HomeMy WebLinkAboutBoutique Hotel Staff PresentationTuesday, August 5th, 2025
•Proposal to develop vacant parcel
that serves as parking lot
•Six-story hotel
•Located with the NCOD, outside of
a Historic District
•Deviation request is to allow for
encroachment into the watercourse
setback (Bozeman Creek)
•Zoned B-3
•Decision issued May 20, 2025
•Commission approved
reconsideration June 24, 2025
Boutique Hotel Site Plan/Commercial Certificate of Appropriateness with
deviation request, application #24147
Site Context
City Hall
Subject
Property
Hawthorne
Elementary
Main Street
Soroptimist
Park
Proposed Site Plan
Six-story hotel
•Ground floor: hotel lobby,
commercial space, back of house
operations
•Second-sixth floor: hotel rooms
•Sixth floor: rooftop bar
Total number of rooms: 71
Open space between Bozeman
Creek and building
Proposes off-site parking and valet
services
Building Design
Proposed off-site parking
Proposes off-site parking to accommodate the required 48 spaces
Parking agreement required prior to final site plan approval
Subject
Property
Proposed
off-site
parking
Deviation Request
Project is directly adjacent to Bozeman Creek which
requires a 35-foot setback per 38.410.100
Deviation requests to allow for up to a 30-foot
encroachment into watercourse setback.
•Building footprint is outside of watercourse setback
•Open space hardscaping, building awning, and
supporting utility infrastructure are in watercourse
setback
•Requires City Commission review where a
deviation is more than 20% of the standard
Deviation Request
Open space area features
-Permeable pavers on patio space
-Retaining wall between landscaped area
and patio
Landscape Features
-Watercourse setback planting to meet
standards suited for riparian area
-Non-disturbance zone along 5 feet of
stream bank
-Native seed provided where necessary
-18 trees to remain, 7 to be removed
Deviation Review Criteria
1)Modifications must be more historically appropriate for the building and site in question
and the adjacent properties,
2)Modifications will have minimal adverse effects on abutting properties or the permitted
uses thereof
3)Modifications must assure the protection of the public health, safety and general
welfare.
Deviation Criteria #1
Modifications must be more historically appropriate for the building and site in question
and the adjacent properties.
Modifications will have minimal adverse effects on abutting properties or the permitted
uses thereof.
Deviation Criteria #2
Modifications must assure the protection of the public health, safety and general welfare.
Deviation Criteria #3
Downtown Creek Enhancement Plan
Conformance with other adopted City of Bozeman Plans
Downtown Bozeman Improvement Plan
Revitalize Relatives Art Installation & Demonstration Garden outside City Hall
Examples of existing Bozeman Creek improvements
Bogert Park Bozeman Creek Restoration
•Public notice was posted on-site, published in the newspaper, and mailed to property owners
within 200 feet.
• 69 written comments were received as of the date of the staff report. Four public comments
have been received between the finalization of the staff report and today.
•Comment for and against the project.
• The comments relevant to the review criteria not in favor of the project are focused on the
following issues:
•Not in favor of the use of adjacent off-site parking
•Loss of parking spaces used by downtown businesses
•The need for a parking analysis of the general area
•Not in favor of watercourse setback encroachment
•The comments in favor focus on the quality of the building and the improvement of the site
downtown, improvement of the access to Bozeman Creek, and support for archaeological
conditions.
Public Comment
•BMC 38.230.100 – Plan Review Criteria
•BMC 38.230.080 – Certificate of Appropriateness Criteria
•BMC 38.250.050 – Deviations
The Development Review Committee finds the application is sufficient for approval with
conditions and code provisions.
If City Commission denies the deviation request, a new site plan application would be
required, and open space area would just be landscaped with no access to Bozeman
Creek
Review Criteria
Recommended Motion
Having reviewed and considered the application materials, public comment, and
all the information presented, I hereby adopt the staff findings as presented in
the staff report for application 24147 that the application does meet the criteria
required for approval and move to approve with conditions the Boutique Hotel
application for the deviation requested to allow for encroachment of open space
hardscaping, a 4-foot awning, and supporting utility infrastructure into the 35-
foot watercourse setback.
4.Prior to final site plan approval, the applicant must submit additional
information to the Community Development Department depicting the
concept submitted at the public meeting on August 5, 2025, including the
reduction in the patio width and the provision of a natural fines path, for
review and approval by the Community Development Director.
Conditions of Approval
1.BMC 38.340.010.F. The applicant must consult with a qualified professional,
approved by the Director of Community Development, to conduct
archeological monitoring or another similar process before and during
excavation work. Any items of significance found must be reported and
cataloged. A report of the process conducted and the findings following the
exploration and monitoring must be submitted to the Community
Development Department.
2.BMC 38.340.010.F. The applicant must submit a proposal to the Community
Development Department for an on-site installation that recognizes the
history and significance of the site. This may include, but is not limited to a
sign, artwork, plaque, or other commemorative display. The proposal must
specify the design, content, and the intended location on the site. The
content must include, at a minimum, the site's history, historic photographs,
and recognition of the creek. The applicant is encouraged to work with the
Downtown Bozeman Partnership and other appropriate parties to adhere to
the Downtown Bozeman Improvement Plan. The proposed installation must
be reviewed and approved by the Community Development Department
prior to installation and must be in place prior to planning approval of final
routing for occupancy.
3.The applicant must ensure the exterior patio is a public-use area (as defined
by the International Building Code 2021) that makes exterior spaces
available to the general public.
Building Design
Building Design
Proposed valet services
Proposes 2 valet parking spaces along Mendenhall Street which eliminates some on-street
parking along Mendenhall
Requires compensation for each on-street parking space eliminated and Parking Commission