310 PERMIT Decision Date Application Number
STREAMBED AND LAND PRESERVATION ACE(310 Law) Supervisors' Decision 12/1512022 GD 86.22
Note: Landowner permission, easements or other federal, state, or local permits, licenses, special use permits, or authorizations may be required before
construction of the project. h is the duty of the holder of this permit to determine which are necessary and obtain them prior to construction of the
project
Name of Applicant Business Name Address
Casey Ti ens Bozeman Trax Partners, LLC 5148 US 89 S.
city State Zip Name of Perennial Stream
Livingston MT 59715 Mandeville Creek
Section Township Range Su ervisor's Decision
36 1S 5E Approval with modifications
Proposed Activity
The project is for the Bozeman Trax-Track C Rail Extension project on Bozeman Trax Partners, LLC owned property that is located on the
north end of the project and will involve development of areas for industrial use with rail sidings. As part of the future development for
the site to include a rail siding, a crossing culvert will be required for the Track C rail extension where it will cross Mandeville Creek. The
rail extension will be used as a future loading and unloading area that is in future plans.
Modifications
Bed/Bank should be constructed within culvert to ensure base flow is not an impediment-too wide and shallow.
Work may not commence on a project for True Waiver of 15- False Recurrent Permit Expiration Date Permit Transmittal Date
15 days after receipt of this decision day Waiting Permit
unless district has checked the waiver Period 12/1512023 12/16/2022
box.
SUPERVISORS' SIGNATURES:
Est.1949
Conservation
December 16,2022 Development
GALLATIN
CONS 16 E R V A T I O N Self Government
Casey Tippens D TRICT
c/o Bozeman Trax Partners,LLC
5148 US 89 S.
Livingston,MT 59715
RE: 310 Application GD 86-22 PERENNIAL STREAM: Mandeville Creek
Dear Casey:
The Gallatin Conservation District(GCD)received your 310 application on December 1,2022.The purpose of
the 310 application was for the Bozeman Trax-Track C Rail Extension project on Bozeman Trax Partners,LLC
owned property that is located on the north end of the project and will involve development of areas for industrial
use with rail sidings. As part of the future development for the site to include a rail siding,a crossing culvert will be
required for the Track C rail extension where it will cross Mandeville Creek. The rail extension will be used as a
future loading and unloading area that is in future plans. Representatives from the GCD 310-team inspected the
project site on December 7,2022.
After a discussion and a review of the 310-permit application on December 15,2022,the GCD Board of
Supervisors approved the project with modifications. Modifications include: Bed/Bank should be constructed
within culvert to ensure base flow is not an impediment-too wide and shallow.
Enclosed are two copies of Form 273 (310 Permit).Keep one copy for your records.The District recommends that
you retain all information for current and future reference.The second copy is for the job site.The contractor must
maintain a copy of Form 273 and any pertinent design information in his equipment while conducting all fieldwork
to ensure your project is implemented according to the permit.
REQUIREMENTS
• Form 273 (310 Permit): Please fill out and sign the bottom portion of one copy of the 310 Permit and
return it to this office within 15 days.If we have not received the permit within that time,you will be in
violation of the 310 Law and your permit will not be valid.
• Please take pre-and post-photos of the project.
• Completion Form:At the completion of the project,fill out the enclosed form,attach photos,and
return to this office within 15 days of the completion of the project.
**IMPORTANT-Other permits may be needed for your project. It is your responsibility to ensure all
necessary permits are obtained BEFORE starting your project.**
A 310 Permit does not give an individual permission to do a project,only to do a project in a specific manner once
all other permits are satisfied.This permit is only for the work specified above.If the scope of the work changes,
you must apply for a new permit.All individuals undertaking activities specified in a 310 Permit are encouraged to
obtain accurate cost estimates for projects and ensure water rights are in order before starting any work.
If you have any questions or concerns,please contact me at 406-282-4350.
Sincerely,
Becky Clements
District Administrator
Gallatin Conservation District po Box 569
Manhattan,MT 59741
Enclosures 406-2824350
www.gatiatincd.org
Form 273(Rev.07/01/97)
310 PERMIT Decision Date Application Number
STREAMBED AND LAND PRESERVATION ACE(310 Law)Supervisors'Decision 1211512022 GD 86.22
Note: Landowner permission,easements or other federal,state,or local permits,licenses,special use permits,or authorizations may be required before
construction of the project. It is the duty of the holder of this permit to determine which are necessary and obtain them prior to construction of the
project
Name of Applicant Business Name Address
Casey Ti ens Bozeman Trax Partners,LLC 5148 US 89 S.
Ci State ' _. Zip Name of Perennial Stream
Livin ston MT 59715 Mandeville Creek
Section I Township Ran e: Su ervisor's Decision
36 1S 5E Aoproval with modifications
Proposed Activity
The project is for the Bozeman Trax-Track C Rail Extension project on Bozeman Trax Partners,LLC owned property that is located on the
north end of the project and will involve development of areas for industrial use with rail sidings. As part of the future development for
the site to include a rail siding,a crossing culvert will be required for the Track C rail extension where it will cross Mandeville Creek. The
rail extension will be used as a future loading and unloading area that is in future plans.
Modifications
Bed/Bank should be constructed within culvert to ensure base flow is not an impediment-too wide and shallow.
Work may not commence on a project for True Waiver of 15- False Recurrent Permit Expiration Date Permit Transmittal Date
15 days after receipt of this decision day Waiting Permit
unless district has checked the waiver Period 12/1512023 12116/2022
box.
S PEWISORS'SIGNATURES:
--------------------------------------(cut here)-----------------------------------------------------------
The applicant must agree to abide by the conditions of this permit by checking the appropriate box, signing below,
and returning this form to the district office within 15 days. GD 86-22
❑ I hereby agree to proceed with the project in accordance with the approved application and will allow follow-up inspection.
❑ I understand the project as proposed has been denied,and I may resubmit my application with modifications.
❑ I hereby agree to proceed with the project in accordance with the modifications contained herein,and will allow follow-up inspection.
If the applicant disagrees with the supervisors' decision and wishes to formally resolve the dispute, the applicant must check the box below, sign,
and return this form to the district within 5 working days.
❑ I disagree with the supervisors'decision and hereby request arbitration,
Signature of Applicant: Date:
SHORT-TERM WATER QUALITY STANDARD
FOR TURBIDITY RELATED TO
<--7;� NVIRONMENTAL
na Department. of CONSTRUCTION ACTIVITY
YUALITY (318 Autlrorizatiou)
Dear Applicant;
This 318 authorization is the result of your rcoent appl ication for•a 310 permit from your local Conservation District or a
124 perut from Montana Fish,Wildlife and Parks.This authorization is valid for'the tinmc frame noted on your permit.
This is not your 310 or 124 permit and no construction activity should occur until you have received n valid 310 or
124 permit as well as any other permits that apply to this proposed construction activity.
This authorization is the result of an Operating Agreement between the Montana Department of Environmental Quality
(DEQ),and Montana Fish,Wildlife and Parks(FWP).
The applicant agrees to the comply with the conditions stated below,as well as other conditions listed in the 310 or
L24 permit issued for this project. Signatures of the applicant and FWP are required to validate this authorization.
1. Construction activity in or near the watercourse are to be limited to the minimum area necessary,and conducted
sons to minimize increases in suspended solids and turbidity that could degrade water quality and adversely affect
aquatic life outside the brimediate area of operation.
2. The use of machinery in the watercourse shall be avoided unless absolutely necessary.
3. All disturbed stream banks and adjacent areas.created by the construction activity shall be protected with erosion
control measures during construction.These areas shall be reclaimed with appropriate erosion control measures
and revegetated to provide long-term erosion control.
4. Any excess material generated from this project must be disposed of above the ordinary high water mark,ill an
area not classified as a wetland,and in a position not to cause pollution of State waters.
5. Cleaning of vegetation will be limited to that which is absolutely necessary for construction of the project.
6. This authorization does not authorize a point source surface water discharge.
MPDES pennit is required for said discharge,
7. Open cut creek crossings will not be allowed in flowing water.Stream water must be diverted around the open cut'
area(pump,flume etc.)
8. The applicant must conduct all activities in full and complete compliance with all terms and conditions of all
permits required for this activity issued pursuant to the Montana Natural Streambed and Land Preservation Act
(310 permit),the Stream Protection Act(124 permit)the Federal Clean Water Act(404 Permit),any MPDES
permits for dewatering or storm water control in the construction area and any valid Memorandum of Agreement
and Authorization(MAA)negotiated for this activity.
The FWP representative has determined t t this proje is within the scope of the pi- rammatic Environmental
Ass nr nt rep�tred by DEQ and FWP fa the issuan of narrative turbidity star ids.
Date: _ Date L�
tative's Signature plic s Siur e 2,2
Name and location of project: ._. _.. ._..__._...._. .____-•___
310 Permit Work Completion Form
310 PERMIT INFORMATION
310 Permit#GD 86-22
Legal Description:Township: 1S, Range: 5E,Section: 36
Landowner:
Applicant:Casey Tippens,Bozeman Trax Partners, LLC
Agent:
Stream: Mandeville Creek
Approved Project: 12/15/2022
Permit Expiration Date: 12/15/2023
REQUIREMENTS
• The Applicant/Landowner is required to return this form to the Gallatin Conservation District
when work is completed or the permit expires.
• Include pre-and post-photos of the project.
Date work completed
Note:If work is not completed,provide explanation bellow
Explanation
Signature: Date:
Contact Information(Required for Follow-up Inspection)
Name:
Address:
Phone/Cell#:
Email:
Gallatin Conservation District
120 S 51"Street • PO Box 569
Manhattan MT 59741
406-282-4350
Email: becky@gallatincd.org