Tyler Steinway
From:Derek Williams <derek@bridgerdevelop.com>
Sent:Saturday, March 1, 2025 8:20 PM
To:Chris Naumann; Chad Schreiner; Bobby Egeberg; Glen Perry; Tyler Steinway; Rob Pertzborn
Subject:FW: [EXTERNAL]Meadow Bridge and payback districts
Attachments:ATT00001.txt; ATT00002.htm
Hey team,
See email below from Lance Lehigh. Short of it, we will not have to pay anything into the payback districts for
Meadow Bridge. He has already discussed this with Alicia also.
Derek
Derek Williams, P.E. | Owner/Founder
PO Box 10130
Bozeman, Montana 59719
303-887-4045
derek@bridgerdevelop.com
From: Lance Lehigh <llehigh@BOZEMAN.NET>
Sent: Friday, February 28, 2025 2:20 PM
To: Derek Williams <derek@bridgerdevelop.com>
Subject: RE: [EXTERNAL]Meadow Bridge and payback districts
Hey Derek,
I apologize for not getting back to you sooner.
Meadow Bridge is located within the originating development/subdivision of Meadow Creek. Parcel 10 was the
originating development, which includes your development.
The originating development has paid their respective Pro-Rata share for the associated improvements as they
were the ones who put the infrastructure in to service the area.
The Meadow Creek Payback applies to properties that were not in the originating development. Therefore, the
payback does not apply to Meadow Bridge.
I have discussed this with Alicia, and these comments will be resolved as part of the preliminary plat application.
Please let me know if you need anything else.
Lance
2
City of Bozeman MT
Lance Lehigh, PE, CFM | Engineer III
From: Derek Williams <derek@bridgerdevelop.com>
Sent: Monday, February 17, 2025 11:16 AM
To: Lance Lehigh <llehigh@BOZEMAN.NET>
Subject: [EXTERNAL]Meadow Bridge and payback districts
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the
sender and know the content is safe.
Hey Lance,
Hope you are doing well! I wanted to follow up on the conversation you and I had back in December about Meadow
Bridge and payback districts. I had called you about the notice we got (see attached) and you had stated that the
notice did not apply to us and that we probably would not be obligated to pay into any of the payback districts
since Meadow Creek (which we are part of) was the project that created those districts.
We have received comments back on our preliminary plat and one of the comments made by Alicia was that our
project is subject to those payback districts. There was a caveat in her comment though that stated “If the subject
property did not participate in the original cost of construction of improvements the subject property will be
accessed a payback charge prior to final plat approval”. So my question is can you confirm that we would not be
subject to the payback districts or point me in a direction that I could get confirmation?
Thanks Lance!
Derek
Derek Williams, P.E. | Owner/Founder
PO Box 10130
Bozeman, Montana 59719
303-887-4045
derek@bridgerdevelop.com