RESOLUTION 5474
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN,
MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT WITH
DICK ANDERSON CONSTRUCTION, INC., BOZEMAN, MONTANA
WHEREAS, the City Commission did, on the March 23, 2021, authorize award of the bid
for the WRF Solids Dewatering Building Expansion and Headworks Improvement Project to Dick
Anderson Construction, Inc., Bozeman, Montana; and
WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such
alterations or modifications of the specifications and/or plans of the contract be made by
resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make alterations or
modifications to the specifications and/or plans of the contract to reflect the project scope and price
at final completion.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of
Bozeman, Montana,that the proposed modifications and/or alterations to the contract between the
City of Bozeman, a municipal corporation, and Dick Anderson Construction, Inc., as contained in
Change Order No. 2, attached hereto,be and the same are hereby approved; and the City Manager
is hereby authorized and directed to execute the contract change order for and on behalf of the
City; and the City Clerk is authorized and directed to attest such signature.
PASSED, ADOPTED, AND APPROVED by the City Commission of the City of
Bozeman, Montana, at a regular session thereof held on the 71h day of February, 2023.
DocuSigned by:
RFSA0.(:7f:'IRR-R
CYNTHIA L. ANDRUS
Mayor
DocuSign Envelope ID: B573184A-3D66-4152-97AA-92F87D9818B6
ATTEST: DocuSigned by:
s
DocuSigned by:
�l.t�Ct, M.aaS
F41 F922095AB475...
MIKE MAAS
City Clerk
APPROVED AS TO FORM:
DocuSigned by:
1/�wVji i
G -C9 `,tTVAN
City Attorney
DocuSign Envelope ID:B573184A-3D66-4152-97AA-92F87D9818B6
ENGINEERS JOINT CONTRACT
D OCIMENTS COMMITTEE
Change Order No. 02
Date of Issuance: Effective Date: 12/16/2022
Owner: City of Bozeman Owner's Contract No.:
Contractor: Dick Anderson Construction Contractor's Project No.:
Engineer: HDR Engineering Engineer's Project No.: 10176456
Project: WRF Solids Handling and Headworks Improvements
Project
The Contract is modified as follows upon execution of this Change Order:
Description: This Change Order accounts for the funds left over from the project.A breakdown of the remaining funds by
schedule and line item is shown in the attached Table.
Attachments: Table of Excess and Unused project Funds
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIMES
Original Contract Price: Original Contract Times: 240 days
Substantial Completion: 240 days
$2,296,033.00 Ready for Final Payment:
days or dates
Increase from previously approved Change Orders No. 1: Increase from previously approved Change Orders:
Substantial Completion: 0
$274,114.00 Ready for Final Payment: 0
0 days or dates
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial Completion: 240 days
$2,570,147.00 Ready for Final Payment:
days or dates
Decrease of this Change Order: Increase of this Change Order:
Substantial Completion: 37 days
$26,655.00 Ready for Final Payment:
days or dates
Contract Price incorporating this Change Order: Contract Times with all approved Change Orders:
Substantial Completion: 277 days
$2,543,492.00 Ready for Final Payment:
DocuSigned by:days or dates
RECOMMENDED: ACCEPTED: 1302tj
9 ACCEPTED:
DocuSigned by:
DocuSigned by: •�'
hh- �
By: `T By: ff �Ltu�11 By. Fav'bin, fj�Vw,
251607FDSA824A6._
Engineer(if required) Owner(Authorized Signature) Contractor(Authorized Signature)
Project Manager City Manager Project Manager
Title: 1 g Title: Title:
Date: 1/16/2023 Date February 7, 2023 Date: 1 19 2023
EJCDC®C-941,Change Order.
Prepared and published 2013 by the Engineers Joint Contract Documents Committee.
Page 1 of 2
DocuSign Envelope ID:B573184A-3D66-4152-97AA-92F87D9818B6
EJUDURt
ENGINEERS JOINT CONTRACT
DOCUMENTS COMMITTEE
Table of Excess and Unused project Funds
Contingency Funded by Contract $ 50,000.00
CPR 01 -CAT6 CABLE & CONDUIT $ 9,840.15
CPR 02 - FRESH WATER SUPPLY TO NEW SCREW PRESS $ 9,109.22
CPR 03— NOT USED -
CPR 04- EXISTING CONVEYOR REPAIR $ 2,664.38
CPR 05 - DRAIN LINE MODIFICATIONS $ 3,654.13
CPR 06 - ROOF CRICKET HEAT TAPE $ 3,472.25
CPR 07 - POWER & CONTROLS FOR OH DOOR(S) $ 4,604.87
CPR 08 - FAD CREDIT FOR PVC ($10,000.00)
Subtotal $ 23,345.00
Contingency Leftover $ 26,655.00
EJCDC'C-941,Change Order.