Irrigation Performance and Design Standards Manual”, Section 3.2.1 “Landscape Design Standards”, “Soil Quality Requirements”, 1).Acknowledged. Please refer to the Landscape and Irrigation Plans.Info Only12 1 Water Conservation DivisionEric Neustrup12/6/24 8:15 AMCommentThe applicant will need to select a landscape design approval pathway when the project is submitted for site plan review. See “City of Bozeman Landscape and Irrigation Performance and Design Standards Manual”, Section 3.2.1 "Landscape Design Standards", "Landscape Design Approval Pathways".Acknowledged. Please refer to the Landscape and Irrigation Plans.Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM13 1 Water Conservation DivisionEric Neustrup12/6/24 8:15 AMCommentWhen completing the irrigation water requirement for submission refer to the "City of Bozeman Water Conservation Division Plant List" to determine the plant factor for the relevant plant materials.Acknowledged. Please refer to the Landscape and Irrigation Plans.Info Only14 1 Water Conservation DivisionEric Neustrup12/6/24 8:16 AMCommentIrrigation zones must be separated based on hydrozone. See "City of Bozeman landscape and Irrigation Performance and Design Standards Manual", Section 3.3.1 "Irrigation Design Standards", "Irrigation Stations/Zones", 2).Acknowledged. Please refer to the Landscape and Irrigation Plans.Info Only15 1 Water Conservation DivisionEric Neustrup12/6/24 8:16 AMCommentIrrigation stations that irrigate trees may not irrigate other plant types. See "City of Bozeman landscape and Irrigation Performance and Design Standards Manual", Section 3.3.1 "Irrigation Design Standards", "Irrigation Stations/Zones", 3).Acknowledged. Please refer to the Landscape and Irrigation Plans.Info Only16 1 Water Conservation DivisionEric Neustrup12/6/24 8:16 AMCommentOperating pressure of the irrigation system must meet the manufacturers recommended operating pressure. See "City of Bozeman landscape and Irrigation Performance and Design Standards Manual", Section 3.3.1 "Irrigation Design Standards", "System", 3).Acknowledged. Please refer to the Landscape and Irrigation Plans.Info Only17 1 Water and Sewer DivisionNick Pericich12/17/24 8:44 AMChangemarkW/S Sewer ManholeThis can't be in parking spots. Please eliminate the parking or move the manhole out of the parking to the west. 003 C1.0 - Site Plan.pdf Acknowledged. Parking has been removed from over the manhole. Manhole now located in landscape island.Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM18 1 Water and Sewer DivisionNick Pericich12/17/24 8:48 AMChangemarkW/S Sewer Main DepthI believe this sewer main is very shallow at four feet or less of cover. You will need a plan with these smaller sewer services to make sure they are adequately insulated to prevent them from freezing. 003 C1.0 - Site Plan.pdf Acknowledged. Insulation will be installed around sewer services at locations where adequate cover can not be achieved. Info Only19 1 Parks DepartmentRoss Knapper12/18/24 8:55 AMCommentCILP may be requested for this project. Please include a narrative that addresses the commission criteria for CILP requests. Please include a vicinity map showing existing parks within 0.5 miles of the project location that are accessible via pedestrian pathways or sidewalks. If you would like to propose any improvements to Oak Meadows Park, please contact Park Staff to discuss completing a park master plan for Oak Meadows Park. Acknowledged. CILP is proposed for this project. A park is located directly North, across Juniper Street. Info Only20 1 EngineeringSuzanne Ryan12/18/24 9:34 AMLibrary CommentDSSP V.D.1 - Water mains, sanitary sewers, and storm sewers within the proposed development shall be arranged to allow the suitable development of any adjoining un-developed land, and shall be constructed to the boundary lines of the tract being developed, unless prevented by topography or other physical conditions, in which case a variance must be approved by the City of Bozeman.Acknowledged. Utility mains will run under the proposed Oak Park Drive along the property's boundary line allowing connection access to the adjacent undeveloped property.Info Only21 1 EngineeringSuzanne Ryan12/18/24 9:34 AMLibrary CommentThe applicant must provide and file with the County Clerk and Recorder's office executed Waivers of Right to Protest Creation of Special Improvement Districts (SIDs) on City standard record Form. Acknowledged. SIDs waiver will be signed and recorded once provided by the City during Site Plan Review process to insure all SIDs applicable are captured. Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM22 1 EngineeringSuzanne Ryan12/18/24 9:34 AMLibrary CommentBMC 38.410.130. Water Adequacy: The development will need to satisfy the water adequacy code requirement prior to a future site plan approval. If sufficient water rights cant be provided to offsets the development's annual demand then a cash-in-lieu of water rights (CILWR) payment will be required. The City assesses the CILWR fee at a rate of $6,000 per acre-foot. The fee determination will take place during the site plan review, however if there are any questions or if a preliminary review is desired please contact Griffin Nielsen with the Engineering/Utilities Department directly at gnielsen@bozeman.net or (406) 582-2279. The City encourages the use of groundwater wells to supply irrigation demands, which in turn will reduce the CILWR fee. Applicant must obtain a pre-determination from the DNRC demonstrating that a well groundwater well may be permitted under Montanas exempt appropriation or that provide the water right documentation if existing prior to finalization of the CILWR fee determination. Finally, the City would like to make the owner aware of an available CILWR rebate of approximately 20% for residential units if high-efficiency fixtures (toilets, washers, and shower heads) meeting the City Water Conservation Division standards are installed. The rebate would be released at occupancy and requires an agreement defining the terms and amount rebate be finalized and executed prior to final plan approval. If the owner is interested or has any questions please reach out to Griffin Nielsen.Acknowledged. The CILWR Rebate of approximately 20% for residential units with high-efficiency fixtures installed is being considered for this project. Info Only23 1 EngineeringSuzanne Ryan12/18/24 9:34 AMLibrary CommentConcurrent construction has been an identified purpose of the initial project review. The applicant must complete the following concurrent construction form (https://www.bozeman.net/home/showpublisheddocument/11704/637769761956630000) to apply for concurrent construction for on site or adjacent improvements associated with site development. Acknowledged. A concurrent construction plan and CCON form is provided with this submittal. Additional concurrent construction requirements will be acquired during site plan review (approval from Fire Department) and with the review of the infrastructure submittal.Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM24 1 EngineeringSuzanne Ryan12/18/24 9:34 AMLibrary CommentBMC 38.410.060 - Easements: All Easements indicated below must be provided on city standard easements templates. Drafts must be prepared for review and approval by the city with site plan submittal. Signed hard copies of the easements must be submitted to the city prior to site plan approval. The applicant may find the City Standard Easement Templates in the City Documents and Staff Reports folder. These templates represent the citys required easement. If the applicant chooses to request changes they must contact the development review engineer assigned to the project. If any changes are made to these templates the applicant must indicate in the document the specific changes when returned to the City.Acknowledged. Applicable draft easements are included in this submittal. The applicant would like to note that this comment does not outline the which easements the city is requiring and the templates were not provided in the 'City Documents and Staff Reports' folder. Info Only25 1 EngineeringSuzanne Ryan12/18/24 9:34 AMLibrary CommentDSSP Plans and Specifications Review Policy A. -Plans, specifications, and submittals for public infrastructure improvements must be submitted to the City Engineering Department through the engineering Project Dox Portal (https://www.bozeman.net/services/development-center) for infrastructure review. (List Improvements).Acknowledged. Infrastructure design will be submitted following Site Plan adequacy. Info Only26 1 Stormwater DivisionAdam Oliver12/18/24 6:43 PMChangemarkNo Storm InfoThe applicant has not provided any stormwater information or proposed topography for review. 003 Concept Plan Checklist.pdf Acknowledged. For stormwater information please refer to the Grading and Drainage design drawing and the Stormwater Management Report included in this submittal. Info Only27 1 Stormwater DivisionAdam Oliver12/18/24 6:45 PMChangemarkLegend Entry Not Present"O" not found on this sheet. The drainage plan is also a preliminary plat requirement.003 C1.0 - Site Plan.pdf Acknowledged. For stormwater information please refer to the Grading and Drainage design drawing and the Stormwater Management Report included in this submittal. Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM28 1 Stormwater DivisionAdam Oliver12/18/24 6:59 PMCommentSeveral lots are proposed to have significant impervious area constructed and alter drainage patterns although no details have been provided to account for the quality and quantity of this increased runoff. Site plan submittals must include a full grading and drainage plan as well as stormwater design report showing the points of stormwater discharge and the ultimate destination of stormwater from across all parcels. BMC 38.220.080 will require existing and proposed contours to extend 100 feet beyond the project boundary. Based on the existing topography, it is not apparent that it will be possible to fit retention or detention features on the proposed site. Acknowledged. For stormwater information please refer to the Grading and Drainage design drawing and the Stormwater Management Report included in this submittal. Info Only29 1 Fire DepartmentScott Mueller12/23/24 9:07 AMCommentAttached floor plans don't match building footprints on site plans. FDC/Horn-Strobe shall not be located above landscaping beds. They shall have landing/sidewalk to public way and not be obstructed with future growth of vegetation. Fire Riser Room shall have exterior access with sidewalk to public way and include the Fire Alarm Control Panel. 2021 International Fire Code D103.5 Fire apparatus access road gates. Gates securing the fire apparatus access roads shall comply with all of the following criteria: 1. Where a single gate is provided, the gate width shall be not less than 20 feet (6096 mm). Where a fire apparatus road consists of a divided roadway, the gate width shall be not less than 12 feet (3658 mm). 2. Gates shall be of the swinging or sliding type. 3. Construction of gates shall be of materials that allow manual operation by one person. 4. Gate components shall be maintained in an operative condition at all times and replaced or repaired when defective. 5. Electric gates shall be equipped with a means of opening the gate by fire department personnel for emergency access. Emergency opening devices shall be approved by the fire code official. 6. Methods of locking shall be submitted for approval by the fire code official. 7. Electric gate operators, where provided, shall be listed in accordance with UL 325. 8. Gates intended for automatic operation shall be designed, constructed and installed to comply with the requirements of ASTM F2200. D103.6 Signs. Where required by the fire code official, fire apparatus access roads shall be marked with permanent NO PARKING—FIRE LANE signs complying with Figure D103.6. Signs shall have a minimum dimension of 12 inches (305 mm) wide by 18 inches (457 mm) high and have red letters on a white reflective background. Signs shall be posted on one or both sides of the fire apparatus road as required by Section D103.6.1 or D103.6.2. Fire hydrant locations not shown on site plans. Proposed Building 5 will require due to height/fourth floor, fire sprinkler standpipes and a fire hydrant within 100 feet of Acknowledged. Please refer to the updated civil and architectural drawings included in this submittal. Fire riser rooms have been given exterior access. A fire hydrant has been added in the Southeast corner of the site off of Oak Park Drive and less than 100 feet away from the FDC in building 5. Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM30 1 EngineeringSuzanne Ryan12/23/24 9:46 AMCommentBMC 38.220.060 11 g. Since a TIS was not completed during the subdivision review process, a TIS will be required for this site plan application. The applicant is advised that some mitigation may identified and required upon review of the TIS. Acknowledged. Please refer to the Traffic Impact Study (TIS) included in this submittal.Info Only31 1 PlanningDanielle Garber12/23/24 1:04 PMCommentThe preliminary plat application #24533 to create the development lot is still in DRC review. The final plat to create the development lot must be approved and recorded prior to final plan approval and building permit approval. Acknowledged. The applicant understands that the final plat to create the development lost must be approved and recorded prior to final plan approval and building permit approval. Info Only32 1 PlanningDanielle Garber12/23/24 1:04 PMCommentA site plan application is required for entitlement. The site plan application will need to provide a phasing plan for the future pad site development of the proposed day care and HRDC homes. If no details surrounding these portions of the development are included with the site plan application then they will most likely need to be reviewed under a separate site plan application depending on the proposed development of those areas and the thresholds of BMC 38.230.160. Acknowledged. The HRDC Homes Lot and County lot will need to be reviewed under a separate site plan application when they are developed. The details of these lots are not a part of this Site Plan submittal.Info Only33 1 PlanningDanielle Garber12/23/24 1:23 PMCommentWhere incentives for affordable housing are sought with the formal application please group the desired incentives in the application narrative. Please include the affordable housing plan as well as the review memo from the Community Housing Division. BMC 38.380.Acknowledged. The desired incentives are outlined on the Architectural Sheets as well as in the Site Plan Narrative included in this submittal. Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM34 1 PlanningDanielle Garber12/23/24 1:24 PMCommentWhere departures for housing creation are sought with the formal application please group the desired departures in the application narrative and provide analysis of the criteria utilized to determine departure approval for each departure requested. BMC 38.270.070. Where other departures from design standards are requested or necessary. Please group those departures in the narrative citing the specific code section and criteria utilized to determine departure approval per each individual code section. Acknowledged. The desired departures for housing creation are outlined on the Architectural Sheets as well as in the Site Plan Narrative included in this submittal. Info Only35 1 PlanningDanielle Garber12/23/24 1:26 PMCommentApartments and apartment buildings are principal uses in the R-4 zoning district. Day care centers are principal uses in the R-4 zoning district. The future HRDC homes appear to be rowhouses. Townhouses and rowhouses are principal uses in the zoning district at two attached to 5+ attached configurations. Townhouse and rowhouse dwellings are subject to the supplemental use criteria of BMC 38.360.250 including a different open space calculation. Acknowledged. Specifics of the HRDC Homes lot will be outlined in a separate, subsequent site plan application. Info Only36 1 PlanningDanielle Garber12/23/24 1:26 PMCommentThe application is meeting minimum lot area, lot width, and lot coverage requirements as currently designed per the form and intensity standards in BMC 38.320.030.A-C. The applicant will also need to consider form and intensity standards for the two future lots for the county daycare and the HRDC homes. Those lots will be required to meet setbacks, lot coverage, and minimum lot area from the proposed future lot lines per this section if the applicant wishes to subdivide. Please also provide a density calculation per net acre. The calculation for net acres is located in BMC 38.700.130 under N definitions. In that calculation commercial land area, streets and rights of way, and common open spaces are deducted. Acknowledged. The HRDC Homes Lot and County lot will need to be reviewed under a separate site plan application when they are developed. The details of these lots are not a part of this Site Plan submittal. A density calculation per net acre can be found on the Cover sheet drawing. Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM37 1 PlanningDanielle Garber12/23/24 1:27 PMCommentProviding the maximum allowable height on the elevations is helpful, but not required. The applicant must also show the maximum ridge height from grade to the highest point on the roof with formal submittal. BMC 38.320.030.C The four-story building is exceeding the maximum allowable height of 50-feet by about 5-feet. Staff acknowledges that deep incentives are proposed to increase allowable height for the development. Please see comments above regarding incentive documentation in the project narrative. Acknowledged. The elevations are noted are the architectural drawings and the maximum allowable height is documented on the architectural site plan. Please refer to the included narratives which outline the incentives taken. Info Only38 1 PlanningDanielle Garber12/23/24 1:28 PMCommentBMC 38.230.030.C provides setbacks. Juniper Street and Oak Park Drive have an R-4 front setback of 15-feet. Per BMC 38.350.050.A ground level porches and patios may encroach 5-feet into the required 15-foot front setback, and 20-foot rear setback. Upper level patios may not encroach into required setbacks. Apartment buildings along landscaped block frontages are also subject to a minimum setback of 10-feet. Since the apartment buildings are subject to block frontage standards, a minimum setback of 10-feet is required in lieu of the 15-foot R-4 setback. Per BMC 38.500.020.A where block frontage provisions conflict with other sections of the UDC, the block frontage provisions prevail. The proposed rowhouses or HRDC homes are subject to the 15-foot R-4 front setback. The applicant has indicated that affordable housing incentives regarding setbacks will be submitted, please see comments above regarding documentation of setback reductions per the incentives. Acknowledged. The project utilizes the incentive of a 10% reduction in required setbacks as indicated in the Site Plan narrative. The HRDC Homes lot will be subject to a separate site plan review - requirements for the design of lot will be established and met in said review. Info Only39 1 PlanningDanielle Garber12/23/24 1:29 PMCommentBMC 38.410.040.D – Rights of way for pedestrians. The applicant is required to show the required east-west easement, currently proposed to the south of Building 4 on the formal site plan submittal. Easements that are 10-feet wide require 10-foot setbacks on either side. No buildings or parking may encroach into those setbacks. Per the meeting on Dec. 12, staff suggests the applicant swap the locations of the HRDC lot and building 1 with building 4 to allow room for the easement through the open space area without losing units or parking. No continuous length of block may exceed 600 feet without intersecting a street or pedestrian walk. The applicant is required to construct the pedestrian connection to Durston Road through the rest home parcel with site plan approval. This is considered a transportation pathway per BMC 38.400.110. Acknowledged. Please refer to the Site Plan which includes the east-west pedestrian connection and 30' easement. The applicant is aware of the requirement to build a pedestrian connection from the property South to Durston Road, please refer to the architectural site plan. The specifics of this north-south pedestrian connection are still being discussed with the City and County as it crosses property belonging to the County and the exact width of the path and easement has not been determined. There is only a small strip of land for the proposed pathway that also includes a sewer main and overhead power lines so the layout is not straight-forward and may require adjustments in the field during construction. Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM40 1 PlanningDanielle Garber12/23/24 1:29 PMCommentNo surface stormwater ponds are currently proposed. If any surface stormwater ponds are proposed with the formal submittal, they must meet landscaping requirements in BMC 38.410.080.H. Drainage facilities that are 10% grade or less may be grassed and irrigated to blend into the adjacent landscaped area. Facilities over 10% grade require vegetation and boulders to create a functional and natural site feature. Acknowledged. For stormwater information please refer to the Grading and Drainage design drawing and the Stormwater Management Report included in this submittal. Info Only41 1 PlanningDanielle Garber12/23/24 1:33 PMCommentJuniper and Oak Park Drive are designated landscaped block frontages. Provisions for this designation are in BMC 38.510.030.C. Based on the submittal the following provisions, in addition to the full standard, are required to be met with the formal submittal: • Building Placement: 10' minimum front setback is met for the apartment buildings. 13.5 feet is proposed at both street frontages. However, the HRDC homes (if not considered apartment uses) are required to have 15-feet with. As discussed above incentives are available for reduced front setbacks. •  Building Entrances: Building entrances must be visible and directly accessible from the street. This appears to be me by proposing two primary entrances accessible from Juniper Street. • Façade Transparency: For residential uses, at least 15% of the entire façade (all vertical surfaces generally facing the street). The applicant must demonstrate adequate façade transparency at formal submittal but providing a calculation for the elevations facing Juniper and Oak Park Drive. • Weather Protection: Provide weather protection at least 3' deep over primary residential entries. • Parking Location: Private or shared garage entries must occupy no more than 50% of façade width. Provide a 10' minimum buffer of landscaping between the street and off street parking areas meeting the performance standards of division 38.550 of this chapter. • Landscaping: The area between the street and building must be landscaped, private porch or patio space, and/or pedestrian-oriented space. For setbacks adjacent to buildings with windows, provide low level landscaping that maintains views between the building and the street. Also provide plant materials that screen any blank walls and add visual interest at both the Acknowledged. Requirements for the HRDC homes lot will be addressed in a separate site plan application. Transparency calculations are provided on the architectural design sheets. Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM42 1 PlanningDanielle Garber12/23/24 1:33 PMComment This application also contains special residential block frontages per BMC 38.510.030.J. Demonstrate in the narrative and drawings in the formal submittal how the application is meeting this code section: For residences with ground floor living spaces facing a sidewalk or pedestrian path in a residential or mixed use development, the building must feature at least one of the public/private space transition elements described below. The objective of this standard is to ensure privacy and security for residents, and an attractive and safe pathway that complements the qualities of adjoining residences within a residential complex. 1. Raised deck or porch option. Provide at least a 60 square foot porch or deck raised at least one foot above grade. The porch or deck must be at least six feet deep, measured perpendicular to the building face. (The deck may be recessed into the unit floor plan so that deck does not extend from the building face a full six feet.) A low fence, rail or hedge, two feet to four feet high, may be integrated between the sidewalk or internal pathway and deck or porch. 2. Front setback options. Provide a minimum ten-foot setback between the sidewalk or internal pathway and the face of the residence. Design options for the front setback: i. Landscaped area, meeting the provisions of division 38.550. ii. Semi-private patio space screened by a low fence or hedge (see section 38.350.060). 3. Raised ground floor. If the residence's ground floor is a minimum of three feet above the grade adjacent to the building, then the landscaped area in Acknowledged. For residences with ground floor living spaces facing a sidewalk or pedestrian path, a ten-foot setback landscaped area is proposed. The majority of ground floor residences also have a recessed porch between the building and pathways to further create a transitional space. Info Only43 1 PlanningDanielle Garber12/23/24 1:34 PMCommentPer BMC 38.520.030.B - Balconies alongside and rear property lines adjacent to residentially zoned properties. Balconies or rooftop decks within 15 horizontal feet of a side property line abutting a residentially zoned property must feature a railing system that is at least 50 percent opaque. Specifically, 50 percent of the area below the railing must be a sight-obscuring structure. Departures from this standard will be allowed if the balcony will not cause visual or privacy impacts due to its location, orientation, design or other consideration.Acknowledged. Please refer to the architectural plans included in this submittal. Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM44 1 PlanningDanielle Garber12/23/24 1:34 PMCommentPer BMC 38.520.030.C - Light and air access and privacy alongside and rear property lines. Buildings or portions thereof containing multi-household dwelling units whose only solar access (windows) is from the applicable side of the building (facing towards the side property line) must be set back from the applicable side or rear property lines at least 15 feet. See figures 38.520.030.B and C. Departures will be allowed where it's determined that, based on the unique site context, the proposed design won't create a compatibility problem in the near or long term.Acknowledged. The setbacks along the West and South property line are greater than 15 feet. The North and East property lines border local streets have a setback of 13.5 feet but are considered front setbacks. Info Only45 1 PlanningDanielle Garber12/23/24 1:34 PMCommentPer BMC 38.520.040.C.2 – The middle trash enclosure does not appear to have a pedestrian connection. Pedestrian access is required to all services on the site.Acknowledged. Please refer to the Site Plan. All three of the trash enclosures are adjacent to a pedestrian area. Info Only46 1 PlanningDanielle Garber12/23/24 1:34 PMCommentPer BMC 38.520.040.C.3 - Crosswalks are required when a walkway crosses an on-site paved area accessible to vehicles. Crosswalks must contain contrasting material (such as concrete) and/or patterns (such as stamped asphalt), excluding painted surfaces. The conceptual design appears to be meeting this standard. Acknowledged. The crosswalks are consistent to what was proposed on the concept plan, the crosswalks are proposed to be painted. An additional crosswalk was added crossing Juniper Street and the intersection with Oak Park Drive. This crosswalk will facilitate pedestrian access to the park located on the other side of Juniper Street. Info Only47 1 PlanningDanielle Garber12/23/24 1:35 PMCommentPer BMC 38.520.040.C.5-6 – Connections to adjacent properties are required. The sidewalk connection along the Oak Park Drive extension must extend to the southern property line and connect to the required path. Acknowledged. The sidewalk connection has been updated in this site plan submittal. Info Only48 1 PlanningDanielle Garber12/23/24 1:35 PMCommentPer BMC 38.520.060 – Usable residential open space per this section is required for the apartments in the development. With formal submittal provide a breakdown of open space provided per open space area and type (shared open space, private residential (ground level patios), balconies, and indoor. For the open space reduction proposed provide a narrative for the departure as described in the comment above. Acknowledged. Please refer to the Open Space Plan drawing included in this submittal. The sheet also includes a breakdown of the open space calculations and departures taken. Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM49 1 PlanningDanielle Garber12/23/24 1:36 PMComment BMC 38.520.070 contains requirements for the location and design of service areas and mechanical equipment. The formal application must demonstrate compliance with: • Trash enclosure screening per section C. Structural enclosures must be constructed as outline in this provision and contain a horizontal cover. 5-feet of landscaping is required around solid waste enclosures. • Utility meter screening per section D • Location and screening of any roof mounted mechanical equipment such as HVAC condensers. The elevations seem to indicate the use of wall mounted PTAC units. Please include details for the cover or screening for the vents.Acknowledged. Please refer to the included design plans specifically the architectural and landscaping plans for proposed screening. Sheet AS501 details the proposed trash enclosure. Info Only50 1 PlanningDanielle Garber12/23/24 1:36 PMComment BMC 38.530 contains requirements for building design. The formal application must demonstrate compliance in the narrative and drawing for: • Massing and articulation for residential buildings. Including articulation and maximum façade width mitigation. • Building details including articulated building entries. • Building materials including special limitations for certain materials (metal siding and cementitious wall board. • Blank wall treatments for any walls areas over 10-feet high and 15-feet wide without a transparent window or door.Acknowledged. Please refer to the included architectural design plans. Info Only51 1 PlanningDanielle Garber12/23/24 1:37 PMCommentBMC 38.540.050.4-5 provides standards for bicycle rack type, location, and parking area dimensions. Provide a detail with the formal submittal showing that each bicycle parking space meets these requirements, including a 2-foot wide by 6-foot long space with area for circulation. Acknowledged. Please refer to Sheet AS501 for a detail of the proposed bicycle parking. Bicycle parking areas are denoted on the Site Plan sheet. Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM52 1 PlanningDanielle Garber12/23/24 1:37 PMComment With the formal submittal the applicant must provide landscaping plans that meet the standards required in BMC 38.550 including mandatory landscaping provisions for: • Parking lot landscaping • Parking lot screening • Street frontage landscaping and other public landscaping including pedestrian crossings. • Required trees for residential adjacency • Irrigation standards The Water Conservation Division will also evaluate landscaping plans per the City of Bozeman Landscape and Irrigation Performance and Design Standards Manual. The applicant will be required to provide the required details to demonstrate compliance with the provisions in the manual.Acknowledged. Please refer to the Landscape Plans included in this submittal.Info Only53 1 PlanningDanielle Garber12/23/24 1:39 PMCommentNo lighting and photometric plans were provided. With the formal submittal provide plans for lighting that are compliant with BMC 38.570.040 including a photometric plan in footcandles that extend to the property line, and fixture details demonstrating full cutoff shielding for any building mounted lighting and site lighting. Acknowledged. Please refer to the Photometric Plans included in this submittal. Info Only54 1 PlanningDanielle Garber12/23/24 1:41 PMChangemarkPLNG Curbing at HRDC HomesPlease provide further justification in the phasing plan for the curbing proposed to serve individual driveways for the HRDC homes. Since no timing for that development is provided, the phasing phan should show a continuous curb around the HRDC homes future lot and grass seeding for ground cover between phases. 003 C1.0 - Site Plan.pdf Acknowledged. Please refer to the updated proposed design which features full curb along the HRDC Homes Lot. As the specifics of this lot's design are unknown at this time, a separate site plan will be submitted and subject to its individual review. Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM55 1 EngineeringSuzanne Ryan12/23/24 3:48 PMCommentBMC 38.410.080 D. Stormwater retention or detention ponds may be located within public parkland, but such areas must not count towards the parkland dedication requirement. Any stormwater ponds located on parkland must be designed, constructed and/or added to so as to be conducive to the normal use and maintenance of the park. Stormwater ponds serving multiple lots in separate ownership must not be located on private lots or public rights-of-way. Stormwater retention or detention ponds must be maintained by the property owners' association. Acknowledged. For stormwater information please refer to the Grading and Drainage design drawing and the Stormwater Management Report included in this submittal. No stormwater ponds are proposed to be within parkland. Info Only56 1 EngineeringSuzanne Ryan12/23/24 3:51 PMCommentBMC 38.410.050 Front setback utility easements. Front setback utility easements must be ten feet wide, and must always be provided unless written confirmation is submitted to the community development department from all utility companies providing service indicating that front setback easements are not needed.Acknowledged. The design with non-municipal utility companies is still being coordinated, however a 10' easement is proposed to be granted. Info Only57 1 EngineeringSuzanne Ryan12/23/24 3:54 PMLibrary CommentDSSP Section V.A. - A water design report must be prepared by a professional engineer for the proposed project. The water distribution system must be designed to meet the maximum day demand plus fire flow and the peak hour demand.Acknowledged. Please refer to the water design report included in this submittal. Info Only58 1 EngineeringSuzanne Ryan12/23/24 3:54 PMLibrary CommentDSSP Section V.B. - A sewer design report prepared by a professional engineer liscenced in the state of Montana deomonstrating compliance with these requirements shall be submitted. Design parameters and the critical conditions shall be shown on an overall plan of the study area. An overall plan of the development, including all areas outside of the study area which would naturally be served through the study area shall be included. Acknowledged. Please refer to the sewer design report included in this submittal. Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM59 1 EngineeringSuzanne Ryan12/23/24 3:58 PMLibrary CommentBMC 38.220.020 A. - The developer must provide the community development department with a copy of all required streambed, streambank or wetlands permits, or written notification from the appropriate agency that a permit is not required, prior to the commencement of any work on the site and/or final plat approval, whichever is sooner. These permits include but are not limited to: (list permits) Acknowledged. There is not a wetland on the property. There is an irrigation ditch on the adjacent property along the site's eastern boundary line. Please refer to the correspondence from the Farmers Canal Company included in the Documents portion of this submittal. Info Only60 1 EngineeringSuzanne Ryan12/23/24 3:58 PMLibrary CommentThe applicant is advised that the proposed project falls within the Bozeman Solvent Site boundary. The applicant must contact the Citys solvent site consultant, Jim Sullivan, the Principal Engineer at Tasman Geosciences, Inc. and the DEQ project manager, Katy Frye for additional information on construction requirements within the solvent site. Acknowledged. Please refer to the previously submitted Preliminary Plat application which addresses this comment. Info Only61 1 EngineeringSuzanne Ryan12/23/24 3:58 PMLibrary CommentDSSP II.B.1 A Storm Drainage Plan shall include a map or plat showing building site(s), open areas, drainage ways, ditches, culverts, bridges, storm sewers, inlets, storage ponds, roads, streets, and any other drainage improvements. The map shall also include identification and square foot coverage of the various ground surfaces (i.e. vegetation, gravel, pavement, structures).Acknowledged. Please refer to the stormwater managemtn deisgn report included in this submittal.Info Only62 1 EngineeringSuzanne Ryan12/23/24 3:58 PMLibrary CommentDSSP Section II A. 4. - The applicant must include a storm drainage plan with post-construction storm water management controls that are designed to infiltrate, evapotranspire, and/or capture for reuse the post-construction runoff generated from the first 0.5 inches of rainfall from a 24-hour storm preceded by 48 hours of no measurable precipitation.Acknowledged. For stormwater information please refer to the Grading and Drainage design drawing and the Stormwater Management Report included in this submittal. Info Only Plan Review - Review Comments ReportProject Name: 24641 Hidden Creek CONR Workflow Started: 11/13/2024 1:29:04 PM Report Generated: 01/13/2025 10:16 AM63 1 EngineeringSuzanne Ryan12/23/24 3:58 PMLibrary CommentMontana Post Construction Storm Water BMP Design Manual - The proposed project is located in an area that is known to have seasonally high groundwater. The applicant must demonstrate that seasonal high groundwater will not impact the function or maintenance of the proposed facilities. Industry guidance recommends a three-foot minimum separation from the bottom of the proposed facility to the underlying groundwater table. The applicant must provide local seasonal high groundwater elevations to support the proposed design.Acknowledged. For stormwater information please refer to the Grading and Drainage design drawing and the Stormwater Management Report included in this submittal. Info Only64 1 EngineeringSuzanne Ryan12/23/24 3:58 PMLibrary CommentDSSP Section II C. - The applicant must provide on-site detention with release rates limited to predevelopment runoff rates. Retention ponds must be sized based on a 10-year, 2-hour storm intensity.Acknowledged. For stormwater information please refer to the Grading and Drainage design drawing and the Stormwater Management Report included in this submittal. Info Only65 1 EngineeringSuzanne Ryan12/23/24 3:59 PMLibrary CommentBMC 38.270.020 - Construction Routes: A construction route map must be provided showing how materials and heavy equipment will travel to and from the site. Acknowledged. Please refer to the Construction Management Plan sheet included in this submittal. Info Only66 1 EngineeringSuzanne Ryan12/23/24 4:36 PMChangemarkENG Crosswalk38.400.010 The applicant must install a crosswalk across Juniper.004 C1.1 - Dimension Plan.pdf Acknowledged. Please refer to the updated design which includes a painted crosswalk across juniper street. Info Only67 1 EngineeringSuzanne Ryan12/23/24 4:37 PMChangemarkChangemark note #02The sanitary Sewer manhole must not be located in a parking spot.004 C1.1 - Dimension Plan.pdfAcknowledged. The parking has been reconfigured to keep the existing manhole outside of a parking space and within landscaped area. Info Only68 1 EngineeringSuzanne Ryan12/23/24 4:37 PMChangemarkENGShow snow storage on site plan.004 C1.1 - Dimension Plan.pdf Acknowledged. Snow storage is shown on site and denoted on the Site Plan. If additional snow storage is required, snow will be hauled off-site. Info Only