Arielle Stoness
From:Karl A. Johnson <kajohnson@BOZEMAN.NET>
Sent:Wednesday, April 19, 2023 8:20 AM
To:Jake T. Grubisch
Cc:Jesse Sobrepena; Jacob Doesschate; Arielle Stoness
Subject:RE: Pines Phase 2 - Traffic Study
Attachments:ATT00001.txt; ATT00002.htm
Jake,
A full TIS is not required for the proposed project. As I mentioned below due to the proposed access on to 19th and its
proximity to additional access locations, an access modification request and approval will be required to approve the
project as proposed. The reviewing engineer may require additional traffic related information during the planning
review to ensure public health and safety.
Thanks,
Karl Johnson, P.E. | Engineer II
City of Bozeman | 20 E. Olive St. | Bozeman, MT 59715
C: 406.451.1693
O: 406.582.2281
kajohnson@bozeman.net
From: Jake T. Grubisch <Jake.T.Grubisch@imegcorp.com>
Sent: Tuesday, April 18, 2023 10:32 AM
To: Karl A. Johnson <kajohnson@BOZEMAN.NET>
Cc: Jesse Sobrepena <jesse@jdsarchitectsbozeman.com>; Jacob Doesschate <jdoesschate@BOZEMAN.NET>; Arielle
Stoness <arielle@jdsarchitectsbozeman.com>
Subject: RE: Pines Phase 2 - Traffic Study
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the
sender and know the content is safe.
Hey Karl,
To summarize the traffic count:
The 15 existing units from phase 1 and 12 proposed units generated a total of 180 trips/day.
Thanks,
Jake Grubisch, EI
Civil Designer IV
IMEG | formerly C&H Engineering
1143 Stoneridge Drive | Suite 1 | Bozeman, MT 59718
(406) 587-1115 | phone
(406) 624-5160 | mobile
jake.t.grubisch@imegcorp.com
2
website | vCard | map | regional news
Learn more about us and the IMEG story!
AN EQUAL OPPORTUNITY/AFFIRMATIVE ACTION EMPLOYER
This email may contain confidential and/or private information. If you received this email in error please delete and notify sender.
From: Karl A. Johnson <kajohnson@BOZEMAN.NET>
Sent: Tuesday, April 18, 2023 9:59 AM
To: Arielle Stoness <arielle@jdsarchitectsbozeman.com>
Cc: Jesse Sobrepena <jesse@jdsarchitectsbozeman.com>; Jake T. Grubisch <Jake.T.Grubisch@imegcorp.com>; Jacob
Doesschate <jdoesschate@BOZEMAN.NET>
Subject: RE: Pines Phase 2 - Traffic Study
External Email: Treat links and attachments with caution.
Arielle,
The spreadsheet is hard to follow. Its not clear what the inputs or the conclusions are. Please write a clear summary with
only the applicable data per my email below. This needs to come from engineer competent in estimating traffic
demands.
Please do not CC additional engineers not involved in the project on future emails. We all get a lot of emails and
appreciate your help to declutter our inbox when possible.
Thanks,
Karl Johnson, P.E. | Engineer II
City of Bozeman | 20 E. Olive St. | Bozeman, MT 59715
C: 406.451.1693
O: 406.582.2281
kajohnson@bozeman.net
From: Arielle Stoness <arielle@jdsarchitectsbozeman.com>
Sent: Monday, April 17, 2023 4:36 PM
To: Karl A. Johnson <kajohnson@BOZEMAN.NET>
Cc: Jesse Sobrepena <jesse@jdsarchitectsbozeman.com>; Jake T. Grubisch <Jake.T.Grubisch@imegcorp.com>; Lance
Lehigh <llehigh@BOZEMAN.NET>; Griffin Nielsen <GNielsen@BOZEMAN.NET>; Jacob Doesschate
<jdoesschate@BOZEMAN.NET>
Subject: RE: Pines Phase 2 - Traffic Study
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the
sender and know the content is safe.
Karl,
The traffic count is attached for the Pines TIS waiver. It includes both lots/phases.
Thank you,
Arielle Stoness
JDS Architects, Inc.
719 West Mendenhall