COMMISSION RESOLUTION NO. 3376
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN,
MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT
WITH CONCRETE SPECIAL TIES OF
MONTANA, INC., BOZEMAN,
MONTANA.
WHEREAS, the City Commission did, on the 1 st day of May 2000, authorize award
of the bid for construction of Langohr Park sidewalks, under Project No. STPE 1299(9), to
Concrete Specialties of Montana, Inc., Bozeman, Montana; and
WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such
alterations or modifications of the specifications and/or plans of the contract be made by
resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make
alterations or modifications to the specifications and/or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of
Bozeman, Montana, that the proposed modifications and/or alterations to the contract
between the City of Bozeman, a municipal corporation, and Concrete Specialties of Montana,
Inc., as contained in Change Order No.1, attached hereto, be and the same are hereby
approved; and the City Manager is hereby authorized and directed to execute the contract
change orders for and on behalf of the City; and the Clerk of the Commission is authorized
and directed to attest such signature.
PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana,
at a regular session thereof held on the 17th day of July 2000.
MA~~~Yor
ATTEST:
~JJp~
ROBIN L. SULLIVAN
Clerk of the Commission
APPROVED AS TO FORM:
,gdi: ~
City kitorney
. . --.---.....
-.-.-..----
CHANGE ORDER
No. 1
DATE OF ISSUANCE 6/28/00 EFFECTIVE DATE 6/28/00
OWNER Ci ty of Bozeman
CONTRACTOR r.()nrrptp Sppc:i alti es of Montana. Inc.
Conttact Langohr Park Sidewalks
Project: S TP E 1299 (9 )
OWNER's Contract No. ENGINEER's Contract No.
ENGfNEER r.ity ~nginppr
You are directed to make the following changes in the Conttact Documents:
Description: . C S d C t. St t d. t t
Install sldewalks on ypress treet an ur lSS ree a Jacen 0
Lindley Park.
Reason for Change Order:
Owner's need for additional sidewalks
Attachments: (List documents supporting change)
Work Directive No.1
Estimated Quantities and Price for Change Order No. 1
I CHANGE IN CONTRACT PRICE: I I CHANGE IN CONTRACT TIMES: I
Original Contract Price Original Contract Times:
Substantial Completion: 30
$ 58.801 . fj 8 Ready for final payment:
da s or dates)
Net Increase (Decrease) ITom previous Change Orders Net change from previous Change Orders No. _ to
No. to No. :
-0 00 Substantial Completion: 0
$ . Ready for final payment:
(da s)
Contract Price prior to this Change Order: Contract Times prior to this Change orger
Substantial Completion:
$ 58,801.68 Ready for final payment:
(days or dates)
Net increase-(aecreas~) ofthis Change Order: Net increase (-decr~e)-this Change Order:
Substantial Completion: 15
$ 25.000.00 Ready for final payment:
(days)
Contract Price with all approved Change Orders: Contract Times with all approved Chan,.ge Orders:
Substantial Completion: 4~
$ 83.801.68 Ready for final payment:
(da s or dates)
RE~~ APPROVED, _--
By: /v-- BY:--'~---
GINEER (A~thorized Signature) OWNER (Authorized Signature)
Date: ~ht;;;() Date: 07-17-00
EJCDC 191O-8-B (1996 Edition)
Prepared by the Engir\tt1'! Joint Contract Documents Committee 0U>d endorsed by The Associated Gene",1 COntJ3cto~ of America a.'1d the C""'tnI<;tio[\ Spc<;ifi~on$
InstilUte.
- .. --.----....----
.....-...-.........-..
.
WORK CH...c\NGE DIRECTIVE 1
No.
DATE OF ISSUANCE 6/26/00 EFFECTIVE DATE 6/26/00
OWNER City of Bozeman
CONTRACTOR Concrete Speci a 1 ti es of Montana, Inc.
Contract: Langohr Park Sidewalks
Project: SIPE 1299(9)
OWNER's Contract No. ENGINEER's Project No.
You are directed to proceed promptly with the foUowing change(s):
Description: Install sidewalks on Cyoress Street and Curtiss Street adjacent
to Lindley Park as shown on attached plan sheets 1 of 2 and 2 of 2.
Purposc of Work Change Directive:
Owner's need for additional sidewalks
Attachments: (List documents supporting change)
Plan Sheets 1 of 2 and 2 of 2, "Lindley Park Sidewalks"
If OWNER or CONTRACTOR believe that the above change has affected Contract Price any Claim for a
Change Order based thereon will involve one or more of the foHowing methods as defined in the
Contract Documents.
Method of determining change in
Contract Price:
~ Unit Prices
[X1 Lump Sum (for additional excavation)
o Cost of the Work
Estimated increase (decrea~-in Contr;lct Price: Estimated increase ~~~u.)-in Contract
S 25; 000.00 Times:
If the change involves an increase, the estimated Substantial Completion:
15 days;
amount is not to be exceeded without further Ready for final payment:
days.
authorization.
RECOMMENDED: AUTHORlZED:
City Engireering DeDt.
By:' ~%/~ By:
EJCDC No. 191o--8-F (1'996 Edition)