HomeMy WebLinkAboutConstruction Phase TimelineTask Begin Construction Erosion control Install Utilites * Building Pad Foundation Vertical Construction Paving ** Landscaping Closeout Construction Phase - EHC Bozeman - Lot 21A, Block 1, Nelson Meadows Month 8 Month 9 Month 10 Month 14 Month 15 Month 16Month 1 Month 3 Month 4 Month 5 Month 6 Month 7 (Project to be constructed in one phase) Month 2 Month 11 Month 12 Month 13 * Inlcudes water, santiary sewer, storm sewer, electric and gas and the termination of existing water services in Nelson Road ** Includes Driveway Connections to Nelson Road and Royal Wolf Way