HomeMy WebLinkAbout002 Project Narrative
Site Plan Application
The Arbor Houses at Blackwood Groves
Lot 1 and Lot 2, Block 9, Phase 3A
BLACKWOOD GROVES
Site Plan Application – The Arbor Houses Block 9
November 2024
Page 2 of 4
Table of Contents
NARRATIVE
Section I. – Project Team
Section II – Introduction
Section III – Site Plan
Section IV – Engineering
Section V – Schedule
Section VI – Pre-Application Meeting
I. PROJECT TEAM
OWNER & Blackwood Land Fund, LLC
APPLICANT 115 W. Kagy Blvd, Suite L
Bozeman, MT 59715
p: 406.539.6015
PLANNER Intrinsik Architecture, Inc.
111 N. Tracy Avenue,
Bozeman, MT 59715
p: 406.582.8988
ARCHITECT Humphreys & Partners Architects
5339 Alpha Road, Suite 300
Dallas, TX 75240
p: 972.701.9636
ENGINEER Alpine Engineering and Surveying
714 Stoneridge Drive, Suite 3
Bozeman, MT 59718
p: 406.586.5599
LANDSCAPE ARCHITECT Cashman Landscaping
2055 Springhill Road
Bozeman, MT 59718
p: 406.587.3406
BLACKWOOD GROVES
Site Plan Application – The Arbor Houses Block 9
November 2024
Page 3 of 4
II. INTRODUCTION
The Arbor Houses at Blackwood Groves, Block 9 (the project) is a proposed 30-unit rental apartment
project located on Lot 1 and Lot 2, Block 9, Blackwood Groves Subdivision, Phase 3A. The 1.41-acre
project is on vacant land, zoned Residential Emphasis Mixed-Use (REMU), and is wholly surrounded by
REMU zoning. A 2.13-acre public park adjoins the property to the west, single-household residential is
platted to the north and east of the project, and mixed-use development is planned to the south on
the south side of Victoria St.
Three (3) buildings with 10 dwelling units each are proposed with this site plan. The units are a mix of
one-, two-, and three-bedroom units ranging from 753 – 1,383 square feet in floor area.
III. SITE PLAN
The proposed buildings will front on Park 3 (west) and will have garages for all units accessed off the
Arbor Way alley on the east and north side of the buildings. The site, including all ground-floor units
fronting Park 3, provides direct pedestrian connections to Park 3 as well as Victoria Street to the north
and S 11th Ave to the east.
Phasing:
The buildings will be constructed concurrently but occupancy will be requested for individual buildings
as they’re completed. Building #1 is anticipated to request occupancy first, Building #2 second, and
Building #3 third. There are no public main extensions associated with this project. Please see the
phasing plan in the documents folder of this submittal.
Parking:
Parking for this project is primarily provided by attached garages within the buildings but additional
parking is provided by driveway spaces and off-street spaces. Fifty-four (54) parking spaces are
required for this project and 63 spaces are provided. This project does not count any of the angled
parking spaces on Victoria St. as these spaces are intended to be counted towards the community
commercial district to the south of Victoria St. Please refer to the parking calculations on the Cover
Sheet (CS).
On-Site Residential Open Space:
On-site residential open space is provided by private balconies, ground level private outdoor space,
and shared open space. Please refer to the open space calculations provided on the Cover Sheet (CS).
Only qualifying balconies were included in these calculations. In addition to the on-site open space,
residents will have direct access to the 2.13-acre public park (Park 3) adjoining the west side of this
project.
Parkland:
The Blackwood Groves Subdivision provided parkland dedication in excess of the maximum 12
dwelling units per acre for parkland dedication and/or cash-in-lieu of parkland dedication for Block 9.
No additional parkland dedication or cash/improvements-in-lieu of parkland dedication is required for
this proposal. Residents will have direct access to the 2.13-acre public park (Park 3) adjoining the west
BLACKWOOD GROVES
Site Plan Application – The Arbor Houses Block 9
November 2024
Page 4 of 4
side of this project. Park 3 contains a large playground area, trails, pavilions, lawn areas, and pickleball
courts.
IV. ENGINEERING
Utilities:
Water and sanitary sewer services were stubbed into the project as part of the Phase 3A public
improvements. No main extensions are necessary for this development.
Stormwater:
The Stormwater Master Plan for Blackwood Groves is designed to manage the runoff from Block 9.
The site is graded to drain to the surrounding street network where stormwater runoff will be
conveyed to the Subdivision’s stormwater facilities. The Stormwater Design Report is included in the
documents folder of this application.
Fire Access:
Fire hydrants are located: at the bend in Arbor Way (Alley), at the intersection of 11th Ave/Cambridge
Dr., mid-block on 11th Ave, at the intersection of Victoria St/11th Ave, at the intersection of Spring
Ridge Dr/Victoria St, and at the mid-block crossing on Spring Ridge Dr. All buildings will contain fire
sprinkler systems.
Solid Waste:
Individual totes for each unit are planned for this development. The totes will be rolled to Arbor Way
on pick-up day.
Snow Storage:
Snow will be plowed to various landscape areas and landscape islands – please see civil sheet C3.0 for
snow storage locations.
Traffic Impact Study:
The Traffic Impact Study (TIS) for the Blackwood Groves Subdivision accounted for the 30 residential
units proposed with this development. This TIS is included in the documents folder of this application.
V. SCHEDULE
This project intends to begin construction as soon as site plan approval is received and intends to
break ground in May/June 2025 in order to complete the project in late 2025/early 2026.
VI. Pre-Application Meeting
The pre-application meeting was conducted on July 18, 2024. Attendees of this meeting included:
Alicia Paz-Soils, Susana Montana, Scott Mueller, and Jacob Doesschate from the City of Bozeman as
well as Matt Hausauer from the design team.