HomeMy WebLinkAbout013_FloodHazardReport2023
MEMO
32 Discovery Drive Bozeman, MT 59718 (406) 582-0221 Fax (406) 582-5770
To: City of Bozeman
From: Rory Romey, PE, Tom Chingas, PE, CFM, Eric Foss, EI
Project Name: North Park Development, Phase 1 - Flood Study Update
Project Number: 14-167.10
Date: 6/20/2023
Re:
Update to 2016 Flood Hazard Evaluation for Mandeville Creek
45.705525°, -111.055547°, Bozeman, Montana
Introduction
The original flood hazard evaluation for Mandeville Creek was completed in 2016 using 1-D
modeling. The model used surveyed cross sections gathered throughout the length of the study area.
Elevation data from the 2007 City of Bozeman LiDAR mapping was utilized between the surveyed
cross sections. This model focused on the North Park Development property extending from Frontage
Road upstream to Mandeville Drive. The original flood hazard evaluation discussed flood water being
directed to the northwest along the southern side of the railroad right-of-way (ROW) due to backwater
of the existing culverts under Frontage Road, the main railroad track, and Red Wing Drive. This flow
path was not studied or mapped because it was beyond the Master Site Plan extents for the
development. The purpose of this Flood Study update is to discuss the phases of the North Park
property development along with the required hydraulic improvements associated with each phase
and to show the corresponding effects to the floodplain inundation boundary and water surface
elevations (WSEs).
Project Phasing
Existing Conditions
For this study the existing condition of the North Park Development property is considered to be the
site conditions prior to any development. This was the site condition analyzed for the 2016 Flood
Study. Figure 2 shows the existing condition topography and site features. This model run is intended
to show the comparison of the 1-D modeling from the original flood hazard evaluation to the new
modeling.
Phasing of the North Park Development will include three new creek crossing locations that will
impact the flood hazard boundary. No structures exist near the flood hazard boundary. Phasing also
includes upsizing the two remaining existing culverts under Frontage Road and the main railroad
track.
6/20/2023
Allied Engineering Services, Inc. Flood Hazard Evaluation Page 2
As-Built Condition (as of 3/27/2023)
In 2022 there was a significant amount of earthwork that took place within the railroad ROW to add
siding tracks and stubs for future spur lines. Some of this earthwork filled in the low-laying areas that
convey floodwater to the northwest. The Red Wing Drive crossing was removed as part of this work
and the existing 36” cast iron railroad culvert was extended approximately 40’ upstream to account for
the additional railroad tracks. Figure 3 shows the As-Built conditions topography and site features.
Intermediate Condition
The next phase of the project is to add three crossings to Mandeville Creek. The first crossing will be
for a rail spur line (Track C) to access Tract 2-B. This crossing is anticipated to be constructed in late
2023 or 2024 and is proposed as a precast concrete box culvert with a span of 12’ and a height of 7’
with a 1’ embedment. The remaining two crossings are for Wheat Drive and Cultivar Street. These
two are anticipated to be constructed in 2024 or 2025 and are proposed as precast concrete box
culverts with a span of 18’ and rise of 6’ with embedment depths of 1’.
This phase of the project also involves upsizing the existing 36” cast iron culvert at the main rail line.
The upsized culvert will need to be equal to the capacity of the upstream culvert (for Track C) and the
future upsized downstream culvert at Frontage Road. We anticipate the existing 36” cast iron culvert
will be replaced with a CMP arched culvert with an embedment depth of 1’. The construction of this
culvert replacement is anticipated to take place in late 2023 or 2024. We have been coordinating with
Montana Rail link about the design of this replacement culvert.
Additional rail spurs are proposed to be constructed to the west of Mandeville Creek as well. Figure 4
shows the intermediate condition topography and site features. The intermediate condition assumes
the existing culvert at Frontage Road is left as the 36” RCP/CMP. We do not recommend upsizing the
existing 36” cast iron culvert at the main rail line before upsizing the Frontage Road culvert because
the new overflow path that would be activated (see the Intermediate Condition described in the
Hydraulic Analysis section of this report). However, it is ultimately up to Montana Rail Link on what
they want to decide for replacing their culvert and the associated risks.
Final Condition
The final phase of the project involves replacing the existing 36” RCP/CMP culvert at Frontage Road.
We anticipated this replacement will be a precast concrete box culvert with a span of 12’, rise of 8’,
and embedment depth of 2’. The Frontage Road culvert is anticipated to be replaced in 2024 or 2025.
We have been coordinating with Montana Department of Transportation about the design of this
culvert replacement. Figure 5 shows the final condition topography and site features. All timelines
outlined above are subject to change. As of now, all crossing improvements outlined above are being
included under a single general permit with the Army Corps of Engineers being a primary driver due
to wetland impacts.
Hydrology Analysis
A hydrologic analysis was performed for the 2016 Flood Study. The same flow values were adopted
for this study which are 390-cfs for Mandeville Creek and 127-cfs the Farmer’s Canal. The 2016
Flood Study is included in this report as Attachment 1.
6/20/2023
Allied Engineering Services, Inc. Flood Hazard Evaluation Page 3
Hydraulic Analysis
The updated Flood Study was performed using The Army Corps of Engineer’s Hydrologic
Engineering Center’s River Analysis System (HEC-RAS) version 6.3.1 (USACE, 2022). Mandeville
Creek and the surrounding floodplain area was modeled using a steady-state 2D model consisting of a
cell mesh, inflow and outflow boundary conditions, and 2D connections for the hydraulic structures.
Elevation data for the model was obtained from survey data provided by Allied Engineering, Inc. and
LiDAR data obtained from the 2018 City of Bozeman mapping project. The data’s vertical datum is
NAVD88.
Figure 1 shows the model extents and geometry of the existing conditions. Manning’s n values were
obtained by referencing aerial imagery and from “Open-Channel Hydraulics” (Chow 1959). A
Manning’s n value of 0.045 was appointed to the main channels describing a winding channel with
some weeds and stones. The model was extended far enough downstream so the downstream
boundary conditions did not affect the hydraulics in the development area. However, a normal depth
boundary condition with a friction slope of 0.004 was used for the East Gallatin River outflow
location. Flow hydrograph boundary conditions with constant flow values were used for the inflow
locations where Mandeville Creek and the Farmer’s Canal enter the model area. A 12 hour initial
conditions time was used to ramp up the flows to increase model stability. A model simulation time of
12 hours was used for all plans and the models were checked to ensure a steady-state condition was
met. A Courant controlled time step was selected with a maximum and minimum courant values of
1.0 and 0.4 respectively with a base time step of 1 second.
Existing Conditions
The existing conditions were modeled using the 2D methodology to compare to the 1D model from
the 2016 Flood Study. Figure 2 shows a comparison of the 1D and 2D flood hazard boundaries and
WSEs for the existing condition. As depicted in Figure 2, the flood hazard boundary and WSEs of the
1D and 2D model are similar. The 2D model flood hazard boundary will be used as the existing
condition flood hazard boundary for the remainder of this study.
Where the 1D model ended, the 2D model was extended further downstream to the confluence with
the East Gallatin River as well as further to the northwest and eventually to the East Gallatin River.
The overflow path that flows along the southern side of the railroad ROW to the northwest from the
main track railroad crossing of Mandeville Creek is shown in the 2D model. Approximately 438-cfs
of the total 517-cfs is being directed along this overflow path because the culverts at Frontage Road,
the main railroad track, and Red Wing Drive are undersized.
As-Built Condition (as of 3/27/2023)
A plan was created with an updated geometry and terrain to reflect the As-Built conditions and the
flood hazard boundary was remapped. The resulting flood hazard boundary was the same from the
upstream end of the model to within approximately 400-ft of the railroad ROW. In this case, the
grading associated with the railroad siding tracks requires backwater to build up more head to overtop
to the northwest. This increased WSE causes backwater to extend further upstream and laterally in the
adjacent floodplain. The overflow path to the northwest is maintained in this configuration with
6/20/2023
Allied Engineering Services, Inc. Flood Hazard Evaluation Page 4
approximately 423-cfs being directed that way. Figure 3 shows a comparison between the existing
condition and the as-built condition flood hazard boundary.
Intermediate Condition
The modeling for this phase of the project was completed using the anticipated culvert sizing and
grading discussed in the Project Phasing section. The three new crossings upstream of the main rail
line in this intermediate condition have minimal impact to the flood hazard extents because each
culvert is sized to handle the 517-cfs. However, there is a small backwater area at the Cultivar Street
crossing where the flood hazard extent increases due to a localized increase in the WSE. This
backwater area extends approximately 400’ upstream of the proposed Cultivar Street crossing. The
areas are considered to be ineffective flow areas not providing conveyance. The areas will be
impacted by the approved (but not yet constructed) shared use trail. The areas are noted Figure 5 and
are considered to be filled as part of future development. Because the areas are considered to be
ineffective flow areas, impacts to the BFEs are not anticipated. Figure 4 shows a comparison between
the existing conditions flood hazard boundary and this intermediate condition.
It is important to note that upsizing the main rail line culvert before the Frontage Road culvert creates
a new overflow path on north side of the railroad tracks. In previous iterations the northwest overflow
path remains on the south side of the railroad tracks until crossing under N 19th Ave and I-90. In this
scenario, a large amount of backwater would form just upstream of the existing Frontage Road culvert
and would overtop Frontage Road near the intersection with Reeves Road. This new overflow path
has the potential to flood existing structures before the flood water reaches the East Gallatin River.
Final Condition
The final condition will allow the full flow from the 100-year event to reach the East Gallatin River
without backwatering upstream of the railroad or the Frontage Road crossing as well as without
activating the northwest overflow path. In this configuration the flood hazard boundary along
Mandeville Creek is very similar to the existing condition with the exception of the area immediate
upstream of Cultivar Lane as discussed in the intermediate condition section above. Figure 5 shows
the flood hazard boundary for the final condition.
It should be noted that the elevation data used for the current study has been updated since the original
study took place. The most recent (year 2018) COB Lidar was used for the current study along with
finished design grading for the proposed conditions. Table 1 shows a comparison of base flood
elevations at key locations for the various conditions previously outlined.
Table 1. BFE Comparisons (Units = Feet, Datum = NAVD 88)
Location* Existing Condition
(2016 Flood Study)
As-Built Condition
(as of 3/27/3023)
Intermediate
Condition
Final
Condition
Cultivar Lane 4701.9 4701.9 4706.2 4706.2
Wheat Drive 4675.0 4675.1 4677.1 4677.0
Track C 4670.5 4673.8 4673.2 4671.3
Railroad Main
Track 4670.5 4673.8 4671.8 4668.7
*The WSE for these were taken just upstream of the indicated location
FIGURE: 1DRAWN BY: TWCDATE: 5/17/2023PROJECT: 14-167³0 540 1,080 1,620Feet
NORTH PARK2D MODEL SET UP - EX. CONDITIONSBOZEMAN, MT P:\2014\14-167 North Park\08 ArcGIS\2023 - Flood Study\Zoomed In\Figure 1 - Model Set Up.mxd1 inch = 900 feet
Mandeville Creek
Legend
2D Model Area
Boundary Condition Lines (Inflow/Outflow Locations)
2D Connections (Hydraulic Structure Locations)
2D Existing Conditions - 1% AC Flood Hazard Boundary
East Gallatin River
46684692466647084698467647004695469047154 7 1 04680 47204670473047254700468546654660466547454740473047254675467046654 6 5 54650
47254 7 2 0
470547004 6 8 0
4655
46454730472046654 67 04660 47354735473047304725472547 1 54695
4 6 7 5 46704665466 04655 4655473046604680.44709.84707.84706.24702.947004697.54694.64691.54686.74683.54715.74672.44669.84675.5FIGURE: 2DRAWN BY: TWCDATE: 5/17/2023PROJECT: 14-167³0 240 480 720Feet
NORTH PARKEX. CONDITIONS - 1D/2D COMPARISON
BOZEMAN, MT P:\2014\14-167 North Park\08 ArcGIS\2023 - Flood Study\Zoomed In\Figure 1 - Existing Conditions.mxd1 inch = 400 feet
Mandeville Creek
Legend
1D Cross Sections
2016 Flood Study 1D - 1% AC Flood Hazard Boundary
2D WSE Contours (2-ft Contour Interval)
2023 Flood Study 2D - 1% AC Flood Hazard Boundary
Northwest Overflow Path
Frontage Road
Main Railroad Track
Red Wing Drive
47154710469046854705470046954660465547454740473547304725467046654665466047204 7 1 54675467046554650 472546704 7 1 5
46954 6 8 0 4 67 046554650 47354730472547304730473047254725468046704665466546 604660 46554730FIGURE: 3DRAWN BY: TWCDATE: 5/17/2023PROJECT: 14-167³0 240 480 720Feet
NORTH PARKAS-BUILT/EX. COND. COMPARISON
BOZEMAN, MT P:\2014\14-167 North Park\08 ArcGIS\2023 - Flood Study\Zoomed In\Figure 3 - As-Built Conditions.mxd1 inch = 400 feet
Mandeville Creek
Legend
Siding Tracks
Existing Conditions - 1% AC Flood Hazard Boundary
As-Built (3/27/2023) - 1% AC Flood Hazard Boundary
Northwest Overflow Path
Frontage Road
Main Railroad Track
Red Wing Drive crossing removed and railroad culvert extended
471547104705469046854670466547454740473546754 6 7 0
4730472546704665466546604 6 5 54650
4 7 2 5
4720
4700468046754 7 1 5
46954 6 8 046554 6604645472047054 6 8 0
4 67 04655 473547304725473047304730472547254 7 1 546954670467046654665
46 604660 46554730FIGURE: 4DRAWN BY: TWCDATE: 5/23/2023PROJECT: 14-167³0 240 480 720Feet
NORTH PARKINTERMEDIATE COND. COMPARISON
BOZEMAN, MT P:\2014\14-167 North Park\08 ArcGIS\2023 - Flood Study\Zoomed In\Figure 4 - Intermediate Condition.mxd1 inch = 400 feet
Legend
Intermediate Condition Features
Existing Conditions - 1% AC Flood Hazard Boundary
Intermeditate Condition - 1% AC Flood Hazard Boundary
Mandeville Creek
Exisintg FrontageRoad culvert
Main Railroad Track
Red Wing Drive crossingremoved and railroad culvertreplaced with box culvert
Cultivar LaneWheat Drive
Additional railroad tracks
Track C with box culvert
Northwest overflowpath is eliminated
New flow path createdon north side of railroad ROW
471547104705469046854670466547454740473546754 6 7 0
4730472546704665466546604 6 5 54650
4 7 2 5
4720
4700467546804 7 1 5
46954 6 8 046554 660464547204 6 8 0
4 67 04655 473547304725473047304730472547254 7 1 546954690467046654665
46 604660 46554730FIGURE: 5DRAWN BY: TWCDATE: 6/20/2023PROJECT: 14-167³0 240 480 720Feet
NORTH PARKFINAL/EX. COND. COMPARISON
BOZEMAN, MT P:\2014\14-167 North Park\08 ArcGIS\2023 - Flood Study\Zoomed In\Figure 5 - Final Condition.mxd1 inch = 400 feet
Mandeville Creek
Legend
Final Condition Features
Shared Use Trail
Existing Conditions - 1% AC Flood Hazard Boundary
Final Condition - 1% AC Flood Hazard Boundary
Frontage Road culvertreplaced with box culvert
Main Railroad Track
Red Wing Drive crossingremoved and railroad culvertreplaced with box culvert
Cultivar Lane
Wheat Drive
Additional railroad tracks
Northwest overflowpath is eliminated
Track C with box culvert
Area of ineffective flowand shallow flooding,anticipated impact from approvedshared use trail location
Area of ineffective flowand shallow flooding
Shared use trail