May 21, 2025
Taylor Lonsdale, PE
City of Bozeman
20 East Olive Street
Bozeman, MT 59715
Reference: Traffic Impact Study Update Letter – Bozeman Health Phase 1
Project No. 17095.13
Dear Taylor:
The purpose of this letter is to provide a traffic impact study (TIS) update for Phase 1
of the Bozeman Health Campus Master Plan. A TIS was originally completed in
support of the original master site plan, which was submitted in November of 2023. A
TIS was resubmitted in May of 2025 with an updated phasing plan. This letter will
address internal and external impacts to be considered with construction of Phase 1.
The current Phase 1 plan proposes expansion of Lot E further west to add
approximately 165 parking spaces, expansion of Lot A to the northwest to add
approximately 180 parking spaces, and removal of Lot I, which will displace
approximately 150 parking spaces. The old maintenance yard will also be brought to
compliance with this phase. The net number of new parking spaces added with Phase
1 will be 195. The current phasing plan is shown in the attached figure.
The construction of additional parking is typically accompanied by an increase in
demand. However, in this case the Phase 1 parking expansion serves to meet an
existing demand for surplus spaces as determined through surveys of current
patrons, and will allow for visitors to park closer to the building frontages. The
proposed parking increase will also prepare the campus for future phases of the
master plan, which will ultimately include a new building and two existing building
expansions.
Due to the above, trip generation estimates were not calculated for the proposed
parking lot expansions in Phase 1. Future phases that include new building square
footage will include update letters with trip generation calculations to evaluate
consistency with the assumptions presented in the 2025 Master Plan TIS and review
of recommendations from that study. Intermediate traffic volume, capacity, and/or
signal warrant analysis may also be included in updates for future phases.
The proposed Phase 1 parking expansion is likely to shift a majority of existing
vehicles using Lot I to Lot E. The external ingress and egress routes from Highland
Mr. Taylor Lonsdale, PE
May 21, 2025
Page 2
Boulevard are not anticipated to change significantly based on the Lot E expansion,
although some vehicles may shift to access Lot E via Ellis Street. Access to the Lot A
expansion will be via Entrance 1 from Highland Boulevard and exiting vehicles will
have the option to utilize a northbound one-way approach onto Ellis Street east of Lot
G. This approach will be maintained as a northbound one-way road due to the large
trucks that access a loading bay on the east side of Medical Office Building (MOB) 4.
It is anticipated that a higher demand of ingress trips to Lot A will utilize Entrance 1
and a higher demand of egress trips from Lot A will utilize Ellis Street. This increase
in trips is projected to have minor impacts to approach delay at the impacted
intersections.
The intersections of Highland Boulevard with Old Highland Boulevard and Entrance 1
each have northbound left-turn lanes and Entrance 1 has a southbound right-turn
lane. The Highland Boulevard/Ellis Street intersection is signalized with left-turn
lanes on all four approaches. Each of these intersections is equipped to handle
additional demand from a potential redistribution of parking demand on the site.
The proposed Phase 1 plan is consistent with the most recent TIS. This update letter
does not include a 15-year projection, as Phase 1 will not generate additional traffic
but will instead result in an internal redistribution of existing site traffic.
As future phases are developed, subsequent update letters will be prepared to
compare each phase against the master TIS. These future updates will also address
the timing and implementation of the recommended improvements.
If you have any questions or concerns, please feel free to contact me at 406-922-4326
or astoltzfus@sanbell.com.
Sincerely,
Audrey Stoltzfus, PE, RSP2I
Project Engineer
SJW/ars/jhs
Enc.
Bozeman Health: Campus Phasing Plan
P:17095.13_Bozeman_Health_Phase_1_Traffic_5.21.2025
MOB 2MOB 1
MOB 4
MOB 3
MOB 5
MOB 6
Highlan
d
Blv
d
A
B
C
D
E
G
F
2
1
Campus Parking Calculation
1
2
165 Parking Spaces
180 Parking Spaces
NET NEW SPACES: 525 Spaces
Parking Garage
55 displaced, 500 new
445 NET spaces
+
+
–
–
115 Displaced Spaces
150 Displaced spaces (With the removal of Lot I)
Campus Phasing Plan
PHASE 1
PHASE 3
PHASE 5
PHASE 2
PHASE 4
MOB 6
5 Floors, 100,000 Total SF
Emergency Dept Expansion
7,500 Total SF
Bridger Tower Expansion
2 New Floors,
32,000 Total SF
Wayfinding Concourse
Existing Parking Lot
NamesA
Parking Garage
500 total parking spaces
Maintenance Yard
Old maintenance yard to be brought to compliance
Bozeman Health: Campus Phasing Plan