HomeMy WebLinkAbout018 - C5.1 - Details MATERIALS NOTES: 1. RAIL TO BE 115—LB. PROFILE DESIGN ELEVATION 2. TIES TO BE NEW, WOOD, 7"x9" (No. 5), 8'-6" LONG, INDUSTRIAL GRADE, PLACED ON A MINIMUM OF 21.5" CENTERS. TOP OF RAILS (TOR) 3. RAIL ANCHORAGE SHALL BE PROVIDED AT A MINIMUM RATE OF 16 ANCHORS PER 39, PANEL. 11.4 4. BALLAST TO BE BNSF CLASS 2 (AREMA SIZE 5) AND NO LARGER THAN 1" IN SIZE. SEE BALLAST GRADATION BELOW. 4. WALKWAY BALLAST TO BE BNSF CLASS 2 (AREMA SIZE 5) AND NO LARGER THAN 1" IN SIZE. SEE BALLAST GRADATION WALKWAY THIS SHEET. 2H 5. SUB—BALLAST MATERIAL SHALL CONTAIN NO MATERIAL LARGER THAN THAT WHICH WILL PASS THROUGH A 3" SQUARE 1V O O O O O O 2 SIEVE. SUB—BALLAST SHALL BE CRUSHED STONE OR CRUSHED GRAVEL WITH A MINIMUM 75% OF THE MATERIAL HAVING 2H 2.07 TWO FRACTURED FACES. SUB—BALLAST MUST MEET THE QUALITY REQUIREMENTS OF ASTM DESIGNATION D1241 AND BE ]�� APPROVED BY THE ENGINEER. 2 0%, 2H 1VI • I SUB BALLAST iV . - -- OPENING 2 1" 2" 1 X" 1 X" 111' 1" 3/4" 1/2" 3/8" N. 4 2:1 CUT/FILL TO DAYLIGHT(TYP.) 2:1 CUT/FILL TO DAYLIGHT (TYP.) 1BNRSEF,,(lass2 1"-3/8" 111 e0-111 40-11 11-31 0-11 1-5 A Size 5) DESCRIPTION OF WORK TO BE PERFORMED BY BNSF: DETAIL — CONSTRUCT APPROXIMATELY 290 LINEAL FEET OF TRACK UP TO EDGE OF RIGHT—OF—WAY LINE. OR ALLOW TRACK C TYPICAL SECTION STA:---4+5®-6+50 CONTRACTOR TO CONSTRUCT 290 LINEAL FEET OF TRACK WITHIN RIGHT—OF—WAY. C5.1 NTS DESCRIPTION OF WORK TO BE PERFORMED BY CONTRACTOR: — CONSTRUCT APPROXIMATELY 1,095 LINEAL FEET OF TRACK BEYOND EDGE OF RIGHT—OF—WAY, CONSTRUCT APPROXIMATELY 480 LINEAL FEET OF ACCESS ROAD, PERFORM ALL GRADING, INSTALL CULVERT AT MANDEVILLE CREEK, INSTALL SLIDER DERAIL WITH WHEEL CROWDER, CONSTRUCT EARTHEN BUMPER. PROFILE DESIGN ELEVATION CL TOP OF RAILS (TOR) 24.0' �5.25' ------ 11.0' 2H 2H 1V�o Oo 2 �1V �1BALLAST 13.0' WIDE ACCESS ROAD 2H O O 22 2.0% O O 2.0% OUO�O iV�., ', -`. ,I SUB BALLAST ..,,. %- 2H =1T/FlI_L �TODAYI�GHT (TYP�) 1V 6" THICK 3/4" MINUS CRUSHED BASE COURSE COMPACTED TO 2:1 CUT/FILL TO DAYLIGHT(TYP.) 95% MAXIMUM DRY DENSITY DETAIL C5.1 TRACK C TYPICAL SECTION STA:6+50-11+25 NTS 30' (NOT TO SCALE) 3� PROFILE DESIGN ELEVATION01 CL TOP OF RAILS (TOR) 0 BERM REQUIRED IF o O �5.25' S.25'� ^•1.0' WIDE EXISTING GROUND v � 2H 2H SLOPES TOWARDS a' PROVIDE OVERTOPPING SPILLWAY AT WEST END. 4' WIDE, 6" THICK ----- ------ TRACKSIDE SWALE - CLASS 1 RIPRAP LINED WITH EROSION CONTROL FABRIC. 2H 2H EXISTING GROUND PROFILE — 1VI �1V — — — OVERTOPPING ELEVATION: 4675.50 1' 1V�o Oo 2' 1V _ 1 _ _ _ _ _ _ — — — — — — — — — — - - FINISHED GRADE NO BERM REQUIRED BOTTOM OF STORM POND — — BALLAST ^-1.0' TALL BERM ENSURE POSITIVE DRAINAGE PATH v TO WEST IS MAINTAINED ALONG ELEVATION: 4674.60 — — O O O 2.0% O 2.0% CSU O�O UPHILL SIDE OF BERM IF EXISTING GROUND _ _ — 2H 2H BOTTOM OF STORM POND 2H SLOPES AWAY — — iV�. ,�iV ELEVATION: 4674.60 iV� 2H - SUB BALLAST PROVIDE OVERTOPPING SPILLWAY AT WEST END. 4' WIDE, 6" THICK 1.0'____ gH ______ __ 1, , _________ 9H ___ 1.0' CLASS 1 RIPRAP LINED WITH EROSION CONTROL FABRIC. TRACKSIDE STORM POND ——— — —— OVERTOPPING ELEVATION: 4675.50 V V EXCAVATE TO NATIVE TRACKSIDE STORM POND GRAVELS EVERY 200—FT AND o 0 o APPROX 4' DIA. HOLE APPROX 4' DIA. HOLE EXCAVATE TO NATIVE GRAVELS EVERY 200—FT AND BACKFILL WITH COBBLES TO WITH COBBLE BACKFILL WITH COBBLE BACKFILL BACKFILL WITH COBBLES TO PROMOTE INFILTRATION PROMOTE INFILTRATION NATIVE GRAVELS a- _ NATIVE GRAVELS J�DETAIL C5.1 TRACK C TYPICAL SECTION STA:11+25-18+81 NTS si NO. REVISIONS DRAWN BY DATE �O NTq Nq PROJECT #: 14-167 SHEEN' 1�®/Ld�C'alLV1LL�1�' T R1- X — TRACK C RAIL EXTENSION 32 DISCOVERY DRIVE � DATE: 07/07/2025 ��o Eaic JAMES BOZEMAN,MT 59718 Civil Engineering FOSS ��1����� PHONE(406)582-0221 Geotechnical Engineering a s as PE FAX(406)582-5770 ALLIED PROJECT ENGINEER: PER DRAWN BY: EJF = w .allieclengineering.com Land Surveying EW�NEERiNR �Ss`'`EA BOZ EMANI T�1IONTANA B� y BOZEMAN TRAX DESIGNED BY: RSR, EJF REVIEWED BY: RSR q'VA ID DETAILS