HomeMy WebLinkAbout12 Evergoods Geotechnical Report
January 22, 2025
Doug Minarik
Minarik Architecture, Inc.
618 N. Wallace Ave.
Bozeman, MT 59715
e-mail: doug@minarikarch.com (Sent via email only)
jack@evergoods.us
Re: Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Commerce Sub. – Bozeman, MT
Dear Mr. Minarik:
This letter and attachments comprise our final geotechnical report for the proposed Evergoods project,
which will be constructed on Lot 2A, Block 1 of the Glen Lake Commerce Subdivision on the northeast
side of Bozeman, MT. This project site is located along the west side of Manley Road and across the
street from the Mesa Moving and Storage facility. The new site development will include a two-story
commercial building that is underlain by an at-grade slab (slab-on-grade) and surrounded on its west
and south sides by a small, asphalt parking lot area.
The content and geotechnical recommendations in this report are based on our understanding of the
project, investigation of the project area’s subsurface conditions (via 10 test pits that were dug back on
February 13, 2003 and May 9, 2018), and our previous geotechnical experience on other commercial
building projects in Bozeman. The purpose of the report is to summarize the site’s soil and groundwater
conditions; identify any geotechnical issues that either exist or we foresee; and present geotechnical-
related recommendations for planning, design, and construction. This report should be reviewed and
used by the Design Team, General Contractor, and the Site/Earthwork Contractors.
• Note: In 2003, AESI dug seven test pits and prepared a geotechnical report for the property that
was subdivided/developed into the Glen Lake Commerce Subdivision. At that time, the property
was being considered for a new City of Bozeman solid waste transfer station project. The seven
test pit logs from this earlier work are included as part of this report, which updates and builds
upon our 2003 geotechnical report and provides specific recommendations for Lot 2A.
• Note: In May 2018, AESI dug three additional test pits in the project area (along the west side of
Manley Road) as part of our geotechnical investigation for the Manley Road improvements. The
test pit logs and test pit photos from this earlier work are also included as part of this report.
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 2
• Note: In May 2018, Iron Horse Road, which is the city street within the Glen Lake Commerce
Subdivision, was constructed. AESI was retained to observe/inspect the roadway’s subgrade soil
conditions (which consisted of shallow, native sandy gravel). A few subgrade photos from the
road construction are included as part of this report.
• Note: No current test pits were conducted on Lot 2A during the preparation of this geotechnical
report. Due to all of our existing 2003 and 2018 soils information from the project area, which
includes six test pits that were dug on or very near Lot 2A, we do not believe that additional test
pits are warranted for this project.
• Note: During our 2003 test pits, which were dug across an undeveloped piece of property, the
Lot 2A area was found to be blanketed by about a 6 to 9-inch thick layer of gravelly fill material
(ie. random surface fill) that overlies a buried layer of native topsoil. There is a possibility that
during the development of Glen Lake Commerce Subdivision (in 2018) that some additional fill
material was spread on Lot 2A. Therefore, the thickness of surface fill may be thicker than what
is shown in this report. If this is found to be the case, we do not expect it will be significantly
different, since the site terrain generally appears to be unchanged from the 2003 work.
UNDERSTANDING OF SUBSURFACE CONDITIONS
Test pit logs and photos are attached to this report for reference. However, trying to review 10 test pit
logs and relate them to a map showing the test pit locations can be time consuming and difficult to do.
For this report, we have prepared five figures that illustrate and summarize the site conditions across
the entire Glen Lake Commerce Subdivision area. We recommend these attached figures be reviewed
since they show an easy-to-understand, “snapshot view”. A description of the figures is as follows:
• Figure 1 – Test Pit Locations: This figure shows the Lot 2A project site and the approximate
locations of the 10 test pits. Pits 1 through 7 were dug in 2003; while pits A through C were dug
in 2018. The base map for all five figures is an OnXmaps aerial photo of the project area.
• Figure 2 – Test Pit Locations w/ Thickness of Native Topsoil (Incl. Any Surface Fill): This figure
shows the thickness of native topsoil (including any surface fill material) at each of the test pit
locations. In most test pits, the ground surface is covered by a 6 to 9-inch layer of surface fill
that in turn overlies a 3 to 12-inch layer of buried, native topsoil (depending on the location).
• Figure 3 – Test Pit Locations w/ Thickness of Native Silt/Clay (Under Topsoil Layer): This figure
shows the thickness of native silt/clay (underlying the buried topsoil layer) at each of the test pit
locations. In most areas, the silt/clay thickness ranges from 0.5 to 1.0 feet, but it was found to
have a “top-end” thickness of 1.5 feet in TP-B (which lies adjacent to Lot 2A).
• Figure 4 – Test Pit Locations w/ Depth to Native Sandy Gravel (“Target” Bearing Material): This
figure shows the depth to top of native sandy gravel (“target” bearing material) at each of the
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 3
test pit locations. In most areas, the depth to native gravel ranges from 1.5 to 2.5 feet; with the
deepest gravel being found in TP-B at 3.2 feet. It should be noted that the upper 6 to 9 inches of
native gravel is often a little more of a smaller, silty, sandy gravel, which transitions to “cleaner”
gravel with depth. Ideally, the “target” foundation bearing material for all perimeter, interior,
and exterior footings is the “cleaner” gravel.
• Figure 5 – Test Pit Locations w/ Depth to Groundwater on 2/13/03: This figure shows the depth
to groundwater on 2/13/03 (during test pit exploration) at each of the test pit locations. Depth
to groundwater ranged from 10 feet to > 15 feet (depending on location). In the area of Lot 2A,
the water level was > 12 feet.
UNDERSTANDING OF FOUNDATION RECOMMENDATIONS
The two main foundation recommendations include: 1) Support all footings directly on native gravel or
on granular structural fill that in turn bears on the “target” gravel; and 2) Support the interior slab on a
minimum 18-inch gravel section consisting of 6 inches of crushed rock underlain by 12 inches of granular
structural fill. Two foundation details (ie. Figures 6 and 7) are provided that illustrate the site conditions
and our recommendations. Figure 6 presents Option 1, which entails supporting the interior slab on the
minimum gravel section and excavating (over-excavating as necessary) all perimeter/exterior/interior
footings down to footing grade and to reach “target” gravel. In contrast, Figure 7 shows Option 2, which
consists of mass over-excavating the entire building slab area to “target” gravel and excavating (over-
excavating as necessary) all perimeter/exterior footings down to footing grade and to reach “target”
gravel. Due to shallow gravel depths, most perimeter footings should bear in or very near the “target”
gravel; meaning there should not be much need for footing over-excavation/replacement. In contrast,
the interior footings (under slab) will likely require more/deeper over-excavation/replacement in order
to reach “target” gravel. The excavation choice (by the Contractor) between Options 1 and 2 (ie. trench
excavation of interior footings vs. mass excavation of building footprint) will likely be dictated by the
locations, spacing, and concentration of interior footings.
SITE LOCATION AND EXISTING CONDITIONS
Lot 2A is a 1.06-acre property located in the southern half of the Glen Lake Commerce Subdivision. It is
bounded by Manley Road (on the east), by Iron Horse Road (on the west), by Lot 1 (on the south), and
by Lot 5 (on the north). The site terrain is relatively flat-lying that slopes to the north at about a 1.0 to
2.0 percent grade. Nearby businesses include Mesa Moving and Storage and Map Brewing. To date, all
lots in the subdivision remain undeveloped, except for one. See Figures 1 through 5 for a site map that
shows an aerial image of the project area.
PROJECT UNDERSTANDING
Provided below (on the following page) is our understanding of the site development project and what it
will include (based on review of Architectural concept plans):
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 4
• The building will be located on the north/northeast side of the lot.
• It will be a two-story, commercial building that is underlain by an at-grade slab (slab-on-grade)
and supported on a conventional shallow foundation (consisting of perimeter footings/frost
walls and interior footings).
• No basement or crawl space areas are being planned under the building.
• Site utilities will include water, fire, and sewer services that connect to City of Bozeman water
and sewer mains within Iron Horse Road as well as on-site stormwater drainage improvements
(piping and infrastructure).
• Most likely, the project will include an underground stormwater system for stormwater disposal
and detention.
• Site concrete areas will include sidewalks, building entryways, and exterior patio spaces.
• Asphalt parking lots will border the west and south sides of the building with two driveway
approaches to Iron Horse Road. The site will not be accessed directly from Manley Road (on the
east). Due to the nature of the commercial business, the parking lot will predominately be used
by light vehicles with truck traffic being limited to weekly garbage truck service.
SUMMARY OF SITE CONDITIONS
Provided below is a quick summary of the site conditions. More detail is provided later in the report.
• In 2003, the Lot 2A area was blanketed by about a 1.5-foot thick section of “random surface fill
material overlying a buried topsoil layer”. The surface fill is gravelly with intermixed silt/clay and
ranges from 6 to 9 inches thick; while the underlying topsoil is black/organic and ranges from
about 6 to 12 inches. Due to the subdivision development/construction in 2018, there may be a
little more fill thickness on the lot now than what was observed in 2003.
• Underlying the buried topsoil layer is a 0.5 to 1.5-foot layer of native silt/clay (depending on the
location). These soils are dark brown to brown, stiff to very stiff, and slightly moist to moist.
• Beginning at depths of 1.5 to 2.5 feet (in most areas) and as deep as 3.2 feet (in TP-B) is the
native sandy gravel with cobbles. These gravel materials extended to the bottom of all test pits
at depths of 12 to 15 feet. In general, the uppermost 6 to 9 inches of the native gravel is a little
more of a silty, sandy gravel (“dirtier gravel) with smaller gravels. Below this depth, the gravels
transition to “cleaner” gravels with larger cobbles.
• In February 2003, the groundwater depth was > 12 feet (in the area near Lot 2A).
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 5
SUMMARY OF RECOMMENDATIONS
Provided below is a quick summary of the geotechnical recommendations. More detail is provided later
in the report.
• The native sandy gravel beginning at depths of 1.5 to 2.5 feet (in most areas) is the “target”
bearing material for foundation support. Ideally, all footings should bear on the “cleaner” gravel
that begins about 6 to 9 inches below the top of the gravel.
• All building footings (including perimeter, interior, and exterior footings) must bear on “target”
sandy gravel or on granular structural fill that in turn bears on “target” gravel. Based on gravel
bearing conditions, the design soils bearing pressure for foundation design is 2,500 psf.
• The interior slab shall be underlain by a minimum 18-inch section of crushed rock and granular
structural fill. Depending on topsoil stripping depths (relative to bottom of slab grade), more
than 18 inches of gravel may be needed.
• All structural fill under footings, slabs and for interior wall backfill shall be imported gravel. We
do also recommend that exterior wall backfill under slabs consist of imported or on-site gravel
(to minimize any frost heaving potential).
• We recommend the interior slab be underlain by a 15-mil vapor barrier for moisture protection.
If required by the IBC, perimeter foundation walls shall be damp-proofed. Due to the at-grade
slab foundation configuration, no perimeter footing drains are necessary.
• Exterior concrete slabs for sidewalks, building entryways, and patios shall be 4 inches thick
(min.) and supported on 6 to 12 inches of crushed rock (depending on the slab location relative
to the building foundation). Concrete areas away from building shall be underlain by 6 inches
(min.) of crushed rock; while those adjacent to the building shall be underlain by 12 inches
(min.) of crushed rock. A greater thickness of crushed rock will further reduce frost heaving.
• Exterior concrete slabs for driveway approaches shall be 6 inches thick (min.) and supported on
an 18-inch gravel section consisting of crushed rock (6 inches) and sub-base gravel (12 inches).
• We recommend a light-duty, pavement section for the asphalt parking lot. This is our standard
section for commercial/office-type projects. Provided below is the design pavement section:
o 3” Asphalt
o 6” Base Course Gravel (1.5”-minus)
o 15” Sub-Base Course Gravel (6”-minus) – New or Salvaged Gravel
o 8 oz. Non-Woven Geotextile Fabric (Not necessary for “clean” gravel subgrade)
o Stable subgrade (dry/hard/compaced)
24” Total Section Thickness
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 6
DESIGN CONSIDERATIONS
Provided below are some design considerations for the project:
• Geotechnical Report included in Bid Documents: This geotechnical report should be included in
the bidding documents and made part of the project specifications. All bidding contractors need
to be informed of the site conditions and geotechnical recommendations.
• Polyethylene Encasement of DIP Fire Service: The building’s water service line will most likely be
copper; while the fire service will be ductile iron pipe (DIP) per Bozeman design standards. For
conservancy, we recommend that DIP fire lines be wrapped with V-bio enhanced, polyethylene
encasement (for added corrision protection).
• Hydraulic Connection of Stormwater System to Native Gravel: We recommend that the under-
ground stormwater system(s) be designed/sized for a gravel infiltration rate of 4.0 inches/hour
(per Circular DEQ-8). By doing so, the system footprint will be smaller (as opposed to using a
much slower silt/clay rate). This will require the system be hydraulically connected to the native
sandy gravel. This can be accomplished by bearing the system directly in/on native gravels or by
over-excavating under the system as needed (down to native gravel) and placing free-draining
gravel/rock/cobble material (back up to system grade). The Civil Plans should clearly state that
the system needs to drain into native gravels.
CONSTRUCTION CONSIDERATIONS
Provided below are some construction considerations for the project:
• Footing Excavation vs. Mass Excavation: All footings need to bear on either native gravel or on
granular structural fill that in turn bears on “target” gravel. We expect all perimeter footings
will be trench excavated (and over-excavated as necessary to reach “target” gravel). The main
choice (by the Contractor) will be how to excavate interior footings. Two options are provided.
Option 1 consists of individual over-excavation of interior footings (down to “target” gravel);
while Option 2 consists of mass over-excavation of the slab area (down to “target” gravel). The
number and spacing of interior footings will likely drive the excavation decision.
• Over-Excavation of Sand Seams at Footing Grade: In some areas, the native gravels will likely
contain some interbedded, thin seams of sand. If during foundation excavation there are sandy
areas within the “target” gravel surface at footing grade, we recommend these areas/pockets of
loose sand be removed/replaced down to more gravelly material.
• Salvaging/Re-Use of Native Gravel: Due to the site’s shallow gravels, foundation excavation may
generate some native gravel. Provided the gravel is “clean” and not contaminated with silt/clay,
it can be salvaged/re-used for exterior wall backfill and sub-base gravel under pavements.
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 7
• Use of 1”-Minus Clean Crushed Rock for Plumbing Trench Backfill under Slabs: We have found
that the use of 1”-minus, clean crushed rock works great for backfill of plumbing trenches under
slabs. This material is easy to place and vibratory compact with small, walk-behind equipment
(plate compactors). We recommend using crushed rock for all sub-slab trench backfill material.
EXPLORATIONS, TESTING, AND SUBSURFACE CONDITIONS
Subsurface Explorations
Subsurface conditions were investigated across the Glen Lake Commerce Subdivision area by Lee Evans,
a professional geotechnical engineer with Allied Engineering, on February 13, 2003. At the time, this site
was being considered by the City of Bozeman for a new solid waste transfer station. Seven test pits
were dug as part of this work and identified as TP-1 through TP-7. All pits extended to depths of 12 to
15 feet. In May 2018, AESI dug test pits along Manley Road as part of the geotechnical investigation for
the road improvements project. Three of the pits, which extended to depths of 3 to 6 feet, were located
adjacent to the subdivision area. These were identified as TP-A through TP-C. See Figures 1 through 5
for site maps that show the approximate test pit locations.
• Note: The test pits located on or near Lot 2A include TP-5 through TP-7 and TP-A through TP-C.
• Note: In addition to the test pits, AESI was also involved during the construction of Iron Horse
Road in 2018. We inspected the subgrade conditions, which consisted of clean, cobbly sandy
gravel beginning at shallow depths. Five construction photos are attached.
During the explorations, soil and groundwater conditions were visually characterized, measured, and
logged. The relative density of the soils was estimated based on pocket penetrometer measurements,
ease/difficulty of digging, and the sidewall stability of the test pit excavations. Test pit logs are attached.
Each log provides an array of field information, such as soil depths, thicknesses, and descriptions,
groundwater depth measurements (at the time of exploration), relative density data, soil sample
information, and a sketch of the soil stratigraphy. Please be aware that the detail provided on the logs
cannot be accurately summarized in a paragraph; thus, it is important to review the logs in conjunction
with the report. Following completion of the fieldwork, the excavations were backfilled, staked with
identifying lath, and cleaned up to the best extent possible.
To better illustrate the on-site soil conditions, a few test pit photos from our 2018 Manley Road test pits
are attached. The photos show the excavation sidewalls and soil piles. The purpose of the photos is to
clearly illustrate the soil stratigraphy (ie. surface fill overlying topsoil overlying silt/clay overlying sandy
gravel) and the “target” sandy gravel (in sidewall and upon excavation). All photos have been marked
up to call out the soil layers and materials that are described on the logs.
• Note: Please be aware that compaction of test pit backfill soils was not done; therefore, these
areas could be susceptible to future settlement. As discussed in a later section of the report, all
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 8
old test pit locations (that are found to be soft/loose) should be re-excavated to their original
depth and properly backfilled/compacted if they underlie any of the building site improvements,
including foundation footprints, exterior slabs, and asphalt pavement areas.
Laboratory Testing
In 2003, several soil samples were collected and tested for natural moisture content, gradation, and
atterberg limits. See the test pit logs for all available lab testing data.
Soil Conditions
The best way to fully comprehend the site’s soil conditions is to review the test pit location maps
(Figures 1 through 5) in conjunction with the test pit logs/photos. The purpose of the figures is to give a
“snapshot” of the conditions that were found in each test pit, including thickness of native topsoil
(including any random surface fill), thickness of native silt/clay (under the topsoil layer), depth to native
sandy gravel (“target” bearing material), and depth to groundwater on February 13, 2003.
As discussed throughout the first half of the report, the Lot 2A area was found to be blanketed by about
6 to 9 inches of random surface fill in 2003. This material was generally “dirty” sandy gravel with areas
of intermixed silt/clay.
• Note: Due to the 2018 development/construction of Glen Lake Commerce Subdivision, there is
a chance that more random surface fill has been spread on the lot area since the test pits were
dug in 2003. Therefore, the thickness of fill may be found to be thicker than 6 to 9 inches. If this
is the case, the depth to bottom of native topsoil and the depth to top of native sandy gravel will
both be greater than what is presented herein. With that said, the site terrain of Lot 2A does
look very similar to the 2003 conditions; thus, if more fill was spread, it’s likely not overly thick.
Underlying the random surface fill is a 6 to 12-inch layer of buried, native topsoil, which in turn overlies
a 0.5 to 1.5-foot layer of native silt/clay. The topsoil is black; while the silt/clay is dark brown to brown,
stiff to very stiff, and slightly moist to moist.
Beginning at a depth of 1.5 to 2.5 feet (in most areas) and as deep as 3.2 feet on the east side of Lot 2A
(in TP-B) is the top of the native sandy gravel. The gravel materials extended to the bottom of all test
pits at depths of 12 to 15 feet. In general, the upper 6 to 9 inches of the native gravel is a little more of a
silty, sandy gravel (“dirtier” gravel) with smaller gravels. Below this depth, the sandy gravel is “cleaner”
and contains larger gravels and cobbles.
Provided in Tables 1 and 2 (on the following page) are quick summaries of the soil conditions observed
in TP-1 through TP-7 (from the 2003 geotechnical investigation of the subdivision area/property) and in
TP-A through TP-C (from the 2018 geotechnical investigation for the 2020 Manley Road improvements
project). This terminology matches the attached test pit logs.
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 9
Table 1. Summary of Soil Conditions in TP-1 through TP-7 – Subdivision Area
TP
#
RANDOM
SURFACE FILL
NATIVE
TOPSOIL
(BURIED LAYER)
NATIVE
SILT/CLAY
NATIVE
SANDY GRAVEL
1 0.0’ - 0.8’ 0.8’ - 1.7’ 1.7’ - 2.3’ 2.3’ - 13.0’
2 0.0’ - 0.5’ 0.5’ - 0.8’ 0.8’ - 1.6’ 1.6’ - 13.0’
3 -------- 0.0’ - 0.5’ 0.5’ - 1.5’ 1.5’ - 15.0’
4 0.0’ - 0.8’ 0.8’ - 1.4’ 1.4’ - 2.0’ 2.0’ - 15.0’
5 0.0’ - 0.5’ 0.5’ - 1.3’ 1.3’ - 2.3’ 2.3’ - 14.0’
6 0.0’ - 0.7’ 0.7’ - 1.3’ 1.3’ - 2.3’ 2.3’ - 12.0’
7 0.0’ - 0.5’ 0.5’ - 1.5’ -------- 1.5’ - 12.0’
Notes: 1) All soil measurements are depths below existing ground.
2) The closest test pits to Lot 2A include TP-5, TP-6, and TP-7.
Table 2. Summary of Soil Conditions in TP-A through TP-C – Manley Road Corridor
TP
#
ASPHALT
(MANLEY RD)
GRAVEL
SECTION
(MANLEY RD)
RANDOM
SURFACE FILL
NATIVE
TOPSOIL
(BURIED LAYER)
NATIVE
SILT/CLAY
NATIVE
SANDY GRAVEL
A -------- -------- 0.0’ - 1.0’ 1.0’ - 1.5’ 1.5’ - 2.5’ 2.5’ - 6.0’
B 0.0’ - 0.2’ 0.2’ - 1.8’ -------- -------- 1.8’ - 3.2’ 3.2’ - 3.5’
C -------- -------- 0.0’ - 0.4’ 0.4’ - 1.0’ 1.0’ - 2.0’ 2.0’ - 6.0’
Notes: 1) All soil measurements are depths below existing ground.
2) All three test pits lie on the southeast, east, and northeast sides of Lot 2A.
Groundwater Conditions
Groundwater depths are expected to be at 10 feet (or greater) throughout the year in the Lot 2A area.
During our test pits on February 13, 2003, no groundwater was observed in the two, on-site test pits
(TP-5 and TP-7) or the two, nearby test pits (TP-4 and TP-6), all of which extended to 12 to 15 feet. The
shallowest groundwater was found on the west side of the subdivision area (next to railroad) at 10 feet.
GEOTECHNICAL ISSUES
The site conditions do not present any foreseeable geotechnical issues for the proposed project. The
shallow gravels will provide “target” foundation bearing; the building will not have a basement, which
negates high groundwater as a possible concern; and the silt/clay is stiff/slightly moist and will provide
suitable subgrade support for interior/exterior slabs and asphalt pavements.
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 10
GENERAL CONSTRUCTION RECOMMENDATIONS
Re-Excavation of Test Pits
Some of the old test pits will be encroached upon during site work, foundation earthwork, and asphalt
area construction. During backfilling of the pits, the spoils were not compacted. As a result, they may
undergo some soil settlement over time. It is standard practice to address any soft test pit backfill areas
during construction (if they are found). As a general rule, where any of site and building improvements,
including foundations, interior/exterior concrete slabs, underground utilities, and asphalt pavement
areas, will overlie any of the old test pits (especially those that are soft/loose), we recommend they be
re-excavated down to their original depth and properly backfilled/compacted with suitable material
using suitable means/methods. The two, 2003 test pits on Lot 2A were dug to depths of 12 to 14 feet.
Topsoil Stripping and Re-Use
All native topsoil (and old surface fill) must be completely removed from within the building foundation
footprint areas and from under all exterior concrete slab and asphalt pavement areas. Final site grading
(in landscape areas) and the reclamation of disturbed construction areas are the only recommended
uses for organic topsoil or organic-laden materials.
• Note: The Lot 2A area is blanketed by a minimum of 6 to 9 inches of gravelly, random fill that in
turn overlies a 6 to 12-inch layer of buried native topsoil. Due to recent construction activity,
there may be more random fill on the site now as compared to 2003.
Groundwater Dewatering
Due to deep groundwater conditions, groundwater dewatering should not be needed.
Silt/Clay Subgrade Conditions
Once the buried topsoil layer is stripped from under the building, under exterior concrete areas, and
from under parking lots, the subgrade soils will consist of native, dark brown to brown, silt/clay. Based
on the test pits, these soils should be in a slightly moist to moist and stiff to very stiff condition. As a
result, we do not expect any subgrade challenges (ie. overly moist or soft soils). We anticipate stable
subgrade will exist or can be easily achieved with air drying (once the subgrade surface is exposed).
Salvaging and Re-Use of On-Site Gravels
Due to the site’s shallow gravel conditions, there may be an opportunity to generate and salvage some
on-site gravel during foundation excavation and parking lot earthwork. As long as the on-site gravels are
“clean” and not contaminated with silt/clay, they can be re-used for exterior foundation wall backfill
(under exterior slabs) and/or for the sub-base component of the asphalt pavement section.
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 11
Areas Where New Gravel Will Be Required
• All granular structural fill under footings and interior slabs shall consist of new gravel (either 3”-
minus gravel or 1.5”-minus gravel). A commercially-processed gravel material will be more
uniform and compact better.
• We recommend that interior foundation wall backfill under interior slabs consist of new gravel
(either 3”-minus gravel, 1.5”-minus gravel, or 1”-minus crushed rock). Here again, it will be
important to use a small aggregate size material that is easy to compact with small equipment.
• All base course gravel under asphalt pavements shall be new gravel (1.5”-minus gravel).
• Assuming not much quantity of on-site “clean” gravel can be stripped, salvaged, and re-used
from the site work, then most, if not all, of the sub-base course gravel under asphalt pavements
will need to be new gravel (6”-minus gravel).
STRUCTURAL DESIGN PARAMETERS
Foundation Design
The building will be underlain by an at-grade slab (slab-on-grade) and supported on a conventional
shallow foundation consisting of perimeter strip footings/frost walls and interior strip/spread footings
(under the slab).
Seismic Design Factors
A main requirement of the Structural Engineer’s seismic analysis will be a determination of the site class.
Based on our on-site explorations and knowledge of the underlying geology, the site class for the project
site will be Site Class D (as per criteria presented in the 2021 IBC). This site class designation is valid as
long as our foundation recommendations are followed.
To obtain site-specific seismic loading and response spectrum parameters, a web-based application from
the USGS Earthquake Hazards Program can be used. The link to their web page is as follows:
https://earthquake.usgs.gov/hazards/designmaps/. Upon entering this page, there are links to three third-
party interfaces that can be used to obtain the seismic information. The user needs to enter the design
code reference document, site soil classification, risk category, site latitude, and site longitude.
Foundation Bearing Pressure (Conventional Foundation)
As long as our foundation earthwork recommendations are followed, the allowable bearing pressure for
all perimeter, interior, and exterior footings and any other foundation component is 2,500 pounds per
square foot (psf). Allowable bearing pressures from transient loading (due to wind or seismic forces)
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 12
may be increased by 50 percent. We estimate that the above-referenced design bearing pressure will
result in total foundation settlements of one inch or less, with only minor differential settlements.
Lateral Earth Pressures
All foundation walls that will be fixed at the top prior to the placement of backfill should be designed for
an “at rest” equivalent fluid pressure of 60 pounds per cubic foot (pcf). Cantilevered retaining walls
may be designed for a lower, “active” equivalent fluid pressure of 45 pcf, provided either some slight
outward rotation of the wall is acceptable upon backfilling or the wall is constructed in such a way that
accommodates the expected rotation. These “at rest” and “active” design values are only applicable for
walls that will have backfill slopes of less than ten percent; and which will not be externally loaded by
surface pressures applied above and/or behind the wall.
Lateral forces from wind, earthquakes, and earth pressures on the opposite side of the structure will be
resisted by passive earth pressure against the buried portion of the foundation wall and by friction at
the bottom of the footing. Passive earth pressures in compacted backfill should be assumed to have an
equivalent fluid pressure of 280 pcf; while a coefficient of friction of 0.5 is estimated between cast-in-
place concrete and the “target” sandy gravel (or granular structural fill that is placed to build back up to
footing grade from the “target” gravel subgrade). Actual footing loads (not factored or allowable loads)
should be used for calculating frictional resistance to sliding along the base of the footing. Please be
aware that the friction coefficient has no built-in factor of safety; therefore, an appropriate safety factor
should be selected and used in all subsequent calculations for each load case.
The above-referenced, equivalent fluid pressures (for at rest, active, and passive conditions) assume
that the wall will be backfilled with a suitable material that is compacted to an unyielding condition and
it will lie above the groundwater table and/or be well drained; thereby, preventing the backfill from
becoming saturated and the wall from experiencing hydrostatic pressure. Each of these design
pressures is for static conditions and will need to be factored accordingly to represent seismic loading.
We recommend that we be retained to evaluate lateral earth pressures for geometries and/or loading
conditions that do not meet the previously mentioned criteria.
Subgrade Reaction Modulus (under Slabs)
As long as our interior slab support recommendations are followed (as presented later in the report),
the subgrade reaction modulus (k) can be assumed to be 200 pounds/cubic inch (pci). This is a modified
design value that uses the subgrade reaction modulus (k) of the native silt/cay and factors it (increases
it) based on a minimum section thickness of imported gravel to be placed under the slab. This design
value assumes the slab will be underlain by at least 18 inches of compacted gravel or crushed rock.
• Note: We recommend a minimum 18-inch thick, gravel support section under all interior slabs.
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 13
Interior Slab Thickness
We expect that the interior slab thickness will be 4 to 5 inches; and may be reinforced with rebar or wire
mesh. The Structural Engineer is designing the slab.
Soil Corrosivity to Concrete
According to Montana Department of Transportation (MDT) highway design standards, Type I-II cement
is used when soil sulfate contents are less than 0.20%. However, if sulfate levels are between 0.20 and
2.00%, then Type V cement is used.
• Note: Over the years, we have tested several samples of Bozeman-area silt/clay and sandy
gravel. All samples have been non-corrosive to standard concrete.
• Note: Based on previous test results of similar soils, the on-site silt/clay and sandy gravel soils
will not be corrosive to standard concrete. There is no reason to use Type V cement in the
foundation concrete.
FOUNDATION RECOMMENDATIONS
General
Two detailed illustrations showing our excavation/fill/earthwork, foundation bearing, slab support, and
moisture protection recommendations for a slab-on-grade (at-grade slab) foundation configuration are
included as Figures 6 and 7. Both figures are identical, except for providing different options for the
excavation/support of interior footings (under the slab). Please refer to this figure during the review of
the report.
• Note: Figure 6 shows trench over-excavation/replacement of individual interior footings down
to “target” gravel. This is Option 1. The minimum width of over-excavation/structural fill under
footings is dependent on the thickness of structural fill. See the criteria/formula on the figure.
• Note: Figure 7 shows mass over-excavation/replacement of the entire building slab area down
to “target” gravel (which would hence include all interior footings). This is Option 2.
Foundation Design
• The building foundation will be designed as a conventional foundation that consists of perimeter
footings/frost walls and interior footings (under the slab). It will underlain by an at-grade slab.
• The minimum depth of cover for frost protection of perimeter and exterior footings is four feet.
This dimension is measured from bottom of footing up to the final grade of the ground surface.
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 14
Foundation Support
• The “target” foundation bearing material for all perimeter, interior, and exterior footings is the
native sandy gravel that underlies the Lot 2A area beginning at depths of 1.5 to 2.5 feet (in most
areas) and as a deep as 3.2 feet on the east side (in TP-B). Ideally, the best/preferred bearing
material is the “cleaner” sandy gravel with cobbles that underlies the uppermost 6 to 9 inches of
silty, sandy gravel (“dirtier” gravel) with smaller gravels.
• All footings must bear directly on “target” gravel or on granular structural fill that in turn bears
on “target” gravel. Most perimeter frost wall footings are expected to bear in or very near the
shallow target” gravel (meaning a possibility for little or no over-excavation/replacement); while
the interior footings under the slab will require more/deeper over-excavation/replacement to
reach the “target” gravel.
• In some areas, the native gravel contains some pockets/seams/veins of loose sand. If footing
grade has any of these sandy areas, they should be excavated deeper (down to better gravel)
and re-filled with granular structural fill.
• The bottom of all perimeter, interior, and exterior footing excavations (or over-excavations)
must consist of native, “clean” cobbly, sandy gravel.
• To minimize disturbance to the native gravel subgrade surface, the excavation should be dug
with a smooth-edge foundation bucket.
• Prior to placing granular structural fill or forming footings, the native gravel subgrade surface
shall be cleaned of loose spoil materials and re-compacted to a dense and unyielding condition
with a smooth drum roller. No compaction testing is required on the gravel subgrade.
• All granular structural fill that is placed under footings must consist of either 3”-minus, sandy
(pitrun) gravel or 1.5”-minus, crushed (roadmix) gravel. Specifications for these materials are
provided in a later section of the report. We recommend new 3”-minus gravel for structural fill.
• The granular structural fill section should be placed in multiple lifts (depending on thickness of
fill required and the size of the roller used) with each lift being vibratory compacted to a dense
and unyielding condition. See a later report section for additional compaction specifications. A
large, smooth drum roller should be used wherever possible. Small, walk-behind sheepsfoot
rollers and hand-held, jumping jack compactors should be used in narrow/confined excavations
and along edges and in corners of the excavation.
FOUNDATION WALL BACKFILL RECOMMENDATIONS
Provided on next page are general recommendations for interior and exterior foundation wall backfill.
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 15
• For interior foundation wall backfill (under interior slab areas), all backfill material must consist
exclusively of either 3”-minus granular structural fill or 1”-minus, clean crushed rock. Both of
these materials are easy to compact and will minimize any settlement potential under the slab.
All backfill must be placed in thin lifts and be vibratory compacted to a dense and unyielding
condition (even the crushed rock). We do not recommend using any on-site silt/clay and sandy
gravel soils for any interior backfill.
• Select native silt/clay/sand or sandy gravel soils can be used for exterior foundation wall backfill.
These materials must be well compacted to prevent unwanted settlements, especially under
exterior slab areas. Use only the driest material available. If on-site sandy gravel is used, it
should be a 6”-minus material to prevent point loading the foundation walls with large, over-
sized, cobbles and boulders. All backfill must be placed in lifts and be well compacted.
• Under exterior slab areas (at doorways and under patios), we recommend foundation backfill
consist of relatively clean, sandy gravel. By doing so, any frost heaving potential is minimized.
INTERIOR SLAB RECOMMENDATIONS
All interior building slabs shall be supported on a minimum, 18-inch thick, compacted gravel section
consisting of 6 inches of clean crushed rock underlain by 12 inches of granular structural fill that overlies
stable and compacted subgrade (ie. non-organic silt/clay with all surface fill and buried topsoil stripped).
• Note: Depending on the slab elevation relative to the bottom of the stripped topsoil surface,
more than 18 inches of gravel/crushed rock may be needed under the slab area.
• Note: Depending on the locations/spacing/concentrations of interior footings, it may be more
advantageous and cost effective to mass over-excavate the building slab area down to “target”
gravel (thereby removing the 0.5 to 1.5-foot silt/clay layer that underlies the topsoil) and re-fill
the excavation with structural fill (as opposed to individually over-excavating interior footings).
MOISTURE PROTECTION AND SUBSURFACE DRAINAGE RECOMMENDATIONS
Provided below are our foundation moisture protection and subsurface drainage recommendations for
the at-grade slab configuration.
• The interior slab area shall be underlain by a heavy-duty, 15-mil vapor barrier. The barrier that
we recommend is a Stego 15-mil vapor barrier. The barrier must be sealed at all seams, pipe
penetrations, and walls.
• Unless required by the IBC, damp proofing of foundation walls is not typical for at-grade slabs.
• A perimeter footing drain is not needed/required.
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 16
EXTERIOR SLAB RECOMMENDATIONS
Provided in Table 3 are our recommendations for the design section under the light-duty, exterior slabs
(including standard pedestrian sidewalks away from the building foundation and next to streets).
Table 3. Exterior Concrete Slab (Light-Duty) – Sidewalks Away From Building – Stable Subgrade
COMPONENT COMPACTED THICKNESS (IN)
Concrete Slab: 4 (min.)
1”-Minus Clean Crushed Rock: 6
Granular Structural Fill – 3”-Minus Gravel or 1.5”-Minus Roadmix: No
8 oz. Non-Woven Geotextile Fabric (Mirafi 180N or Equal): No
Stable Subgrade Soils (Less Topsoil) or Embankment Fill: Rolled/Compacted
TOTAL SECTION THICKNESS: 6 + Slab Thickness
Notes: 1) We recommend this section for std. pedestrian sidewalks away from the building foundation and next to streets.
2) We expect pedestrian slabs will be 4 inches thick (min.).
3) The purpose of the 6-inch thick, crushed rock section is to provide better support under the slab.
Provided in Table 4 (below and continuing on following page) are our recommendations for the design
section under the light-duty, exterior slabs (including pedestrian sidewalks next to building foundation
wall, slabs in front of all doorway entries, patios, and garbage enclosure slabs).
• Note: In the table below, we recommend a minimum of 12 inches of crushed rock under these
slabs. For doorway and patio slabs, a better recommendation to further lower the potential for
frost heaving is to increase the gravel section to 24 inches (instead of 12 inches). This 24-inch
sub-slab section can consist of 12 to 18 inches of granular structural fill topped by 6 to 12 inches
of clean crushed rock. Sidewalk slabs next to foundation walls (but not at doors or patios) and
garbage enclosure slabs (under the dumpster) can be underlain by 12 inches of crushed rock.
• Note: To remove all frost heaving risk under slabs adjacent to doorways (including patio area
slabs), strong consideration should be given to fully backfilling these relatively small areas with
either “clean” on-site sandy gravel, granular structural fill, or clean crushed rock from footing
grade up to the bottom of slab grade.
Table 4. Exterior Concrete Slab (Light-Duty) – Sidewalks Next To Building – Stable Subgrade
COMPONENT COMPACTED THICKNESS (IN)
Concrete Slab: 4 (min.)
1”-Minus Clean Crushed Rock: 12 (See Below for Recommendations)
Granular Structural Fill – 3”-Minus Gravel or 1.5”-Minus Roadmix: No
8 oz. Non-Woven Geotextile Fabric (Mirafi 180N or Equal): No
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 17
Stable Subgrade Soils (Less Topsoil) or Embankment Fill: Rolled/Compacted
TOTAL SECTION THICKNESS: 12 + Slab Thickness
Notes: 1) We recommend this section for pedestrian sidewalks next to the building, at doorways, and garbage enclosures.
2) We expect pedestrian slabs and garbage enclosure slabs will be 4 inches thick (min.).
3) The purpose of the 12-inch thick, crushed rock section is to lower the frost heaving risk of the underlying silt/clay.
4) For slabs in front of doorways (incl. patios), we recommend the sub-slab gravel section be increased to 24 inches.
5) The purpose of the “expanded” 24-inch gravel section under slabs is to further reduce frost heaving potential.
6) Option 1: The 24-inch gravel section can consist of 6 inches of crushed rock and 18 inches of structural fill.
7) Option 2: The 24-inch gravel section can consist of 12 inches of crushed rock and 12 inches of structural fill.
8) Option 3: The 24-inch gravel section can consist entirely of 24 inches of crushed rock.
9) An option for removing all frost heaving risk next to doors (incl. patios) is to backfill under slabs w/ structural fill.
10) The granular backfill material shall extend from footing grade up to the bottom of the layer of clean crushed rock.
11) In lieu of granular structural fill, the doorway/patio slabs can be fully backfilled with clean crushed rock.
Provided in Table 5 are our recommendations for the design section under heavy-duty, exterior slabs for
vehicle and truck traffic (including driveway approaches).
Table 5. Exterior Concrete Slab (Heavy-Duty) – Vehicle Slabs – Stable Subgrade
COMPONENT COMPACTED THICKNESS (IN)
Concrete Slab: 6 (min.)
1”-Minus Clean Crushed Rock or 1.5”-Minus Base Course Gravel: 6
Granular Structural Fill (3”-Minus) or Sub-Base Gravel (6”-Minus): 12
8 oz. Non-Woven Geotextile Fabric (Mirafi 180N or Equal): Yes
Stable Subgrade Soils (Less Topsoil) or Embankment Fill: Rolled/Compacted
TOTAL SECTION THICKNESS: 18 + Slab Thickness
Notes: 1) We recommend this section for driveway approaches.
2) We expect driveway approaches will be 6 inches thick (min.); but could be up to 8 inches.
3) The final design of the slab thickness and slab reinforcement will be provided by others.
4) If our recommendation is needed for reinforcement, we recommend #4 rebars at 18” on-center (at a minimum).
5) The purpose of the 18-inch thick, total gravel section is to provide better support under the vehicle slabs.
6) We recommend a 24-inch total section thickness for slabs that will be subjected to vehicle/truck traffic loading.
7) If the slab thickness will be 8 inches instead of 6 inches, then reduce the crushed rock thickness from 6 to 4 inches.
SURFACE DRAINAGE RECOMMENDATIONS
Final site grading next to the building must establish and promote positive surface water drainage away
from the foundation footprint in all directions. Absolutely no water should be allowed to accumulate
against or flow along any exposed wall (and thereby soak into the foundation wall backfill). Concrete or
asphalt surfacing that abut the foundation should be designed with a minimum grade of two percent;
while adjacent landscaped areas should have a slope of at least five percent within ten feet of the wall.
Steeper side slopes than five percent (in landscape areas) are encouraged wherever possible. By doing
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 18
this, any minor settlements in the foundation backfill should not negatively affect the positive drainage
away from the building.
Note: The “dirt grade” in all adjacent backfill and landscape areas must be properly graded away from
the foundation walls with positive slopes of five percent (min.) prior to the placement of the landscape
bed/covering materials. This also applies to the subgrade surface under adjacent concrete areas (below
the gravel/crushed rock section materials).
To further reduce the potential for moisture infiltration along foundation walls, backfill materials should
be placed in thin lifts and be well compacted, and in landscaped areas, they should be capped by four to
six inches of topsoil. With the exception of the locations that will be surfaced by concrete or asphalt,
finished grades (next to foundation walls) should be set no less than six inches below the top of the
interior concrete slab or below the bottom of the sill plate for framed floor applications.
FOUNDATION-RELATED FILL MATERIAL RECOMMENDATIONS
Provided below are specifications for the fill materials that are recommended for use during foundation
earthwork construction. These include on-site excavated soils, sandy (pitrun) gravel, crushed (road mix)
gravel and clean crushed rock. Fill placement/compaction criteria follow the specifications.
On-Site Excavated Soils
All on-site generated, non-organic silt/clay that has a moisture content conducive to proper compaction
can be re-used for exterior foundation wall backfill. If “clean” gravel (not contaminated with silt/clay)
can be salvaged, it can be re-used for exterior foundation wall backfill (under doorway and patio slabs)
and for the sub-base component of the asphalt pavement section.
Sandy (pitrun) Gravel
Sandy (pitrun) gravel is a granular structural fill alternative for placement under footings and slabs and
behind walls. This material shall be a non-plastic, well-graded, mixture of clean, sand and gravel with
100 percent of its gravels/cobbles passing a three-inch screen and between 2 and 10 percent of its
silt/clay particles (by weight) finer than the No. 200 sieve. It should meet all material and gradation
specifications as presented in Section 02234 of the Montana Public Works Standard Specifications
(MPWSS) for 3”-minus, uncrushed, sub-base course gravel.
Crushed (road mix) Gravel
Crushed (road mix) gravel is a granular structural fill alternative for placement under footings and slabs
and behind walls. This material shall be a non-plastic, well-graded, mixture of clean, sand and gravel
that is processed (crushed) such that 100 percent of its rock fragments pass a 1-1/2-inch screen and
between 0 and 8 percent of its silt/clay particles (by weight) are finer than the No. 200 sieve. It should
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 19
meet all material and gradation specifications as presented in Section 02235 of the MPWSS for 1-1/2”-
minus, crushed, base course gravel.
Clean Crushed Rock
The primary uses for crushed rock include placement under concrete slabs and behind foundation and
retaining walls for drainage-related purposes. Crushed rock shall be a clean assortment of angular
fragments with 100 percent passing a one-inch screen and less than 1 percent (by weight) finer than the
No. 100 sieve. This aggregate product needs to be manufactured by a crushing process and over 50
percent of its particles must have fractured faces. It is not acceptable to use rock containing abundant
spherical particles for foundation-related applications.
Fill Placement and Compaction
All fill materials should be placed in uniform, horizontal lifts and compacted to an unyielding condition.
This includes clean crushed rock, which can be readily compacted by vibratory means. In general, the
maximum “loose lift thickness” for all fill materials (prior to compaction) should be limited to 12 inches
for large, self-propelled rollers, 6 inches for remote-controlled, dual drum rollers and walk-behind,
jumping jack compactors, and 4 inches for walk-behind vibratory plate compactors. The moisture
content of any material to be compacted should be within approximately two percent (+/-) of its
optimum value for maximum compaction.
Provided in Table 6 are compaction recommendations for general foundation applications. These are
presented as a percentage of the maximum dry density of the fill material as defined in ASTM D-698.
Table 6. Compaction Recommendations (Application vs. Percent Compaction)
APPLICATION % COMPACTION
Granular Structural Fill Under Footings and Slabs: 97
Interior Wall Backfill under Slabs (Granular Structural Fill): 97
Exterior Wall Backfill (Native Soil or Granular Structural Fill): 95
Clean Crushed Rock Under Footings/Slabs and Behind Walls: N/A (Vibration Required)
Site Fill Around Building and Under Concrete and Pavement Areas: 95
UNDERGROUND UTILITIES
General
The underground utilities for this project will include water/fire/sewer services, storm drainage piping
and infrastructure, and underslab piping/plumbing.
• Note: See the following report section for a discussion on underground stormwater systems.
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 20
Installation
The installation of all water, sewer, and storm drainage outside of the building should follow the project
plans/specifications, Monana Public Works Standard Specifications, and City of Bozeman Specifications.
Pipe Bedding
In some areas, the native gravels contain large, 6” to 10” cobbles and boulders. In order to protect the
pipes during installation/backfilling (from being damaged or point-loaded by the rocky gravel material),
generous amounts of 1”-minus crushed rock pipe bedding material should be used under, around, and
over the pipes.
Soil Corrosivity Potential and Recommendations for DIP Pipes
Based on past experience, the site’s silt/clay and sandy gravel soils are not corrosive to standard ductile
iron pipe (DIP). With that said, we do recommend installing the DIP fire service line (into the building
and under the building slab) with polyethylene encasement for added corrosion protection. This is
considered cheap insurance. Most likely, the water service line will be copper and therefore, does not
require any polyethylene encasement. In summary, our recommendations include:
• Use standard DIP pipe that is wrapped in V-bio enhanced, polyethylene encasement.
• The site conditions do not require the use of special, zinc-coated, DIP pipe.
Sub-Slab Plumbing Excavation and Trench Backfill
In our opinion, the best material for trench backfill of sub-slab plumbing is 1”-minus, clean crushed rock.
This material is easy to place and compact in tight and confined areas. We recommend that the crushed
rock be placed in reasonable lifts and be vibratory compacted to a dense and unyielding condition with
small, walk-behind, plate compactors.
UNDERGROUND STORMWATER SYSTEMS
Provided below are recommendations for designing and installing underground stormwater systems:
Design Infiltration Rate
We recommend designing the system to drain into the underlying native sandy gravels. By doing so, the
system footprint area will be much smaller; and the surface water drainage will rapidly drain out of the
system. We recommend using Table 3 in Appendix A of Circular DEQ-8 for the design infiltration rate for
native sandy gravel. According to the table, an infiltration rate of 4.0 inches per hour can be assumed
for sand and gravel.
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 21
Hydraulic Connection
Using the above-referenced design infiltration rate for native gravel will require that the system be
hydraulically connected to the native gravel. This can be done by bearing the system directly in the
native gravel (where the native gravels are shallow); or by over-excavation and replacement under the
system (where the native gravels are deeper and below the bottom of system elevation).
Excavation and Replacement (If Needed)
If needed (based on native gravel depth), we recommend mass over-excavating under the stormwater
system down to “clean” sandy gravel. In order to re-fill the excavation area and build back up to the
system elevations, we recommend either using clean crushed rock or over-sized cobbles (available from
a commercial pit) as the replacement material. Since the cobbles are free-draining, we prefer them over
standard 6”-minus pitrun gravel. When using “open-graded” cobbles, the top of the cobbles must be
covered with a layer of 8 oz. non-woven geotextile separator fabric (Mirafi 180N or equal) before placing
the bedding rock/gravel under the stormwater systems. A detail that shows the over-excavation and
replacement material should be included on the civil plans. The civil plans should clearly state that the
system must drain into the native gravels and that this may require over-excavation and replacement.
ASPHALT PAVEMENT SECTION RECOMMENDATIONS
Pavement Section Design
Provided in Table 7 is our recommended light-duty pavement section for the parking lot improvements.
This section requires stable subgrade and is our standard section for light commercial/office building-
type project sites.
Table 7. Pavement Section (Light-Duty) – Stable Subgrade
COMPONENT COMPACTED THICKNESS (IN)
Asphalt Concrete: 3
Base Course – 1.5”-Minus Crushed (Roadmix) Gravel: 6
Sub-Base Course – 6”-Minus Uncrushed Sandy (Pitrun) Gravel: 15
8 oz. Non-Woven Geotextile Fabric (Mirafi 180N or Approved Equal): Yes (for Silt/Clay & “Dirty” Gravel)
Stable Subgrade Soils (Less Topsoil): Hard and Compacted
TOTAL SECTION THICKNESS: 24
Notes: 1) Base course gravel shall be new gravel.
2) Sub-base gravel can be new gravel or salvaged gravel (provided it is “clean” and not contaminated with silt/clay).
3) For silt/clay and/or “dirty” gravel subgrade, place an 8 oz. non-woven fabric for subgrade separation.
4) The placement of geotextile fabric is not required/not needed where subgrade consists of “clean” sandy gravel.
5) Stable subgrade conditions are required, meaning it must be dry, hard, and compacted.
6) If subgrade soils are overly moist and rut/pump/deflect, they must be dried out to a stable condition.
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 22
Pavement Section Materials, Placement, and Compaction
The sub-base and base course materials that comprise the granular parts of the pavement section shall
consist of 6-inch minus uncrushed sandy (pitrun) gravel and 1-1/2-inch minus crushed (road mix) gravel,
respectively. Both gravel courses shall meet the material and gradation specifications as presented in
the MPWSS, Sections 02234 and 02235. All gravels shall be placed in loose lifts not exceeding 12 inches
in thickness and be compacted to at least 95 percent of the material’s maximum dry density as defined
in ASTM D-698. Asphalt pavement shall meet specifications in MPWSS Section 02510 and be compacted
to a minimum of 93 percent of the Rice mix density.
GEOTECHNICAL INSPECTION
If desired, AESI can be retained for geotechnical inspection of the foundation excavation. We request
that we be given about a week notice and we will need to be involved from the first day of foundation
excavation. As part of our work, we will observe the bottom of the excavation (down to “target” native
gravel) and the placement/compaction of granular structural fill (up to footing grade).
• Note: A City Building Department requirement is that a stamped, geotechnical inspection letter
(prepared by a professional engineer) be provided that documents the foundation earthwork
prior to scheduling the City’s pre-pour footing inspection. We can provide this; but we will need
to be retained for geotechnical inspection services under a separate contract.
PRODUCTS
Provided in Table 8 is a reference guide for all products that have been recommended within this report.
Listed below is the product name, its intended use, and where it can be obtained. The manufacturer
specification sheet for each of these products is attached at the end of the report.
• Note: Several notes are presented under the table that describe the recommended products,
where they can be obtained, and where they can be used.
Table 8. Product Reference Guide
PRODUCT USE SOURCE PHONE
Stego 15-mil Vapor Barrier Moisture Protection under Bldgs MaCon Supply – Bozeman 551-4281
Mirafi 180N Non-Woven Fabric Road Subgrade Separation Multiple Sources – Belgrade N/A
Notes: 1) Use Stego 15-mil vapor barrier only. There are no approved equals for this product. 2) Stego 15-mil vapor barrier has a water transmission rate that meets national standards for vapor barriers.
3) Stego 15-mil vapor barrier is a heavy-duty vapor barrier for placement under interior slabs and in crawl spaces.
4) We recommend the placement of a Stego 15-mil vapor barrier under building slabs.
5) Use Mirafi 180N non-woven fabric or an approved equal that meets or exceeds Mirafi 180N fabric specifications. 6) Approved equals for Mirafi 180N non-woven fabric are available from multiple sources in the Belgrade.
Final Geotechnical Report – Evergoods Project
Lot 2A, Blk 1, Glen Lake Com. Sub. – Bozeman, MT
Project: 24-166
January 22, 2025
Page 24
enc: Figure 1 – Test Pit Locations
Figure 2 – Test Pit Locations w/ Thickness of Native Topsoil (Incl. Any Surface Fill)
Figure 3 – Test Pit Locations w/ Thickness of Native Silt/Clay (Under Topsoil Layer)
Figure 4 – Test Pit Locations w/ Depth to Native Sandy Gravel (“Target” Bearing Material)
Figure 5 – Test Pit Locations w/ Depth to Groundwater on 2/13/03
Figure 6 – Foundation Detail – At-Grade Slab – Option 1 (Interior Footing Over-Excavation)
Figure 7 – Foundation Detail – At-Grade Slab – Option 2 (Building Slab Mass Over-Excavation)
Test Pit Logs for TP-1 through TP-7 from 2/13/03 (Glen Lake Commerce Sub. Area)
Test Pit Logs for TP-A through TP-C from 5/9/18 (Manley Road Improvements)
Test Pit Photos for TP-A through TP-C – Excavation Sidewalls and Spoil Piles
Iron Horse Road Construction Photos from 5/2/18 – Native Sandy Gravel Subgrade
Product Sheet – Stego 15-mil Vapor Barrier
Product Sheet – Mirafi 180N Non-Woven Geotextile Fabric
Limitations of your Geotechnical Report
REFERENCES
International Code Council, 2021, “International Building Code”.
Montana Contractors’ Association, April 2021, “Montana Public Works Std. Specifications”, 7th Edition.
P:\2024\24-166 Lot 2A, Block 1, Glen Lake Commerce Sub. - Geotech\Design\Geotech\Report\Text\Lot 2A, GLCS - Geotechnical Report - 01.22.25
Figure 6
24-166 Jan. 2025
Lot 2A, Blk 1, Glen Lake Commerce Sub.
Foundation Detail - At-Grade Slab - Option 1
Bozeman, Montana
Damp-Proofing As Required (typ.)
Foundation Wall (typ.)Approved Non-Woven Filter Fabric To Encase Bedding Gravel (typ.) Interior Floor Slab (typ.)Interior Steel Column (typ.)Interior Spread Footing (typ.)
6” Of 3/4" Minus Crushed Washed Gravel
Hydraulically Connected To Sub-Drain or
Existing Surface Drainage (typ.)
Native Topsoil andRandom Surface Fill Imported 4-Inch Minus Sandy Pitrun Gravel Native Silt/ClayImported Flowable Fill
Six Inch Diameter Sub-Drain Pipe
(Graded To Drain To Sump Area)
Concrete SidewalkLow Permeability Soils(Landscaped Area)LegendConcrete Wall and/or Footing Low Permeable Topsoil No Scale (Parts Of This Exhibit Have Been Exaggerated For Clarity)
ALLIEDENGINEERING
SERVICES, INC.
Civil Engineering
Geotechnical Engineering
Land Surveying
32 Discovery Drive
Bozeman, MT 59718
Phone: (406) 582-0221
Fax: (406) 582-5770
Slope Away @ 2%
In All Concrete Or
Pavement Areas (typ.)
Footings 6’ max.
depth below
existing ground
Native Topsoil 6” Minus Sandy (Pitrun) Gravel 4” Minus Sandy PitrunGravel (ie. Structural Fill)4’ max fill above existing ground
4' min.
4’ Max Fill Above
Existing Ground
3” (min.)
Thickness Will Vary Due To
Depth Of Bedbrock Strata
6” (min.)
3” (min.)
8” (min.)
4.0’ (min.)
6” (min.) Of Rock Bedding To Be
Placed Around Drain Piping (typ.)
Under-Slab Rock Layer To Be Hydraulically
Connected To Sub-Drain System By 3” Of Rock
Or 2” Sch. 80 Piping Spaced On 10’ Centers (typ.)
B
H (Variable; Depends
On Depth To Gravel)
18” (min.)
18” (min.)
6” (min.)
6” (min.)
1’ (min.)
H = 3.5’ (Based On4.0’ Footing Depth And The Depth To Gravel In TP-4) H = 5.5’ (Based On4.0’ Footing Depth And The Depth To Gravel In TP-2)
D D
Woven Geotextile Filter Fabric (Amoco 2004)Vapor Barrier Under Slab (typ.)
9.5’ Deep
(TP-2)
7.5’ Deep
(TP-4)
Non-Woven Filter
Fabric To Encase
1-Inch Minus Rock
6” (min.) Rock Layer (typ.)
Asphalt/Concrete Areas
To Be Sloped Away
@ 2% (min.).
6” (min.)
6” (min.)4” PE Sub-Drain (typ.)
Crawl Space Opening
Must Be Properly Vented.
Note: Elevation Difference Between The Top Back Of Curb
And The Finished Floor Should Be Maximized. I Believe The
Subdivision Covenants Call For A Minimum Separation Of 2.0’
And A Maximum Of 5.0’. Due To High Groundwater Concerns,
An Elevation Difference Of More Than 2.0’ Is Recommended.
This Should Be Thoroughly Considered On A Case By Case
Basis. Please Refer To The Covenants For More Detail.
Important Notes: The Three-Foot Wide (Min.) Over-Excavation From The Center Of The Footing Is Calculated Based On A 16-Inch
Footing Width (B) And An Average Depth To Native Gravel (GD) Below The Footing Elevation Equal To Five Feet. If The Footing
Is Substantially Wider Or The Depth To Gravel Substantially Deeper; The Width Of The Excavation Will Need To Be Increased. The
Equation For Determining Excavation Width (EW) From The Center Of Footing Is: EW = (B + GD) / 2.0. If Caving (ie. Sloughing)
Of The Excavation Side Walls Is A Problem; EW Will Need To Be Increased Accordingly. Since The Footings Are Supported On
Structural Fill That Bears On Native Gravel; There Is No BenefitTo Increasing Footing Size Beyond What Is Shown On The Plans.
If Groundwater Is Encountered In The Over-Excavation Above The Native Sandy Gravel Surface,
We Recommend A Layer Of Crushed Rock First Be Used To Get Above The Groundwater Elevation.
The Crushed Rock Should Be Placed In A Single Lift That Does Not Extend More Than Four Inches
Above The Groundwater. After Placement, The Crushed Rock MUST Be Compacted By Vibratory
Methods. Compactors That Are Suitable For Crushed Rock Include Walk-Behind Plate Compactors;
Remote-Controlled Sheepsfoot Trench Rollers; And Self-Propelled Smooth Drum Rollers.
Note: If Groundwater Is Not Encountered, The Use Of Crushed Rock Is Not Necessary.
Compacted Structural Fill. Use Sandy Pitrun Gravel,
Not Crushed Rock. Gravelly Materials Are Not Only
Less Expensive But They Will Also Reduce The In-Flow
Of Groundwater Into The Crawl Space In The Event That
High Groundwater Exceeds The Crawl Space Elevation.
Place The Pitun In Lifts (Six-Inch Thick Max. For Small
Remote-Controlled Sheepsfoot Trench Rollers And
Twelve-Inch Thick Max. For Self- Propelled Smooth
Drum Rollers) And Compact To An Unyielding Condition.
Note: A Material That Works Very Well For Foundation
Structural FilI Is The 3” Minus Pitrun Gravel Product
That Is Available From TMC In Belgrade.
Pay Special Attention To Compaction
Of Crushed Rock And Structural Fill
Along Edges. Native Soils Could Be
Soft. Rock / Fill Will Need To Be
Compacted Into Side Of Excavation.
Place Woven Geotextile
Fabric Over The Crushed
Rock. This Will Prevent
Fines Migration Into The
Rock After Placement Of
The Structural Fill.
4” (max.)
3’ (min.)
3’ (min.)
Interior Footing
As A Precaution For Groundwater,
Install 4” PE Slotted Drain Piping
Along The Inside Of The Perimeter
Footings And Grade To A Shallow
Sump Chamber In The Crawl Space.
If Water Becomes An Issue, Install
Sump Pump And Discharge Out Of
The Crawl Space. A Four-Inch Layer
Of Crushed Rock Will Facilitate
Rapid Drainage And Eliminate The
Sight Of Standing Water. If A Vapor
Barrier Is Placed Above The Crushed
Rock; Ensure It Is A Material That
Can Breathe (Not Polyethylene).
All Interior Footings Shall Bear On Structural Fill.
Finished Floor Elev. (At-Grade Slab)
GD
Existing Ground Surface
Existing
Ground
4” Slotted PE Pipe. Install Drain Piping Around Inside Perimeter Of Foundation. Piping
Should Be Placed At Footing Grade Or Preferably Below The Top Of The Crushed Rock
Fill (When Used). Connect Piping To Shallow Sump Chamber. If High Groundwater Is An
Issue, A Pump Can Be Installed At A Later Time.
32”
48”
Reviewed By: __________________
4” To 6” (Min.)
Thickness
As Required
2.5’
4’ (min.)
Damp
Proofing
4” Footing
Drain (typ.)
Min. Depth Of Cover
For Frost Protection
Min. Required Width Of
Mass Over-Excavation
Beyond Edge Of Footing
1.0’ - 17.0’ Depth To
“Target” Bearing Material.
Silt/Clay Below 2.5’ (+/-) Is
Generally V. Moist To Wet.
See TP Logs For Soil And
Groundwater Conditions.
5.0’ - 13.5’ Depth To
“Target” Bearing Material.
Groundwater Depth Ranged From 6.0’ to 13.5’. Depending
On Time Of Year, Groundwater May Be At Or Above The
Sandy Gravel (“Target” Bearing Material). Therefore,
Groundwater Dewatering May Be Needed. Dewatering Wells
Are Recommended To Lower Water Below Gravel Surface.
Strip, Remove, And Replace All Random Fill
From Under The Entire Building Area, Including
Under Interior House And Garage Slabs (typ.)
Note: De-Watering Will Likely Not Be
Required For Foundation Excavation.
Based On Our Test Pits,
All Evidence Suggests
The Groundwater Table
Stays Within The Sandy
Gravel Most Of The Time.
LSE, 1/17/25
Prior To The Placement Of Granular Structural Fill,
The Site’s Shallow Groundwater Conditions May
Require That An Initial Layer Of Clean Crushed Rock
Be Placed And Compacted Up To A Height Of At Least
6 Inches Above The Level Of The Standing Water.
Structural Fill: Use 4” Minus Sandy (pitrun) Gravel
Due To Shallow, Seasonal High Groundwater Conditions,
Footing And Crawl Space Depth Must Be Minimized Below
The Existing Ground Surface. Bottom Of Footing Elevation
Should Be Kept Within At Least 2.5’ To 3.0’ Of Existing Grades.
As An Added Precaution Against High Groundwater In The Crawl Space (And Especially
If Footing Depth Nears Or Exceeds 2.5’ To 3.0’ Below Existing Site Grades), We Strongly
Encourage The Placement Of A 6” To 8” Layer Of Crushed Rock In The Crawl Space To
Raise The Floor Elevation Up To The Top Of Footings. In The Event That Groundwater
Ever Rises Above The Crushed Rock Layer, A Sump Chamber And Pump Can Easily Be
Installed Later To Address The Problem.
We Do Not Recommend Placing The Initial Layer Of Clean Crushed Rock In Standing Water Exceeding 10 Inches In Depth.
Therefore, Depending On The Time Of Year, Some Groundwater De-Watering May Be Required During Foundation Earthwork.
All Perimeter, Interior, And Exterior Footings Must Bear
On A Minimum 2.0’ Thickness Of Granular Structural Fill
That In Turn Is Supported On The Native Sandy Gravel
(Which Is The ”Target” Foundation Bearing Material).
Given The 4.5’ To 6.5’ Depth To Gravel, Along With The
Anticipated Slab Grade, Perimeter Footings Will Likely
Lie 2.0’ to 6.0’ Above The Top Of The “Target” Gravel.
Mass Over-Excavate The Entire Foundation Footprint Area, Including All Exterior Footing Locations, Down To The “Target”
Bearing Material (Native Sandy Gravel); Thereby, Completely Removing All Native Silt, Clay, Sand From Under The Building.
Over-Dig The Excavation To The Minimum Width Dimensions As Shown On This Figure And As Stated In The Report.
Important Note: Mass Over-Excavation Of The Foundation (As Illustrated By Option #2)
Will Be Required If The Individual Footing Over-ExcavationsThat Are Depicted As Option #1
Will Not Stay “Open” Due To Trench Wall Collapse.
Foundation Earthwork Notes: 1) Slab On Grade - Option “B” Consists Of Over-Excavating Under All Perimeter, Interior, And Exterior Footings.2) This Is Most Applicable Where The Building Is Underlain By Relatively Deep Gravels And The Foundation Contains Less Interior Footings.3) Where Present, All Random Surface Fill Material Must Be Fully Removed From Under The Entire Building Area Down To Native Soils. Foundation Excavation Recommendations: Due To The Large Number and Close Spacing Of Interior Footings (Many Of Which Are 13 To 14 Feet On-Center), We Recommend The Entire Foundation Footprint Area Of The Apartment Buildings Be Mass Over-Excavated Down to Native Sandy Gravel And Built Back Up To Footing And Slab Grades With Compacted Structural Fill. The Limits Of The Mass Excavation Must Encapsulate All Perimeter And Exterior Footings. Important Note: It Is Now COB Policy That The Foundation Earthwork Be Inspected And Certified By The Geotechnical Engineer.
Suggestions: In Order To Reduce The Amount Of Required Structural Fill Under
Footings And The Slab Area, The Finished Floor Elevation Should Be Minimized
Above Existing Site Grades. Another Option To Reduce Fill Under Perimeter
Footings Is To Use A 6’ Tall Foundation Wall.
Foundation Backfill and Embankment Fill Granular Structural Fill(1.5”Minus Roadmix Gravel)Granular Structural Fill(1.5”Minus Roadmix Gravel)Sandy Gravel(”Target” Bearing Material) Low Permeable Topsoil Native Silt/Clay(Unsuitable Bearing Material) Native Silt
Native Silt/Clay/SandAnd Sand w/ Small Gravels(Unsuitable Bearing Material) Native Silt/Clay/SandAnd Sand w/ Small Gravels(Unsuitable Bearing Material) Native Topsoil Granular Structural Fill(4” Minus Sandy Gravel)Granular Structural Fill(1.5” Minus Roadmix Gravel)1” Minus CleanCrushed Rock Groundwater (on 4/19/16) Concrete Slab
Exterior Foundation Wall Backfill
Should Only Consist Of Excavated
Soils That Are Not Overly Moist. It
Must Be Placed In Multiple Lifts
And Properly Compacted.
Slab Grade Should Be Set Above
Existing Grades. For The Mass Over-
Excavation Option, There Is No Limit
On Slab Height Above Existing Grades.
H
W = Footing Width + H; (5’ min.)
All Foundation Fill Materials Should Be Placed In Uniform,
Horizontal Lifts And Be Well Compacted. Granular Structural Fill
Shall Be Compacted To A Dense, Unyielding Condition, While Clean
Crushed Rock Or Lean Mix Concrete Must Be Compacted By
Vibratory Means. In General, The “Loose” Thickness Of Each Lift
Prior To Compaction Should Not Exceed 12 Inches For Large, Self-
Propelled Rollers; 6 Inches For Remote-Controlled Trench Rollers
And Walk-Behind Jumping Jack Compactors; And 4 Inches For Walk-
Behind, Plate Compactors. Pay Special Attention To Compaction Of
Structural Fill Along Edges And In Corners Of The Excavation.
Place Crushed Rock As Fill Under
Slab (6” min.) And Interior Wall Backfill
Strip Topsoil
Under Slab and
Re-Compact The
Subgrade Surface.
Vapor Barrier Under Slab. Seal Barrier At Seams/Penetrations.
Minimize
New Fill
Height For
Settlement
Reasons
The Uppermost 6” Of Lean Mix
Concrete Fill Can Be Replaced w/
Clean Crushed Rock For Easier
Leveling Of Footing Grade.
Bearing Pressure
4000 psf (max.) Important Note: To Stabilize The Trench Excavations And Minimize The Potential For Caving/Sloughing, Groundwater Dewatering May Be Required.
Shallow Frost-
Proof Foundation.
Insulate As Per
Applicable Codes.
Interior Footing (typ.)
Radon Mitigation System Should
Be Considered Under Interior Slab.
Important Note: If Foundation Construction Will Occur During The Cold/Winter Weather Season, The
Contractor Shall Take All Necessary
Precautions To Prevent The Earth-
Work From Freezing And/Or From
Being Contaminated With Snow.
Note: At A Minimum, Use A Large, Smooth Drum Roller To Compact
The Upper-Most Lift Of Structural Fill Under Footings And Slabs.
6” (min.) Crushed Rock Layer Under Slab Areas (typ.)
Additional Thickness
Of Gravel Building Pad
As Req’d To Bear On
“Target” Gravel.
For Mass Excavation, Over-Excavation
Width Beyond Perimeter Ftgs Is 5.0’ (typ.)
See Fig. 6 For Over-Excavation Width
Under Individual Ftg Excavations.
Embankment Fill Can Be Used Below 18” Of Slab Grade.
Note: No Topsoil Observed In On-Site Borings. Product Recommendation: A Stego 15-mil Vapor Barrier Is Recommended.Available From MaCon Supply In Bozeman.
W = Footing Width + H; (5’ min.)
Min. Width = 1/2(H);
But Must Be 5’ Min.
H
H = 2’ Min.
Important Note: If TP-3, A Clay
Layer Was Observed Under The
Native Sandy Gravel At A Depth
Of 6.0’. It Is Recommended That
All Footings Bear On A Minimum
24” Thickness Of Native Gravel
Or Granular Structural Fill. This
Should Be Confirmed With Test
Pits Around The Perimeter Of The
Building During Construction.
Important Note: If The Trench
Excavations Are Prone To Minor
Caving, Their Width Will Have To
Be Increased Accordingly To
Prevent Slough From Underlying
Or Being Mixed Into The Minimum
Required Width Of Structural Fill.
Given The 4.5’ To 6.0’ Depth To
Native Sandy Gravel, We Do Not
Expect That Most (If Any) Of The
Perimeter Footings Will Bear
Directly On Native Gravel. Most
Likely, Footings Will Need To Be
Supported On Structural Fill That
In Turn Bears On Native Gravel
(Similar To All Interior Footings).
Excavation Alternative: In Lieu Of Only
Excavating Footings, The Entire Foundation
Footprint Area Of The Building Can Be Mass
Over-Excavated Down To Native Sandy Gravel
And Filled With Granular Structural Fill. Given
The Gravel Depth, This Is Far Less Economical
As Compared To The Above Recommendations.
Prior To Granular Structural Fill Placement, The Excavated Gravel Surface (Under Entire Foundation Footprint Area)
Must Be Vibratory Re-Compacted With A Large, Smooth Drum Roller In Order To Densify The Native Sandy Gravel.
Due To Groundwater Depths Of 7.8’ To 9.8’, Wet Subgrade Conditions Should Not Be An Issue.
Depending On Location, Groundwater Could
Be At Or Above The Top Of Native Sandy Gravel
During The Seasonal High Water Time Of Year.
A Large, Smooth Drum
Roller Must Be Used To
Compact All Granular
Structural Fill Whenever
and Wherever Possible.
Lean Mix Concrete(Flowable Fill)Embankment Fill(On-Site or Import Material)Non-Organic Embankment Fill(On-Site, “Drier” Silt/Clay/Sand)
2500 psf (max.)
B
2500 psf (max.)
B
Mass Excavate Under Entire Foundation Footprint Area Down To Native, Clean Sandy Gravel; Thereby
Removing All Of The Silt/Clay Under The Interior Slab. All Footings Must Bear On Native Sandy Gravel
Or On Compacted Granular Structural Fill That In Turn Is Supported On This “Target” Bearing Material.
Shallow Frost-Proof Foundation
Per IBC Is Also Acceptable.
H
H
If Exc. Walls Slough,
Widen Exc. To Ensure
Min. Struct. Fill Width
Beyond Edge Of Ftg.
Bottom Of Exc. Measurement
Centered Under The Footing.
If Exc. Walls Slough,
Widen Exc. To Ensure
Min. Struct. Fill Width
Beyond Edge Of Ftg.
Bottom Of Exc. Measurement
Centered Under The Footing.
Min. Width = (B + H); But 5’ (min.)
Crushed Rock
Is Only Needed
If Gravel Subgrade
Is Wet Or Contains
Standing Water.
All Fill Material Placed Under Footings And
Slabs To Consist Of Compacted Granular
Structural Fill. No On-Site Soils Are To Be
Used As Embankment Fill Under Slabs.
Do Not Place Granular Structural Fill Materials Over
Wet Subgrade Or In Shallow Standing Water. De-Water
The Excavation If Required. If Bottom Of Excavation
Is Wet, Place An Initial, Thin Layer Of Clean Crushed
Rock Under The Structural Fill. The Crushed Rock
Should Extend A Minimum Of About 4” Above The Wet
Conditions. Vibratory Compact The Crushed Rock And
Then Cover With A Medium-Weight, Non-Woven Fabric
Prior To Structural Fill Placement. Overlap Seams Of
Fabric By 12” Minimum.
Over-Excavate Under All Perimeter,
Interior, And Exterior Footings Down
To Native, Clean Sandy Gravel; Thereby
Removing All Silt/Clay Under Footings.
All Footings Must Bear On Native Sandy
Gravel Or On Compacted Granular
Structural Fill That In Turn Is Supported
On This “Target” Bearing Material.
Embankment Fill Under Structural Fill Layer
Must Be Compacted To Project Specifications.
See Figure 7 For
Recommendations
For Foundation Fill
Material Placement
And Compaction.
See Figure 7 For
Recommendations
For Ext. Foundation
Wall Backfill Material
And Compaction.
For Basements, Additional SubsurfaceDrainage And Moisture Protection Recommendations Will Need To BeIncorporated That Are Not Shown On This Exhibit. See Report For More Details. No Scale (Parts Of This Exhibit Have Been Exaggerated For Clarity)
No Scale (Parts Of This
Exhibit Have Been
Exaggerated For Clarity,
Especially The Depth To
Gravel & The Thickness
Of Req’d Structural Fill.)
This Figure Shows A Deeper Gravel
Depth On One End Of The Building
To Illustrate The Possible Need For
Over-Excavation/Replacement Under
Perimeter Footings. Due To Shallow
Gravel Depths Across The Site, This
May Not Be Applicable/Necessary.
Geotechnical Notes:
1) Figure 6 Provides Our Option 1 Recommendations For Foundation Earthwork And Support Under An At-Grade Slab Foundation Configuration.
2) Option 1 Includes Supporting The Slab On A 18-Inch (min.) Gravel Section And Over-Exc. Perimeter Footings (As Necessary) To Reach “Target” Gravel.
3) Due To Shallow Gravel Depths, Perimeter Footings Will Likely Bear In Native Gravel. Over-Excavation/Replacement May Be Limited To Interior Footings.
Granular Structural Under Footings And Slabs Can Consist Of4”-Minus Sandy Pitrun Gravel Or 1.5”-Minus Roadmix Gravel. Based On Test Pits, Depth To “Target” Bearing Material Is 4’ To 5’ On Downhill Side And 3’ On Uphill Side Of The Lot.
Legend
Random Fill (Unsuitable Bearing Material) Random Fill (Unsuitable Bearing Material) Low Permeable Topsoil Granular Structural Fill(4”-Minus Sandy Gravel)Granular Structural Fill (*)Place In Thin Lifts And Vib. Compact To 97% (min.).
Import Granular Structural Fill (*)
Under Interior Slab Area (Rq’d)
Vibratory Compact To 97% (min.).
Import Granular Structural Fill (*)
Under Footings (As Needed)
Vibratory Compact To 97% (min.).
1” Minus CleanCrushed Rock
1” Minus Clean
Crushed Rock
1” Minus CleanCrushed Rock1” Minus CleanCrushed RockExisting Grade (Ground Surface)
Native Topsoil
Topsoil or Asphalt/GravelSurfacing Materials Native Topsoil Floor Joist
Exterior Wall Backfill
And/Or Site Fill
(Silt/Clay Or Gravel)
Borrow Pit Fill (Silt/Clay)
Native Topsoil Native “Clean” Sandy Gravel
(“Target” Bearing Material)
Native “Dirty” Sandy Gravel(Unsuitable Bearing Material)
Native Silt/Clay
Native Topsoil
Random Fill Material
(“Dirty” Gravel w/
Intermixed Silt/Clay)
Flowable Fill (Lean Mix Concrete)Under Footings (Option 2)(500 psi Mix; Consolidate w/ Vib.)
Interior Wall Backfill
(Gran. Struct. Fill
Or Crushed Rock)
Interior Wall Backfill(Gran. Struct. Fill Or Crushed Rock)
“Target” Bearing Material Is The Glacial Till. It Is Identifiable Based On Its Clean
Sandy Composition, Abundance Of 6”-Minus, Sub-Rounded Gravels, And Dense
Configuration. It Looks Like “Clean Pitrun Gravel” w/ Large Cobbles And Boulders.
All Footings Shall Bear On A Minimum Of 1’ Of
Granular Structural Fill That In Turn Bears On
“Target” Glacial Till (typ). Additional Structural Fill
Thickness Will Be Required Under Some Footings
In Order To Reach “Target” Bearing Material.
Recompact Subgrade Prior To Fill Placement (typ).
All Foundation Fill Materials Should Be Placed In Uniform, Horizontal Lifts
And Be Well Compacted. Granular Structural Fill, Embankment Fill, And Wall
Backfill Shall Be Compacted To A Dense, Unyielding Condition, While Clean
Crushed Rock Must Be Compacted By Vibratory Means. In General, The “Loose”
Thickness Of Each Lift Prior To Compaction Should Not Exceed 12 Inches For
Large, Self-Propelled Rollers; 6 Inches For Remote-Controlled Trench Rollers
And Walk-Behind Jumping Jack Compactors; And 4 Inches For Walk-Behind,
Plate Compactors. Pay Special Attention To Compaction Of Fill Materials Along
Edges And In Corners Of The Excavation; And Along Foundation Walls.
Daylight Footing And
Sub-Slab Drains (typ.)
See Figures 8 And 9
For Note On Exterior
Foundation Wall Backfill.
Granular Structural Fill
Should Be Used For
Interior Wall Backfill
Under Slabs.
See Figures 8 And 9 For Note
On Foundation Fill Material
Placement And Compaction.
All Excavated Soils Can Be Re-Used For Exterior Wall Backfill
Or Embankment Fill Provided They Are Not Organic Or Overly Moist.
All Fill Must Be Placed In Thin, Level Lifts And Properly Compacted.
H = 1’ or 2’ (Depending On Ftg Width)
H = 1.0’ (min.)
H
H = 1.0’ (min.)
15-mil Vapor Barrier Under Slab (Above Rock Layer).
Seal Barrier At Seams, Penetrations, And Footings.
Vapor Barrier Not Typ. Under Garage Slabs. Note: Due To Unheated/Non-Insulated Buildings, Consider Insulating Under Interior Slabs To Minimize Frost Heaving Potential Of Silt/Clay.
(*) Granular Structural Fill Can Consist
Of 3”-Minus Sandy (Pitrun) Gravel Or
1.5”-Minus Crushed (Roadmix) Gravel
Note: Deep Groundwater Conditions Exist At The Site. In Feb. 2003, Groundwater Was > 14.0’ Deep In The Area Of Lot 2A.
Note: In October 2022, Groundwater Depths Ranged From 5.0’ To 10.0’ Across The Property. High Groundwater Depths In 2023 Ranged From 2.9’ To 6.9’ (Highest GW Depths On West Side). Note: We Do Not Recommend Trench Over-Excavating Footings On An Individual Basis; But Rather Mass Over-Exc.
Strip Topsoil And
Bench Subgrade Level
Prior To Placing Fill (typ.)
About 6” Of
Dirty Gravel
Overlies The
Clean Gravel.It Is Important To Vibratory Re-Compact The
Excavated “Target” Gravel Subgrade Surface
Prior To Pouring Ftgs Or Placing Struct. Fill.
Where Possible, Enlarge The Excavation To
Allow For Use Of Large, Smooth Drum Roller.
Product Recommendation:
A Stego 15-mil Vapor Barrier
Is Recommended.
Perimeter Footing Drain
To Wrap Around The
Exterior Of Home (typ.)
Over-Excavate Under All Perimeter, Interior, And
Exterior Footings Such That They Bear On A
Minimum Of 1’ Of Compacted Granular Structural
Fill That In Turn Bears On “Target” Glacial Till.
Min. Width Is B+H, But It Shall Not Be Less Than 5’.
Use Light-Weight Fabric Around Footing Drains (typ.).
Over-Excavation Width
Must Be Centered On
The Footings (typ.)
More Than 1.0’
Of Structural Fill
Is Expected (typ.)
Min. Width = (B + H);
But Shall Be 5.0’ (min.)
This Is A Bottom
Of Exc. Dimension.
Assumes No Sloughing
Of Exc. Side Walls.
Min. Width = (B + H);
But Shall Be 5.0’ (min.)
This Is A Bottom
Of Exc. Dimension.
Assumes No Sloughing
Of Exc. Side Walls.
A Large, Smooth Drum
Roller Should Be Used
To Vibratory Compact
Subgrade Soils And
Granular Structural Fill
Wherever Possible.
Concrete Slab
The Excavated Gravel Surface (Under All Footings) Must Consist Of Dense, Clean, Native Sandy Gravel. Use A Smooth Foundation
Bucket To Prevent Unnecessary Disturbance To The Native Gravel Subgrade. Do Not Stop Excavation In Lowermost Silt/Clay, Which
Does Contain Some Scattered Gravels. The Silt/Clay w/ Gravels (Which Looks Like A “Dirty Gravel”) Does Not Constitute The Clean,
Native Sandy Gravel (“Target” Bearing Material). Vibratory Re-Compact Subgrade Surface Whenever Possible.
Re-Compact Subgrade
Prior To Fill Placement.
Additional Structural Fill
Thickness As Required.
For Strip Footings With Width
Of 2.0’ Or Less, Min. Structural
Fill Thickness (H) Is 1.0’.
For Larger Pad Footings With Width
Of 3.0’ To 6.0’, Min. Structural Fill
Thickness (H) Is 2.0’.
Exterior Wall Backfill Can Consist Of Any Non-Organic Soil.
Suggest Removing Cobbles Over 6” Directly Next To Walls.
Strip Topsoil/Surfacing Material And Cut To A Min.
Depth Of 18 Inches Below Bottom Of Slab Grade.
For Easier Compaction, Consider
Using Only High Quality Granular
Material Or Clean Crushed Rock
For Interior Backfill. Place In
Lifts / Vibratory Compact.
“Target” Clean Gravel Surface.
Re-Compact Prior To Placing Fill.
Pad Footing
Over-Excavation
On Individual Basis
“Target” Clean
Gravel Surface.
Re-Compact Prior
To Pouring Ftgs Or
Placing Struct. Fill.
“Target” Clean
Gravel Surface.
Re-Compact Prior
To Pouring Ftgs Or
Placing Struct. Fill.
Foundation Bearing Recommendation:
All Footings Must Bear On “Target”
Sandy Gravel Or On Granular Structural
Fill That In Turn Bears On “Target” Gravel.
Note: Remove Any Sand Seams
In “Target” Gravel From Bottom
Of Excavation (Prior To Fill
Placement Or Pouring Footings).
All Excavations And Structural Fill
Under Footings Must Be Centered
Under The Footing.
Note: If Native Gravel Is Wet, Place An Initial Thin Layer
Of Clean Crushed Rock Covered By Non-Woven Fabric
Prior To Structural Fill. Vibratory Compact The Rock.
Excavations Should Be Wide Enough
To Permit The Use Of A Large, Smooth
Drum Roller For Compaction Of Gravel
Subgrade And Granular Structural Fill.
Footing Subgrade Will Consist Of
Native Silt/Clay. Dig With Smooth-
Edged Bucket To Prevent Disturbance.
Vibratory Compact To Re-Tighten Soils
And Induce Consolidation/Settlement.
Due To Dry Soils, Construction Water
May Need To Be Added To Facilitate
Better Compaction. (Typ. All Locations)
Over-Excavation And Structural Fill
To Be Centered Under Footing And
Extend A Minimum Of 2.0’ Beyond
Outside Edge Of Ftg In All Directions.
Over-Excavation And
Structural Fill To Be
Centered Under Footing
And Extend A Minimum Of
2.0’ Beyond Outside Edge
Of Ftg In All Directions.
Strip Topsoil Before
Placing Fill Material.
Strip Gravel.
Depending On The Number/Spacing Of Interior Footings.
Consideration Should Be Given To Mass Excavating Down
To “Target” Gravel Throughout Foundation Footprint And
Increasing Thickness Of The 12-Inch Structural Fill Layer.
By Doing This, Over-Excavation (On An Individual Basis)
Under Interior Footings Could Be Avoided.
H
Min. Width = H / 2 Min. Width = H / 2
Existing
Ground
Landscape Areas
To Grade Away
@ 5% (min.).
Perimeter
Footing And
Foundation
Wall (typ.)
Depth To “Target” Sandy
Gravel Ranges From 1.5’
To 5.0’; But Is 3.0’ To 5.0’
In Most Areas. (See Fig. 3)
Note: Due To Site’s 3.0’ To 5.0’ Gravel Depth, Most
Perimeter Ftgs Will Need To Bear On Struct. Fill.
Note: Depending On Finished
Floor Elevation And Perimeter
Footing Depth, (Below Ex. Grades),
Some Perimeter Footings May Bear
Directly On “Target” Gravel.
Strip Surface Fill And
Topsoil Prior To Filling.
Most Likely, Perimeter Footings Will
Readily Bear In Or Near “Target” Gravel
(Meaning Either No Req’d Structural Fill
Or Only A Relatively Thin Amount).
The Benefit Of Mass Over-Excavation
And Replacement Is That Interior
Footings Now Do Not Have To Be Over-
Excavated On An Individual Basis.
“Target” Clean Gravel Must
Be Exposed Throughout
The Bottom Of Excavation.
Re-Compact Subgrade Prior To Structural Fill Placement.
See Figure 5 For An Illustration That ShowsA Crawl Space Foundation Configuration.
We Recommend Mass Over-Excavation Under Slab-On-Grade Foundations Down To “Target”
Bearing (In Lieu Of Trench Excavating Under All Perimeter, Interior, And Exterior Footings On
An Individual Basis). This Excavation Approach Is Faster; But It Requires In-Filling/Backfilling
Inside The Foundation Walls With Granular Structural Fill Back Up To Interior Footing Grade.
For Figure 6, We Have Shown A Deep Native Gravel Surface To Purposely Illustrate The Need
For The Placement Of A Structural Fill Building Pad Back Up To Perimeter Footing Grade. Due
To Shallow Gravels, Most Perimeter Footings Should Readily Bear In/Near The “Target” Gravels.
Due To The Complexity Of Most Foundation Plans (Many/Closely Spaced Interior Footings),Individual Footing Over-Excavation Is Time Consuming, Difficult, And Not Recommended.
Due To The Shallow Gravels, Assumed Complexity Of The Foundation
Plan (Number And Spacing Of Interior Footings), And Need To Fully Remove
All Fill Material (That Was Found In The NE Corner), The Best Approach Will
Likely Be Mass Over-Excavation Of The Entire Foundation Footprint Area.
Some Perimeter
Ftgs May Require
Some Struct. Fill.
No Underslab Drains Req’d.
Due To Shallow Gravels And Likely Complexity
Of The Foundation Plan (Many/Closely Spaced
Interior Footings), We Assume Most Building
Foundations Will Be Mass Over-Excavated
Down To “Target” Gravel And Re-Filled With
Structural Fill Up To Interior Footing Grade.
Interior Footings
Will Most Likely
Require Struct. Fill.
Min. Exc. Width = H / 2; 2.0’ (min.)
Compacted Subgrade
(Non-Organic Silt/Clay)
Edge Of Borrow Pit
Compacted Subgrade
(“Target” Sandy Gravel)Compacted Subgrade
(“Target” Sandy Gravel)
No Footing Over-Excavation Or
Structural Fill Rq’d Where Footings
Bear In “Target” Sandy Gravel.
Compacted Subgrade
(“Target” Sandy Gravel)
Given The Shallow Gravel Depth In Most Areas,
Footing Grade Should Be Close To “Target” Gravel.
Structural Fill Thickness (H) As Needed/Required
To Build Up From “Target” Gravel To Ftg. Grade.
Due To Shallow Gravel Depths, Perimeter Footings Should Bear In Or Near
The Native Gravel, With Limited Needed For Over-Excavation (To Reach
“Target” Gravel). The Majority Of Over-Excavation/Replacement Will Likely
Be Required Under The Higher Elevation Interior Footings (Under The Slab).
Note: The Upper 6” To 9” Of Native
Gravel Is Generally A Little More Of A
Silty, Sandy Gravel, Which Transitions
To “Cleaner” Sandy Gravel With Depth.
Note: Where Possible, Use
Medium to Large Smooth Drum
Roller For Compaction Of Native
Subgrade And Granular Struct. Fill.
“Target” Clean Gravel Surface At Bottom
Of Mass Excavation. If The Surface Is Dry,
Vibratory Re-Compact Prior To Pouring
Footings Or Placing Granular Structural Fill.
Note: Dig Foundation Exc. With Smooth-Edged Bucket
To Minimize DisturbanceTo Native Gravel Subgrade.
Unless The Site Has Been
Filled With A Little More
Surface Fill Since The Test
Pits Were Dug In Feb. 2003,
The Depth To Gravel Will
Range From 1.5’ To 3.0’.
“Target” Clean Gravel Surface At Bottom
Of Mass Excavation. If The Surface Is Wet,
Track-Pack With Excavator And Static Roll
With Roller Prior To Placing Crushed Rock.
No Ftg
Drains
Req’d
4’ (min.)
For Frost
Protection
If Rq’d By IBC,
Damp Proof
Foundation
Walls
Note: This Figure
Illustrates The Possible
Need For Some Fabric-
Covered, Clean Crushed
Rock To Get Above Wet
Conditions Or Shallow
Groundwater. If The
Bottom Of Excavation Is
Dry, Then No Crushed
Rock Will Be Necessary.
If Groundwater Is Above The Native Gravel, Lower Groundwater By De-Watering.
If The Gravel Subgrade Is Wet Or Contains Areas Of Shallow Standing Water,
Place And Vibratory Compact An Initial Layer Of 1”-Minus Clean Crushed Rock
To Get Above The Wet Conditions. Cover The Crushed Rock Layer With A Layer
Of 8 oz. Non-Woven Geotextile Fabric Prior To Placing The Granular Structural Fill.
Min. Exc. Width = H / 2; 2.0’ (min.)
Min. Exc. Width = H / 2; 2.0’ (min.)
W W
W W
Note: Due To Expected
5.0’ To 7.0’ Gravel Depth,
Interior Ftgs Will Need To
Bear On Several Feet Of
Structural Fill.
Note: Due To Mass Over-Exc., A Thick Structural Fill Bldg Pad Will Be Placed Under Interior Ftgs.
Landscape Areas To Slope Away
@ 5% (min.) Within 10’ Of Wall.
Upper 4” - 6” Of Backfill Should
Consist Of Low Permeable Topsoil.
2500 psf (max.)
B
12” (min.) Structural Fill Layer
Under Interior Slab Area. (typ.)
More Than 12 Inches Of Structural Fill
May Be Required In Areas Of Thicker
Surface Fill And Deeper Topsoil Stripping.
Gravel/Rock
Backfill Is
Recommended
Under Interior
Slabs (typ.)
In Most Areas,
Thickness Of
Silt/Clay Ranges
From 0.5’ To 1.5’.
Gravel Backfill
Is Recommended
Under Exterior
Concrete Areas
To Minimize Frost
Heaving Potential
Crushed Rock/
Gravel Section
H
H
W
W Note: Deep Over-Excavations
Will Require Wider Excavations
For Rq’d Min. Structural Fill Width.
Note: Depending On Borrow Pit
Edge/Location, Shape, Depth, And
Side Wall Slope, Significant Over-
Excavation May Be Required Under
The East Side Footing/Wall Line.
Important Note: An Old Borrow Pit Area That Is
Re-Filled With Silt/Clay Is Located On The East Side
Of The Phase 1 Building Location. The West Edge
Of The Borrow Pit Encroaches Inside The East Side
Of The Building. In Most Areas Along The East
Footing/Wall Line, The Depth To “Target Bearing”,
Sandy Gravel Should Be Between About 2.0’ And 7.0’;
However The Pit Depth Falls Sharply To The East Down
To A Depth Of About 15.5’. (See Figures 2, 3, 4, & 5)Strip Topsoil And Place Site Fill Under Ext. Slabs.
Figure 7
24-166 Jan. 2025
Lot 2A, Blk 1, Glen Lake Commerce Sub.
Foundation Detail - At-Grade Slab - Option 2
Bozeman, Montana
Damp-Proofing As Required (typ.)
Foundation Wall (typ.)Approved Non-Woven Filter Fabric To Encase Bedding Gravel (typ.) Interior Floor Slab (typ.)Interior Steel Column (typ.)Interior Spread Footing (typ.)
6” Of 3/4" Minus Crushed Washed Gravel
Hydraulically Connected To Sub-Drain or
Existing Surface Drainage (typ.)
Native Topsoil andRandom Surface Fill Imported 4-Inch Minus Sandy Pitrun Gravel Native Silt/ClayImported Flowable Fill
Six Inch Diameter Sub-Drain Pipe
(Graded To Drain To Sump Area)
Concrete SidewalkLow Permeability Soils(Landscaped Area)LegendConcrete Wall and/or Footing Low Permeable Topsoil No Scale (Parts Of This Exhibit Have Been Exaggerated For Clarity)
ALLIEDENGINEERING
SERVICES, INC.
Civil Engineering
Geotechnical Engineering
Land Surveying
32 Discovery Drive
Bozeman, MT 59718
Phone: (406) 582-0221
Fax: (406) 582-5770
Slope Away @ 2%
In All Concrete Or
Pavement Areas (typ.)
Footings 6’ max.
depth below
existing ground
Native Topsoil 6” Minus Sandy (Pitrun) Gravel 4” Minus Sandy PitrunGravel (ie. Structural Fill)4’ max fill above existing ground
4' min.
4’ Max Fill Above
Existing Ground
3” (min.)
Thickness Will Vary Due To
Depth Of Bedbrock Strata
6” (min.)
3” (min.)
8” (min.)
4.0’ (min.)
6” (min.) Of Rock Bedding To Be
Placed Around Drain Piping (typ.)
Under-Slab Rock Layer To Be Hydraulically
Connected To Sub-Drain System By 3” Of Rock
Or 2” Sch. 80 Piping Spaced On 10’ Centers (typ.)
B
H (Variable; Depends
On Depth To Gravel)
18” (min.)
18” (min.)
6” (min.)
6” (min.)
1’ (min.)
H = 3.5’ (Based On4.0’ Footing Depth And The Depth To Gravel In TP-4) H = 5.5’ (Based On4.0’ Footing Depth And The Depth To Gravel In TP-2)
D D
Woven Geotextile Filter Fabric (Amoco 2004)Vapor Barrier Under Slab (typ.)
9.5’ Deep
(TP-2)
7.5’ Deep
(TP-4)
Non-Woven Filter
Fabric To Encase
1-Inch Minus Rock
6” (min.) Rock Layer (typ.)
Asphalt/Concrete Areas
To Be Sloped Away
@ 2% (min.).
6” (min.)
6” (min.)4” PE Sub-Drain (typ.)
Crawl Space Opening
Must Be Properly Vented.
Note: Elevation Difference Between The Top Back Of Curb
And The Finished Floor Should Be Maximized. I Believe The
Subdivision Covenants Call For A Minimum Separation Of 2.0’
And A Maximum Of 5.0’. Due To High Groundwater Concerns,
An Elevation Difference Of More Than 2.0’ Is Recommended.
This Should Be Thoroughly Considered On A Case By Case
Basis. Please Refer To The Covenants For More Detail.
Important Notes: The Three-Foot Wide (Min.) Over-Excavation From The Center Of The Footing Is Calculated Based On A 16-Inch
Footing Width (B) And An Average Depth To Native Gravel (GD) Below The Footing Elevation Equal To Five Feet. If The Footing
Is Substantially Wider Or The Depth To Gravel Substantially Deeper; The Width Of The Excavation Will Need To Be Increased. The
Equation For Determining Excavation Width (EW) From The Center Of Footing Is: EW = (B + GD) / 2.0. If Caving (ie. Sloughing)
Of The Excavation Side Walls Is A Problem; EW Will Need To Be Increased Accordingly. Since The Footings Are Supported On
Structural Fill That Bears On Native Gravel; There Is No BenefitTo Increasing Footing Size Beyond What Is Shown On The Plans.
If Groundwater Is Encountered In The Over-Excavation Above The Native Sandy Gravel Surface,
We Recommend A Layer Of Crushed Rock First Be Used To Get Above The Groundwater Elevation.
The Crushed Rock Should Be Placed In A Single Lift That Does Not Extend More Than Four Inches
Above The Groundwater. After Placement, The Crushed Rock MUST Be Compacted By Vibratory
Methods. Compactors That Are Suitable For Crushed Rock Include Walk-Behind Plate Compactors;
Remote-Controlled Sheepsfoot Trench Rollers; And Self-Propelled Smooth Drum Rollers.
Note: If Groundwater Is Not Encountered, The Use Of Crushed Rock Is Not Necessary.
Compacted Structural Fill. Use Sandy Pitrun Gravel,
Not Crushed Rock. Gravelly Materials Are Not Only
Less Expensive But They Will Also Reduce The In-Flow
Of Groundwater Into The Crawl Space In The Event That
High Groundwater Exceeds The Crawl Space Elevation.
Place The Pitun In Lifts (Six-Inch Thick Max. For Small
Remote-Controlled Sheepsfoot Trench Rollers And
Twelve-Inch Thick Max. For Self- Propelled Smooth
Drum Rollers) And Compact To An Unyielding Condition.
Note: A Material That Works Very Well For Foundation
Structural FilI Is The 3” Minus Pitrun Gravel Product
That Is Available From TMC In Belgrade.
Pay Special Attention To Compaction
Of Crushed Rock And Structural Fill
Along Edges. Native Soils Could Be
Soft. Rock / Fill Will Need To Be
Compacted Into Side Of Excavation.
Place Woven Geotextile
Fabric Over The Crushed
Rock. This Will Prevent
Fines Migration Into The
Rock After Placement Of
The Structural Fill.
4” (max.)
3’ (min.)
3’ (min.)
Interior Footing
As A Precaution For Groundwater,
Install 4” PE Slotted Drain Piping
Along The Inside Of The Perimeter
Footings And Grade To A Shallow
Sump Chamber In The Crawl Space.
If Water Becomes An Issue, Install
Sump Pump And Discharge Out Of
The Crawl Space. A Four-Inch Layer
Of Crushed Rock Will Facilitate
Rapid Drainage And Eliminate The
Sight Of Standing Water. If A Vapor
Barrier Is Placed Above The Crushed
Rock; Ensure It Is A Material That
Can Breathe (Not Polyethylene).
All Interior Footings Shall Bear On Structural Fill.
Finished Floor Elev. (At-Grade Slab)
GD
Existing Ground Surface
Existing
Ground
4” Slotted PE Pipe. Install Drain Piping Around Inside Perimeter Of Foundation. Piping
Should Be Placed At Footing Grade Or Preferably Below The Top Of The Crushed Rock
Fill (When Used). Connect Piping To Shallow Sump Chamber. If High Groundwater Is An
Issue, A Pump Can Be Installed At A Later Time.
32”
48”
Reviewed By: __________________
4” To 6” (Min.)
Thickness
As Required
2.5’
4’ (min.)
Damp
Proofing
4” Footing
Drain (typ.)
Min. Depth Of Cover
For Frost Protection
Min. Required Width Of
Mass Over-Excavation
Beyond Edge Of Footing
1.0’ - 17.0’ Depth To
“Target” Bearing Material.
Silt/Clay Below 2.5’ (+/-) Is
Generally V. Moist To Wet.
See TP Logs For Soil And
Groundwater Conditions.
5.0’ - 13.5’ Depth To
“Target” Bearing Material.
Groundwater Depth Ranged From 6.0’ to 13.5’. Depending
On Time Of Year, Groundwater May Be At Or Above The
Sandy Gravel (“Target” Bearing Material). Therefore,
Groundwater Dewatering May Be Needed. Dewatering Wells
Are Recommended To Lower Water Below Gravel Surface.
Strip, Remove, And Replace All Random Fill
From Under The Entire Building Area, Including
Under Interior House And Garage Slabs (typ.)
Note: De-Watering Will Likely Not Be
Required For Foundation Excavation.
Based On Our Test Pits,
All Evidence Suggests
The Groundwater Table
Stays Within The Sandy
Gravel Most Of The Time.
LSE, 1/17/25
Prior To The Placement Of Granular Structural Fill,
The Site’s Shallow Groundwater Conditions May
Require That An Initial Layer Of Clean Crushed Rock
Be Placed And Compacted Up To A Height Of At Least
6 Inches Above The Level Of The Standing Water.
Structural Fill: Use 4” Minus Sandy (pitrun) Gravel
Due To Shallow, Seasonal High Groundwater Conditions,
Footing And Crawl Space Depth Must Be Minimized Below
The Existing Ground Surface. Bottom Of Footing Elevation
Should Be Kept Within At Least 2.5’ To 3.0’ Of Existing Grades.
As An Added Precaution Against High Groundwater In The Crawl Space (And Especially
If Footing Depth Nears Or Exceeds 2.5’ To 3.0’ Below Existing Site Grades), We Strongly
Encourage The Placement Of A 6” To 8” Layer Of Crushed Rock In The Crawl Space To
Raise The Floor Elevation Up To The Top Of Footings. In The Event That Groundwater
Ever Rises Above The Crushed Rock Layer, A Sump Chamber And Pump Can Easily Be
Installed Later To Address The Problem.
We Do Not Recommend Placing The Initial Layer Of Clean Crushed Rock In Standing Water Exceeding 10 Inches In Depth.
Therefore, Depending On The Time Of Year, Some Groundwater De-Watering May Be Required During Foundation Earthwork.
All Perimeter, Interior, And Exterior Footings Must Bear
On A Minimum 2.0’ Thickness Of Granular Structural Fill
That In Turn Is Supported On The Native Sandy Gravel
(Which Is The ”Target” Foundation Bearing Material).
Given The 4.5’ To 6.5’ Depth To Gravel, Along With The
Anticipated Slab Grade, Perimeter Footings Will Likely
Lie 2.0’ to 6.0’ Above The Top Of The “Target” Gravel.
Mass Over-Excavate The Entire Foundation Footprint Area, Including All Exterior Footing Locations, Down To The “Target”
Bearing Material (Native Sandy Gravel); Thereby, Completely Removing All Native Silt, Clay, Sand From Under The Building.
Over-Dig The Excavation To The Minimum Width Dimensions As Shown On This Figure And As Stated In The Report.
Important Note: Mass Over-Excavation Of The Foundation (As Illustrated By Option #2)
Will Be Required If The Individual Footing Over-ExcavationsThat Are Depicted As Option #1
Will Not Stay “Open” Due To Trench Wall Collapse.
Foundation Earthwork Notes: 1) Slab On Grade - Option “B” Consists Of Over-Excavating Under All Perimeter, Interior, And Exterior Footings.2) This Is Most Applicable Where The Building Is Underlain By Relatively Deep Gravels And The Foundation Contains Less Interior Footings.3) Where Present, All Random Surface Fill Material Must Be Fully Removed From Under The Entire Building Area Down To Native Soils. Foundation Excavation Recommendations: Due To The Large Number and Close Spacing Of Interior Footings (Many Of Which Are 13 To 14 Feet On-Center), We Recommend The Entire Foundation Footprint Area Of The Apartment Buildings Be Mass Over-Excavated Down to Native Sandy Gravel And Built Back Up To Footing And Slab Grades With Compacted Structural Fill. The Limits Of The Mass Excavation Must Encapsulate All Perimeter And Exterior Footings. Important Note: It Is Now COB Policy That The Foundation Earthwork Be Inspected And Certified By The Geotechnical Engineer.
Suggestions: In Order To Reduce The Amount Of Required Structural Fill Under
Footings And The Slab Area, The Finished Floor Elevation Should Be Minimized
Above Existing Site Grades. Another Option To Reduce Fill Under Perimeter
Footings Is To Use A 6’ Tall Foundation Wall.
Foundation Backfill and Embankment Fill Granular Structural Fill(1.5”Minus Roadmix Gravel)Granular Structural Fill(1.5”Minus Roadmix Gravel)Sandy Gravel(”Target” Bearing Material) Low Permeable Topsoil Native Silt/Clay(Unsuitable Bearing Material) Native Silt
Native Silt/Clay/SandAnd Sand w/ Small Gravels(Unsuitable Bearing Material) Native Silt/Clay/SandAnd Sand w/ Small Gravels(Unsuitable Bearing Material) Native Topsoil Granular Structural Fill(4” Minus Sandy Gravel)Granular Structural Fill(1.5” Minus Roadmix Gravel)1” Minus CleanCrushed Rock Groundwater (on 4/19/16) Concrete Slab
Exterior Foundation Wall Backfill
Should Only Consist Of Excavated
Soils That Are Not Overly Moist. It
Must Be Placed In Multiple Lifts
And Properly Compacted.
Slab Grade Should Be Set Above
Existing Grades. For The Mass Over-
Excavation Option, There Is No Limit
On Slab Height Above Existing Grades.
H
W = Footing Width + H; (5’ min.)
All Foundation Fill Materials Should Be Placed In Uniform,
Horizontal Lifts And Be Well Compacted. Granular Structural Fill
Shall Be Compacted To A Dense, Unyielding Condition, While Clean
Crushed Rock Or Lean Mix Concrete Must Be Compacted By
Vibratory Means. In General, The “Loose” Thickness Of Each Lift
Prior To Compaction Should Not Exceed 12 Inches For Large, Self-
Propelled Rollers; 6 Inches For Remote-Controlled Trench Rollers
And Walk-Behind Jumping Jack Compactors; And 4 Inches For Walk-
Behind, Plate Compactors. Pay Special Attention To Compaction Of
Structural Fill Along Edges And In Corners Of The Excavation.
Place Crushed Rock As Fill Under
Slab (6” min.) And Interior Wall Backfill
Strip Topsoil
Under Slab and
Re-Compact The
Subgrade Surface.
Vapor Barrier Under Slab. Seal Barrier At Seams/Penetrations.
Minimize
New Fill
Height For
Settlement
Reasons
The Uppermost 6” Of Lean Mix
Concrete Fill Can Be Replaced w/
Clean Crushed Rock For Easier
Leveling Of Footing Grade.
Bearing Pressure
4000 psf (max.) Important Note: To Stabilize The Trench Excavations And Minimize The Potential For Caving/Sloughing, Groundwater Dewatering May Be Required.
Shallow Frost-
Proof Foundation.
Insulate As Per
Applicable Codes.
Interior Footing (typ.)
Radon Mitigation System Should
Be Considered Under Interior Slab.
Important Note: If Foundation Construction Will Occur During The Cold/Winter Weather Season, The
Contractor Shall Take All Necessary
Precautions To Prevent The Earth-
Work From Freezing And/Or From
Being Contaminated With Snow.
Note: At A Minimum, Use A Large, Smooth Drum Roller To Compact
The Upper-Most Lift Of Structural Fill Under Footings And Slabs.
6” (min.) Crushed Rock Layer Under Slab Areas (typ.)
Additional Thickness
Of Gravel Building Pad
As Req’d To Bear On
“Target” Gravel.
For Mass Excavation, Over-Excavation
Width Beyond Perimeter Ftgs Is 5.0’ (typ.)
See Fig. 6 For Over-Excavation Width
Under Individual Ftg Excavations.
Embankment Fill Can Be Used Below 18” Of Slab Grade.
Note: No Topsoil Observed In On-Site Borings. Product Recommendation: A Stego 15-mil Vapor Barrier Is Recommended.Available From MaCon Supply In Bozeman.
W = Footing Width + H; (5’ min.)
Min. Width = 1/2(H);
But Must Be 5’ Min.
H
H = 2’ Min.
Important Note: If TP-3, A Clay
Layer Was Observed Under The
Native Sandy Gravel At A Depth
Of 6.0’. It Is Recommended That
All Footings Bear On A Minimum
24” Thickness Of Native Gravel
Or Granular Structural Fill. This
Should Be Confirmed With Test
Pits Around The Perimeter Of The
Building During Construction.
Important Note: If The Trench
Excavations Are Prone To Minor
Caving, Their Width Will Have To
Be Increased Accordingly To
Prevent Slough From Underlying
Or Being Mixed Into The Minimum
Required Width Of Structural Fill.
Given The 4.5’ To 6.0’ Depth To
Native Sandy Gravel, We Do Not
Expect That Most (If Any) Of The
Perimeter Footings Will Bear
Directly On Native Gravel. Most
Likely, Footings Will Need To Be
Supported On Structural Fill That
In Turn Bears On Native Gravel
(Similar To All Interior Footings).
Excavation Alternative: In Lieu Of Only
Excavating Footings, The Entire Foundation
Footprint Area Of The Building Can Be Mass
Over-Excavated Down To Native Sandy Gravel
And Filled With Granular Structural Fill. Given
The Gravel Depth, This Is Far Less Economical
As Compared To The Above Recommendations.
Prior To Granular Structural Fill Placement, The Excavated Gravel Surface (Under Entire Foundation Footprint Area)
Must Be Vibratory Re-Compacted With A Large, Smooth Drum Roller In Order To Densify The Native Sandy Gravel.
Due To Groundwater Depths Of 7.8’ To 9.8’, Wet Subgrade Conditions Should Not Be An Issue.
Depending On Location, Groundwater Could
Be At Or Above The Top Of Native Sandy Gravel
During The Seasonal High Water Time Of Year.
A Large, Smooth Drum
Roller Must Be Used To
Compact All Granular
Structural Fill Whenever
and Wherever Possible.
Lean Mix Concrete(Flowable Fill)Embankment Fill(On-Site or Import Material)Non-Organic Embankment Fill(On-Site, “Drier” Silt/Clay/Sand)
2500 psf (max.)
B
2500 psf (max.)
B
Mass Excavate Under Entire Foundation Footprint Area Down To Native, Clean Sandy Gravel; Thereby
Removing All Of The Silt/Clay Under The Interior Slab. All Footings Must Bear On Native Sandy Gravel
Or On Compacted Granular Structural Fill That In Turn Is Supported On This “Target” Bearing Material.
Shallow Frost-Proof Foundation
Per IBC Is Also Acceptable.
H
H
If Exc. Walls Slough,
Widen Exc. To Ensure
Min. Struct. Fill Width
Beyond Edge Of Ftg.
Bottom Of Exc. Measurement
Centered Under The Footing.
If Exc. Walls Slough,
Widen Exc. To Ensure
Min. Struct. Fill Width
Beyond Edge Of Ftg.
Bottom Of Exc. Measurement
Centered Under The Footing.
Min. Width = (B + H); But 5’ (min.)
Crushed Rock
Is Only Needed
If Gravel Subgrade
Is Wet Or Contains
Standing Water.
All Fill Material Placed Under Footings And
Slabs To Consist Of Compacted Granular
Structural Fill. No On-Site Soils Are To Be
Used As Embankment Fill Under Slabs.
Do Not Place Granular Structural Fill Materials Over
Wet Subgrade Or In Shallow Standing Water. De-Water
The Excavation If Required. If Bottom Of Excavation
Is Wet, Place An Initial, Thin Layer Of Clean Crushed
Rock Under The Structural Fill. The Crushed Rock
Should Extend A Minimum Of About 4” Above The Wet
Conditions. Vibratory Compact The Crushed Rock And
Then Cover With A Medium-Weight, Non-Woven Fabric
Prior To Structural Fill Placement. Overlap Seams Of
Fabric By 12” Minimum.
Over-Excavate Under All Perimeter,
Interior, And Exterior Footings Down
To Native, Clean Sandy Gravel; Thereby
Removing All Silt/Clay Under Footings.
All Footings Must Bear On Native Sandy
Gravel Or On Compacted Granular
Structural Fill That In Turn Is Supported
On This “Target” Bearing Material.
Embankment Fill Under Structural Fill Layer
Must Be Compacted To Project Specifications.
See Figure 7 For
Recommendations
For Foundation Fill
Material Placement
And Compaction.
See Figure 7 For
Recommendations
For Ext. Foundation
Wall Backfill Material
And Compaction.
For Basements, Additional SubsurfaceDrainage And Moisture Protection Recommendations Will Need To BeIncorporated That Are Not Shown On This Exhibit. See Report For More Details. No Scale (Parts Of This Exhibit Have Been Exaggerated For Clarity)
No Scale (Parts Of This
Exhibit Have Been
Exaggerated For Clarity,
Especially The Depth To
Gravel & The Thickness
Of Req’d Structural Fill.)
This Figure Shows A Deeper Gravel
Depth On One End Of The Building
To Illustrate The Possible Need For
Over-Excavation/Replacement Under
Perimeter Footings. Due To Shallow
Gravel Depths Across The Site, This
May Not Be Applicable/Necessary.
Geotechnical Notes:
1) Figure 7 Provides Our Option 2 Recommendations For Foundation Earthwork And Support Under An At-Grade Slab Foundation Configuration.
2) Option 2 Includes Mass Excavating The Building Area Down To “Target” Gravel; And Over-Exc. Perimeter Ftgs (As Necessary) To Reach “Target” Gravel.
3) Due To Shallow Gravel Depths, Perimeter Footings Will Likely Bear In Native Gravel. Mass Exc. Will Eliminate Trench Over-Excavaton Under All Interior Ftgs.
Granular Structural Under Footings And Slabs Can Consist Of4”-Minus Sandy Pitrun Gravel Or 1.5”-Minus Roadmix Gravel. Based On Test Pits, Depth To “Target” Bearing Material Is 4’ To 5’ On Downhill Side And 3’ On Uphill Side Of The Lot.
Legend
Random Fill (Unsuitable Bearing Material) Random Fill (Unsuitable Bearing Material) Low Permeable Topsoil Granular Structural Fill(4”-Minus Sandy Gravel)Granular Structural Fill (*)Place In Thin Lifts And Vib. Compact To 97% (min.).
Import Granular Structural Fill (*)
Under Interior Slab Area (Rq’d)
Vibratory Compact To 97% (min.).
Import Granular Structural Fill (*)
Under Footings (As Needed)
Vibratory Compact To 97% (min.).
1” Minus CleanCrushed Rock
1” Minus Clean
Crushed Rock
1” Minus CleanCrushed Rock1” Minus CleanCrushed RockExisting Grade (Ground Surface)
Native Topsoil
Topsoil or Asphalt/GravelSurfacing Materials Native Topsoil Floor Joist
Exterior Wall Backfill
And/Or Site Fill
(Silt/Clay Or Gravel)
Borrow Pit Fill (Silt/Clay)
Native Topsoil Native “Clean” Sandy Gravel
(“Target” Bearing Material)
Native “Dirty” Sandy Gravel(Unsuitable Bearing Material)
Native Silt/Clay
Native Topsoil
Random Fill Material
(“Dirty” Gravel w/
Intermixed Silt/Clay)
Flowable Fill (Lean Mix Concrete)Under Footings (Option 2)(500 psi Mix; Consolidate w/ Vib.)
Interior Wall Backfill
(Gran. Struct. Fill
Or Crushed Rock)
Interior Wall Backfill(Gran. Struct. Fill Or Crushed Rock)
“Target” Bearing Material Is The Glacial Till. It Is Identifiable Based On Its Clean
Sandy Composition, Abundance Of 6”-Minus, Sub-Rounded Gravels, And Dense
Configuration. It Looks Like “Clean Pitrun Gravel” w/ Large Cobbles And Boulders.
All Footings Shall Bear On A Minimum Of 1’ Of
Granular Structural Fill That In Turn Bears On
“Target” Glacial Till (typ). Additional Structural Fill
Thickness Will Be Required Under Some Footings
In Order To Reach “Target” Bearing Material.
Recompact Subgrade Prior To Fill Placement (typ).
All Foundation Fill Materials Should Be Placed In Uniform, Horizontal Lifts
And Be Well Compacted. Granular Structural Fill, Embankment Fill, And Wall
Backfill Shall Be Compacted To A Dense, Unyielding Condition, While Clean
Crushed Rock Must Be Compacted By Vibratory Means. In General, The “Loose”
Thickness Of Each Lift Prior To Compaction Should Not Exceed 12 Inches For
Large, Self-Propelled Rollers; 6 Inches For Remote-Controlled Trench Rollers
And Walk-Behind Jumping Jack Compactors; And 4 Inches For Walk-Behind,
Plate Compactors. Pay Special Attention To Compaction Of Fill Materials Along
Edges And In Corners Of The Excavation; And Along Foundation Walls.
Daylight Footing And
Sub-Slab Drains (typ.)
See Figures 8 And 9
For Note On Exterior
Foundation Wall Backfill.
Granular Structural Fill
Should Be Used For
Interior Wall Backfill
Under Slabs.
See Figures 8 And 9 For Note
On Foundation Fill Material
Placement And Compaction.
All Excavated Soils Can Be Re-Used For Exterior Wall Backfill
Or Embankment Fill Provided They Are Not Organic Or Overly Moist.
All Fill Must Be Placed In Thin, Level Lifts And Properly Compacted.
H = 1’ or 2’ (Depending On Ftg Width)
H = 1.0’ (min.)
H
H = 1.0’ (min.)
15-mil Vapor Barrier Under Slab (Above Rock Layer).
Seal Barrier At Seams, Penetrations, And Footings.
Vapor Barrier Not Typ. Under Garage Slabs. Note: Due To Unheated/Non-Insulated Buildings, Consider Insulating Under Interior Slabs To Minimize Frost Heaving Potential Of Silt/Clay.
(*) Granular Structural Fill Can Consist
Of 3”-Minus Sandy (Pitrun) Gravel Or
1.5”-Minus Crushed (Roadmix) Gravel
Note: Deep Groundwater Conditions Exist At The Site. In Feb. 2003, Groundwater Was > 14.0’ Deep In The Area Of Lot 2A.
Note: In October 2022, Groundwater Depths Ranged From 5.0’ To 10.0’ Across The Property. High Groundwater Depths In 2023 Ranged From 2.9’ To 6.9’ (Highest GW Depths On West Side). Note: We Do Not Recommend Trench Over-Excavating Footings On An Individual Basis; But Rather Mass Over-Exc.
Strip Topsoil And
Bench Subgrade Level
Prior To Placing Fill (typ.)
About 6” Of
Dirty Gravel
Overlies The
Clean Gravel.It Is Important To Vibratory Re-Compact The
Excavated “Target” Gravel Subgrade Surface
Prior To Pouring Ftgs Or Placing Struct. Fill.
Where Possible, Enlarge The Excavation To
Allow For Use Of Large, Smooth Drum Roller.
Product Recommendation:
A Stego 15-mil Vapor Barrier
Is Recommended.
Perimeter Footing Drain
To Wrap Around The
Exterior Of Home (typ.)
Over-Excavate Under All Perimeter, Interior, And
Exterior Footings Such That They Bear On A
Minimum Of 1’ Of Compacted Granular Structural
Fill That In Turn Bears On “Target” Glacial Till.
Min. Width Is B+H, But It Shall Not Be Less Than 5’.
Use Light-Weight Fabric Around Footing Drains (typ.).
Over-Excavation Width
Must Be Centered On
The Footings (typ.)
More Than 1.0’
Of Structural Fill
Is Expected (typ.)
Min. Width = (B + H);
But Shall Be 5.0’ (min.)
This Is A Bottom
Of Exc. Dimension.
Assumes No Sloughing
Of Exc. Side Walls.
Min. Width = (B + H);
But Shall Be 5.0’ (min.)
This Is A Bottom
Of Exc. Dimension.
Assumes No Sloughing
Of Exc. Side Walls.
A Large, Smooth Drum
Roller Should Be Used
To Vibratory Compact
Subgrade Soils And
Granular Structural Fill
Wherever Possible.
Concrete Slab
The Excavated Gravel Surface (Under All Footings) Must Consist Of Dense, Clean, Native Sandy Gravel. Use A Smooth Foundation
Bucket To Prevent Unnecessary Disturbance To The Native Gravel Subgrade. Do Not Stop Excavation In Lowermost Silt/Clay, Which
Does Contain Some Scattered Gravels. The Silt/Clay w/ Gravels (Which Looks Like A “Dirty Gravel”) Does Not Constitute The Clean,
Native Sandy Gravel (“Target” Bearing Material). Vibratory Re-Compact Subgrade Surface Whenever Possible.
Re-Compact Subgrade
Prior To Fill Placement.
Additional Structural Fill
Thickness As Required.
For Strip Footings With Width
Of 2.0’ Or Less, Min. Structural
Fill Thickness (H) Is 1.0’.
For Larger Pad Footings With Width
Of 3.0’ To 6.0’, Min. Structural Fill
Thickness (H) Is 2.0’.
Exterior Wall Backfill Can Consist Of Any Non-Organic Soil.
Suggest Removing Cobbles Over 6” Directly Next To Walls.
Strip Topsoil/Surfacing Material And Cut To A Min.
Depth Of 18 Inches Below Bottom Of Slab Grade.
For Easier Compaction, Consider
Using Only High Quality Granular
Material Or Clean Crushed Rock
For Interior Backfill. Place In
Lifts / Vibratory Compact.
“Target” Clean Gravel Surface.
Re-Compact Prior To Placing Fill.
Pad Footing
Over-Excavation
On Individual Basis
“Target” Clean
Gravel Surface.
Re-Compact Prior
To Pouring Ftgs Or
Placing Struct. Fill.
“Target” Clean
Gravel Surface.
Re-Compact Prior
To Pouring Ftgs Or
Placing Struct. Fill.
Foundation Bearing Recommendation:
All Footings Must Bear On “Target”
Sandy Gravel Or On Granular Structural
Fill That In Turn Bears On “Target” Gravel.
Note: Remove Any Sand Seams
In “Target” Gravel From Bottom
Of Excavation (Prior To Fill
Placement Or Pouring Footings).
All Excavations And Structural Fill
Under Footings Must Be Centered
Under The Footing.
Note: If Native Gravel Is Wet, Place An Initial Thin Layer
Of Clean Crushed Rock Covered By Non-Woven Fabric
Prior To Structural Fill. Vibratory Compact The Rock.
Excavations Should Be Wide Enough
To Permit The Use Of A Large, Smooth
Drum Roller For Compaction Of Gravel
Subgrade And Granular Structural Fill.
Footing Subgrade Will Consist Of
Native Silt/Clay. Dig With Smooth-
Edged Bucket To Prevent Disturbance.
Vibratory Compact To Re-Tighten Soils
And Induce Consolidation/Settlement.
Due To Dry Soils, Construction Water
May Need To Be Added To Facilitate
Better Compaction. (Typ. All Locations)
Over-Excavation And Structural Fill
To Be Centered Under Footing And
Extend A Minimum Of 2.0’ Beyond
Outside Edge Of Ftg In All Directions.
Over-Excavation And
Structural Fill To Be
Centered Under Footing
And Extend A Minimum Of
2.0’ Beyond Outside Edge
Of Ftg In All Directions.
Strip Topsoil Before
Placing Fill Material.
Strip Gravel.
Depending On The Number/Spacing Of Interior Footings.
Consideration Should Be Given To Mass Excavating Down
To “Target” Gravel Throughout Foundation Footprint And
Increasing Thickness Of The 12-Inch Structural Fill Layer.
By Doing This, Over-Excavation (On An Individual Basis)
Under Interior Footings Could Be Avoided.
H
Min. Width = H / 2 Min. Width = H / 2
Existing
Ground
Landscape Areas
To Grade Away
@ 5% (min.).
Perimeter
Footing And
Foundation
Wall (typ.)
Depth To “Target” Sandy
Gravel Ranges From 1.5’
To 5.0’; But Is 3.0’ To 5.0’
In Most Areas. (See Fig. 3)
Note: Due To Site’s 3.0’ To 5.0’ Gravel Depth, Most
Perimeter Ftgs Will Need To Bear On Struct. Fill.
Note: Depending On Finished
Floor Elevation And Perimeter
Footing Depth, (Below Ex. Grades),
Some Perimeter Footings May Bear
Directly On “Target” Gravel.
Strip Surface Fill And
Topsoil Prior To Filling.
Most Likely, Perimeter Footings Will
Readily Bear In Or Near “Target” Gravel
(Meaning Either No Req’d Structural Fill
Or Only A Relatively Thin Amount).
The Benefit Of Mass Over-Excavation
And Replacement Is That Interior
Footings Now Do Not Have To Be Over-
Excavated On An Individual Basis.
“Target” Clean Gravel Must
Be Exposed Throughout
The Bottom Of Excavation.
Re-Compact Subgrade Prior To Structural Fill Placement.
See Figure 5 For An Illustration That ShowsA Crawl Space Foundation Configuration.
We Recommend Mass Over-Excavation Under Slab-On-Grade Foundations Down To “Target”
Bearing (In Lieu Of Trench Excavating Under All Perimeter, Interior, And Exterior Footings On
An Individual Basis). This Excavation Approach Is Faster; But It Requires In-Filling/Backfilling
Inside The Foundation Walls With Granular Structural Fill Back Up To Interior Footing Grade.
For Figure 6, We Have Shown A Deep Native Gravel Surface To Purposely Illustrate The Need
For The Placement Of A Structural Fill Building Pad Back Up To Perimeter Footing Grade. Due
To Shallow Gravels, Most Perimeter Footings Should Readily Bear In/Near The “Target” Gravels.
Due To The Complexity Of Most Foundation Plans (Many/Closely Spaced Interior Footings),Individual Footing Over-Excavation Is Time Consuming, Difficult, And Not Recommended.
Due To The Shallow Gravels, Assumed Complexity Of The Foundation
Plan (Number And Spacing Of Interior Footings), And Need To Fully Remove
All Fill Material (That Was Found In The NE Corner), The Best Approach Will
Likely Be Mass Over-Excavation Of The Entire Foundation Footprint Area.
Some Perimeter
Ftgs May Require
Some Struct. Fill.
No Underslab Drains Req’d.
Due To Shallow Gravels And Likely Complexity
Of The Foundation Plan (Many/Closely Spaced
Interior Footings), We Assume Most Building
Foundations Will Be Mass Over-Excavated
Down To “Target” Gravel And Re-Filled With
Structural Fill Up To Interior Footing Grade.
Interior Footings
Will Most Likely
Require Struct. Fill.
Min. Exc. Width = H / 2; 2.0’ (min.)
Compacted Subgrade
Non-Organic Silt/Clay
Edge Of Borrow Pit
Compacted Subgrade
(“Target” Sandy Gravel)
Perimeter Footing Excavation
Compacted Subgrade
(“Target” Sandy Gravel)
No Footing Over-Excavation Or
Structural Fill Rq’d Where Footings
Bear In “Target” Sandy Gravel.
Compacted Subgrade
(“Target” Sandy Gravel)
Given The Shallow Gravel Depth In Most Areas,
Footing Grade Should Be Close To “Target” Gravel.
Structural Fill Thickness (H) As Needed/Required
To Build Up From “Target” Gravel To Ftg. Grade.
Due To Shallow Gravel Depths, Perimeter Footings Should
Bear In Or Near The Native Gravel, With Limited Needed For
Over-Excavation (To Reach “Target” Gravel).
Note: The Upper 6” To 9” Of Native
Gravel Is Generally A Little More Of A
Silty, Sandy Gravel, Which Transitions
To “Cleaner” Sandy Gravel With Depth.
Note: Where Possible, Use
Medium to Large Smooth Drum
Roller For Compaction Of Native
Subgrade And Granular Struct. Fill.
“Target” Clean Gravel Surface At Bottom
Of Mass Excavation. If The Surface Is Dry,
Vibratory Re-Compact Prior To Pouring
Footings Or Placing Granular Structural Fill.
Note: Dig Foundation Exc. With Smooth-Edged Bucket
To Minimize DisturbanceTo Native Gravel Subgrade.
Unless The Site Has Been
Filled With A Little More
Surface Fill Since The Test
Pits Were Dug In Feb. 2003,
The Depth To Gravel Will
Range From 1.5’ To 3.0’.
“Target” Clean Gravel Surface At Bottom
Of Mass Excavation. If The Surface Is Wet,
Track-Pack With Excavator And Static Roll
With Roller Prior To Placing Crushed Rock.
No Ftg
Drains
Req’d
4’ (min.)
For Frost
Protection
If Rq’d By IBC,
Damp Proof
Foundation
Walls
Note: This Figure
Illustrates The Possible
Need For Some Fabric-
Covered, Clean Crushed
Rock To Get Above Wet
Conditions Or Shallow
Groundwater. If The
Bottom Of Excavation Is
Dry, Then No Crushed
Rock Will Be Necessary.
If Groundwater Is Above The Native Gravel, Lower Groundwater By De-Watering.
If The Gravel Subgrade Is Wet Or Contains Areas Of Shallow Standing Water,
Place And Vibratory Compact An Initial Layer Of 1”-Minus Clean Crushed Rock
To Get Above The Wet Conditions. Cover The Crushed Rock Layer With A Layer
Of 8 oz. Non-Woven Geotextile Fabric Prior To Placing The Granular Structural Fill.
Min. Exc. Width = H / 2; 2.0’ (min.)
Min. Exc. Width = H / 2; 2.0’ (min.)
W
W
W W
Note: Due To Expected
5.0’ To 7.0’ Gravel Depth,
Interior Ftgs Will Need To
Bear On Several Feet Of
Structural Fill.
Note: Due To Mass Over-Exc., A Thick Structural Fill Bldg Pad Will Be Placed Under Interior Ftgs.
Landscape Areas To Slope Away
@ 5% (min.) Within 10’ Of Wall.
Upper 4” - 6” Of Backfill Should
Consist Of Low Permeable Topsoil.
2500 psf (max.)
B
12” (min.) Structural Fill Layer
Under Interior Slab Area. (typ.)
More Than 12 Inches Of Structural Fill
May Be Required In Areas Of Thicker
Surface Fill And Deeper Topsoil Stripping.
Gravel/Rock
Backfill Is
Recommended
Under Interior
Slabs (typ.)
In Most Areas,
Thickness Of
Silt/Clay Ranges
From 0.5’ To 1.5’.
Mass Over-Excavation/Replacement Under The
Entire Building Area Down To “Target” Gravel.
Due To Shallow Gravels, This Will/May Be More
Advantageous If There Are Numerous Interior
Footings. This Will Eliminate Having To Trench
Over-Excavate/Replace Under Interior Footings.
Gravel Backfill
Is Recommended
Under Exterior
Concrete Areas
To Minimize Frost
Heaving Potential
Crushed Rock/
Gravel Section
H
H
W
W Note: Deep Over-Excavations
Will Require Wider Excavations
For Rq’d Min. Structural Fill Width.
Note: Depending On Borrow Pit
Edge/Location, Shape, Depth, And
Side Wall Slope, Significant Over-
Excavation May Be Required Under
The East Side Footing/Wall Line.
Important Note: An Old Borrow Pit Area That Is
Re-Filled With Silt/Clay Is Located On The East Side
Of The Phase 1 Building Location. The West Edge
Of The Borrow Pit Encroaches Inside The East Side
Of The Building. In Most Areas Along The East
Footing/Wall Line, The Depth To “Target Bearing”,
Sandy Gravel Should Be Between About 2.0’ And 7.0’;
However The Pit Depth Falls Sharply To The East Down
To A Depth Of About 15.5’. (See Figures 2, 3, 4, & 5)Strip Topsoil And Place Site Fill Under Ext. Slabs.
% WATERCONTENTSAMPLESDEPTH (FT)HORIZONTAL DISTANCE (FT):
JOB NUMBER: 18-024
PROJECT: Manley Road
DATE: May 9, 2018
BACKHOE TYPE: Hitachi Mini-Excavator
BACKHOE OPERATOR: TJ - Townsend Backhoe
LOGGED BY: Lee S. Evans - AESI
SURFACE ELEVATION: 4714.28’
TOTAL DEPTH: 6.0’
GROUNDWATER: Dry
TEST PIT DESIGNATION: TP-A
2 4.0’
8.0’
4.25’
5.0’
2.5’
9.0’
0.7’
4
6
8
10
12
2 4 8 106
4
Nuclear Density Test at 3.5’ Dry Unit Wt. = 73 pcf Moisture Content = 13.3%
Den
Notes:
1. Nuclear Density Testing at 2.5’
Dry Unit Weight = 123 pcf
Moisture Content = 3.6%
ALLIEDENGINEERING
SERVICES, INC.
Civil Engineering
Geotechnical Engineering
Land Surveying
32 Discovery Drive
Bozeman, MT 59718
Phone: (406) 582-0221
Fax: (406) 582-5770
DESCRIPTION OF MATERIALS
4
5
67
LOCATION: Sta. 14+80 (+/-); W. Side of Ex. Road
15.6% 21.1% 20.1% 42.4% 8.4%
7.9%
N/A
8.3%
5.1%
3.4%
15.7%
24.9%
23.0%
21.4%
00.0%
N/A
23.9%
2
S2-E
@ 9.0’
(Sack)
11.1%
S2-C
@ 3.0’
(Sack)
S5-D
@ 3.5’
(Sack)
S1-A
@ 2.0’
(Sack)
13.6%
N/A Comp. A
@ 2.0’
(Bucket)
3.2%
S2-B
@ 4.0’
(Sack)
N/A
Comp. B
@ 3.0’
to 4.0’
(Bucket)
N/A
Comp. 2
@ 1.5’
to 3.0’
(Bucket)
S5-D
@ 1.0’
to 2.0’
(Bucket)
S2-C
@ 6.0’
(Sack)
S1-C
@ 3.0’
(Sack)
CS-2/5
@ 5.0’
(Bucket)
N/A
N/A
S1-D
@ 1.0’
to 2.0’
(Bucket)
CS-1/2
@ 2.0’
(Bucket)
S1-D
@ 8.0’
(Sack) S2-B
@ 5.3’
to 9.0’
S2-C
@ 9.0’
to 10.5’
S2-D
@ 10.5’
to 14.0’
S2-E
@ 14.0’
to 15.0’
S-1
@ 1’
7
Qu @ 4.0’ - 9.0’ = 0.5 - 1.5 tsf
Percentage and size
of shale fragments
increases w/ depth.
Density of layer
appears to increase
near a depth of 4.0’.
No apparent bedding
of rock fragments.
Depth
of roots
TD = 12.0’
Assumed watertable based on seepage depth.
Due to water pressure
in pit walls, moderate
soil caving began at
depth of 6.0’. Caving
was confined to the
clays only.
Very distinct
North Natural Ground Slope South
4
5 6
Liquid Limit
Plastic Limit
Plasticity Index
121.0 %
= 48.2 %
= 72.8 %
Atterberg Limits for S2-C
Based on the orientation of the boundary
between soil types, it appears that the soils dip
toward the east at grades from 0 to 10 percent.
Based on previous site grading, the test pit area is relatively flat.
Soil consistency
decreases w/
increased depth.
(See Fig. 1 & 2 for Surveyed Location)
Lab Testing Results: S1-C
Gravel Portion
Sand Portion
Silt/Clay Portion
Liquid Limit
Plastic Limit
Plasticity Index
= 67.1%
= 26.5%
= 6.4%
= NP
= NP
= NP
@ 6.0’ (approx.)
Soils were very
moist; darker in
color; and walls
tended to cave.
Qu > 3.5 tsf
General Note: Depth to groundwater was
measured about 0.5 hr after excavation. This
is the “stabilized” groundwater table depth. Reviewed By: __________________ GENERAL NOTES:
- Orange discoloration at 6.0’ may indicate high water
- Sandy gravel below 6.0’ was silty to clayey and moist
- Installed PVC monitoring well (4” diameter, 10’ long)
No Samples CollectedGROUNDWATER MONITORING NOTE:
Test pit explorations were dug before 2015 seasonal
high groundwater date. If time permits, monitoring
should be conducted during spring/summer of 2015
to identify high groundwater depth.
Monitoring well installed (MW-1).Bottom of 4” PVC well extends to a depth of between 9.5’ and 10.0’.
(*) Groundwater seepage entering pit at 13.0’ and below. If pit had been left open for longer period of time, groundwater would have risen to a depth of about 13.0’ (+/-).
STD. PROCTOR TEST RESULTS
Composite A: TP-1, 2, 3, & 4
Max. Dry Density
Optimum Moisture
= 000.0 pcf
= 00.0 %
STD. PROCTOR TEST RESULTS
Composite B: TP-1, 2, 3, & 4
Max. Dry Density
Optimum Moisture
= 000.0 pcf
= 00.0 % STD. PROCTOR TEST RESULTS
Composite A: TP-1 - TP -7
Max. Dry Density
Optimum Moisture
= 113.3 pcf
= 15.7 %
STD. PROCTOR TEST RESULTS
Composite B: TP-1, 2, 3, & 4
Max. Dry Density
Optimum Moisture
= 000.0 pcf
= 00.0 %
LAB TESTING RESULTS
Sample: S2-B
Sand Portion
Silt/Clay Portion
Liquid Limit
Plastic Limit
Plasticity Index
Soil Classification
= 2.4 %
= 97.6 %
= 36.5 %
= 25.1 %
= 11.4 %
= ML
“Target” foundation bearing in
“clean” cobbly, sandy GRAVEL
below 3.0’ depth.
Orangish “banding” in gravels at 6.0’ (+/-).Could be a sign of seasonal high groundwater.
General Note: From the top down, this
TP was the most rocky of all four. Upon
backfilling, the surface of this TP was
the most difficult to clean up due to the
quantity and size of the rocks.
Soil profile turned dark
brown and moist below
6.5’ depth, which may be
an indication of seasonal
high groundwater levels.
Other than surfacing materials,
all soils in test pit are native. No
random/foreign fill encountered.
1
2
3
4
{0.0’ - 1.0’}: Random Fill
Dense; dark brown to brown;
“dirty” sandy GRAVEL w/ some
intermixed silt/clay; slightly moist.
Notes:
- Mostly small gravels.
- Not much for silt/clay.
{1.0’ - 1.5’}: Native Topsoil
Very stiff; black to dark brown;
organic clayey SILT; slightly moist.
Notes:
- B-horizon soil. Not very organic.
{1.5’ - 2.5’}: Native Silt/Clay
Stiff to very stiff; brown; sandy SILT
to sandy lean CLAY w/ some small
gravels in lowermost 6 inches; moist.
Notes:
- Qu = 1.75 - 2.25 tsf.
- Moist, but stiff soil.
- Transition zone to underlying
sandy gravel from 2.0’ to 2.5’.
{2.5’ - 6.0’}: Native Sandy Gravel
Dense; brown; sandy GRAVEL w/
abundant 6”-minus gravels and
scattered 6” to 10” cobbles; slightly
moist.
Notes:
- “Clean” sandy gravel.
1
“Target” foundation bearing in
sandy GRAVEL below 7.0’ depth.
Groundwater depth
on 08/12/14 was 5.92’.
No signs or evidence of seasonal high groundwater down to a depth of 3.0’ (+/-).
Moisture break at 1.0’ (+/-).
Very moist/very soft below.
Band of intermixed gravel from 0.5’ to 1.0’. LSE, 3/10/20
Pretty gravelly in lower 1.0’.
Abundant 6”-minus gravels
and scattered 6” to 10” cobbles
Some caving below
groundwater table.
Very stiff; black to brown;silt/clay w/ multiple, inter-bedded, thin, sand seams. Layers of asphalt millings inter-bedded w/ layers of small gravels.
Clean sandy gravel (native)
Silt/clay (native)
B-horizon topsoil (native)
Random fill (gravelly)
This pit had much moretopsoil than other 6 pits.
Very moist/wet and very soft at 4.5’ (+/-).
Based on saturated soil conditions, high groundwater could rise to a depth of 2.5’ (+/-).
2
POCKET PENETROMETER
MEASUREMENTS (tsf)
@ 1.0’: Qu = 2.50, 2.50, 2.75, 2.75, 3.00
@ 2.0’: Qu = 0.50, 0.50, 1.00, 1.00, 1.00
POCKET PENETROMETER
MEASUREMENTS (tsf)
@ 1.0’: Qu = 2.50, 2.75, 2.75, 2.75, 2.75
@ 2.0’: Qu = >4.50, >4.50, >4.50, >4.50
@ 3.0’: Qu = >4.50, >4.50, >4.50, >4.50
10’ monitoring well installed (MW-1), casing height = 12” (+/-)
3
4
5 Loose, gravelly sand
LOCATION NOTE:
TP-A was dug well off the
west side of the ex. road.
{7.0’ - 10.0’}: Native Sandy Gravel
Dense; brown; sandy GRAVEL w/ abundant
6”-minus gravels and scattered 8” to 10”
cobbles; slightly moist to wet.
Notes:
- “Clean” sandy gravel.
- “Target” bearing material.
DESCRIPTION OF MATERIALS (cont.):
5
6
{0.0’ - 0.2’}: Asphalt (2” Thick)
% WATERCONTENTSAMPLESDEPTH (FT)HORIZONTAL DISTANCE (FT):
JOB NUMBER: 18-024
PROJECT: Manley Road
DATE: May 9, 2018
BACKHOE TYPE: Hitachi Mini-Excavator
BACKHOE OPERATOR: TJ - Townsend Backhoe
LOGGED BY: Lee S. Evans - AESI
SURFACE ELEVATION: 4713.09’
TOTAL DEPTH: 3.5’
GROUNDWATER: Dry
TEST PIT DESIGNATION: TP-B
2 4.0’
8.0’
4.25’
5.0’
2.5’
9.0’
0.7’
4
6
8
10
12
2 4 8 106
4
Nuclear Density Test at 3.5’ Dry Unit Wt. = 73 pcf Moisture Content = 13.3%
Den
Notes:
1. Nuclear Density Testing at 2.5’
Dry Unit Weight = 123 pcf
Moisture Content = 3.6%
ALLIEDENGINEERING
SERVICES, INC.
Civil Engineering
Geotechnical Engineering
Land Surveying
32 Discovery Drive
Bozeman, MT 59718
Phone: (406) 582-0221
Fax: (406) 582-5770
DESCRIPTION OF MATERIALS
4
5
67
LOCATION: Sta. 15+90 (+/-); W. Side of Ex. Road
15.6% 21.1% 20.1% 42.4% 8.4%
7.9%
N/A
8.3%
5.1%
3.4%
15.7%
24.9%
23.0%
21.4%
00.0%
N/A
23.9%
2
S2-E
@ 9.0’
(Sack)
11.1%
S2-C
@ 3.0’
(Sack)
S5-D
@ 3.5’
(Sack)
13.6%
N/A
S1-A
@ 2.0’
(Sack)
Comp. A
@ 2.0’
(Bucket)
3.2%
S2-B
@ 4.0’
(Sack)
N/A
Comp. B
@ 3.0’
to 4.0’
(Bucket)
N/A
Comp. 2
@ 1.5’
to 3.0’
(Bucket)
S5-D
@ 1.0’
to 2.0’
(Bucket)
S2-C
@ 6.0’
(Sack)
S1-C
@ 3.0’
(Sack)
CS-2/5
@ 5.0’
(Bucket)
N/A
N/A
S1-D
@ 1.0’
to 2.0’
(Bucket)
CS-1/2
@ 2.0’
(Bucket)
S1-D
@ 8.0’
(Sack) S2-B
@ 5.3’
to 9.0’
S2-C
@ 9.0’
to 10.5’
S2-D
@ 10.5’
to 14.0’
S2-E
@ 14.0’
to 15.0’
S-1
@ 1’
7
Qu @ 4.0’ - 9.0’ = 0.5 - 1.5 tsf
Percentage and size
of shale fragments
increases w/ depth.
Density of layer
appears to increase
near a depth of 4.0’.
No apparent bedding
of rock fragments.
Depth
of roots
TD = 12.0’
Assumed watertable based on seepage depth.
Due to water pressure
in pit walls, moderate
soil caving began at
depth of 6.0’. Caving
was confined to the
clays only.
Very distinct
North Natural Ground Slope South
4
5 6
Liquid Limit
Plastic Limit
Plasticity Index
121.0 %
= 48.2 %
= 72.8 %
Atterberg Limits for S2-C
Based on the orientation of the boundary
between soil types, it appears that the soils dip
toward the east at grades from 0 to 10 percent.
Based on previous site grading, the test pit area is relatively flat.
Soil consistency
decreases w/
increased depth.
(See Fig. 1 & 2 for Surveyed Location)
Lab Testing Results: S1-C
Gravel Portion
Sand Portion
Silt/Clay Portion
Liquid Limit
Plastic Limit
Plasticity Index
= 67.1%
= 26.5%
= 6.4%
= NP
= NP
= NP
@ 6.0’ (approx.)
Soils were very
moist; darker in
color; and walls
tended to cave.
Qu > 3.5 tsf
General Note: Depth to groundwater was
measured about 0.5 hr after excavation. This
is the “stabilized” groundwater table depth. Reviewed By: __________________ GENERAL NOTES:
- Orange discoloration at 6.0’ may indicate high water
- Sandy gravel below 6.0’ was silty to clayey and moist
- Installed PVC monitoring well (4” diameter, 10’ long)
No Samples CollectedGROUNDWATER MONITORING NOTE:
Test pit explorations were dug before 2015 seasonal
high groundwater date. If time permits, monitoring
should be conducted during spring/summer of 2015
to identify high groundwater depth.
Monitoring well installed (MW-1).Bottom of 4” PVC well extends to a depth of between 9.5’ and 10.0’.
(*) Groundwater seepage entering pit at 13.0’ and below. If pit had been left open for longer period of time, groundwater would have risen to a depth of about 13.0’ (+/-).
STD. PROCTOR TEST RESULTS
Composite A: TP-1, 2, 3, & 4
Max. Dry Density
Optimum Moisture
= 000.0 pcf
= 00.0 %
STD. PROCTOR TEST RESULTS
Composite B: TP-1, 2, 3, & 4
Max. Dry Density
Optimum Moisture
= 000.0 pcf
= 00.0 % STD. PROCTOR TEST RESULTS
Composite A: TP-1 - TP -7
Max. Dry Density
Optimum Moisture
= 113.3 pcf
= 15.7 %
STD. PROCTOR TEST RESULTS
Composite B: TP-1, 2, 3, & 4
Max. Dry Density
Optimum Moisture
= 000.0 pcf
= 00.0 %
LAB TESTING RESULTS
Sample: S2-B
Sand Portion
Silt/Clay Portion
Liquid Limit
Plastic Limit
Plasticity Index
Soil Classification
= 2.4 %
= 97.6 %
= 36.5 %
= 25.1 %
= 11.4 %
= ML
“Target” foundation bearing in
“clean” cobbly, sandy GRAVEL
below 3.0’ depth.
Orangish “banding” in gravels at 6.0’ (+/-).Could be a sign of seasonal high groundwater.
General Note: From the top down, this
TP was the most rocky of all four. Upon
backfilling, the surface of this TP was
the most difficult to clean up due to the
quantity and size of the rocks.
Soil profile turned dark
brown and moist below
6.5’ depth, which may be
an indication of seasonal
high groundwater levels.
Other than surfacing materials,
all soils in test pit are native. No
random/foreign fill encountered.
1
2
3
4
5
6
7
8
{0.0’ - 0.17’}: Asphalt (2”)
{0.17’ - 0.5’}: Base Gravel (4”)
Dense; brown; 1.5”-minus base
course GRAVEL (“clean” roadmix
gravel); slightly moist.
{0.5’ - 0.83’}: Silt/Clay Layer (4”)
Very stiff; black to dark brown;
sandy SILT to sandy lean CLAY;
slightly moist.
{0.83’ - 1.17’}: Sub-Base Gravel (4”)
Dense; brown; 3”-minus sub-base
course GRAVEL (“clean” pitrun
gravel); slightly moist.
{1.17’ - 1.33’}: Silt/Clay Layer (2”)
Very stiff; black to dark brown;
sandy SILT to sandy lean CLAY;
slightly moist.
{1.33’ - 1.75’}: Sub-Base Gravel (5”)
Dense; brown; 3”-minus sub-base
course GRAVEL (“clean” pitrun
gravel); slightly moist.
{1.75’ - 3.2’}: Native Silt/Clay
Stiff to very stiff; black to brown;
sandy SILT to sandy lean CLAY;
slightly moist.
{3.2’ - 3.5’}: Native Sandy Gravel
Dense; brown; sandy GRAVEL w/
abundant 6”-minus gravels and
scattered 6” to 10” cobbles; sl. moist.
1
“Target” foundation bearing in
sandy GRAVEL below 7.0’ depth.
Groundwater depth
on 08/12/14 was 5.92’.
No signs or evidence of seasonal high groundwater down to a depth of 3.0’ (+/-).
Moisture break at 1.0’ (+/-).
Very moist/very soft below.
Band of intermixed gravel from 0.5’ to 1.0’. LSE, 3/10/20
Pretty gravelly in lower 1.0’.
Abundant 6”-minus gravels
and scattered 6” to 10” cobbles
Some caving below
groundwater table.
Very stiff; black to brown;silt/clay w/ multiple, inter-bedded, thin, sand seams. Layers of asphalt millings inter-bedded w/ layers of small gravels.
Clean sandy gravel (native)
Silt/clay (native)
B-horizon topsoil (native)
Asphalt (2”)
Base Course (4”)
Sub-Base Course (4”)
Sub-Base Course (5”)
This pit had much moretopsoil than other 6 pits.
Very moist/wet and very soft at 4.5’ (+/-).
Based on saturated soil conditions, high groundwater could rise to a depth of 2.5’ (+/-).
2
POCKET PENETROMETER
MEASUREMENTS (tsf)
@ 1.0’: Qu = 2.50, 2.50, 2.75, 2.75, 3.00
@ 2.0’: Qu = 0.50, 0.50, 1.00, 1.00, 1.00
POCKET PENETROMETER
MEASUREMENTS (tsf)
@ 1.0’: Qu = 2.50, 2.75, 2.75, 2.75, 2.75
@ 2.0’: Qu = >4.50, >4.50, >4.50, >4.50
@ 3.0’: Qu = >4.50, >4.50, >4.50, >4.50
10’ monitoring well installed (MW-1), casing height = 12” (+/-)
3
4
7
6
8
5
5 Loose, gravelly sand
LOCATION NOTE:
TP-B was dug perpendicular to the road
directly off the west edge of the ex. road.
The purpose of the pit was to “knife in”
and observe the pavement section
structure and underlying subgrade soils.
SUB-BASE NOTE:
Interbedded within the 3”-minus sub-base
gravel section were two thin layers (4” & 2”)
of silt/clay. These were located at depths of
0.5’ to 0.83’ and from 1.17’ to 1.33’.
{7.0’ - 10.0’}: Native Sandy Gravel
Dense; brown; sandy GRAVEL w/ abundant
6”-minus gravels and scattered 8” to 10”
cobbles; slightly moist to wet.
Notes:
- “Clean” sandy gravel.
- “Target” bearing material.
DESCRIPTION OF MATERIALS (cont.):
5
6
{0.0’ - 0.2’}: Asphalt (2” Thick)
% WATERCONTENTSAMPLESDEPTH (FT)HORIZONTAL DISTANCE (FT):
JOB NUMBER: 18-024
PROJECT: Manley Road
DATE: May 9, 2018
BACKHOE TYPE: Hitachi Mini-Excavator
BACKHOE OPERATOR: TJ - Townsend Backhoe
LOGGED BY: Lee S. Evans - AESI
SURFACE ELEVATION: 4710.93’
TOTAL DEPTH: 6.0’
GROUNDWATER: Dry
TEST PIT DESIGNATION: TP-C
2 4.0’
8.0’
4.25’
5.0’
2.5’
9.0’
0.7’
4
6
8
10
12
2 4 8 106
4
Nuclear Density Test at 3.5’ Dry Unit Wt. = 73 pcf Moisture Content = 13.3%
Den
Notes:
1. Nuclear Density Testing at 2.5’
Dry Unit Weight = 123 pcf
Moisture Content = 3.6%
ALLIEDENGINEERING
SERVICES, INC.
Civil Engineering
Geotechnical Engineering
Land Surveying
32 Discovery Drive
Bozeman, MT 59718
Phone: (406) 582-0221
Fax: (406) 582-5770
DESCRIPTION OF MATERIALS
4
5
67
LOCATION: Sta. 17+75 (+/-); W. Side of Ex. Road
15.6% 21.1% 20.1% 42.4% 8.4%
7.9%
N/A
8.3%
5.1%
3.4%
15.7%
24.9%
23.0%
21.4%
00.0%
N/A
23.9%
2
S2-E
@ 9.0’
(Sack)
11.1%
S2-C
@ 3.0’
(Sack)
S5-D
@ 3.5’
(Sack)
S2-A
@ 1.5’
(Sack) 13.6%
N/A
Comp. A
@ 1.5’
(Bucket)
3.2%
S2-B
@ 4.0’
(Sack)
N/A
Comp. B
@ 3.0’
to 4.0’
(Bucket)
N/A
Comp. 2
@ 1.5’
to 3.0’
(Bucket)
S5-D
@ 1.0’
to 2.0’
(Bucket)
S2-C
@ 6.0’
(Sack)
S1-C
@ 3.0’
(Sack)
CS-2/5
@ 5.0’
(Bucket)
N/A
N/A
S1-D
@ 1.0’
to 2.0’
(Bucket)
CS-1/2
@ 2.0’
(Bucket)
S1-D
@ 8.0’
(Sack) S2-B
@ 5.3’
to 9.0’
S2-C
@ 9.0’
to 10.5’
S2-D
@ 10.5’
to 14.0’
S2-E
@ 14.0’
to 15.0’
S-1
@ 1’
7
Qu @ 4.0’ - 9.0’ = 0.5 - 1.5 tsf
Percentage and size
of shale fragments
increases w/ depth.
Density of layer
appears to increase
near a depth of 4.0’.
No apparent bedding
of rock fragments.
Depth
of roots
TD = 12.0’
Assumed watertable based on seepage depth.
Due to water pressure
in pit walls, moderate
soil caving began at
depth of 6.0’. Caving
was confined to the
clays only.
Very distinct
North Natural Ground Slope South
4
5 6
Liquid Limit
Plastic Limit
Plasticity Index
121.0 %
= 48.2 %
= 72.8 %
Atterberg Limits for S2-C
Based on the orientation of the boundary
between soil types, it appears that the soils dip
toward the east at grades from 0 to 10 percent.
Based on previous site grading, the test pit area is relatively flat.
Soil consistency
decreases w/
increased depth.
(See Fig. 1 & 2 for Surveyed Location)
Lab Testing Results: S1-C
Gravel Portion
Sand Portion
Silt/Clay Portion
Liquid Limit
Plastic Limit
Plasticity Index
= 67.1%
= 26.5%
= 6.4%
= NP
= NP
= NP
@ 6.0’ (approx.)
Soils were very
moist; darker in
color; and walls
tended to cave.
Qu > 3.5 tsf
General Note: Depth to groundwater was
measured about 0.5 hr after excavation. This
is the “stabilized” groundwater table depth. Reviewed By: __________________ GENERAL NOTES:
- Orange discoloration at 6.0’ may indicate high water
- Sandy gravel below 6.0’ was silty to clayey and moist
- Installed PVC monitoring well (4” diameter, 10’ long)
No Samples CollectedGROUNDWATER MONITORING NOTE:
Test pit explorations were dug before 2015 seasonal
high groundwater date. If time permits, monitoring
should be conducted during spring/summer of 2015
to identify high groundwater depth.
Monitoring well installed (MW-1).Bottom of 4” PVC well extends to a depth of between 9.5’ and 10.0’.
(*) Groundwater seepage entering pit at 13.0’ and below. If pit had been left open for longer period of time, groundwater would have risen to a depth of about 13.0’ (+/-).
STD. PROCTOR TEST RESULTS
Composite A: TP-1, 2, 3, & 4
Max. Dry Density
Optimum Moisture
= 000.0 pcf
= 00.0 %
STD. PROCTOR TEST RESULTS
Composite B: TP-1, 2, 3, & 4
Max. Dry Density
Optimum Moisture
= 000.0 pcf
= 00.0 % STD. PROCTOR TEST RESULTS
Composite A: TP-1 - TP -7
Max. Dry Density
Optimum Moisture
= 113.3 pcf
= 15.7 %
STD. PROCTOR TEST RESULTS
Composite B: TP-1, 2, 3, & 4
Max. Dry Density
Optimum Moisture
= 000.0 pcf
= 00.0 %
LAB TESTING RESULTS
Sample: S2-B
Sand Portion
Silt/Clay Portion
Liquid Limit
Plastic Limit
Plasticity Index
Soil Classification
= 2.4 %
= 97.6 %
= 36.5 %
= 25.1 %
= 11.4 %
= ML
“Target” foundation bearing in
“clean” cobbly, sandy GRAVEL
below 3.0’ depth.
Orangish “banding” in gravels at 6.0’ (+/-).Could be a sign of seasonal high groundwater.
General Note: From the top down, this
TP was the most rocky of all four. Upon
backfilling, the surface of this TP was
the most difficult to clean up due to the
quantity and size of the rocks.
Soil profile turned dark
brown and moist below
6.5’ depth, which may be
an indication of seasonal
high groundwater levels.
Other than surfacing materials,
all soils in test pit are native. No
random/foreign fill encountered.
1
2
3
4
{0.0’ - 0.4’}: Random Fill
Dense; dark brown to brown;
“dirty” sandy GRAVEL w/ some
intermixed silt/clay; slightly moist.
Notes:
- Mostly small gravels.
- Not much for silt/clay.
{0.4’ - 1.0’}: Native Topsoil
Very stiff; black to dark brown;
organic clayey SILT; slightly moist.
Notes:
- More black and organic than TP-1.
{1.0’ - 2.0’}: Native Silt/Clay
Stiff to very stiff; brown; sandy SILT
to sandy lean CLAY w/ some small
gravels in lowermost 6 inches; moist.
Notes:
- Qu = 2.5 - 3.0 tsf.
- Moist, but stiff soil.
- Transition zone to underlying
sandy gravel from 1.5’ to 2.0’.
{2.0’ - 6.0’}: Native Sandy Gravel
Dense; brown; sandy GRAVEL w/
abundant 6”-minus gravels and
scattered 6” to 10” cobbles; slightly
moist.
Notes:
- “Clean” sandy gravel.
1
“Target” foundation bearing in
sandy GRAVEL below 7.0’ depth.
Groundwater depth
on 08/12/14 was 5.92’.
No signs or evidence of seasonal high groundwater down to a depth of 3.0’ (+/-).
Moisture break at 1.0’ (+/-).
Very moist/very soft below.
Band of intermixed gravel from 0.5’ to 1.0’. LSE, 3/10/20
Pretty gravelly in lower 1.0’.
Abundant 6”-minus gravels
and scattered 6” to 10” cobbles
Some caving below
groundwater table.
Very stiff; black to brown;silt/clay w/ multiple, inter-bedded, thin, sand seams. Layers of asphalt millings inter-bedded w/ layers of small gravels.
Clean sandy gravel (native)
Silt/clay (native)
Organic topsoil (native)
Random fill (gravelly)
This pit had much moretopsoil than other 6 pits.
Very moist/wet and very soft at 4.5’ (+/-).
Based on saturated soil conditions, high groundwater could rise to a depth of 2.5’ (+/-).
2
POCKET PENETROMETER
MEASUREMENTS (tsf)
@ 1.0’: Qu = 2.50, 2.50, 2.75, 2.75, 3.00
@ 2.0’: Qu = 0.50, 0.50, 1.00, 1.00, 1.00
POCKET PENETROMETER
MEASUREMENTS (tsf)
@ 1.0’: Qu = 2.50, 2.75, 2.75, 2.75, 2.75
@ 2.0’: Qu = >4.50, >4.50, >4.50, >4.50
@ 3.0’: Qu = >4.50, >4.50, >4.50, >4.50
10’ monitoring well installed (MW-1), casing height = 12” (+/-)
3
4
5 Loose, gravelly sand
LOCATION NOTE:
TP-C was dug well off the
west side of the ex. road.
{7.0’ - 10.0’}: Native Sandy Gravel
Dense; brown; sandy GRAVEL w/ abundant
6”-minus gravels and scattered 8” to 10”
cobbles; slightly moist to wet.
Notes:
- “Clean” sandy gravel.
- “Target” bearing material.
DESCRIPTION OF MATERIALS (cont.):
5
6
{0.0’ - 0.2’}: Asphalt (2” Thick)
LIMITATIONS OF YOUR GEOTECHNICAL REPORT
GEOTECHNICAL REPORTS ARE PROJECT AND CLIENT SPECIFIC
Geotechnical investigations, analyses, and recommendations are project and client specific. Each project
and each client have individual criterion for risk, purpose, and cost of evaluation that are considered in the
development of scope of geotechnical investigations, analyses and recommendations. For example, slight
changes to building types or use may alter the applicability of a particular foundation type, as can a
particular client’s aversion or acceptance of risk. Also, additional risk is often created by scope-of-
service limitations imposed by the client and a report prepared for a particular client (say a construction
contractor) may not be applicable or adequate for another client (say an architect, owner, or developer for
example), and vice-versa. No one should apply a geotechnical report for any purpose other than that
originally contemplated without first conferring with the consulting geotechnical engineer. Geotechnical
reports should be made available to contractors and professionals for information on factual data only and
not as a warranty of subsurface conditions, such as those interpreted in the exploration logs and discussed
in the report.
GEOTECHNICAL CONDITIONS CAN CHANGE
Geotechnical conditions may be affected as a result of natural processes or human activity. Geotechnical
reports are based on conditions that existed at the time of subsurface exploration. Construction operations
such as cuts, fills, or drains in the vicinity of the site and natural events such as floods, earthquakes, or
groundwater fluctuations may affect subsurface conditions and, thus, the continuing adequacy of a
geotechnical report.
GEOTECHNICAL ENGINEERING IS NOT AN EXACT SCIENCE
The site exploration and sampling process interprets subsurface conditions using drill action, soil
sampling, resistance to excavation, and other subjective observations at discrete points on the surface and
in the subsurface. The data is then interpreted by the engineer, who applies professional judgment to
render an opinion about over-all subsurface conditions. Actual conditions in areas not sampled or
observed may differ from those predicted in your report. Retaining your consultant to advise you during
the design process, review plans and specifications, and then to observe subsurface construction
operations can minimize the risks associated with the uncertainties associated with such interpretations.
The conclusions described in your geotechnical report are preliminary because they must be based on the
assumption that conditions revealed through selective exploration and sampling are indicative of actual
Allied Engineering Services, Inc. Page 2
conditions throughout a site. A more complete view of subsurface conditions is often revealed during
earthwork; therefore, you should retain your consultant to observe earthwork to confirm conditions and/or
to provide revised recommendations if necessary. Allied Engineering cannot assume responsibility or
liability for the adequacy of the report’s recommendations if another party is retained to observe
construction.
EXPLORATIONS LOGS SHOULD NOT BE SEPARATED FROM THE REPORT Final explorations logs developed by the consultant are based upon interpretation of field logs (assembled
by site personnel), field test results, and laboratory and/or office evaluation of field samples and data.
Only final exploration logs and data are customarily included in geotechnical reports. These final logs
should not be redrawn for inclusion in Architectural or other design drawings, because drafters may
commit errors or omissions in the transfer process.
To reduce the likelihood of exploration log misinterpretation, contractors should be given ready access to
the complete geotechnical report and should be advised of its limitations and purpose. While a contractor
may gain important knowledge from a report prepared for another party, the contractor should discuss the
report with Allied Engineering and perform the additional or alternative work believed necessary to
obtain the data specifically appropriate for construction cost estimating purposes.
OWNERSHIP OF RISK AND STANDARD OF CARE
Because geotechnical engineering is much less exact than other design disciplines, there is more risk
associated with geotechnical parameters than with most other design issues. Given the hidden and
variable character of natural soils and geologic hazards, this risk is impossible to eliminate with any
amount of study and exploration. Appropriate geotechnical exploration, analysis, and recommendations
can identify and lesson these risks. However, assuming an appropriate geotechnical evaluation, the
remaining risk of unknown soil conditions and other geo-hazards typically belongs to the owner of a
project unless specifically transferred to another party such as a contractor, insurance company, or
engineer. The geotechnical engineer’s duty is to provide professional services in accordance with their
stated scope and consistent with the standard of practice at the present time and in the subject geographic
area. It is not to provide insurance against geo-hazards or unanticipated soil conditions.
The conclusions and recommendations expressed in this report are opinions based our professional
judgment and the project parameters as relayed by the client. The conclusions and recommendations
assume that site conditions are not substantially different than those exposed by the explorations. If
during construction, subsurface conditions different from those encountered in the explorations are
observed or appear to be present, Allied Engineering should be advised at once such that we may review
those conditions and reconsider our recommendations where necessary.
RETENTION OF SOIL SAMPLES
Allied Engineering will typically retain soil samples for one month after issuing the geotechnical report.
If you would like to hold the samples for a longer period of time, you should make specific arrangements
to have the samples held longer or arrange to take charge of the samples yourself.