HomeMy WebLinkAboutConstruction Phase TimelineTask
Begin Construction
Erosion control
Install Utilites *
Building Pad
Foundation
Vertical Construction
Paving **
Landscaping
Closeout
Construction Phase - EHC Bozeman - Lot 21A, Block 1, Nelson Meadows
Month 8 Month 9 Month 10 Month 14 Month 15 Month 16Month 1 Month 3 Month 4 Month 5 Month 6 Month 7
(Project to be constructed in one phase)
Month 2 Month 11 Month 12 Month 13
* Inlcudes water, santiary sewer, storm sewer, electric and gas and the termination of existing water services in Nelson Road
** Includes Driveway Connections to Nelson Road and Royal Wolf Way