HomeMy WebLinkAbout013 - Appendix L - Concurrent Construction LetterCity of Bozeman
Bailey Minnich and Danielle Garber
Development Review Planners
20 E. Olive St.
Bozeman, MT 59771
August 27, 2025
RE: South Range Crossing II Subdivision, Alder Ridge Apartments, and Sage Peak Apartments
Concurrent Construction Request
Please accept this letter as a request for concurrent construction, as outlined in section
38.270.030B.1.b.(2), of the South Range Crossing II Subdivision infrastructure, site
infrastructure and building improvements on Block 1 Lot 1 & Block 2 Lots 1-2 of the South
Range Crossing II Subdivision as shown on the Preliminary Plat, Civil Plans, and as shown on the
Alder Ridge and Sage Peak Site Plan and Civil Plans.
As currently proposed South Range Crossing II consists of a stand-alone project with 3 lots
platted for development and 1 restricted lot. The construction of infrastructure for South Range
Crossing II will begin as soon as practical after engineering approvals have been obtained and
the initial phase of construction shall include clearing, grading, wet utilities, gravel roads, and
charged fire hydrants. At that point, the remaining improvements for the subdivision (dry
utilities, asphalt, curb, gutter, sidewalk, landscaping, streetlights, etc.) shall be part of an
Improvement Agreement and one or more performance bonds will be submitted to the city in
order to record the final plat. This is to allow the recording of the Final Plat prior to construction
completion and to facilitate an expedited review and approval of the Alder Ridge and Sage Peak
Apartments site plan, civils, and building plans. Upon recording of the final plat and the creation
of the two lots for the Alder Ridge and Sage Peak apartments projects, the remaining South
Range Crossing II Subdivision infrastructure construction will resume with the concurrent
construction of the apartments.
We understand the need for functional subdivision infrastructure to support construction
activities and will commit to a Concurrent Construction Plan. Subdivision streets will be
improved to a gravel surface and fire hydrants activated prior to final plat recording and any
construction on the apartments lots. Access to the entire Subdivision will be closed to the
public until Subdivision infrastructure is complete. Subdivision infrastructure will be completed
prior to occupying any structure on the concurrent construction lots (Alder Ridge & Sage Peak).
In addition, the occupancy will be staged as shown in the site plan application for Block 2.
Prior to the Final Plat application, the concurrent construction request will be supported by the
following project specific conditions and standard conditions per UDC 38.270.30 D and
stipulated in the Subdivision Improvements Agreement.
1. The initial construction phase shall bring the Subdivision infrastructure to the minimum
stage so that access and life safety can be ensured, including wet utilities installed,
Subdivision streets improved to gravel surfacing for access, and fire hydrants activated.
2. After the completion of the minimum stage infrastructure improvements, the
Subdivision Final Plat will be submitted along with an Improvement Agreement
application requesting to bond remaining Subdivision infrastructure. The remaining
Subdivision infrastructure will be financially guaranteed prior to the recording of the
Final Plat.
3. It is understood that all utilities installed are the responsibility of the owner until the
final acceptance by the City of Bozeman.
a. Sewer service lines will be video inspected for damage and provided to the City
for review and approval prior to occupancy.
b. Snow removal will be performed during the winter to provide access for fire and
emergency service vehicles. Two points of access (17th and 15th from Graf Street)
will be maintained throughout the concurrent construction of the subdivision.
4. Subdivision Park improvements (Subdivision will pay fee in lieu only) will be approved
prior to the city issuing occupancy of any residential structure on the Subdivision lots.
5. Public access to the entire Subdivision will be closed to the public until the final
subdivision infrastructure is complete and accepted by the city.
6. Upon recording the Final Plat, Site Plan Approval, On-Site Infrastructure Approval, and
Building Permit Issuance, construction of both the Subdivision and On-Site
infrastructure, and vertical construction will begin sequentially and concurrently under
the supervision of a single general contractor and controlled by a single entity
7. It is understood that onsite grading and utilities construction for the Graf Site Plan/On-
site cannot occur unit the Final Plat is recorded creating the lots, the Site Plan is
approved, and the on-site Infrastructure Plans are approved.
It is understood that building foundation work cannot begin prior to final plat recording,
site plan approval, and building permit issuance.
8. The subdivision and concurrent construction site projects will be under control of a
single entity, with a single general contractor for subdivision construction, site
construction and vertical construction. There will be no third-party builders onsite per
38.270.030.D.13, until all improvements are completed, inspected, and accepted by the
city.
9. Applicant will provide insurance, risk acknowledgement, and indemnification in a form
acceptable to the city prior to Final Plat and/or Building Permit issuance.
10. It is understood that per BMC 38.270.030.D.9, no occupancy of any structures will be
allowed until required Subdivision infrastructure improvements have been completed,
inspected, and accepted by the city, and a certificate of occupancy has been issued.
11. Sage Peak and Alder Ridge will apply for an Improvement Agreement to performance
bond non-functional site plan amenities and landscaping to support building sequencing
and occupancy of buildings as they are completed. A building sequencing plan has been
included in the Site Plan submittal materials for city review.
Enclosed with this letter is a preliminary construction sequence with durations. The SRX II
Subdivision work is noted as SRX II/Offsite and the Alder Ridge and Sage Peak work is noted as
Graf/Onsite.
DevCo Development and Providence Development both understand the complexity of the
concurrent construction requirements and working through the requirements throughout civil
infrastructure review(s). Please let us know if there is anything more required at this time to
request concurrent construction for the subdivision, site plan, and residential building
construction.
Sincerely,
Providence Development
Parker Lange
Parker Lange
Development Manager
Graf St. Apartments, LLC.
Melanie Davies
Melanie Davies
Pre-Con Construction Project Manager
DevCo Development
*Sequence Does Not Take Into Effect Multiple Crews Working On Different Tasks. Durations
Based On A Single Crew*
SRX II SUBDIVISION INFRASTRUCTURE CONSTRUCTION PRIOR TO FINAL PLAT
SRXII Site Stripping And Rough Grade ~ 1.5 Weeks
• Strip topsoil and rough grade of S 17th Avenue, Staudaher Street, And South 15th
Avenue to facilitate installation of underground utilities.
• Traffic control will be set up prior to the start of construction activities.
• Erosion control measures will be implemented during this time.
SRXII Sanitary Sewer Improvements ~ 3.5 Weeks
• Installation of sewer mains, manholes, and new services under future S 17th
Avenue, Staudaher Street, And South 15th Avenue.
• New sewer services on existing mains to be completed with onsite
infrastructure construction.
• Temporary bypass pumping is to be expected for sewer main connection in
South 19th Avenue.
• Pavement and curb patching on South 19th Avenue will be necessary.
• Temporary construction dewatering system will be set up prior to the start of
underground infrastructure installation.
SRXII Water Improvements ~ 4 Weeks
• Installation of water mains, valves/fittings, fire hydrants, and new services
under future S 17th Avenue, Staudaher Street, And South 15th Avenue.
• New water services on existing mains to be completed with onsite
infrastructure construction.
SRXII Stormwater Improvements ~ 2 Weeks
• Installation of stormwater mains and structures under future S 17th Ave
Avenue, Staudaher Street, And South 15th Avenue.
• Temporary and permanent ponds will be constructed during this time.
SRX II SUBDIVISION INFRASTRUCTURE CONTSTRUCTION FOLLOWING FINAL PLAT
RECORDING
SNOW REMOVAL AS NECESSARY (Schedule and Weather Dependent)
SRXII Site Subgrade Prep And Gravel Import ~ 3.5 Weeks
• Subgrade prep and gravel import for S 17th Avenue, Staudaher Street, And
South 15th Avenue.
• Main haul route will utilize Graf Street to South 19th Avenue.
• Additional traffic control will be implemented during this time for increased
construction traffic.
SRXII Dry Utilities (Power, Gas, Telecom) ~
• By utility provider
SRXII/Offsite Hardscape, Signage, And Striping ~ 5 Weeks
• Concrete and asphalt paving for S 17th Avenue, Staudaher Street, And South 15th
Avenue.
• Concrete will be placed first and then asphalt after concrete cure time
SRXII/Offsite Landscaping ~ 4 Weeks
• Landscaping for S 17th Avenue, Staudaher Street, And South 15th Avenue.
Graf/Onsite Site Stripping And Rough Grade ~ 3 Weeks
• Strip topsoil and rough grade of future parking lot and open spaces.
Topsoil will be stockpiled onsite for future redistribution.
• Excess material will be hauled off during this time.
• Onsite erosion control measures will be implemented during this time.
Graf/Onsite Sanitary Sewer Improvements ~ 1.5 Weeks
• Installation of sewer mains, manholes, and new services within lot lines.
• New sewer services on existing mains in Graf Street will need to coordinated
with the City for tapping and traffic control purposes.
• Sewer services will be terminating five feet from proposed buildings.
Graf/Onsite Water Improvements ~ 2.5 Weeks
• Installation of water mains, valves/fittings, fire hydrants, and new services within lot
lines.
• New sewer services on existing mains in Graf Street will need to coordinated
with the City for tapping and traffic control purposes.
• Water services will be stubbed into final location under the supervisor of a
licensed plumber. OSCY valves will be flow tested.
Graf/Onsite Stormwater Improvements ~ 5 Weeks
• Installation of stormwater mains, roof drains, inlets, structures, and underground
retention systems within lot lines.
• Proposed underground retention system will need to be barricaded to
protect against equipment damage. Area will be barricaded until asphalt
paving is completed.
Graf/Onsite Building Excavation, Gravel Import, And Backfill~ 2.5 Weeks Per Building
(10 EA)
• Excavation, gravel import, and backfill for onsite buildings including clubhouse.
• Time does not account for concrete cure time or other trades to complete work.
Graf/Onsite Site Subgrade Prep And Gravel Import ~ 8.5 Weeks
• Subgrade prep and gravel import for parking lots, sidewalks, approaches, and
concrete pads.
• Main haul route will utilize Canter Avenue to Graf Street to South 19th Avenue.
• Additional traffic control will be implemented during this time for increased
construction traffic.
Onsite Hardscape, Signage, And Striping ~ 18 Weeks
• Concrete and asphalt paving for parking lots, sidewalks, approaches, and concrete
pads.
• Paving will be phased into multiple mobilizations.
• Concrete will be placed first and then asphalt after concrete cure time.
Onsite Landscaping ~ TBD
• Landscaping for open space areas within lot line.
• Improvement Agreement and Performance Bonding (similar to N. 3rd/Westlake Heights) in
order to obtain building occupancies as buildings are completed
BP BP BP
BP BP
BP BP BP BP BP
F
TV
TV
E
I
III
I
S
D
S
D
S
P
P
WCO
TV
TV
I I
I
SP P SDMW XXXXXX XXXXXXXXXXXXXXXX
XXXXXXXXCOS
S XXXXMW
MW
MW
MW
MW
MW
MW
MW
MW
SD SD
BP BP BP BP BP BP BPBP
BPW
S S SSSS
SD SDSDNGNGNGNGNGNGNG
S
S
4980.72
10W 10W 10W 10W 10W 10W 10W 10W
10W
10W
10W
DYH DYH
DYH
DYH
10S 10S 10S 10S DYH
8W 8W 8W 8W 8W 8W 8W 8W 8W 8W 8W 8W 8W 8W 8W 8W 8W
8W8W8W8W8W8W8WDYH DYH
DYH
DYH
8W8W8W8W8W8W8WWSFIRE
FIREWS
WSFIRE
WS
WSDYHWSWS
18S18S18S18S18S18S18S18S18S18S18S18S18S18S8S
8S
8S8S8S8S8SS
S
S
S
S
S
S
S S
8S8S8S8S8S8SS
S
10S 10S 10S 10S 10S 10S 10S 10S 10S 10S 10S 10S 10S 10S 10SS
S S
HH
HH
HHHH
HH
HH
HH HH
MSDSDSDSDSDSDD
D
D SDD
D
D SDSDSDSDSDSDSDSDD
SD SD SD SD SDD SDSDD
D
WSWS
WS
S 17TH AVESTAUDAHER ST
BLOCK 1
LOT 1
BLOCK 2
LOT 1
RESTRICTED LOT 1
BLOCK 2
LOT 2
S 15TH AVEARNOLD ST
S 19TH AVE6
1 1
7
6
SRX-II Subdivision
Infrastructure Improvements
Prior to Final Plat
Hydrant
Hydrant
Hydrant
SRX-II Subdivision
Infrastructure Improvements
Prior to Final Plat
Hydrant
Hydrant
All areas outlined in red constructed as described within this request including underground
utilities (water, sewer, storm), storm structures and ponds, roads to gravel base for emergency
access, and fire hydrants shown will be active. All roads (S 17th, Staudaher Street, and S 15th)
surrounding Block 2 will be maintained for emergency vehicles with snow removal during the
winter for concurrent construction of Block 2. Construction and emergency access is from Graf
Street via S 17th and S 15th Ave. No public access until the subdivision improvements are
completed and accepted by the City.
No access to 19th during
initial construction phase.