HomeMy WebLinkAbout13_ADD_1_Special Provisions and Measurement and Payment 9.10.2025Page 1 of 22 City of Bozeman Special Provisions
CITY OF BOZEMAN SPECIAL PROVISIONS
Contents:
1. GENERAL
2. SCOPE OF WORK
3. SCHEDULE OF VALUES
4. AWARD OF CONTRACT
5. TIME OF COMMENCEMENT AND COMPLETION DATE
6. COST LIMITATIONS
7. NAMES, PRODUCTS AND SUBSTITUTIONS
8. APPROVAL OF EQUIPMENT AND MATERIALS
9. BIDDER’S QUALIFICATIONS
10. WARRANTY
11. SCHEDULING
12. PRECONSTRUCTION CONFERENCE
13. UNDERGROUND UTILITIES
14. EASEMENS, RIGHT OF WAYS, ADJOINING PROPERTY
15. TRAFFIC CONTROL
16. DISPOSAL, EROSION, WATER POLLUTION, AND SILTATION CONTROL
17. PROTECTION OF EXISTING PAVEMENT
18. OPERATION OF EXISTING VALVES
19. SALVAGEABLE ITEMS
20. ACCESS TO RECORDS
21. INSURANCE
22. LANDSCAPING RESTORATION
23. PROTECTION OF TREES, SPRINKLER SYSTEMS, AND PROPERTY PINS
24. UNSCHEDULED EMPLOYMENT OF CITY WATER/SEWER SERVICE
WORKERS
25. DELAYS
26. CONSTRUCTION STAKING
1. GENERAL
The work to be performed under this contract involves furnishing all labor, materials,
equipment, supplies, and services necessary for the construction of the Bozeman Sports
Park, Phase 2 in the City of Bozeman.
All work shall be performed in accordance with applicable sections of the Montana
Public Works Standard Specifications Seventh Edition (MPWSS), 7th Edition, and as
further modified by the City of Bozeman Modifications to MPWSS, 7th Edition, which
is hereby included as part of these specifications. All references to MPWSS sections,
unless otherwise noted, are a reference to said Montana Public Works Standard
Specifications.
Page 2 of 22 City of Bozeman Special Provisions
All correspondence and official authorization concerning the work shall be with the
Owner or their designated representatives as identified at the preconstruction meeting.
Any changes in the Work or schedule not authorized by the above shall be deemed as
unauthorized and shall be done at Contractors risk at no cost to the Owner. All
damages, reparations, and costs thus incurred during the progress of such unauthorized
work shall be borne exclusively by the Contractor.
2. SCOPE OF WORK
Construction of a new 119-stall parking lot, including mass grading of the site, 1
artificial turf field, installing new sidewalks, curb and gutter, storm drainage
improvements, landscaping and signage and striping.
3. SCHEDULE OF VALUES
A. Schedule of Values
The contract payment shall be by unit price for work completed as defined by the
quantities and unit price in the Schedule of Values. For the purposes of progress
payments and additive/deductive changes to the design, a Schedule of Values shall be
completed by the Contractor. Items have been quantified and will be measured and paid
in accordance with the Montana Public Works Standard Specifications (MPWSS) where
applicable. Where items are not included in MPWSS or where a different quantification
is used, a brief description of the item and its measurement is provided below.
B. Measurement and Payment
i. Work shall be measured by the Engineer or their representative with
assistance from the contractor prior to preparation of a payment request by
the Contractor.
ii. Unit quantities that are measured in place shall be measured every month.
The contractor shall give the Engineer a minimum of two days’ notice for
making all required measurements.
iii. Materials that must be measured as delivered shall be measured at the time
of delivery be the Engineer or their representative and the contractor shall
provide sufficient notice so that such a measurement can be made.
iv. Work completed on a Lump Sum (LS) basis shall be measured for
completion against the schedule of values provided be the contractor and
operational job bot specifically identified as a pay item shall be included
in the unit price bid for the item to which it pertains.
v. The total bid price for each item of the contract shall cover all work shown
on the contract drawings and required by the specifications and other
Contract Documents.
Page 3 of 22 City of Bozeman Special Provisions
C. Estimated Quantities
All estimated quantities for unit price items, stipulated in the Bid Form or other Contract
Documents, are approximate and are to be used as a basis for comparing the bids
submitted for the Project. The actual amounts of work done, and materials furnished
under unit price items may differ from the estimated quantities. The basis of payment for
work will be the actual amount of work done. The CONTRACTOR agrees that he will
make no claim for damages, anticipated profits or otherwise on account of any
difference between the amounts of work performed and the estimated amounts included
in the Bid Form. The Contractor will not be paid for any work which exceeds the
quantity set forth in the Bid Form without a change order or work change directive
issued before the work is performed unless specifically ordered in writing by the
Engineer. The Contractor will aid the Engineer to check quantities and elevations when
requested.
D. Measurement of Quantities
i. Measurement by Volume – Measured by cubic dimensions using length,
width and height. Unless specified otherwise “Execution – Measurement
and Payment” section below, measurements of volume is to be made in
Cubic Yards (CY).
ii. Measurement by Area - Measured by square dimension using length and
width. Unless specified otherwise in the “Execution – Measurement and
Payment” section below, measurement is to be made in Square Feet (SF)
or Square Yards (SY).
iii. Linear Measurements – Measured by linear dimensions at the centerline.
Unless specified otherwise in the “Execution – Measurement and
Payment” section below, linear measurement is to be made in Linear Feet
(LF) or Vertical Feet (VF).
iv. Measurement by Each – Measured by each singly quantified item. Unless
specified otherwise in the “Execution – Measurement and Payment”
section below, measurement of a singly quantifiable item is the be made
per Each (EA) item.
v. Lump Sum Measurements – Lump Sum (LS) work is measured by work
completed in totality for each item as defined in the ““Execution –
Measurement and Payment” section below.
vi. Time Measurements – Month (Mo) Work is measured by work completed
in totality for each item as defined in the “Execution – Measurement and
Payment”.
E. Execution – Measurement and Payment
Note: Unless otherwise stated, all items are per MPWSS and COB MODS.
Page 4 of 22 City of Bozeman Special Provisions
Startup, Excavation and Grading:
ITEM 101 – Mobilization, Bonding, and Insurance (LS)
Measurement and Payment for Mobilization Bonding and Insurance is to be made on a
Lump Sum (LS) as follows: Twenty-five percent of the amount to bid for
mobilization/demobilization shall be paid when five percent of the contract amount is
paid for Work complete and for invoiced materials in storage; an additional 50% of the
amount bid will be paid when 25% of the work is complete; and the remaining 25% will
be paid when 100% of the work is completed. All construction is to be bonded prior to
construction. Copies of the contractor’s performance and payment bonds, each in
amount equal to 100% of the contract amount shall be filed with the owner. A 2-year
maintenance bond shall be provided to the owner upon project acceptance. The 2-year
maintenance bond is to equal 20% of the actual cost of the improvements.
ITEM 102 – SWPPP BMP Installation and Maintenance (LS)
This item consists of the cost to install and maintain BMPs (Best Management Practices)
throughout construction. Measurement and payment of SWPPP BMP shall be on a
Lump Sum (LS) basis and shall include the maintenance of all temporary and permanent
erosion control BMPs necessary to provide sediment storge as required by the MDEQ
and the City of Bozeman, and any other control structures necessary to meet land
disturbing permit requirements. Any penalty fees incurred due to the BMP deficiencies
shall be paid for by the Contractor. Payment shall include all necessary labor, materials,
tools and equipment in order to construct, maintain and remove all BMP’s once final
stabilization is achieved. Payment is to be made proportionate to amount of work
completed.
ITEM 103 – SWPPP Administration (LS)
This item consists of submitting and maintaining the administrative requirements set
forth by the MDEQ (Montana Department of Environmental Quality) and the City of
Bozeman for a Storm Water Pollution Prevention Plan. Measurement and Payment for
SWPPP Administration shall be on a Lump Sum (LS) basis. Payment of this item shall
include providing and submitting the required SWPPP (Storm Water Pollution
Prevention Plan) documents to obtain administrative coverage of the project. All
administrative fees and permitting requirements, transfer, and close out of the SWPPP
permit shall be paid for by the Owner. Payment is to be made proportionate to amount of
work completed.
ITEM 104 – Topsoil Stripping (15” Depth) and Finish Grade Respread (CY)
Measurement for Topsoil Stripping (15” Depth) and Finish Grade Respread shall be
made on in-place material quantities and quantified using average depth of topsoil
multiplied by the stripping area. Payment for Topsoil Stripping (15” Depth) and Finish
Grade Respread shall be made on a Cubic Yard (CY) basis. This item consists of
removing all the topsoil and organic matter to an estimated average depth of 15” under
hardscapes. Actual topsoil depth may vary. This item consists of respreading topsoil to
finish grade in landscaped areas. Contractor is responsible for maintaining adequate
amounts of usable topsoil stockpiled onsite to allow for respread over the designated
Page 5 of 22 City of Bozeman Special Provisions
landscaped areas.
ITEM 105 – Site Grading (Cut/Fill to Subgrade) (CY)
Measurement for Site Grading (Cut/Fill to Subgrade) shall be made using the engineer
estimate which was based on cutting/filling to the subgrade depth. Measurement shall be
made using the engineer’s estimate unless the topsoil depth changes. Payment for Site
Grading (Cut/Fill to Subgrade) shall be made on a Cubic Yard (CY) basis. This item
consists of grading the site after the topsoil has been removed, to create the final
subgrade surface, and all labor, equipment, tools, material, and other incidentals
required to complete the item.
ITEM 106 – Haul and Grade to Subgrade (CY)
Measurement for Haul and Grade to Subgrade shall be made using the engineer estimate
which was based on hauling and filling to the subgrade depth. Measurement shall be
made using the engineers estimate unless the topsoil depth changes. Payment for Haul
and Grade to Subgrade shall be made on a Cubic Yard (CY) basis. This item consists of
hauling from a stockpile south of phase 1B and placing/grading the site after the topsoil
has been removed, to create the final subgrade surface, and all labor, equipment, tools,
material, and other incidentals required to complete the item.
ITEM 107 – Sign Demo (EA)
Measurement for Sign Demo shall be made on an Each (EA) basis. Payment for Sign
Demo shall be on an Each basis. Payment shall include all labor, equipment, and
materials necessary to remove specified signs. This item consists of the removal and
disposal of sign and base (if necessary), and all labor, equipment, tools, material, and
other incidentals required to complete the item.
Parking Lot
Storm Drainage Improvements
ITEM 201 – Sidewalk Chase (LF)
Measurement and payment for Sidewalk Chase shall be made on a Linear Feet (LF)
basis as defined by the MPWSS and the City of Bozeman. This item consists of the
installation of sidewalk chases at the locations and elevations specified in the Plans, and
all labor, equipment, tools, material, and other incidentals required to complete the item.
Street, Parking and Sidewalk Improvements
ITEM 301 – 12” Utility Sleeves (LF)
Measurement and Payment for 12” Utility Sleeves be made on a Linear Foot (LF) basis
as defined by MPWSS and the COB MODS. This item is for furnishing and installing
sleeves, and all labor, equipment, tools, material, and other incidentals required to
complete the item.
ITEM 302 – Landscaping Irrigation Sleeves
Measurement and Payment for Landscaping Irrigation Sleeves be made on a Lump Sum
(LS) basis as defined by MPWSS and the COB MODS. This item includes installing all
landscape sleeving lengths and sizes as required by the landscape plans. This item is for
Page 6 of 22 City of Bozeman Special Provisions
furnishing and installing sleeves, and all labor, equipment, tools, material, and other
incidentals required to complete the item.
ITEM 304 – Subgrade Prep
Measurement and Payment for Subgrade Prep shall be made on a Square Foot (SF) basis
using in place material quantities quantified using length multiplied by width of
subgrade prep area. Quantities are based on a 2-foot extension past the top back of curb.
No additional quantities will be paid for amounts exceeding the 2-foot extension past the
top back of curb unless directed by the Engineer to do so.
ITEM 305 - MIRAFI 600X Geotextile Stabilization Fabric
Measurement and Payment for MIRAFI 600x Geotextile Stabilization Fabric shall be
made on a Square Yard (SY) basis using length multiplied by width of subgrade prep
area. Quantities are based on a 2-foot extension past the top back of Curb. No additional
quantities will be paid for amounts exceeding the 2-foot extension past the top back of
curb unless directed by the Engineer to do so. This item consists of furnishing and
installing MIRAFI 600x Geotextile Stabilization Fabric at the locations and elevations
shown on the plans, and all labor, equipment, tools, material, and other incidentals
required to complete the item.
ITEM 306 – Sub Base Course (Pit Run 20”)
Measurement for Sub Base Course (Pit Run 20”) shall be made on in place material
quantities and quantified using plan section depth of sub base course multiplied by the
sub base area. Payment for Sub Base Course (Pit Run 20”) shall be made on a Cubic
Yard (CY) basis. Quantities are based on a 2-foot extension past the top back of curb.
No additional quantities will be paid for amounts exceeding the 2-foot extension past the
top back of curb unless directed by the Engineer to do so. This item consists of
furnishing and installing Sub Base Course (Pit Run 20”) at the locations and elevations
shown on the plans, and all labor, equipment, tools, material, and other incidentals
required to complete the item.
ITEM 307 - Base Couse (Road Mix 6”)
Measurement for Base Course (Road Mix 6”) shall be made on in place material
quantities and quantified using plan section depth of base course multiplied by the base
area. Payment for base course shall be made on a Cubic Yard (CY) basis. Quantities are
based on a 2-foot extension past the top back of Curb. No additional quantities will be
paid for amounts exceeding the 2-foot extension past the top back of curb unless
directed by the Engineer to do so. This item consists of furnishing and installing Base
Course at the locations and elevations shown on the plans, and all labor, equipment,
tools, material, and other incidentals required to complete the item.
ITEM 308 – Curb and Gutter
Measurement and Payment for Curb and Gutter shall be made on a Linear Foot (LF)
basis as defined by the MPWSS and the COB MODS. This item consists of the
furnishing and installation of combined Curb and Gutter at the locations and elevations
shown on the plans, and all labor, equipment, tools, material, and other incidentals
Page 7 of 22 City of Bozeman Special Provisions
required to complete the item.
ITEM 309 – 3’ Valley Gutter
Measurement and Payment for 3’ Valley Gutter shall be made on a Square Foot (SF)
basis as defined by the MPWSS. This item consists of the furnishing and installation of
3’ Valley Gutter at the location and elevations on the plans, and all labor, equipment,
tools, material, and other incidentals required to complete the item.
ITEM 310 – Asphalt Pavement (Traffic Rated)
Measurement for Asphalt Pavement shall be made on in place material quantities and
quantified using plan areas. Payment for Asphalt Pavement shall be made on a Square
Foot (SF) basis for installed quantities, and all labor, equipment, tools, material, and
other incidentals required to complete the item.
ITEM 311 – Concrete Approach (Traffic Rated)
Measurement for Concrete Approach (Traffic Rated) shall be made on in place material
quantities and quantified using plan areas. Payment for Concrete Approach (Traffic
Rated) shall be made on a Square Foot (SF) basis for installed quantities. This item
consists of the furnishing and installation of the Concrete Approach at the location and
elevations shown on the plans, and all labor, equipment, tools, material, and other
incidentals required to complete the item.
ITEM 312 – 6” Concrete Flatwork with Base Gravel (Traffic Rated)
Measurement for 6” Concrete Flatwork with Base Gravel (Traffic Rated) shall be made
on in place material quantities and quantified using plan areas. Payment for 6” Concrete
Flatwork with Base Gravel (Traffic Rated) shall be made on a Square Foot (SF) basis for
installed quantities. This item consists of the furnishing and installation of 6” Concrete
Flatwork with Base Gravel (Traffic Rated) at the location and elevations shown on the
plans, and all labor, equipment, tools, material, and other incidentals required to
complete the item.
ITEM 313 - 6” Concrete Flatwork with Fibermesh and Base Gravel
Measurement for 6” Concrete Flatwork with Fibermesh and Base Gravel shall be made
on in place material quantities and quantified using plan areas. Payment for 6” Concrete
Flatwork with Fibermesh and Base Gravel shall be made on a Square Foot (SF) basis for
installed quantities. This item consists of the furnishing and installation of 6” Concrete
Flatwork with Base Gravel at the location and elevations shown on the plans, and all
labor, equipment, tools, material, and other incidentals required to complete the item.
ITEM 314 – Curb Paint
Measurement and Payment for Curb Paint shall be made on a Linear Foot (LF) basis.
This item is for the preparation, layout, and painting of all curb areas as specified in the
plans. The work includes all labor, equipment, tools, material, and other incidentals
required to complete the item.
Page 8 of 22 City of Bozeman Special Provisions
ITEM 315 – White Striping
Measurement and Payment for White Striping shall be made on a Linear Foot (LF)
basis. This item is for the preparation, layout, and painting of all asphalt lines as
specified in the plans. The work includes all labor, equipment, tools, material, and other
incidentals required to complete the item.
ITEM 316 – Water-based Pavement Marking
Measurement and Payment for Water-based Pavement Marking shall be made on an
Each (EA) basis. This item is for the preparation, layout, and painting of all pavement
markings as specified in the plans. The work includes all labor, equipment, tools,
material, and other incidentals required to complete the item.
ITEM 317 – Signage
Measurement for Signage shall be made per Each (EA) installed sign as defined in the
MPWSS and COB MODS. This item consists of the furnishing and installation of each
sign at the locations shown on the plans. The work includes all labor, material, and
equipment required to complete the item.
ITEM 318 - Detectable Warning Surface
Measurement for Detectable Warning Surface shall be made on in place material
quantities and quantified by length of surface by width of surface. Payment for
Detectable Warnings shall be made on a Square Foot (SF) basis. This item consists of
furnishing and installing Detectable Warning Surface at the locations shown on the
plans, and all labor, equipment, tools, material, and other incidentals required to
complete the item.
Center Spine Work
Site Improvements
ITEM 401 – Center Spine Gravel Sidewalk
Measurement for Center Spine Gravel Sidewalk shall be made on in place material
quantities and quantified using plan areas. Payment for Center Spine Gravel Sidewalk
shall be made on a Square Foot (SF) basis for installed quantities. This item consists of
the furnishing and installation of Gravel Sidewalk along the Center Spine at the location
and elevations shown on the plans, and all labor, equipment, tools, material, and other
incidentals required to complete the item.
ITEM 401.2 – Landscaping Irrigation Sleeves
Measurement and Payment for Landscaping Irrigation Sleeves be made on a Lump Sum
(LS) basis as defined by MPWSS and the COB MODS. This item includes installing all
landscape sleeving lengths and sizes as required by the landscape plans. This item is for
furnishing and installing sleeves, and all labor, equipment, tools, material, and other
incidentals required to complete the item.
Page 9 of 22 City of Bozeman Special Provisions
Landscape Improvements
ITEM 402 - Seeding
Measurement and Payment for Seeding shall be made on a Lump Sum (LS) basis. See
attached documentation for seeding special provisions. Payment shall be made on the
proportional amount of Seeding installed. See table below for all work-related items and
quantities included in ITEM 402. This item is to include all of the seeding along
the center spine as shown in the landscape plans, and all labor, equipment, tools,
material, and other incidentals required to complete the item.
ITEM DESCRIPTION QTY UNIT
Soil amendments at dryland seeding area- (compost &
gypsum) 30,228 SF
Tilling - 4" deep 30,228 SF
Drill seeding 30,228 SF
Hydromulch 30,228 SF
ITEM 403 – Irrigation System
Measurement and Payment for Irrigation System shall be made on a Lump Sum (LS)
basis. See attached documentation for Irrigation system special provisions. Payment
shall be made on the proportional amount of Irrigation System installed. See table below
for all work-related items and quantities included in ITEM 403. This item is to include
all labor, equipment, tools and other incidentals to complete the irrigation system along
the center spine as shown in the landscape plans.
Sports Field
Storm Drainage Improvements
ITEM 501 - Core Into Existing Manhole
Measurement and Payment for Core into Existing Manhole shall be per Each (EA)
Manhole that requires to be cored into. This item includes the work and materials to core
into an existing manhole and all labor, equipment, tools and other incidental work
required to tie the new storm pipe into the existing manhole.
ITEM 502 – 36” Storm Manhole
Measurement and Payment for 36" Storm Manhole is per Each (EA) 36" Manhole
installed. This item consists of installing 36” Storm Manhole at the location and
elevation shown on the Plans. Work includes, but is not limited to, furnishing, and
installing the manhole, ring, and cover, and all other materials required to complete the
work as described in the plans and specifications. The work also includes all excavation,
shoring, sheeting, dewatering, backfill and compaction; and all labor, equipment, tools,
and incidentals required to complete the item.
ITEM DESCRIPTION QTY UNIT
Park irrigation (medium rotors) 5,256 SF
Mainline (4") for future fields 45 LF
Isolation valve (4") for future fields 1 EA
Page 10 of 22 City of Bozeman Special Provisions
ITEM 503 - 36” Extra Manhole Depth
Measurement and Payment for 36” Extra Manhole Depth shall be made on a Vertical
Foot (VF) basis as defined by MPWSS.
ITEM 504 – 12” PVC Storm Drain Pipe
Measurement and Payment for 12" PVC Storm Drain Pipe shall be made on a Linear
Foot (LF) basis as defined by MPWSS and the COB MODS. This item consists of
installing 12" PVC Storm Drain Pipe at the location and elevation shown on the plans.
Work includes, but is not limited to, furnishing, and installing the pipe, and all other
materials required to complete the work as described in the plans and specifications. The
work also includes all excavation, shoring, sheeting, dewatering, backfill and
compaction; and all labor, equipment, tools, and incidentals required to complete the
item.
Street and Sidewalk Improvements
ITEM 505 – Subbase Course (Pit Run 20”)
Measurement for Sub Base Course (Pit Run 20”) shall be made on in place material
quantities and quantified using plan section depth of sub base course multiplied by the
sub base area. Payment for Sub Base Course (Pit Run 20”) shall be made on a Cubic
Yard (CY) basis. Quantities are based on a 2-foot extension past the top back of curb.
No additional quantities will be paid for amounts exceeding the 2-foot extension past the
top back of curb unless directed by the Engineer to do so. This item consists of
furnishing and installing Sub Base Course (Pit Run 20”) at the locations and elevations
shown on the plans, and all labor, equipment, tools, and incidentals required to complete
the item.
ITEM 506 – Base Course (Road Mix 6”)
Measurement for Base Course (Road Mix 6”) shall be made on in place material
quantities and quantified using plan section depth of base course multiplied by the base
area. Payment for base course shall be made on a Cubic Yard (CY) basis. Quantities are
based on a 2-foot extension past the top back of Curb. No additional quantities will be
paid for amounts exceeding the 2-foot extension past the top back of curb unless
directed by the Engineer to do so. This item consists of furnishing and installing Base
Course at the locations and elevations shown on the plans, and all labor, equipment,
tools, and incidentals required to complete the item.
ITEM 507 - MIRAFI 600X Geotextile Stabilization Fabric
Measurement and Payment for MIRAFI 600x Geotextile Stabilization Fabric shall be
made on a Square Yard (SY) basis using length multiplied by width of subgrade prep
area. Quantities are based on a 2-foot extension past the top back of Curb. No additional
quantities will be paid for amounts exceeding the 2-foot extension past the top back of
curb unless directed by the Engineer to do so. This item consists of furnishing and
installing MIRAFI 600x Geotextile Stabilization Fabric at the locations and elevations
shown on the plans, and all labor, equipment, tools, and incidentals required to complete
the item.
Page 11 of 22 City of Bozeman Special Provisions
Site Work
Site Improvements
ITEM 601 – East-West Gravel Sidewalk
Measurement for East-West Gravel Sidewalk shall be made on in place material
quantities and quantified using plan areas. Payment for East-West Gravel Sidewalk shall
be made on a Square Foot (SF) basis for installed quantities. This item consists of the
furnishing and installation of Gravel Sidewalk going east to west at the location and
elevations shown on the plans, and all labor, equipment, tools, and incidentals required
to complete the item.
ITEM 602 – Vault Toilet
Measurement and payment for Vault Toilet shall be made on a Lump Sum (LS) basis.
Vault Toilet is to be Missoula Concrete Construction Double Vault Toilet Without
Screen or an approved equal. 50% of payment will be made when the item is ordered
with the remainder to be paid out on completion of install. This item consists of all work
incidental to install the vault toilet, included but now limited to procurement, placement
and all labor equipment and tools to install this item.
Landscape Improvements
ITEM 603 – Planting
Measurement and Payment for Planting shall be made on a Lump Sum (LS) basis. See
attached documentation for Planting special provisions. Payment shall be made on the
proportional amount of Planting installed. See table below for all work-related items and
quantities included in ITEM 603. This item is to include all the planting as shown in the
landscape plans, including all labor equipment, tools and incidental work required to
install the plantings.
ITEM DESCRIPTION QTY UNIT
Planter areas (Plants, weed barrier, edging, and mulch,
amendments) 9,100 SF
Landscape boulders (3-5' dia) 31 EA
Ornamental tree (1-1/2" caliper) 9 EA
Deciduous shade tree (2-1/2" caliper) 34 EA
Evergreen tree (6' tall) 6 EA
ITEM 604 – Seeding
Measurement and Payment for Seeding shall be made on a Lump Sum (LS) basis. See
attached documentation for seeding special provisions. Payment shall be made on the
proportional amount of Seeding installed. See table below for all work-related items and
quantities included in ITEM 604. This item is to include all incidental work to complete
the seeding as shown in the landscape plans (excluding the seeding along the center
spine).
Page 12 of 22 City of Bozeman Special Provisions
ITEM 605 - Irrigation System
Measurement and Payment for Irrigation System shall be made on a Lump Sum (LS)
basis. See attached documentation for Irrigation system special provisions. Payment
shall be made on the proportional amount of Irrigation System installed. See table below
for all work-related items and quantities included in ITEM 605. This item is to include
all labor, equipment, tools and incidental work to complete the Irrigation System as
shown in the landscape plans (excluding the irrigation system along the center spine).
ITEM DESCRIPTION QTY UNIT
Park irrigation (medium rotors) 4,771 SF
Park irrigation (spray) 7,326 SF
Planter irrigation (spray) 8,100 SF
Tree irrigation 49 EA
Irrigation controller 1 EA
Master valve & flow sensor 1 EA
Solar sync 1 EA
Mainline (6") 3,665 LF
SubMainline (3") 50 LF
SubMainline (4") 1,644 LF
Isolation valve (4") 6 EA
Isolation valve (6") 4 EA
Cam-loc assemblies 3 LS
Solar power for controller 1 EA
Repair damage to existing irrigation west of field
5 1 LS
ITEM 606 – Bike Racks
Measurement and Payment for Bike Racks shall be made on an Each (EA) basis. This
item is for all bike racks as specified in the landscape plans. This item consists of all
material, labor equipment, tools and other incidentals required to install the item.
Add Alternates
Add Alt #1 – Center Spine
ITEM ALT 1.1 – 6” Concrete Flatwork with Base Gravel (Non-Traffic Rated)
Measurement for 6” Concrete Flatwork with Base Gravel (Reinforced/Non-Traffic
Rated) shall be made on in place material quantities and quantified using plan areas.
Payment for 6” Concrete Flatwork with Base Gravel (Reinforced/Non-Traffic Rated)
shall be made on a Square Foot (SF) basis for installed quantities. This item consists of
the furnishing and installation of 6” Concrete Flatwork with Base Gravel
(Reinforced/Non-Traffic Rated), including and all labor, equipment, tools, and
incidentals required to complete the item at the location and elevations shown on the
ITEM DESCRIPTION QTY UNIT
Soil amendments at dryland seeding area- (compost &
gypsum) 208,100 SF
Tilling - 4" deep 208,100 SF
Drill seeding 208,100 SF
Hydromulch 208,100 SF
Page 13 of 22 City of Bozeman Special Provisions
plans.
Add Alt#2 – Field 13 Asphalt Apron
ITEM ALT 2.1 – Asphalt Apron (Non-Traffic Rated)
Measurement for Asphalt Apron (Non-Traffic Rated) shall be made on in place material
quantities and quantified using plan areas. Payment for Asphalt Apron shall be made on
a Square Foot (SF) basis for installed quantities. This item consists of placing asphalt
including and all labor, equipment, tools, and incidentals required to complete the item
at the location and elevations shown on the plans.
Add Alt#3 – Field 7 Asphalt Apron
ITEM ALT 3.1 – Asphalt Apron (Non-Traffic Rated)
Measurement for Asphalt Apron (Non-Traffic Rated) shall be made on in place material
quantities and quantified using plan areas. Payment for Asphalt Apron shall be made on
a Square Foot (SF) basis for installed quantities. This item consists of placing asphalt
including and all labor, equipment, tools, and incidentals required to complete the item
at the location and elevations shown on the plans.
Add Alt #4 – Field 13 Chain Link Fence
ITEM ALT 4.1 – 4’ Chain-link Field Fence
Measurement and Payment for Chain-Link Field Fence Shall be made on a Linear Foot
(LF) basis. This item includes all work required to install the 4’ Chain-Link fence at
locations and elevations shown in the plans, including all materials, labor equipment,
tools and incidentals to complete the item.
Add Alt #5 – Field 7 Chain Link Fence
ITEM ALT 5.1 – 4’ Chain link Field Fence
Measurement and Payment for Chain-Link Field Fence Shall be made on a Linear Foot
(LF) basis. This item includes all work required to install the 4’ Chain-Link fence at
locations and elevations shown in the plans, including all materials, labor equipment,
tools and incidentals to complete the item.
Add Alt #6 – Bike Racks
ITEM ALT 6.1 - 6” Concrete Flatwork with Base Gravel (Non-Traffic Rated)
Measurement for 6” Concrete Flatwork with Base Gravel (Reinforced/Non-Traffic
Rated) shall be made on in place material quantities and quantified using plan areas.
Payment for 6” Concrete Flatwork with Base Gravel (Reinforced/Non-Traffic Rated)
shall be made on a Square Foot (SF) basis for installed quantities.
This item consists of the furnishing and installation of 6” Concrete Flatwork with Base
Gravel (Reinforced/Non-Traffic Rated) at the location and elevations shown on the
Plans.
ITEM ALT 6.2 – Bike Racks
Measurement and Payment for Bike Racks shall be made on an Each (EA) basis. This
Page 14 of 22 City of Bozeman Special Provisions
item is for all future bike racks as specified in the landscape plans. This item consists of
all material, labor equipment, tools and other incidentals required to complete the item.
4. AWARD OF CONTRACT
If the contract is awarded, the Owner will award a single Contract in accordance with
the Instructions to Bidders. Bidders shall submit a Bid on a unit price basis for each
item of Work listed as provided and described above. The Owner reserves the right
to accept or reject the Bids, or portions of the Bids denoted as separate schedules or
alternates. The award will be made by the Owner on the basis of that Bid from the
lowest responsive, responsible Bidder which, in the Owner’s sole and absolute
judgment, will best serve the interest of the Owner. The low bidder will be determined
on the basis of the lowest Total Combined Base Bid prior to any Add Alternates.
The award of the contract, if awarded, will be made within the period specified in the
Invitation to Bid to the lowest responsive, responsible Bidder whose Bid complies with
all the requirements prescribed herein. The successful Bidder will be notified by letter,
mailed to the address shown on the Bid, that their Bid has been accepted and that they
have been awarded a contract.
5. TIME OF COMMENCEMENT AND COMPLETION DATE
The beginning of the Contract Time shall be stated in a written NOTICE TO PROCEED
written by the Project Manager to the Contractor. Where multiple schedules are
awarded under a single contract, the contract times shall run concurrently, unless the
City agrees to issue separate notices to proceed. The Contract Time will expire
automatically after the number of calendar days stated as Contract Time, except as the
Contract Time may be extended by change order. The Contract Time is to be 120 days.
In the event of winter conditions as agreed upon by owner, contractor and engineer the
120 days will be put on hold and resumed once winter conditions are over. No additional
payments will be made for working through winter conditions.
6. COST LIMITATIONS
The Owner reserves the right to eliminate or reduce certain proposal items from the
project following the Bid Opening to make the project financially feasible with the
limitations of the funds allocated for this project. The determination of which items
shall be eliminated shall be the responsibility of the Owner.
7. NAMES, PRODUCTS AND SUBSTITUTIONS
Where products or materials are specified by manufacturer, trade name, or brand, such
designations are intended to indicate the required quality, type, utility, and finish.
Requests for proposed substitution shall include complete specifications and descriptive
data to prove the equality of proposed substitutions. Substitutions shall not be made
Page 15 of 22 City of Bozeman Special Provisions
without the written approval of the Owner. No substitutions will be considered until
after contract award.
8. APPROVAL OF EQUIPMENT AND MATERIALS
The Contractor shall furnish to the Owner or its Project Manager for approval the name
of the manufacturer of machinery, mechanical and other equipment and materials which
he contemplates using in execution of the work, together with the performance
capacities and such other information which may be pertinent or required by the Owner.
9. BIDDER'S QUALIFICATIONS
The Contractor shall show evidence that he has the finances, organization, and
equipment to perform the work with a limited number of subcontractors. The
Contractor will be required to have a full-time resident General Superintendent on the
job at all times while the work is in progress. He shall be in a position to direct the work
and make decisions either directly or through immediate contact with his superior.
Absence or incompetence of the superintendent shall be reason for the Owner to stop all
work on the project.
10. WARRANTY
The Contractor is required to provide a 2-year warranty bond after final walk-through of
the project by the Owner.
11. SCHEDULING
Prior to or at the PRECONSTRUCTION CONFERENCE, the Contractor shall provide
the Owner the following schedules:
A. A practicable CONSTRUCTION PROGRESS SCHEDULE showing the order,
timing, and progress in which the Contractor proposes to prosecute the work. This
schedule shall be in Bar Graph, CPM or PERT format. The schedule shall be updated
and re-submitted as necessary to reflect project changes.
B. The Contractor shall limit working hours to meet City of Bozeman ordinance for
construction activities. No work shall be done outside of these hours unless specifically
approved by the Owner.
12. PRECONSTRUCTION CONFERENCE
After the contract(s) have been awarded, but before the start of construction, a
conference will be held at the Project Engineer’s Office, at Stahly Engineering: 851
Bridger Drive Suite 1, for the purpose of discussing requirements on such matters as
project supervision, on-site inspections, progress schedules and reports, payrolls,
Page 16 of 22 City of Bozeman Special Provisions
payment to contractors, contract change orders, insurance, safety, and any other items
pertinent to the project. The Contractor shall arrange to have all supervisory personnel
and a representative from each of the affected utility companies connected with the
project on hand to meet with a representative of the Owner to discuss the project and
any problems anticipated.
13. UNDERGROUND UTILITIES
The Contractor shall be responsible for checking with the Owners of underground
utilities such as the City, County, power, gas and telephone companies, etc. as to the
location of their underground installations in the project area. The Contractor shall be
solely responsible for any damage done to these installations due to failure to locate
them or to properly protect them when their location is known.
It shall be solely the responsibility of the Contractor to fully coordinate his work with
the agencies and to keep them informed of his construction activities so that these vital
installations are fully protected at all times.
A Montana One-call system, phone number 1-800-424-5555 has been set up to facilitate
requests for underground facility locate information. The Contractor is responsible for
contacting the One-call system prior to any excavation.
14. EASEMENTS, RIGHTS-OF-WAY, ADJOINING PROPERTY
The Contractor shall contain all of his construction operations within the easements and
rights of way unless written approval is secured from the owner of the adjoining
property or written approval is given by the Owner to utilize the adjacent land area.
15. TRAFFIC CONTROL
B. General. The Contractor shall at all times conduct his operations so that there is a
minimum interruption in the use of the City's streets affected by the work. Exact
procedures in this respect shall be established in advance of construction with the City
Project Manager.
Barricade function, design and construction shall conform to the latest edition of the
Manual on Uniform Traffic Control Devices (MUTCD) and the Standard Specifications
for Road and Bridge Construction of the State Highway Commission of Montana latest
Edition.
Should construction of the project require the closure of any streets, roads or highways
or require night-time or long-term traffic control, the Contractor will be required to
prepare a detailed TRAFFIC CONTROL PLAN to address the methods and means of
controlling traffic under the specific conditions. Traffic control plans shall be in
conformance with the requirements of the Manual on Uniform Traffic Control Devices.
In regards to closures, the plan shall include specific details on traffic detours and
Page 17 of 22 City of Bozeman Special Provisions
estimated durations of the closures. Details of signing, barricades, flagging and other
traffic control devices shall be presented. The traffic control plan shall be approved by
the Owner prior to construction. The Contractor may be required to modify or adjust a
traffic control set-up to fit specific field conditions encountered during construction.
C. Traffic Access. Construction work shall be programmed by the Contractor so that
local traffic will have continuous access within one block of any given property. It shall
be the responsibility of the Contractor to notify all affected residents in the area of
programmed work, of street closures, parking requirements and restrictions, and any
other conditions, a minimum of twenty-four (24) hours prior to beginning work within
the affected area. All signing, barricades, and other traffic control measures shall be
provided by the Contractor.
D. Warning Signals. All streets, roads, highways and other public thoroughfares which
are closed to traffic shall be protected by means of effective barricades on which shall be
placed, mounted or affixed acceptable warning signs. Barricades shall be located at the
nearest intersecting public highway or street on each side of the blocked section.
All open trenches and other excavations within the construction area shall be provided
with suitable barriers, signs and lights to the extent that adequate public protection is
provided. All abrupt grade changes greater than one inch which traffic is required to
pass over; and obstructions, including but not limited to, material stockpiles and
equipment shall be similarly protected.
All barricades and obstructions shall be illuminated by means of warning lights at night.
All lights used for this purpose shall be kept burning from sundown to sunrise.
E. Notifications. The Contractor shall coordinate all of the Contractor’s construction
activities to minimize conflicts at the work site, off-site events, or other construction
projects nearby. The Contractor shall notify all affected residents and businesses, the
Bozeman Police, Fire, Street, and Sanitation Departments, Laidlaw Bus Service,
Streamline Bus Service, AMR Ambulance Service, and Allied Waste Services of all
planned street closures a minimum of 24 hours before any actual street closure. In
addition, all businesses affected by a street closure shall be given seven (7) days advance
notice of the upcoming street closure. The Contractor shall maintain a log of all
advance notifications that have been made for each street segment construction site.
Prior to closure of any collector or arterial street, the Contractor shall prepare a news
release announcing the upcoming street closure which shall specify at a minimum the
impact of the construction upon the public and the duration of the work. At least three
days prior to the street closure, the Contractor shall submit the news release to all local
news media, and shall cause the news release to be published as a display ad in the
Bozeman Daily Chronicle.
F. Signalized Intersections. The Contractor shall coordinate with the City of Bozeman
Street Department and the Montana Department of Transportation when working in or
near a signalized intersection. Signals shall not be disrupted without prior approval by
Page 18 of 22 City of Bozeman Special Provisions
City of Bozeman Street Department and the Montana Department of Transportation.
G. Work Methods.
1. The Contractor shall position all traffic control devices according to plan prior to
positioning personnel or equipment on the traveled way.
2. The Contractor shall inspect and check the work zone traffic control frequently
including weekends, holidays, and other non-working days, and shall correct any
deficiencies discovered. The Contractor shall keep a log of all inspections.
3. Construction traffic control devices shall be removed or covered when they are not
being used for construction activities.
4. If the Contractor fails to correct a deficiency in the traffic control system that the
Project Manager deems a necessary traffic control modification to expedite the
movement of traffic or an emergency hazard to life and/or property, the Owner may
correct the deficiency and be reimbursed for all costs from the next progress payment to
the Contractor.
5. Flagging shall be only performed by certified and properly equipped flag persons.
Flagging shall be done as described in the booklet “Instructions to Flag persons”
published by the Montana Department of Transportation.
6. Sidewalks and crosswalks shall remain free of debris and open to pedestrians to the
greatest extent possible. When necessary, pedestrian detours shall be established or the
sidewalk shall be properly closed to travel in accordance with the MUTCD and City of
Bozeman requirements.
7. The Contractor shall schedule the work to minimize inconvenience to the Owner and
to adjacent property owners and to minimize interruptions to utility service and through
traffic. The Contractor shall maintain vehicular access to local businesses at all times.
Work shall be scheduled so as to minimize disruptions to local mail and freight delivery.
The Contractor shall maintain vehicular access to residences able to be used after each
shift.
Street closures shall be closures to through traffic with local traffic allowed. Provide
channelization, flaggers, or other measures necessary to allow the safe passage of local
vehicles to access residences that are within the work zone but not blocked by
construction. Notify all residents at least 24 hours in advance of any access restrictions
for individual approach or street closures. Schedule work such that individual approach
closures last no more than a single shift.
The Contractor shall utilize whatever means he deems necessary to allow traffic on
driveway curbs and aprons a maximum of 10 days after they are poured unless approval
Page 19 of 22 City of Bozeman Special Provisions
is specifically granted by the homeowner to leave them closed for a longer period of
time. The Contractor will be responsible for any cracking or broken sidewalk that may
result from use of the driveways.
8. The Contractor shall designate one (1) employee whose primary purpose shall be to
coordinate traffic control and shall provide a 24 hour per day telephone number or
numbers to contact this person.
16. DISPOSAL, EROSION, WATER POLLUTION, AND SILTATION
CONTROL
The Contractor is responsible for proper disposal of all waste soils, materials, and
slurries unless otherwise directed herein. Where waste materials are disposed on private
property not owned by the Contractor, evidence of property owner's written permission
shall be obtained and provided to the Owner. Contractor shall comply with all Local,
State, and Federal laws and regulations pertaining to fill in wetlands and floodplains.
The Contractor shall dispose of all refuse and discarded materials in an approved
location.
This project is greater than 1.0 acres in area and therefore a storm water pollution
prevention plan (SWPPP) is required to be submitted to Montana Department of
Environmental Quality (MDEQ) and the City of Bozeman Stormwater Division.
Compiling and submitting the SWPPP is the responsibility of the contractor. This plan
must be approved by DEQ before submitting to the city; additionally, the SWPPP needs
to be approved prior to scheduling a preconstruction meeting with the City. No
construction activities may take place under this contract until the SWPPP has been
approved. The city will review the permit for adequacy. Please allow 1 week for the
City to review the SWPPP.
The Contractor shall exercise all reasonable precautions throughout the life of the
project to prevent pollution or siltation of the city stormwater system, rivers, streams or
impoundments. Pollutants such as chemicals, slurries, fuels, lubricants, bitumens, raw
sewage, and other harmful wastes shall not be discharged into the city stormwater
system or into or alongside of rivers, streams, impoundments or into natural or manmade
channels leading thereto. In addition, the Contractor shall conduct and schedule his
operations to avoid muddying or silting of rivers, streams or impoundments. The
Contractor shall meet the requirements of the applicable regulations of the Montana
DEQ, Department of Fish, Wildlife and Parks, Department of Health and Environmental
Sciences and other State or Federal regulations relating to the prevention or abatement
of water pollution and siltation. The Contractor's specific attention is directed to the
Montana Water Quality Act and the Montana Stream Preservation Act.
The Contractor shall be responsible for obtaining any required discharge permits
associated with groundwater de-watering operations and stormwater runoff. All debris
or waste materials shall be cleaned up by the end of the work day.
Page 20 of 22 City of Bozeman Special Provisions
17. PROTECTION OF EXISTING PAVEMENT
All equipment shall be fitted with pads on the outriggers and other accessories as
necessary to prevent damage to existing pavement during the course of the project. Any
damages to pavement shall be corrected by the Contractor, at his expense, in a manner
as directed by the Project Engineer.
18. OPERATION OF EXISTING VALVES
All existing City of Bozeman water main valves shall be operated by authorized
personnel of the City of Bozeman only. The Contractor shall not operate any existing
valves without the written consent of the City of Bozeman.
19. SALVAGEABLE ITEMS
Any items removed from the existing system under the terms of this contract shall
remain the property of the Owner. Should the owner choose not to accept any
salvageable items, then the Contractor shall dispose of those items at his expense at a
site or landfill acceptable to the Project Manager. Any costs for the above referenced
work shall be at the contractor’s expense.
20. ACCESS TO RECORDS
The Contractor shall allow access to any books, documents, papers and records which
are directly pertinent to this Contract by the Owner, State or Federal agencies, or any of
their duly authorized representatives for the purpose of making an audit, examination,
excerpts or transcriptions.
21. INSURANCE
Insurance coverage required under this contract shall extend, at a minimum, to the end
of the contract time.
22. LANDSCAPING RESTORATION
CONTRACTOR shall be responsible for the restoration of any and all landscape
features disturbed during construction. All landscaping disturbed by construction
activities must be restored to a condition equal to or better than the conditions existing
prior to construction as judged by the OWNER. The CONTRACTOR shall be required
to stockpile and replace all topsoil and irrigation systems disturbed by construction.
23. PROTECTION OF TREES, SPRINKLER SYSTEMS, AND PROPERTY
PINS
Page 21 of 22 City of Bozeman Special Provisions
Prior to initiation of any excavation or removal of existing concrete, the Contractor shall
cut all tree roots at the back limits of excavation with a Vermeer root cutter or other
similar machine capable of cutting the roots in a neat clean, fashion from existing
ground to subgrade elevation. Indiscriminate ripping of tree roots will not be permitted.
In addition, the Contractor shall take special care when working around trees to avoid
any unnecessary damage to the branches or the trunks of trees. Protective barriers shall
be placed around trees as necessary to prevent inadvertent damage by equipment. The
contractor shall meet with the City forester prior to beginning construction activity to
discuss park tree trimming. All tree trimming is the responsibility of the City forestry
department. The contractor shall be expected to provide reasonable access to forestry
before and during construction to trim trees as needed.
Any substantial damage to a park tree resulting from construction activity may result in
a penalty accessed to the contractor. If such damage occurs, the City Forester will
inspect and access the damage and the contractor may be held liable for such damage at
the discretion of the City Forester.
If tree roots are left exposed due to construction activity, the contractor must cover the
roots with topsoil or an erosion control blanket to prevent damage to the roots. Tree
roots must be protected in this manner whenever the exposure is anticipated to last more
than 2 calendar days.
The contractor shall take extra care when working around trees. A general rule for this
project shall be maintaining a 5-foot radius “no dig zone” around trees when excavating
for deep buried utilities (water and sewer).
The Contractor shall take care to locate any existing sprinkler heads or lines prior to
excavation. Any sprinkler systems which are damaged shall be repaired by the
Contractor. The Contractor shall be responsible for preserving existing property pins in
the field. The cost of resetting property pins removed by the Contractor shall be the
responsibility of the Contractor.
Existing irrigation to trees shall be operational throughout the project or manual
watering must be coordinated with the City Forester.
24. UNSCHEDULED EMPLOYMENT OF CITY WATER/SEWER SERVICE
WORKERS
One City Of Bozeman Water/Sewer Operations Dept service worker will be available
7:15 AM till 5:15 PM Monday-Friday with the exception of City recognized holidays
for the water and sewer main replacement portion of the work. Work scheduled outside
these times with less than 24 hours notice will be billed at 1.5 times the service worker’s
base pay rate of $ 38.00 per hour. Call outs (emergency response with no notice) will be
billed 2 hours double time the base rate. Each succeeding hour thereafter 1.5 times the
base rate.
Page 22 of 22 City of Bozeman Special Provisions
The CONTRACTOR is required to respond to affected property owners within the
project and resolve complaints/issues that are raised. If the City is contacted due to non-
responsiveness on the part of CONTRACTOR, the City will resolve the issue and
charge the CONTRACTOR for its time at the rates provided for in this section.
25. DELAYS
The Contractor shall schedule the Work to be completed within the Contract Time(s)
stipulated in the Agreement, including an allowance for time lost due to abnormally cold
weather, abnormal precipitation, or other natural phenomena. Time extensions will not
be granted for rain, wind, flood, or other natural phenomena of normal intensity for the
locality where Work is performed. Such events will not constitute justification for an
extension of time unless agreed upon by both the Project Manager and Contractor, and
the total time lost to such events exceeds 5% of the Contract Time. For purposes of
determining extent of delay attributable to unusual weather phenomena, a determination
shall be made by comparing the weather for a minimum continuous period of at least
one-fourth of the Contract Time involved with the average of the preceding 5 –year
climatic range during the same time interval based on U.S. Weather Bureau statistics for
the locality where the Work is performed.
26. CONSTRUCTION STAKING
Construction staking is to be provided by Contractor.