F.1 Review and Recommendation Regarding the Impact Fee Capital Improvement Plan for Fiscal
THE COMMUNITY DEVELOPMENT BOARD OF BOZEMAN, MONTANA
CDB AGENDA
Monday, October 20, 2025
General information about the Community Development Board is available in our Laserfiche
repository.
If you are interested in commenting in writing on items on the agenda please send an email to
comments@bozeman.net or by visiting the Public Comment Page prior to 12:00pm on the day of the
meeting. At the direction of the City Commission, anonymous public comments are not distributed to
the Board or staff.
Public comments will also be accepted in-person and through video conference during the appropriate
agenda items.
As always, the meeting will be streamed through the Commission's video page and available in the
City on cable channel 190.
For more information please contact Chris Saunders, csaunders@bozeman.net
This meeting will be held both in-person and also using an online video conferencing system. You
can join this meeting:
Via Video Conference:
Click the Register link, enter the required information, and click submit.
Click Join Now to enter the meeting.
Via Phone: This is for listening only if you cannot watch the stream, channel 190, or attend in-
person
United States Toll
+1 346 248 7799
Access code: 954 6079 2484
Approve
1
Years 2027-2031 for Water, Wastewater, Transportation, and Fire/EMS Impact
Fees(Saunders)
G. Special Presentations
H. Action Items
H.1 Work Session in Preparation for Upcoming Public Hearings and Review Process of the
Unified Development Code Update, application 21381(Saunders)
I. Public Comments on Non-agenda Items Falling within the Purview and Jurisdiction of the Board
J. FYI/Discussions
J.1 Upcoming Items for the November 3, 2025, Community Development Board
Meeting(Saunders)
K. Adjournment
This is the time to comment on any non-agenda matter falling within the scope of the Community
Development Board. There will also be time in conjunction with each agenda item for public
comment relating to that item but you may only speak once per topic.
Please note, the Community Development Board cannot take action on any item which does not
appear on the agenda. All persons addressing the Community Development Board shall speak in a
civil and courteous manner and members of the audience shall be respectful of others. Please
state your name, and state whether you are a resident of the city or a property owner within the
city in an audible tone of voice for the record and limit your comments to three minutes.
General public comments to the Board can be found in their Laserfiche repository folder.
This board generally meets the first and third Monday of the month from 6:00 pm to 8:00 pm.
City Board meetings are open to all members of the public. If you have a disability that requires
assistance, please contact our ADA Coordinator, David Arnado, at 406.582.3232.
2
Memorandum
REPORT TO:Community Development Board
FROM:Trenton Ruffalo
SUBJECT:Approval of Minutes
MEETING DATE:October 20, 2025
AGENDA ITEM TYPE:Minutes
RECOMMENDATION:Approve
STRATEGIC PLAN:1.1 Outreach: Continue to strengthen and innovate in how we deliver
information to the community and our partners.
BACKGROUND:None
UNRESOLVED ISSUES:None
ALTERNATIVES:Approve with corrections
FISCAL EFFECTS:None
Attachments:
100625 CDB Minutes.pdf
Report compiled on: October 16, 2025
3
Bozeman Community Development Board Meeting Minutes, October 6, 2025
Page 1 of 4
THE COMMUNITY DEVELOPMENT BOARD MEETING OF BOZEMAN, MONTANA
MINUTES
OCTOBER 6, 2025
General information about the Community Development Board is available in our Laserfiche repository.
A) 00:06:24 Call to Order - 6:00 pm
Present: Jennifer Madgic, Ben Lloyd, Hap Happel, Chris Egnatz, Jason Delmue
Absent: None
Excused: Mark Egge, Courtney Johnson
B) 00:07:03 Disclosures
C) 00:07:10 Changes to the Agenda
D) 00:07:14 Approval of Minutes
D.1 Approval of Minutes.
090825 CDB Minutes.pdf
00:07:32 Motion to approve
Hap Happel: Motion
Jennifer Madgic: 2nd
00:07:58 Vote on the Motion to approve The Motion carried 5 - 0.
Approve:
Jennifer Madgic
Ben Lloyd
Hap Happel
Chris Egnatz
Jason Delmue
4
Bozeman Community Development Board Meeting Minutes, October 6, 2025
Page 2 of 4
Disapprove:
None
E) 00:08:03 Consent Items
E.1 00:08:07 SRX II Subsequent Minor Subdivision Preliminary Plat application to
further subdivide 5 lots in Minor Subdivision 494 to create 3 buildable lots, 1 restricted
development lot, and road right-of-way extensions. The subdivision is proposed on
35.06 acres and is zoned B-2M (Community Business District Mixed) and REMU
(Residential Emphasis Mixed use). Generally located northeast of the corner of West
Graf Street and South 19th Avenue, Application 24112 (Quasi-Judicial)
24112 Staff Report.pdf
00:09:22 Motion to approve Having reviewed and considered the application materials, public
comment, and all the information presented, I hereby adopt the findings presented in the staff report
for application 24112 and move for the Community Development Board in its capacity as the Planning
Board to recommend approval of the subdivision with conditions and subject to all applicable code
provisions.
Hap Happel: Motion
Jennifer Madgic: 2nd
00:10:11 Daniel Garber responds to Board's questions
00:12:13 Vote on the Motion to approve Having reviewed and considered the application materials,
public comment, and all the information presented, I hereby adopt the findings presented in the staff
report for application 24112 and move for the Community Development Board in its capacity as the
Planning Board to recommend approval of the subdivision with conditions and subject to all applicable
code provisions.
The Motion carried 5 - 0.
Approve:
Jennifer Madgic
Ben Lloyd
Hap Happel
Chris Egnatz
Jason Delmue
Disapprove:
None
E.2 00:12:33 Hidden Creek Minor Subdivision Preliminary Plat application to
subdivide one lot into four lots for civic and residential uses. The subdivision is proposed
on a 9.82 acre tract and is zoned R-4 (Residential High Density District). Currently
5
Bozeman Community Development Board Meeting Minutes, October 6, 2025
Page 3 of 4
addressed at 1221 West Durston Road, the purpose of this subdivision application is to
facilitate a future affordable housing development on the northern portion of the
County owned tract. Application 24533 (Quasi-Judicial)
24533 Staff Report.pdf
00:13:44 Motion to approve Having reviewed and considered the application materials, public
comment, and all the information presented, I hereby adopt the findings presented in the staff report
for application 24533 and move for the Community Development Board in its capacity as the Planning
Board to recommend approval of the subdivision with conditions and subject to all applicable code
provisions.
Hap Happel: Motion
Jennifer Madgic: 2nd
00:14:00 Daniel Garber reponds to Board's questions
00:15:42 Cordell Poole answers the Board's questions.
00:21:33 Vote on the Motion to approve Having reviewed and considered the application materials,
public comment, and all the information presented, I hereby adopt the findings presented in the staff
report for application 24533 and move for the Community Development Board in its capacity as the
Planning Board to recommend approval of the subdivision with conditions and subject to all applicable
code provisions. The Motion carried 4 - 1.
Approve:
Jennifer Madgic
Ben Lloyd
Hap Happel
Jason Delmue
Disapprove:
Chris Egnatz
F) 00:22:07 Action Items
F.1 00:22:13 Bozeman Community Plan Technical Compliance Update Public Hearing
to Consider an Updated Text and Future Land Use Map for the Bozeman Community
Plan to Conform to State Law Changes and Update Data and Document References,
Application 23333
23333 BCPTCU CDB Staff Report 10-1-2025.pdf
23333 BCPTCU Recommended Revisions 9-30-2025.pdf
00:22:27 Chris Saunders presents to the board
01:09:57 Motion to adopt Having reviewed and considered the submitted materials, public comment,
and all information presented, I hereby move to adopt the findings presented in the staff report and
6
Bozeman Community Development Board Meeting Minutes, October 6, 2025
Page 4 of 4
recommend the City Commission approve the Bozeman Community Plan Technical Compliance Update
document and map with revisions as recommended by staff, application 23333.
Hap Happel: Motion
Jennifer Madgic: 2nd
01:18:00 Vote on the Motion to adopt Having reviewed and considered the submitted materials, public
comment, and all information presented, I hereby move to adopt the findings presented in the staff
report and recommend the City Commission approve the Bozeman Community Plan Technical
Compliance Update document and map with revisions as recommended by staff, application 23333. The
Motion carried 5 - 0.
Approve:
Jennifer Madgic
Ben Lloyd
Hap Happel
Chris Egnatz
Jason Delmue
Disapprove:
None
G) 01:18:17 Public Comments on Non-agenda Items Falling within the Purview and
Jurisdiction of the Board
H) 01:18:58 FYI/Discussions
H.1 01:19:02 Upcoming Items for the Oct 20, 2025, Community Development Board
Meeting
I) 01:33:03 Adjournment
This board generally meets the first and third Monday of the month from 6:00 pm to 8:00 pm.
7
Memorandum
REPORT TO:Community Development Board
FROM:Kaitlin Johnson, Budget Manager
Chris Saunders, Community Development Manager
Erin George, Community Development Director
SUBJECT:Review and Recommendation Regarding the Impact Fee Capital
Improvement Plan for Fiscal Years 2027-2031 for Water, Wastewater,
Transportation, and Fire/EMS Impact Fees
MEETING DATE:October 20, 2025
AGENDA ITEM TYPE:Plan/Report/Study
RECOMMENDATION:Recommend approval of the proposed capital improvement plan for impact
fees.
STRATEGIC PLAN:7.5. Funding and Delivery of City Services: Use equitable and sustainable
sources of funding for appropriate City services, and deliver them in a lean
and efficient manner.
BACKGROUND:The State of Montana authorizes municipalities to require payment of
impact fees by development to help offset the costs of capital service
expansion needed by the new development. Standards for fee calculations
are established and the types of fees charged are limited to those authorized
by the State. The City applies impact fees for four service types: water,
wastewater, transportation, and Fire/Emergency Medical Services.
One of the state requirements is the preparation of a capital improvement
plan (CIP) that directs the expenditure of the fees. The state also requires an
advisory committee to review and make recommendations regarding impact
fees which also includes recommendations on the CIP. The City Commission
has designated the Community Development Board as the impact fee
advisory committee. The City's charter requires the CIP to be reviewed
annually, and to be presented to the City Commission not later than
December 15th of each calendar year.
The Finance Department has worked with the other relevant departments to
prepare an updated CIP for consideration by the Board prior to being
presented to the City Commission. The staff has reviewed the infrastructure
planning documents, purposes of impact fees, available and expected
funding, identified appropriate projects that will expand service capacity to
support new development, identified estimated costs for individual projects,
and prepared an fee specific list of projects. The CIP identifies the year(s) of
8
work scheduled and amount expected for each project. The annual review of
the CIP enables the estimated costs to be refined as project design proceeds.
The CIP coordinates total funding across the entire City financial system.
Many projects are funded by multiple sources of revenue and the CIP
describes those interrelationships. The draft document is attached to this
cover memo. All four of the fees are included within the attached
document.
The CIP does not authorize construction. It is a financial planning tool. Before
beginning construction, the City must finalize engineering design and plans,
budget for expenditure of funds, follow the state required notice and bidding
process or other applicable procurement requirements, and have contracts
approved by the City Commission. No public hearing is required for review of
the CIP by the advisory board.
UNRESOLVED ISSUES:No unresolved issues are known at this time.
ALTERNATIVES:As identified in discussion by the City Commission.
FISCAL EFFECTS:No funds are expended by this action. The CIP assists the City administration
in preparing the annual budget.
Attachments:
Draft Proposed FY27-31 CIP_Impact Fee Funds.pdf
Report compiled on: October 16, 2025
9
Draft FY27-31 Proposed Capital Improvement Plan
Impact Fee Funds
Table of Contents
CIP Criteria Tables - Estimate Class & Operating Impact . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3
Street Impact Fee . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
Wastewater Impact Fee . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .13
Water Impact Fee . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .27
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 1 10
Page Intentionally Left Blank
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 2 11
CIP Criteria Tables - Estimate Class & Operating Impact
Cost estimates are evaluated based on the following definitions and criteria:
Estimate Class Purpose
Project Definition Level
Expressed as % of completion
Cost Estimate Range
Typical variation in high & low range
Class 5 Concept or Feasibility 0% to 2%+ 100% / -50%
Class 4 Preliminary Engineering 1% to 15%+ 50% / -30%
Class 3 Semi-Detailed (30%-60% Design)10% to 40%+ 30% / -20%
Class 2 Detailed (60%-100% Design)30% to 75%+ 20% / -15%
Class 1 Final (100% Design/Bid Opening)65% to 100%+ 10% / -10%
N/A Not Applicable
Estimated annual impact on operating costs to maintain the facilities are evaluated based on the following definitions and criteria:
Impact Definition
Positive The project will result in annual operating cost savings or generate additional revenue.
None The project will not result in additional annual operating expenditures.
Negligible The project will increase annual operating expenditures by less than $10k.
Minimal The project will increase annual operating expenditures by more than $10k but less than $50k.
Moderate The project will increase annual operating expenditures by more than $50k but less than $100k.
High The project will increase annual operating expenditures by more than $100k.
Unknown The impacts of the project are unknown at this time.
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 3 12
Page Intentionally Left Blank
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 4 13
Street Impact Fee
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 5 14
Scheduled Projects for Street Impact Fee Fund
Page
Number
Project
Code Project Name FY27 FY28 FY29 FY30 FY31 5-Year Total
9 SIF191 Stucky: 19th to Fowler $ 3,225,600 $ 3,509,600 $ — $ — $ — $ 6,735,200
10 SIF114 Fowler Avenue Connection: Huffine to Oak 2,289,900 — — — — 2,289,900
11 SIF159 Oak: 27th to 19th Widening — — 3,250,000 — — 3,250,000
12 SIF164 S 3rd: Kagy to Graf — — — 1,768,000 8,800,000 10,568,000
Total $ 5,515,500 $ 3,509,600 $ 3,250,000 $ 1,768,000 $ 8,800,000 $ 22,843,100
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 6 15
Unscheduled Projects for Street Impact Fee Fund
SIF193 Fowler: Cattail to E Valley
Center
$ 12,958,500 This project will complete construction of this section of Fowler to City standards
with curb and gutter as well as sidewalks/pathways and street lighting. This
project is identified in the 2017 Transportation Master Plan as MSN-11. This
project is unscheduled due to lack of funding.
SIF149 Babcock: 11th to 15th 3,531,200 This project will improve Babcock from 11th to 15th. This project increases
capacity directly with the incorporation of a left turn lane, bike lanes, and
sidewalks. A payback district or Special Improvement District may be created to
leverage other stakeholders. Design is planned to align with design work on the
Babcock project between 15th-19th. Right-of-way acquisition and construction
have been unscheduled due to funding constraints. This project is identified in
the 2017 Transportation Master Plan as CMSN-9 and is unscheduled in order to
consider a right-sized scope and prioritize higher needs within the fund.
SIF156 Highland/Kagy Intersection
Improvement
3,260,000 This project will upgrade the intersection of Highland and Kagy. An Intersection
Control Evaluation will be performed in the pre-design phase to determine
feasibility of roundabout intersection control. This project is identified in the
2017 Transportation Master Plan as TSM-24 and is unscheduled due to lack of
funding.
SIF192 Fowler: Baxter to Cattail 2,300,000 This project will complete construction of this section of Fowler to City standards
with curb and gutter as well as sidewalks/pathways and street lighting. This
project is identified in the 2017 Transportation Master Plan as MSN-11 and is
unscheduled due to lack of funding.
SIF190 N 15th: Tschache to Baxter 1,222,500 This project will construct N 15th Avenue from the intersection with Tschache
Street to the intersection with Baxter Lane to a three-lane urban collector
standard. This project is identified in the 2017 Transportation Master Plan as
MSN-4 and is unscheduled due to lack of funding.
Total $ 23,272,200
Project
Code Project Name Amount Description
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 7 16
Map of Street Impact Fee Fund Infrastructure Projects
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 8 17
Stucky: 19th to Fowler (SIF191)
FUND DEPARTMENT PROJECT TYPE
Street Impact Fee Streets Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Negligible Class 5
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue $ 6,735,200
TOTAL SCHEDULED PROJECT COST $ 6,735,200
STRATEGIC PLAN
4.3 Strategic Infrastructure Choices
DESCRIPTION OF PROJECT
This project will complete construction of Stucky Road to a City collector standard with
curb and gutter as well as sidewalks/pathways and street lighting. Improvements to the
signal at S 19th will be included as necessary along with widening S 19th immediately
south of 19th/Stucky to complete the necessary additional traffic lane on 19th adjacent
to the existing church. This project is identified in the 2017 Transportation Master Plan
as MSN-16. Engineering: $2,060,600 | Right of Way: $1,500,000 | Construction:
$5,849,300 | Utilities: water utility included in water fund otherwise incidental to
project .
CONSEQUENCES OF DELAYING PROJECT
This project will support the higher capacity of vehicles, bicycles, and pedestrians anticipated due to substantial development immediately
south of Stucky Road. Delaying the project could compromise safety and level of service to the community.
CHANGES FROM PRIOR CIP
None
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Street Impact Fee $ — $ 3,225,600 $ 3,509,600 $ — $ — $ —
Arterial & Collector District $ — $ 405,000 $ 2,339,700 $ — $ — $ —
Total $ — $ 3,630,600 $ 5,849,300 $ — $ — $ —
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 9 18
Fowler Avenue Connection: Huffine to Oak (SIF114)
FUND DEPARTMENT PROJECT TYPE
Street Impact Fee Streets Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Moderate Class 2
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue $ 2,289,900
TOTAL SCHEDULED PROJECT COST $ 2,289,900
STRATEGIC PLAN
4.3 Strategic Infrastructure Choices
DESCRIPTION OF PROJECT
This project will complete Fowler Avenue from Huffine to Oak in four phases; North –
Oak to Durston (FY25 & FY26), Middle – Durston to Babcock (FY26 & FY27), South –
Babcock to Huffine (FY28), Intersection of Huffine and Fowler (Unscheduled). Project
scope approved by Bozeman City Commission includes one travel lane in each direction,
shared-use paths, traffic signalization at Babcock, and roundabout at Durston. This
project is identified in the Transportation Master Plan as MSN-13 and SPOT-39. The
total cost of this project including prior-year actuals and FY26 budget is anticipated to
be $22,596,000. Design is now at 90%. Engineering: funded in prior fiscal years |
Utilities: Sewer installation included in Wastewater Impact Fee fund | Right of Way:
$8,165,000 | Construction: $14,431,000.
CONSEQUENCES OF DELAYING PROJECT
Delaying project will result in significant traffic on surrounding streets which is expected to continue to increase over the next five years.
CHANGES FROM PRIOR CIP
Costs have been updated to reflect 60% design cost estimate.
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Street Impact Fee $ 9,551,800 $ 2,289,900 $ — $ — $ — $ —
Arterial & Collector District $ 401,700 $ 1,327,900 $ 3,771,500 $ — $ — $ —
Total $ 9,953,500 $ 3,617,800 $ 3,771,500 $ — $ — $ —
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 10 19
Oak: 27th to 19th Widening (SIF159)
FUND DEPARTMENT PROJECT TYPE
Street Impact Fee Streets Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Negligible Class 5
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue $ 3,250,000
TOTAL SCHEDULED PROJECT COST $ 3,250,000
STRATEGIC PLAN
4.3 Strategic Infrastructure Choices
DESCRIPTION OF PROJECT
This project will widen Oak St to a five-lane configuration that better aligns with the
adjacent sections of Oak St. It includes an eastbound lane reconfiguration and signal
upgrade at N 19th. These improvements will increase the intersection's capacity by
matching the lane configuration established in the 2016 Oak St 15th to 19th project.
The project will also address multimodal considerations by adding a shared-use path to
this corner of the intersection. It is identified in the 2017 Transportation Master Plan as
TSM-16 and MSN-9.
CONSEQUENCES OF DELAYING PROJECT
Increased delays and reduced level-of-service at the intersection as growth continues to add demand.
CHANGES FROM PRIOR CIP
None
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Street Impact Fee $ — $ — $ — $ 3,250,000 $ — $ —
Arterial & Collector District $ — $ — $ — $ 1,000,000 $ — $ —
Total $ — $ — $ — $ 4,250,000 $ — $ —
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 11 20
S 3rd: Kagy to Graf (SIF164)
FUND DEPARTMENT PROJECT TYPE
Street Impact Fee Streets Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Negligible Class 5
FUNDING SOURCE(S)AMOUNT
Grant(s) & Impact Fee Revenue $ 10,568,000
TOTAL SCHEDULED PROJECT COST $ 10,568,000
STRATEGIC PLAN
4.3 Strategic Infrastructure Choices
DESCRIPTION OF PROJECT
This project consists of reconstructing S 3rd from Graf to Kagy with a 2-lane urban
arterial roadway. Project scope includes one travel lane in each direction, sidewalks or
shared-use path on each side, curb and gutter, and street lighting. This project also
includes intersection improvements to address operational improvements for
multimodal traffic. An Intersection Control Evaluation will be performed in the pre-
design phase to determine feasibility of roundabout intersection control. This project is
identified in the 2017 Transportation Master Plan as MSN-3 and SPOT-36. The project is
anticipated to be selected by City Commission for prioritization of Urban Route funding
following College: 11th to 19th. If not selected for Urban Route funding, the project will
be delayed. Engineering: $1,768,000 | Construction: $8,800,000
CONSEQUENCES OF DELAYING PROJECT
Delays will prolong pedestrian safety challenges and allow pavement to deteriorate further.
CHANGES FROM PRIOR CIP
Moved from unscheduled as the project is anticipated to be prioritized and receive full funding via Urban Route.
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Street Impact Fee $ — $ — $ — $ — $ 1,768,000 $ 8,800,000
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 12 21
Wastewater Impact Fee
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 13 22
Scheduled Projects for Wastewater Impact Fee Fund
Page
Number
Project
Code Project Name FY27 FY28 FY29 FY30 FY31 5-Year Total
18 WW138 MSU Interceptor $ 2,318,000 $ — $ — $ — $ — $ 2,318,000
19 WW129 WRF Phase 1 Upgrades 1,800,000 — — — — 1,800,000
20 WWIF63 Gooch Hill Lift Station 1,625,000 9,464,500 — — — 11,089,500
21 WWIF20 N. Frontage Interceptor 830,000 — 4,891,600 — — 5,721,600
22 WWIF99 Wastewater Development Oversizing 200,000 500,000 400,000 400,000 750,000 2,250,000
23 WW139 4th Avenue, Babcock Street and Grand Avenue
Sewer Main Replacement 39,200 231,100 — — — 270,300
24 WWIF44 Water Reclamation Facility (WRF) Interceptor — 231,600 1,365,100 — — 1,596,700
25 WW140
North 9th Avenue, West Villard Street, and
South 9th Avenue Sewer Main Replacement — 48,000 282,700 — — 330,700
26 WWIF53 Cottonwood Road Sewer Capacity — — 327,000 2,022,000 — 2,349,000
Total $ 6,812,200 $ 10,475,200 $ 7,266,400 $ 2,422,000 $ 750,000 $ 27,725,800
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 14 23
Unscheduled Projects for Wastewater Impact Fee Fund
WW131 Water Reclamation Facility
(WRF) Base Hydraulic
Phase 2
$ 16,220,000 This project will implement hydraulic capacity improvements for the existing
treatment processes employed at the Water Reclamation Facility (WRF), which
are necessary to meet the twenty-year planning horizon. These improvements
will be the second and final phase of a project to upgrade the WRF average daily
flow capacity to 14.6 million gallons per day (mg/d) from the current capacity of
8.5 mg/d, as identified in the 2022 WRF Facilities Plan. The 2022 WRF Facilities
Plan also identifies necessary improvements to existing processes to increase the
base hydraulic capacity to 14.6 mg/d. A phased approach is required, as some
process elements currently have more available capacity than others. Base
hydraulic capacity improvements are intended to maintain the WRF's current
performance levels for treated effluents and are not designed to further reduce
effluent nutrient (nitrogen and phosphorus) concentrations. Phase Two base
hydraulic capacity improvements include the construction of two new secondary
clarifiers, an upgrade of the existing bioreactor number one by retrofitting to a
five-stage Barden Pho process, and the addition of one aeration blower.
WWIF48 Hidden Valley Lift Station 7,000,000 This project will design and construct the Hidden Valley Lift Station and Force
Main as well as add accommodating pumps to the Davis Lane Lift Station. Exact
timing is difficult to estimate, but it is anticipated this new lift station will be
needed in roughly 5-10 years as development in the northwest corner of the
community continues. This project will conform to the City's 2015 Wastewater
Collection Facilities Plan Update.
WWIF60 Water Reclamation Facility
(WRF) Screw Press No. 3
Improvement
2,730,000 This project will install new screw press number three at the Water Reclamation
Facility to increase solids processing capacity. This capital improvement will also
require an expansion of the solids handling building, as defined in the 2023
Water Reclamation Facilities Plan. Solids are a final waste product from the
Water Reclamation Facility that are ultimately disposed at the Logan Landfill, but
the solids must be processed to EPA and landfill requirements prior to disposal at
the landfill.
Project
Code Project Name Amount Description
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 15 24
WWIF59 WRF Screw Press Upgrade 1,590,000 This project will increase solids processing capacity at the Water Reclamation
Facility by replacing existing screw press number one with a new, larger capacity
screw press of similar capacity as the unit installed during the 2022 solids
handling expansion. This capital improvement will require an expansion of the
solids handling building, as defined in the 2023 Water Reclamation Facilities
Plan. Solids are a final waste product from the Water Reclamation Facility that
are ultimately disposed at the Logan Landfill, but the solids must be processed to
EPA and landfill requirements prior to disposal at the landfill.
WWIF61 WRF Additional Peps Pump 900,000 This project entails the installation of additional primary effluent pump station
(peps) at the Wastewater Reclamation Facility (WRF) to provide necessary
pumping capacity to treat 14.6 million gallons per day. This improvement is
outlined in the 2023 Water Reclamation Facilities Plan.
WWIF62 WRF Additional Headworks
Screen
820,000 A headworks screen is the first treatment step at the Wastewater Reclamation
Facility (WRF), which functions to remove large materials from wastewater that
is influent to the plant. This project includes installation of an additional
headworks screen as loading increases. Adaptive planning necessary to
determine year required per the 2023 Water Reclamation Facilities Plan.
Total $ 29,260,000
Project
Code Project Name Amount Description
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 16 25
Map of Wastewater Impact Fee Fund Infrastructure Projects
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 17 26
MSU Interceptor (WW138)
FUND DEPARTMENT PROJECT TYPE
Wastewater Impact Fee Wastewater Operations Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Positive Class 4
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue $ 2,318,000
TOTAL SCHEDULED PROJECT COST $ 2,318,000
STRATEGIC PLAN
4. A Well-Planned City
DESCRIPTION OF PROJECT
This project includes both the replacement and upsizing of approximately 10,250 feet of
existing sewer main, providing the necessary improvements to increase system capacity
to meet future build-out conditions while decreasing overall risk associated with the
aging of critical infrastructure. A critical section of existing sewer main begins on Kagy
Blvd and Hoffman Drive as ten-inch diameter asbestos concrete pipe and continues to
run north through Mason, Wilson Ave, College, 4th Avenue, and finally ending on 6th
Ave.
Once the sewer main reaches Olive Street, the diameter increases to 18-inches in size. Portions of this existing main have been identified as
high-risk given both the condition and age of the existing asset. In addition, the City’s hydraulic model has shown that several segments of main
are near hydraulic capacity during wet weather modeling scenarios. The project was recommended to occur within the City’s five-year planning
horizon and is in conformance with the City’s Wastewater Collection Facility Master Plan. Engineering is scheduled in FY26 and construction in
FY27.
CONSEQUENCES OF DELAYING PROJECT
Delay would limit development immediately south of Kagy and east of 11th Ave and could result in an inability to serve new projects from MSU.
CHANGES FROM PRIOR CIP
None
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Wastewater Impact Fee $ 393,300 $ 2,318,000 $ — $ — $ — $ —
Wastewater Fund $ 443,500 $ 2,613,900 $ — $ — $ — $ —
Total $ 836,800 $ 4,931,900 $ — $ — $ — $ —
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 18 27
WRF Phase 1 Upgrades (WW129)
FUND DEPARTMENT PROJECT TYPE
Wastewater Impact Fee Wastewater Plant Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Moderate Class 4
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue & Rate Revenue $ 1,800,000
TOTAL SCHEDULED PROJECT COST $ 1,800,000
STRATEGIC PLAN
2.2 Infrastructure Investments
DESCRIPTION OF PROJECT
This project will implement hydraulic capacity improvements for the existing treatment
processes employed at the Water Reclamation Facility (WRF), which are necessary to
meet the twenty-year planning horizon of the facility. The targeted twenty-year
hydraulic capacity is 14.6 million gallons per day (mg/d) as identified in the 2022 WRF
Facilities Plan, while the existing average daily capacity is 8.5 mg/d.
The 2022 WRF Facilities Plan also identifies necessary improvements to existing processes to increase the base hydraulic capacity to 14.6 mg/d
as well as when these improvements are required. A phased approach is required, as some process elements currently have more available
capacity than others. Base hydraulic capacity improvements are intended to maintain the WRF's current performance levels for treated
effluents and are not designed to further reduce effluent nutrient (nitrogen and phosphorus) concentrations. Phase One base hydraulic capacity
improvements include the construction of a fourth anaerobic digester, implementation of the InDense™ sludge densification process to
enhance and optimize existing bioreactor nutrient removal, and replacement of existing solids piping restricted by struvite.
CONSEQUENCES OF DELAYING PROJECT
Delay would limit growth of the city until WRF capacity is increased.
CHANGES FROM PRIOR CIP
Added $1,800,000 to existing budget pursuant to predesign phase cost estimates for selected alternative.
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Wastewater Impact Fee $ 1,607,600 $ 1,800,000 $ — $ — $ — $ —
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 19 28
Gooch Hill Lift Station (WWIF63)
FUND DEPARTMENT PROJECT TYPE
Wastewater Impact Fee Wastewater Operations Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Moderate Class 4
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue $ 11,089,500
TOTAL SCHEDULED PROJECT COST $ 11,089,500
STRATEGIC PLAN
4. A Well-Planned City
DESCRIPTION OF PROJECT
The Gooch Hill Lift Station is defined in the City's Wastewater Collection Facilities Plan
to serve the northwestern and western edge of the City. Two potential developments
are looking to annex into the City; one property is 160 acres at the northwest corner of
Baxter and Cottonwood and the second is approximately 430 acres north of
Cottonwood and west of Harper Pucket Road. Both properties need the Gooch Hill Lift
Station in order to provide sanitary sewer service to the area. Both developers will need
to provide up-front capital funding in addition to potential funding from the City's
impact fee program with potential reimbursement via impact fee credits. The proposed
costs provide one of two phases to construct the Gooch Hill Lift Station to reduce up-
front costs. The Gooch Hill Lift Station will also open sanitary sewer service to many
properties along the western boundary of the City.
CONSEQUENCES OF DELAYING PROJECT
Delay would result in stunted growth within the service area of the Gooch Hill Lift Station along the western portion of the City until sewer
infrastructure is constructed to serve the area.
CHANGES FROM PRIOR CIP
None
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Wastewater Impact Fee $ 1,500,000 $ 1,625,000 $ 9,464,500 $ — $ — $ —
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 20 29
N. Frontage Interceptor (WWIF20)
FUND DEPARTMENT PROJECT TYPE
Wastewater Impact Fee Wastewater Operations Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Negligible Class 4
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue $ 5,721,600
TOTAL SCHEDULED PROJECT COST $ 5,721,600
STRATEGIC PLAN
4. A Well-Planned City
DESCRIPTION OF PROJECT
This project will either parallel or replace and upsize certain portions of the sanitary
sewer along the 11,500-foot length of the existing North Frontage Road Interceptor
between Springhill Road and Bridger Drive, which supports large portions of the City’s
southeast and eastern sewersheds. This project will provide the necessary
improvements needed to increase water system capacity to meet future build-out
conditions while decreasing overall risk along the interceptor corridor.
Portions of the existing interceptor have been shown to have an increased risk of failure due to the age and condition of the asset, and other
segments have been identified in the City’s hydraulic model to be near hydraulic capacity during wet weather modeling scenarios. The first
phase of the project is the replacement of existing parallel trunk sewer, including the upsizing of the parallel interceptor main. The second
phase is the installation of a new parallel interceptor main along portions of the existing interceptor which only have a single segment of main.
Lastly, the existing interceptor main that is not mitigated as part of the project will be inspected for current condition and either replaced or
rehabilitated at a later date in order to fully utilize existing City assets through their life cycles. Engineering is scheduled in FY27 and
construction in FY29, and the project will conform to the City’s Wastewater Collection Facility Master plan.
CONSEQUENCES OF DELAYING PROJECT
Delay would risk reaching capacity and limiting growth until an upgrade is completed.
CHANGES FROM PRIOR CIP
None
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Wastewater Impact Fee $ — $ 830,000 $ — $ 4,891,600 $ — $ —
Wastewater Fund $ — $ 304,000 $ — $ 1,791,700 $ — $ —
Total $ — $ 1,134,000 $ — $ 6,683,300 $ — $ —
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 21 30
Wastewater Development Oversizing (WWIF99)
FUND DEPARTMENT PROJECT TYPE
Wastewater Impact Fee Wastewater Operations Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Minimal Class 5
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue $ 2,250,000
TOTAL SCHEDULED PROJECT COST $ 2,250,000
STRATEGIC PLAN
4. A Well-Planned City
DESCRIPTION OF PROJECT
As developers construct their projects, the City asks that sanitary sewer mains are oversized, consistent with the City’s Wastewater
Collection Facilities Master Plan. The developers are responsible for the minimum pipe size required by their development, and the
City reimburses developers for oversized pipes that will accommodate future growth through the wastewater impact fee program.
This is a way to proactively construct the sanitary sewer system to accommodate growth such that pipes aren’t constantly excavated
and replaced with larger mains each time a new development is constructed. Pipe oversizing also serves as a public/private
partnership and provides a highly cost-efficient means of building sewer mains to accommodate future growth.
CONSEQUENCES OF DELAYING PROJECT
Delay would result in higher future costs, as it is much more efficient to pay for pipe oversizing at initial construction than to increase
the pipe size at a later date and with significant disruption to the public.
CHANGES FROM PRIOR CIP
Added rough estimates of oversizing costs in fiscal years 29-31. Projecting pipe oversizing costs beyond two years is challenging
because development applications are not typically submitted that far in advance.
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Wastewater Impact Fee $ 70,000 $ 200,000 $ 500,000 $ 400,000 $ 400,000 $ 750,000
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 22 31
4th Avenue, Babcock Street and Grand Avenue Sewer Main Replacement (WW139)
FUND DEPARTMENT PROJECT TYPE
Wastewater Impact Fee Wastewater Operations Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Positive Class 4
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue $ 270,300
TOTAL SCHEDULED PROJECT COST $ 270,300
STRATEGIC PLAN
4. A Well-Planned City
DESCRIPTION OF PROJECT
This project includes both the replacement and upsizing of approximately 1,300 feet of
existing eight-inch sanitary sewer main along 4th Avenue, Babcock Street, and Grand
Avenue. The project will provide the necessary improvements to increase system
capacity to meet future build-out conditions while decreasing overall risk associated
with aging infrastructure. This critical section of eight-inch vitrified clay pipe has been
identified as high-risk given both its condition and age, and the City’s hydraulic model
has shown several segments to be near hydraulic capacity during wet weather modeling
scenarios. It has been identified for replacement and upsizing per the City’s Wastewater
Collection Facilities Plan, and was recommended to occur within the City’s 5-year short-
term planning horizon per the City’s Wastewater Collection Facility Master Plan Update.
CONSEQUENCES OF DELAYING PROJECT
Delay will limit development served by these pipes and could lead to sewage backups, impacting customers.
CHANGES FROM PRIOR CIP
None
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Wastewater Impact Fee $ — $ 39,200 $ 231,100 $ — $ — $ —
Wastewater Fund $ — $ 69,700 $ 410,900 $ — $ — $ —
Total $ — $ 108,900 $ 642,000 $ — $ — $ —
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 23 32
Water Reclamation Facility (WRF) Interceptor (WWIF44)
FUND DEPARTMENT PROJECT TYPE
Wastewater Impact Fee Wastewater Plant Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Negligible Class 4
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue $ 1,596,700
TOTAL SCHEDULED PROJECT COST $ 1,596,700
STRATEGIC PLAN
4. A Well-Planned City
DESCRIPTION OF PROJECT
This project will install approximately 1,200 feet of forty two-inch trunk main along
Springhill Road from the Wastewater Reclamation Facility (WRF) to North Frontage
Road, with a common hydraulic control structure to be included at the interface of the
WRF and interceptor tie-in location. This project will provide necessary improvements
needed to increase water system capacity to meet future build-out conditions, while
decreasing overall risk. An existing thirty-inch interceptor currently supports the entire
city and is the primary drainage pathway for all wastewater flow into the WRF. This
interceptor has been identified in the City’s hydraulic model to be approaching the
hydraulic capacity of the pipe, specifically during wet weather modeling scenarios.
Engineering is scheduled in FY28 and construction in FY29, and the project will conform
to the City’s Wastewater Collection Facility Master Plan Update.
CONSEQUENCES OF DELAYING PROJECT
Delay would limit growth in the entire community.
CHANGES FROM PRIOR CIP
None
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Wastewater Impact Fee $ — $ — $ 231,600 $ 1,365,100 $ — $ —
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 24 33
North 9th Avenue, West Villard Street, and South 9th Avenue Sewer Main Replacement (WW140)
FUND DEPARTMENT PROJECT TYPE
Wastewater Impact Fee Wastewater Operations Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Positive Class 4
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue $ 330,700
TOTAL SCHEDULED PROJECT COST $ 330,700
STRATEGIC PLAN
4. A Well-Planned City
DESCRIPTION OF PROJECT
This project includes either replacement or upsizing of approximately 3,000 feet of
critical sewer main beginning on South 9th Street and continuing north through
Midtown, ultimately ending at Durston Ave. The project will provide the necessary
improvements to increase system capacity to meet future build-out conditions, while
decreasing overall risk associated with aging critical infrastructure. The existing vitrified
clay pipe has been identified as high-risk given both the condition and age of the asset,
and the City’s hydraulic model has shown several segments of main to be near hydraulic
capacity during wet weather modeling scenarios. The project was recommended to
occur within the City’s 5-year short-term planning horizon and is in conformance with
the City’s Wastewater Collection Facility Plan Update. Engineering is scheduled in FY28
and construction in FY29.
CONSEQUENCES OF DELAYING PROJECT
Delaying will limit development served by these pipes and could lead to potential sewage backups impacting sewer customers.
CHANGES FROM PRIOR CIP
None
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Wastewater Impact Fee $ — $ — $ 48,000 $ 282,700 $ — $ —
Wastewater Fund $ — $ — $ 321,000 $ 1,891,900 $ — $ —
Total $ — $ — $ 369,000 $ 2,174,600 $ — $ —
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 25 34
Cottonwood Road Sewer Capacity (WWIF53)
FUND DEPARTMENT PROJECT TYPE
Wastewater Impact Fee Wastewater Operations Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Negligible Class 4
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue $ 2,349,000
TOTAL SCHEDULED PROJECT COST $ 2,349,000
STRATEGIC PLAN
4. A Well-Planned City
DESCRIPTION OF PROJECT
This project will provide a missing link of sanitary sewer in order to allow development
south of Huffine. It is identified in the Wastewater Collection Facility Plan Update.
CONSEQUENCES OF DELAYING PROJECT
Delay would limit growth south of Huffine in the far southwest part of the community, and a portion of the Davis-Lane Lift Station asset would
be stranded.
CHANGES FROM PRIOR CIP
None
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Wastewater Impact Fee $ — $ — $ — $ 327,000 $ 2,022,000 $ —
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 26 35
Water Impact Fee
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 27 36
Scheduled Projects for Water Impact Fee Fund
Page
Number
Project
Code Project Name FY27 FY28 FY29 FY30 FY31 5-Year Total
31 WIF32
Municipal Groundwater Public Water Supply &
Mitigation System Infrastructure $ 1,000,000 $ 11,500,000 $ — $ — $ — $ 12,500,000
32 WIF99 Water Development Oversizing 720,000 305,000 400,000 655,000 500,000 2,580,000
33 WIF68 Stucky/S 27th Water Improvements 265,700 1,842,500 — — — 2,108,200
34 WIF60 West Sourdough Reservoir #1 — — 4,015,000 — — 4,015,000
35 WIF59
Western Transmission Main / New South
Pressure Zone — — 1,350,000 16,400,000 — 17,750,000
36 WIF72 Sourdough Bypass Expansion — — — — 110,000 110,000
Total $ 1,985,700 $ 13,647,500 $ 5,765,000 $ 17,055,000 $ 610,000 $ 39,063,200
Unscheduled Projects for Water Impact Fee Fund
WIF59 Western Transmission
Main / New South Pressure
Zone
$ 40,000,000 This project is identified as the Western Transmission Main in the 2017 water facility plan.
Funding in the five-year plan would be for Phase 1 design and construction, with
subsequent phases funded outside of the five-year window totaling $40 million. Phase 1
consists of a new transmission main running on the hydraulic grade line from the
Sourdough Water Treatment Plant tank to connect to the southwestern edge of the
existing distribution network (S. 19th and Graf Street) to serve future anticipated growth.
Project scope will be further defined with the ongoing South Pressure Zone Pre-Design and
Water Treatment Plant Facility Plan project including identification of quantity and
location of hydraulic controls valves to connect the new pressure zone to the existing
system.
WIF63 Sourdough Membrane
WTP Expansion
28,840,000 This project consists of a new construction project to increase the capacity of the
Sourdough Water Treatment Plant to 36 million-gallons-per-day. The original plant was
constructed to a capacity of 22 million-gallons-per-day, with features that allow for
expansion of the plant. The need for this expansion project will be determined by future
availability of water rights and other water supply projects that may offset demand at the
facility.
Project
Code Project Name Amount Description
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 28 37
WIF60 West Sourdough Reservoir
#1
7,200,000 This project is identified as 5125 West Sourdough Reservoir 1 within the City's water
facility plan and consists of planning, design, and construction of a new five-million-gallon,
gravity-fed ground storage reservoir to the south/southwest of the city, which would tie
into the west water transmission main - phase 1 (WIF59) and serve the existing City water
distribution system. This project is identified as the next priority in the City's Water Facility
Master Plan. Budget in FY29 is for planning and design. Budget for construction totals $7.2
million and is currently budgeted in unscheduled.
WIF72 Sourdough Bypass
Expansion
1,250,000 The sourdough bypass flow control building is a hydraulic limitation in delivering water to
the city given the existing transmission main configurations. This project will expand the
hydraulic capacity of the bypass piping and flow control valve. This project is needed to
meet 2031 projected water demands, as determined by the Water Treatment Plant (WTP)
Facility Plan. Design is scheduled to be completed in FY31, with construction currently
unscheduled but planned for FY32.
WIF71 Sourdough Transmission
Main Phase 4 - Nash and
Sourdough Highspot
1,100,000 The project will eliminate a high spot on the existing thirty-inch CCP main near the corner
of Nash and Sourdough Road by replacing and lowering approximately 1000 linear feet of
the main, which limits the delivery of water from the Water Treatment Plant (WTP) to the
city. The project will need to be completed prior to the maximum day demand exceeding
17.6 MGD from the Sourdough WTP.
WIF66 Davis Lane Water
Improvement
240,000 This project consists of design and construction of a new 16-inch water main in Davis Lane
from Baxter Lane to Cattail Street per recommendations in the 2015 Water Facility Plan
(FP_1484). Given development occurring in the area, the water main defined in the Facility
Plan may be needed to support additional fire flow protection.
Total $ 78,630,000
Project
Code Project Name Amount Description
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 29 38
Map of Water Impact Fee Fund Infrastructure Projects
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 30 39
Municipal Groundwater Public Water Supply & Mitigation System Infrastructure (WIF32)
FUND DEPARTMENT PROJECT TYPE
Water Impact Fee Water Plant Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
High Class 4
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue $ 12,500,000
TOTAL SCHEDULED PROJECT COST $ 12,500,000
STRATEGIC PLAN
4.3 Strategic Infrastructure Choices
DESCRIPTION OF PROJECT
This project is contingent upon obtaining a municipal groundwater water right authorization from the Montana Department of
Natural Resources and Conservation (MT DNRC) and consists of, but is not limited to, the following major elements: obtaining land in
fee or easement necessary to construct and operate municipal well and aquifer storage or recharge infrastructure necessary to
complete the municipal water right authorization as approved by MT DNRC; Department of Environmental Quality approval and
construction of a municipal public water supply well and attendant infrastructure to connect, operate, and maintain the municipal
well as part of the City's overall municipal water supply system. Attendant infrastructure may include but is not limited to: water
disinfection and treatment processes, class 5 injection wells or infiltration basins for aquifer recharge, a building to house treatment
equipment, power, backup generator power, instrumentation and controls, site improvements, transmission main to tie
groundwater supply into the existing system, water storage, and hydraulic controls.
CONSEQUENCES OF DELAYING PROJECT
The City's unallocated water supply is being used up by new development. This project will help provide additional capacity for
growth in the 8 to 10-year timeframe. Given the possible duration for water rights permitting being 3 to 5 years, this work must be
advanced now to align with the timeframe for water supply needs.
CHANGES FROM PRIOR CIP
Increased FY28 funding to $11.5M per Class 4 estimate prepared for Cash In Lieu of Water Rights fee update study.
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Water Impact Fee $ — $ 1,000,000 $ 11,500,000 $ — $ — $ —
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 31 40
Water Development Oversizing (WIF99)
FUND DEPARTMENT PROJECT TYPE
Water Impact Fee Water Operations Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Minimal Class 5
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue $ 2,580,000
TOTAL SCHEDULED PROJECT COST $ 2,580,000
STRATEGIC PLAN
4. A Well-Planned City
DESCRIPTION OF PROJECT
This project consists of water main oversizing associated with the development projects consistent with the City’s Water Facility Plan
and the approved development plan. Public-private partnership for infrastructure construction allows for development to construct
the pipe infrastructure required of the development, while the City provides oversizing funding for future growth per the water
impact fee program. This is a highly cost-effective way of building infrastructure for future growth.
CONSEQUENCES OF DELAYING PROJECT
Without oversizing funding from the City’s Water Impact Fee program to match private development timeframe, future pipe size
increases will be much more expensive than oversizing the pipe at the original construction of the pipe, also allowing the full useful
life (80-120 years) of the pipe to be achieved before replacement with a larger capacity pipe.
CHANGES FROM PRIOR CIP
Added anticipated amounts to fiscal years 29 and 31. Values are placeholders as it is difficult to project oversizing costs associated
with development until the need arises, and actual values will depend on future development applications.
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Water Impact Fee $ 355,000 $ 720,000 $ 305,000 $ 400,000 $ 655,000 $ 500,000
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 32 41
Stucky/S 27th Water Improvements (WIF68)
FUND DEPARTMENT PROJECT TYPE
Water Impact Fee Water Operations Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
None Class 4
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue $ 2,108,200
TOTAL SCHEDULED PROJECT COST $ 2,108,200
STRATEGIC PLAN
4. A Well-Planned City
DESCRIPTION OF PROJECT
This project includes the design and construction of a new 16-inch water main in Stucky
Road from S 19th to Fowler Ave per recommendations in the Water Facility Plan
(FP_1386, FP_1372, FP_1371). The project is planned simultaneous to the Stucky: 19th
to Fowler (SIF191)Street Impact Fee project.
CONSEQUENCES OF DELAYING PROJECT
Delay will result in significantly higher cost to construct the water main as it will be required for future development. This project must occur
simultaneously with the construction of the Stucky Road Project to avoid a second construction impact on traffic on Stucky Road.
CHANGES FROM PRIOR CIP
None
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Water Impact Fee $ — $ 265,700 $ 1,842,500 $ — $ — $ —
Water Fund $ — $ 88,600 $ 614,200 $ — $ — $ —
Total $ — $ 354,300 $ 2,456,700 $ — $ — $ —
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 33 42
West Sourdough Reservoir #1 (WIF60)
FUND DEPARTMENT PROJECT TYPE
Water Impact Fee Water Plant Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Negligible Class 4
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue $ 4,015,000
TOTAL SCHEDULED PROJECT COST $ 4,015,000
STRATEGIC PLAN
6. A Sustainable Environment
DESCRIPTION OF PROJECT
This project is identified as 5125 West Sourdough Reservoir 1 within the City's water
facility plan and consists of planning, design, and construction of a new five-million-
gallon, gravity-fed ground storage reservoir to the south/southwest of the city, which
would tie into the west water transmission main - phase 1 (WIF59) and serve the
existing City water distribution system. This project is identified as the next priority in
the City's Water Facility Master Plan. Budget in FY29 is for planning and design. Budget
for construction totals $7.2 million and is currently budgeted in unscheduled.
CONSEQUENCES OF DELAYING PROJECT
Delay would result in limiting growth in the south and southwestern areas of the community.
CHANGES FROM PRIOR CIP
None
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Water Impact Fee $ — $ — $ — $ 4,015,000 $ — $ —
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 34 43
Western Transmission Main / New South Pressure Zone (WIF59)
FUND DEPARTMENT PROJECT TYPE
Water Impact Fee Water Operations Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Minimal Class 5
FUNDING SOURCE(S)AMOUNT
Impact Fee Revenue $ 17,750,000
TOTAL SCHEDULED PROJECT COST $ 17,750,000
STRATEGIC PLAN
4. A Well-Planned City
DESCRIPTION OF PROJECT
This project is identified as the Western Transmission Main in the 2017 water facility
plan. Funding in the five-year plan would be for Phase 1 design and construction, with
subsequent phases funded outside of the five-year window totaling $40 million. Phase 1
consists of a new transmission main running on the hydraulic grade line from the
Sourdough Water Treatment Plant tank to connect to the southwestern edge of the
existing distribution network (S. 19th and Graf Street) to serve future anticipated
growth. Project scope will be further defined with the ongoing South Pressure Zone Pre-
Design and Water Treatment Plant Facility Plan project including identification of
quantity and location of hydraulic controls valves to connect the new pressure zone to
the existing system.
CONSEQUENCES OF DELAYING PROJECT
Delay of this work will limit growth in the south and southwestern portions of the community outside the existing water pressure zones capable
of serving those areas.
CHANGES FROM PRIOR CIP
None
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Water Impact Fee $ — $ — $ — $ 1,350,000 $ 16,400,000 $ —
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 35 44
Sourdough Bypass Expansion (WIF72)
FUND DEPARTMENT PROJECT TYPE
Water Impact Fee Water Plant Infrastructure
OPERATING IMPACT COST ESTIMATE CLASS
Negligible Class 5
FUNDING SOURCE(S)AMOUNT
Rate Revenue & Impact Fee Revenue $ 110,000
TOTAL SCHEDULED PROJECT COST $ 110,000
STRATEGIC PLAN
2.2 Infrastructure Investments
DESCRIPTION OF PROJECT
The sourdough bypass flow control building is a hydraulic limitation in delivering water
to the city given the existing transmission main configurations. This project will expand
the hydraulic capacity of the bypass piping and flow control valve. This project is needed
to meet 2031 projected water demands, as determined by the Water Treatment Plant
(WTP) Facility Plan. Design is scheduled to be completed in FY31, with construction
currently unscheduled but planned for FY32.
CONSEQUENCES OF DELAYING PROJECT
Delay would limit the ability of the Sourdough WTP to meet increasing demand within the City.
CHANGES FROM PRIOR CIP
Moved design cost from Unscheduled into FY31. Funding source has been changed from rate revenue to impact fees as the project is capacity-
expanding. Previous project code was W125.
FUND FY26 ADOPTED FY27 FY28 FY29 FY30 FY31
Water Impact Fee $ — $ — $ — $ — $ — $ 110,000
Draft FY27-31 Proposed Capital Improvement Plan - Impact Fee Funds Page 36 45
Memorandum
REPORT TO:Community Development Board
FROM:Chris Saunders, Community Development Manager
Erin George, Community Development Director
SUBJECT:Work Session in Preparation for Upcoming Public Hearings and Review
Process of the Unified Development Code Update, application 21381
MEETING DATE:October 20, 2025
AGENDA ITEM TYPE:Community Development - Legislative
RECOMMENDATION:Receive information and expand understanding of proposed code language.
STRATEGIC PLAN:4.2 High Quality Urban Approach: Continue to support high-quality planning,
ranging from building design to neighborhood layouts, while pursuing urban
approaches to issues such as multimodal transportation, infill, density,
connected trails and parks, and walkable neighborhoods.
BACKGROUND:The City began the code update process in 2022. The project website,
Engage Bozeman [external link] contains public input results, information on
the project, and materials from the many public meetings and engagement
tools throughout the project; as well as the updated draft and map.
The City released the updated draft of Chapter 38, Unified Development
Code, for public review on Sept 19, 2025. This updated draft text and map
include revisions based on months of public input, five City Commission
worksessions considering the received public input and directing revisions,
and changed state laws.
The new draft text and map are available for public review. Summaries of
changes from the prior draft text and map are included on the Engage
Bozeman website under the Code Documents section.
Draft Chapter 38 text
Draft zoning map
As identified in the public notice [external PDF], the Community
Development Board will begin the public hearing on November 3rd and
continue the hearing to November 17th. This presentation will show where
to find the new materials, go over highlights of the changes, and outline the
public hearing and review process. This will assist the Board and public to
prepare for the public hearings.
46
UNRESOLVED ISSUES:None, as a work session no decision is required with this item.
ALTERNATIVES:None, no decision required with this item.
FISCAL EFFECTS:All funds for this project were previously budgeted.
Report compiled on: October 15, 2025
47
Memorandum
REPORT TO:Community Development Board
FROM:Chris Saunders, Community Development Manager
Erin George, Community Development Director
SUBJECT:Upcoming Items for the November 3, 2025, Community Development Board
Meeting
MEETING DATE:October 20, 2025
AGENDA ITEM TYPE:Citizen Advisory Board/Commission
RECOMMENDATION:Information only, no action required.
STRATEGIC PLAN:7.5. Funding and Delivery of City Services: Use equitable and sustainable
sources of funding for appropriate City services, and deliver them in a lean
and efficient manner.
BACKGROUND:The following items are presently scheduled for review at the November 3,
2025, Community Development Board meeting:
1. Public hearing for Application 21381, UDC Update to Chapter 38 Bozeman
Municipal Code, considered in role as Planning Commission.
UNRESOLVED ISSUES:None.
ALTERNATIVES:None.
FISCAL EFFECTS:No budgeted funds are expended with this item.