HomeMy WebLinkAbout015 Trip Generation Memo
To: City of Bozeman, Engineering Department
Attn: Candace Mastel, Transportation Demand Management Coordinator
From: SET Engineering
Re: Sundance Springs Preliminary Trip Generation Analysis Memorandum April 17, 2025
This memo is being provided to provide the City of Bozeman Engineering Staff with preliminary trip generation
values for the subject project based upon the Landscape Plan, Area Plans – West Bldg, and Area Plans – East Bldg
dated January 8th, 2025, provided by Miller Design/Build and included as Attachment A. As part of City’s site plan
approval process, SET Engineering is providing trip generation information in lieu of a formal traffic impact analysis
per engineering staff’s request. The conclusions outlined herein inform the need for further traffic impact analysis.
Time Periods and Trip Generation
The following trip generations values are determined for the purpose of this memo and are outlined in Attachment
B. Calculations are performed with the ITE TripGen Web-Based App, which utilizes trip generation rates derived
from the Institute of Transportation Engineers Trips Generation Manual, 11th Ed. (ITE, 11th Ed.). These values, as
well as entering and exiting values are shown in detail in Attachment C.
• Weekday Average Daily Trips are determined to be 331 Average Daily Trips (ADT).*
• Weekday AM Peak Hour of Adjacent Street Traffic is determined to be 26 trips.
• Weekday PM Peak Hour of Adjacent Street Traffic is determined to be 35 trips.
• Weekday AM Peak Hour of Generator is determined to be 40 trips.
• Weekday PM Peak Hour of Generator is determined to be 51 trips.
* ITE Trip Generation does not have data regarding Weekday Average Daily Trips for Health/Fitness Clubs. Therefore, an expansion factor of 7.3 was
applied to PM Peak Hour traffic data.
Internal Capture Rate
In mixed-use developments, traffic engineers need to assess the trips that originate and terminate internally by
other uses on the site. These trips reduce the overall trip generation produced and are termed internal capture
rates (ICR). National Cooperative Highway Research Program (NCHRP) publication 684 defines ICRs for AM Peak and
PM Peak periods, which are used for analysis of the subject project and highlighted in Attachment D.
Please contact SET Engineering directly with any questions regarding traffic analyses for the subject project.
Sincerely,
Jeff Pillus, P.E.
jeffp@setengineering.com
(970) 403-5088 ext. 700
Riley Shea
rileys@setengineering.com
(970) 403-5088 ext. 707
Attachment A: Landscape Plan and Building Plans
Attachment B: Generation Rates by Land Use
Attachment C: Trip Generation Summary
Attachment D: NCHRP 684 Internal Capture Rate
PACIFIC WILLOW BUSH
RUSSIAN SAGE BUSH
JAPANESE LILAC TREE
TATARIAN MAPLE
QUAKING ASPEN
LILAC - SCREENING
SM
WESTRETENTIONPOND
EAST RETENTIONPOND
SM
OPEN SPACE - LAWN(1,439 SF)
WEST B
U
I
L
D
I
I
N
G
ELEV: 5
0
3
8
'
ENTRAN
C
E
EAST BUILDIINGELEV: 5036'
279.48'
233.92'
LITTLE
H
O
R
S
E
R
O
A
DS. 3RD AVENUEEXISTING OPEN MEADOW
EXISTINGWALKING &BIKE PATH
PROPOSED WALKING &BIKE PATH CONNECTOR
STREET VISION TRIANGLEDESIGNED ACCORDING TO38.400.100 BMC
EXISTINGFIRE HYDRANT
POWERTRANSFORMER
POWER METER &SPRINKLER CONTROLS
PROPOSED WALKING &BIKE PATH CONNECTOR
SETBACK
10' - 0"SETBACK10' - 0"(E) DITCH
EXISTINGWALKING &BIKE PATH
SETBACK10' - 0"(E) WELL
IRRIGATIONMETER, STUB, AND BACKFLOWPREVENTER
ENCLOSED DUMPSTER AREA - SCREENED
ENTRANCE
S
E
T
B
A
C
K
5'
-
0
"
SETBAC
K
10' - 0"
50' WATER SETBACK
30' WATER SETBACK
DELINEATED WETLAND
MIDDLE CREEK DITCH
OUTDOOR PATIO
SNOW STORAGEU.G. WATER LINE
U.G. WATER LINE - SEE CIVIL PLAN
(E) TREE
(E) TREE
(E) TREE
(E) TREE
PROPOSED PARKING LOT ACESS BERTHSIDEWALKSIDEWALK SIDEWALK
FIRE APPARATUS TURN IN
SNOW STORAGEEXISTING OPEN MEADOWEXISTING OPEN MEADOWRIP-RAP BOULDER PERIMETER, TYP.
RIP-RAP BOULDER / FOLIAGE PERIMETER, TYP.
PROPERTY BOUNDARY
PROPERTY BOUNDARY
SIDEW
A
L
K
PLANTING AREAS= MIX OF NATIIVE GRASSES, LOW HEIGHT SHRUBS / FLOWERS,TYPICAL PLANTING AREAS= MIX OF NATIIVE GRASSES, LOW HEIGHT SHRUBS / FLOWERS,TYPICAL
PLANTING AREAS= MIX OF NATIIVE GRASSES, LOW HEIGHT SHRUBS / FLOWERS,TYPICAL
PLANTING AREAS= MIX OF NATIIVE GRASSES, LOW HEIGHT SHRUBS / FLOWERS,TYPICAL
PLANTING AREAS= MIX OF NATIIVE GRASSES, LOW HEIGHT SHRUBS / FLOWERS,TYPICAL
LILAC - SCREENING, TYP. @ PARKING LOT PERIMITER
LILAC - SCREENING, TYP. @ PARKING LOT PERIMITER
6ft Wood Bench, typ.
PROPOSED WALKING &BIKE PATH CONNECTOR
6ft Wood Bench, typ.
DRAWN BY:
SCALE:
PROJECT:
pobox 2016 Bozeman, MT 59771(406)531.9671 millerdesignbuild@gmail.com
DATE:PROJECT NO
REVISION DATE
As indicated
l1.0
SM
Landscape
Plan -
Schematic
Site OverallPhase 1 B - Lot2
Little Horse DriveBozeman, MT 59715
01251-8-2025
Informal Site ReviewPLANTING LEGEND
11 3-12-253-12-25
1/16" = 1'-0"1 Landscape Plan _ Schematic
PARKING LOT = 54 SPACES(1) TREE per (9) SPACES= (6) TREES REQUIRED= (13) TREES PROVIDED ADJACENT TO PARKING LOT
ADJACENT SETBACK TREE REQUIREMENT(1) TREE PER 50 FT OF ADJACENT SETBACK=TOTAL SETBACK APPROX. 630 LINEAR FEET:630FT / 50 = (13) TREES REQUIRED ; (20) PROVIDED
••••••••••
LANDSCAPE PLANTING / TURF NOTES-UTILIZE THE EXISTING LANDSCAPING WELL FOR IRRIGATION NEEDS. -ALL PLANTING AND TURF SHALL UTILIZE U.G. IRRIGATION -MAJORITY OF SITE INTENDS TO UTILIZE NATIVE, DROUGHT TOLERANT AND WATER SMART PLANTING SPECIES, MINIMIZING THE AMOUNT OF TURF WATERING REQUIREMENTS. Achillea x 'Moonshine' (Yarrow)Bouteloua gracilis (Blue Grama)Berberis thunbergii (Concorde Japanese Barberry)Echinacea pallida (Pale Purple Coneflower)Erigeron compositus (Cutleaf Daisy)Festuca glauca (Blue Fescue)Gaillardia aristata (Blanket Flower)Penstemon strictus (Rocky Mountain Penstemon)Schizachyrium scoparium (Little Bluestem)Symphyotrichum oblongifolium (Dream of Beauty)
-APPROXIMATELY 1,440 SQFT OF TURF TO BE UTILIZED AS OPEN SPACE AS SEEN ON PLANS.-TURF SOD SHALL CONSIST OF KENTUCKY BLUEGRASS
1
1
2480 SF
LEVEL 1
2480 SF
LEVEL 2
OPEN TO BELOW
2088 SF
Health Gym
898 SF
Office 1
1052 SF
Office 2
OPEN TO BELOW
DRAWN BY:
SCALE:
PROJECT:
pobox 2016 Bozeman, MT 59771(406)531.9671 millerdesignbuild@gmail.com
DATE:PROJECT NO
REVISION DATE
1/8" = 1'-0"
a1.5
SM
Area Plans
- East Bldg.
EAST BLDG.Phase 1 B - Lot2
Little Horse DriveBozeman, MT 59715
01251-8-2025
Informal Site Plan Reivew0 2 10 18 1/8" = 1'-0"1 Level 1 - Building SQFT
021018 1/8" = 1'-0"2Level 2 - Building SQFT
0 2 10 18 1/8" = 1'-0"3 Level 1 - Parking Area Plan
021018 1/8" = 1'-0"4Level 2 - Parking Area Plan
BUILDING AREA SQUARE FOOTAGE
Level Area
Level 1 2480 SF
Level 2 2480 SF
TOTAL BUILDING SQFT 4960 SF
PARKING AREA CLASSIFICATION per BMC / PARKING LOAD SCHEDULE
Level Name Area Parking LoadFactor Parking Load
Level 1 Health Gym 2088 SF 200 SF 10.44
Level 1 2088 SF 10.44
Level 2 Office 1 898 SF 250 SF 3.59
Level 2 Office 2 1052 SF 250 SF 4.21
Level 2 1950 SF 7.80
Totals 4038 SF 18.24
815.5 SF
RESTAURANT
1141.9SF
RETAIL STORE
682.7 SF
EXTERIOR SEATING Bar Service AreaWaiting AreaKitchen Area
670.1 SF
OFFICE 1
529.5 SF
OFFICE 1
OPEN ATRIUM TO BELOW
Open Walkway
Elevator Shaft
3300.0SF
Level 1
EXTERIOR WALKWAY
EXTERIOR PATIO
EXTERIOR PAD / UTILITY SCREENING
1670.7SF
Level 2
OPEN ATRIUM TO BELOW
Open Walkway
Elevator Shaft
DRAWN BY:
SCALE:
PROJECT:
pobox 2016 Bozeman, MT 59771(406)531.9671 millerdesignbuild@gmail.com
DATE:PROJECT NO
REVISION DATE
1/8" = 1'-0"
a1.1
Author
Area Plans
- West
Bldg.
WEST BLDG.Phase 1 B - Lot2
Little Horse DriveBozeman, MT 59715
01251-8-2025
Informal Site Plan Reivew0 2 10 18 1/8" = 1'-0"2 LEVEL 1 - Parking Area Plan
021018 1/8" = 1'-0"4LEVEL 2 - Parking Area Plan
0 2 10 18 1/8" = 1'-0"1 Level 1 - Building SQFT
021018 1/8" = 1'-0"3Level 2 - Building SQFT
PARKING AREA CLASSIFICATION per BMC / PARKING LOAD SCHEDULE
Level Name Area Parking Load Factor Parking Load
Level 1 EXTERIOR SEATING 682.7 SF 100 SF 6.83
Level 1 RESTAURANT 815.5 SF 50 SF 16.31
Level 1 RETAIL STORE 1141.9 SF 300 SF 3.81
Level 1 2640.1 SF 26.94
Level 2 OFFICE 1 670.1 SF 250 SF 2.68
Level 2 OFFICE 1 529.5 SF 250 SF 2.12
Level 2 1199.7 SF 4.80
Totals 3839.8 SF 31.74
BUILDING AREA SQUARE FOOTAGE
Level Area
Level 1 3300.0 SF
Level 2 1670.7 SF
TOTALBUILDINGSQFT 4970.7 SF
Project:Sundance Springs
Day/Period
Total
Trips
Pass-By
Trips
Avg
Rate
Min
Rate
Max
Rate
Std
Dev
Avg
Size
%
Enter
%
Exit
Use
Eq.Equation R2
Weekday Average Daily Trips 46 14.39 4.44 50.91 10.16 3 50 50 False
Source:Trip Generation Manual 11th Edition
Weekday AM Peak Hour Generator 9 2.61 0.9 7.83 1.49 3 60 40 False
Source:Trip Generation Manual 11th Edition
Weekday AM Peak Hour of Adjacent Street Traffic 6 1.67 0.76 4.12 0.88 3 82 18 False
Source:Trip Generation Manual 11th Edition
Weekday PM Peak Hour Generator 10 3.15 0.56 9.14 2.29 3 42 58 False
Source:Trip Generation Manual 11th Edition
Weekday PM Peak Hour of Adjacent Street Traffic 7 2.16 0.56 5.5 1.26 3 34 66 False
Source:Trip Generation Manual 11th Edition
1
Source: Institue of Transportation Engineergs, Trip Generation Manual 11th Edition
Detailed Land Use Data
For 3.15 1000 Sq. Ft. GFA of Office Space
(712) Small Office Building
Analysis Date: 4/16/2025
Project:Sundance Springs
Day/Period
Total
Trips
Pass-By
Trips
Avg
Rate
Min
Rate
Max
Rate
Std
Dev
Avg
Size
%
Enter
%
Exit
Use
Eq.Equation R2
Weekday Average Daily Trips 62 53.87 33.92 107.06 12.93 98 50 50 False Ln(T) = 0.77 Ln(X) + 5.05 0.83
Source:Trip Generation Manual 11th Edition
Weekday AM Peak Hour Generator 7 5.61 2.9 9.52 2.24 79 51 49 False Ln(T) = 0.74 Ln(X) + 2.82 0.78
Source:Trip Generation Manual 11th Edition
Weekday AM Peak Hour of Adjacent Street Traffic 2 1.18 0.51 2.64 0.69 70 70 30 False Ln(T) = 0.84 Ln(X) + 0.74 0.64
Source:Trip Generation Manual 11th Edition
Weekday PM Peak Hour Generator 7 5.42 3.17 12.14 1.59 98 50 50 False Ln(T) = 0.70 Ln(X) + 3.06 0.75
Source:Trip Generation Manual 11th Edition
Weekday PM Peak Hour of Adjacent Street Traffic 6 4.86 1.57 10.21 1.47 110 50 50 False Ln(T) = 0.84 Ln(X) + 2.30 0.59
Source:Trip Generation Manual 11th Edition
2
Source: Institue of Transportation Engineergs, Trip Generation Manual 11th Edition
Detailed Land Use Data
For 1.14 1000 Sq. Ft. GFA of Retail
(815) Free-Standing Discount Store
Analysis Date: 4/16/2025
Project:Sundance Springs
Day/Period
Total
Trips
Pass-By
Trips
Avg
Rate
Min
Rate
Max
Rate
Std
Dev
Avg
Size
%
Enter
%
Exit
Use
Eq.Equation R2
Weekday Average Daily Trips 161 107.2 13.04 742.41 66.72 5 50 50 False
Source:Trip Generation Manual 11th Edition
Weekday AM Peak Hour Generator 21 13.68 1.74 112.49 11.29 6 57 43 False
Source:Trip Generation Manual 11th Edition
Weekday AM Peak Hour of Adjacent Street Traffic 15 9.57 0.76 102.39 11.61 5 55 45 False
Source:Trip Generation Manual 11th Edition
Weekday PM Peak Hour Generator 25 16.35 3.04 89.99 10.84 4 51 49 False
Source:Trip Generation Manual 11th Edition
Weekday PM Peak Hour of Adjacent Street Traffic 14 9.05 0.92 62.00 6.18 6 61 39 False
Source:Trip Generation Manual 11th Edition
3
Source: Institue of Transportation Engineergs, Trip Generation Manual 11th Edition
Detailed Land Use Data
For 1.50 1000 Sq. Ft. GFA of Restaurant
(932) High Turnover (Sit-Down) Restaurant
Analysis Date: 4/16/2025
Project:Sundance Springs
Day/Period
Total
Trips
Pass-By
Trips
Avg
Rate
Min
Rate
Max
Rate
Std
Dev
Avg
Size
%
Enter
%
Exit
Use
Eq.Equation R2
Weekday Average Daily Trips*62 29.47 50 50 False
Source:Trip Generation Manual 11th Edition
Weekday AM Peak Hour Generator 3 1.4 0.3 2 0.78 42 46 54 False
Source:Trip Generation Manual 11th Edition
Weekday AM Peak Hour of Adjacent Street Traffic 3 1.31 0.3 2 0.64 44 51 49 False
Source:Trip Generation Manual 11th Edition
Weekday PM Peak Hour Generator 9 3.92 3.08 4.3 0.59 40 52 48 False
Source:Trip Generation Manual 11th Edition
Weekday PM Peak Hour of Adjacent Street Traffic 8 3.45 1.48 8.37 1.57 37 57 43 False
Source:Trip Generation Manual 11th Edition
*ITE Trip Generation does not have data regarding Weekday Average Daily Trips for Health/Fitness Clubs. Therefore, an expansion factor of 7.3 was applied to PM Peak Hour traffic data.
4
Source: Institue of Transportation Engineergs, Trip Generation Manual 11th Edition
Detailed Land Use Data
For 2.09 1000 Sq. Ft. GFA Health Gym
(492) Health/Fitness Club
Analysis Date: 4/16/2025
Project:Sundance Springs
ITE Land Use *Enter Exit Total *Enter Exit Total *Enter Exit Total
712 Office Space 23 23 46 5 1 6 2 5 7
3.15 1000 Sq. Ft. GFA
815 Free Standing Discount Store 31 31 62 1 1 2 3 3 6
1.14 1000 Sq. Ft. GFA
932 Restaurant 80.5 80.5 161 8 7 15 9 5 14
1.50 1000 Sq. Ft. GFA
492 Health Club 31 31 62 2 1 3 3 5 8
2.09 1000 Sq. Ft GFA
Unadjusted Volume 166 166 331 17 9 26 17 18 35
Internal Capture Trips 1 1 2 3 3 6
Pass-By Trips
Volume Added to Adjacent Streets 166 166 331 16 8 24 14 15 29
Total Weekday Average Daily Trips Internal Capture = 0 Percent
Total Weekday AM Peak Hour of Adjacent Street Traffic Internal Capture = 8 Percent
Total Weekday PM Peak Hour of Adjacent Street Traffic Internal Capture = 17 Percent
* Custom rate used for selected time period
Source: Institue of Transportation Engineergs, Trip Generation Manual 11th Edition
Trip Generation Summary
Weekday Average Daily Trips
Weekday AM Peak Hour
Adjacent Street Traffic
Weekday PM Peak Hour
Adjacent Street Traffic
Analysis Date: 4/16/2025
Project:Sundance Springs
ITE Land Use *Enter Exit Total *Enter Exit Total
712 Office Space 5 4 9 4 6 10
3.15 1000 Sq. Ft. GFA
815 Free Standing Discount Store 4 3 7 4 4 7
1.14 1000 Sq. Ft. GFA
932 Restaurant 12 9 21 13 12 25
1.50 1000 Sq. Ft. GFA
492 Health Club 1 2 3 5 4 9
2.09 1000 Sq. Ft GFA
Unadjusted Volume 22 18 40 25 26 51
Internal Capture Trips
Pass-By Trips
Volume Added to Adjacent Streets 22 18 40 25 26 51
Total Weekday PM Peak Hour of Generator Internal Capture = 0 Percent
Total Weekday AM Peak Hour of Generator Internal Capture = 0 Percent
* Custom rate used for selected time period
Source: Institue of Transportation Engineergs, Trip Generation Manual 11th Edition
Trip Generation Summary
Analysis Date: 4/16/2025
Weekday AM Peak Hour of Generator Weekday PM Peak Hour of Generator
Project:Sundance Springs
Internal External Total Percent Internal External Total Percent Internal External Total Percent Internal External Total Percent
0 0 0 0%0 0 0 0%0 0 0 0%0 0 0 0%
0 0 0 0%0 0 0 0%0 0 0 0%0 0 0 0%
1 4 5 20%0 1 1 0%0 2 2 0%0 5 5 0%
0 0 0 0%0 0 0 0%0 0 0 0%0 0 0 0%
0 8 8 0%1 6 7 14%1 8 9 11%2 3 5 40%
0 1 1 0%0 1 1 0%2 1 3 67%1 2 3 33%
All Other Land Uses 0 2 2 0%0 1 1 0%All Other Land Uses 0 3 3 0%0 5 5 0%
1 15 16 6%1 9 10 10%3 14 17 18%3 15 18 17%
Internal Capture Report - Sundance Springs Site Plan
AM & PM Peak Hour
Analysis Date: 4/16/2025
Source: Institue of Transportation Engineergs, Trip Generation Manual 11th Edition
AM
Category
Cinema
Hotel
Office
Residential
Restaurant
Retail
Entering Trips Exiting TripsExiting Trips PM
Restaurant
Retail
Totals Totals
Entering Trips
Category
Cinema
Hotel
Office
Residential