HomeMy WebLinkAbout24191 Staff Report MSP FINAL Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 1 of 26
Application No. 24191 Type Master Site Plan
Project Name 7th & Aspen Master Site Plan
Summary A proposed Master Site Plan for a mixed-use development of commercial and residential
uses on three parcels in the North Seventh Addition to Bozeman Subdivision, located in the
Southeast corner of N 7th Avenue and W Aspen Street. Phases 1 and 2 will occupy the
southern two parcels of the development and will each contain a 4-story apartment building
providing affordable housing units. Phase 1, located on the center parcel, will include 46
affordable rental units and Phase 2, located on the southern parcel, will include 50 affordable
rental units. Phase 3 will be located on the northern parcel and is proposed to include a 7-
story mixed-use building with approximately 75 market rate units and 15,000 square feet of
commercial space. The applicant indicated they are currently exploring the feasibility of a
parking lot on Phase 3 in the interim, although no plan has been formally submitted. Each
phase will include associated open space, parking, landscaping, and site improvements. The
project proposes to utilize the deep incentives within BMC 38.380 Affordable Housing as the
affordable units will consist of approximately 56% of the total dwelling units within the entire
development. The applicant is also requesting departures from four code sections, all of
which are available pursuant to BMC 38.320.070 Departures for Housing Creation: the
minimum required building placement per the Landscaped block frontage standards in BMC
38.510.030.C; the light and air setback adjacent to the northern property line between
Phases 1 and 3 per BMC 38.520.030.C; the required screening of ground related service
areas per BMC 38.520.070.B.3; and a reduction in usable open space by 20%. The purpose
of the master site plan is to coordinate phasing and construction management with required
on and off-site improvements, general building and site design, and review required
easements, open space, parking, and parkland. The Phase 1 and 2 Site Plan is being
reviewed under a separate project, #24192, with a separate staff report and decision.
Zoning B-2M Growth Policy Community Commercial
Mixed Use
Parcel Size 1.838 acres (80,063 sqft)
Overlay District(s) None
Street Address 706 N 7th Avenue; North of W Peach Street, South of W Aspen Street, West of N 5th Avenue, and East
of N 7th Avenue.
Legal Description Lots 1-3, Block 1 of North 7th Addition Subdivision and Lots 4A & 6A of North 7th Addition
Subdivision, Plat E-21-D, in Section 1, Township 2 South, Range 5 East, located in P.M.M., City
of Bozeman, Gallatin County, Montana
Owner Midtown Aspen LLC, 233 E Main Street, Suite 404, Bozeman, MT 59715
Applicant Aspekt Architecture LLC, 214 E Mendenhall 201, Bozeman, MT 59715
Representative Same as Applicant
Staff Planner Bailey Minnich Engineer Suzanne Ryan
Noticing Public Comment Period Site Posted Adjacent Owners Mailed
Mailed
Newspaper Legal Ad
8/23/2024 – 9/17/2024
10/7/2024 – 10/29/2024
8/23/2024
10/7/2024
8/23/2024
10/7/2024
N/A
Advisory Boards Board Date Recommendation
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 2 of 26
Development Review
Committee
8/21/2024 The application is adequate, conforms to standards,
and is sufficient for approval with conditions and
code provisions
Recommendation The application is adequate, conforms to standards, and is sufficient for approval with conditions and
code provisions as noted below.
Decision Authority Director of Community Development Date: 10/30/24
Full application and file of record: Community Development Department, 20 E. Olive St., Bozeman, MT 59715
Digital application access located online in the City’s Laserfiche Repository for Application 24191
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 3 of 26
FINDINGS OF FACT AND APPEAL PROVISIONS CERTIFICATE
A) PURSUANT to Chapter 38, Article 2, Bozeman Municipal Code (BMC), and other applicable sections of Ch.38, BMC, public
notice was given, opportunity to submit comment was provided to affected parties, and a review of the Site Plan described in
this report was conducted. The applicant proposed to the City a Master Site Plan (MSP) to permit a mixed-use development of
commercial and residential uses on three parcels in the North Seventh Addition to Bozeman Subdivision and associated site
improvements. Phases 1 and 2 will occupy the southern two parcels of the development and will each contain a 4-story
apartment building providing affordable housing units. Phase 1, located on the center parcel, will include 46 affordable rental
units and Phase 2, located on the southern parcel, will include 50 affordable rental units. Phase 3 will be located on the
northern parcel and is proposed to include a 7-story mixed-use building with approximately 75 market rate units and 15,000
square feet of commercial space. Each phase will include associated open space, parking, landscaping, and site
improvements. The project proposes to utilize the deep incentives within BMC 38.380 Affordable Housing as the affordable
units will consist of approximately 56% of the total dwelling units within the entire development. The applicant is also requesting
departures from four code sections: the minimum required building placement per the Landscaped block frontage standards in
BMC 38.510.030.C; the light and air setback adjacent to the northern property line between Phases 1 and 3 per BMC
38.520.030.C; the required screening of ground related service areas per BMC 38.520.070.B.3; and a reduction in usable open
space by 20% per BMC 38.320.070 Departures for housing creation. The purposes of the Master Site Plan review were to
consider all relevant evidence relating to public health, safety, welfare, and the other purposes of Ch. 38, BMC; to evaluate the
proposal against the criteria of Sec. 38.230.100 BMC, and the standards of Ch. 38, BMC; and to determine whether the
application should be approved, conditionally approved, or denied.
B) It appeared to the Director that all parties and the public wishing to examine the proposed Master Site Plan and offer
comment were provided the opportunity to do so. After receiving the recommendation of the relevant advisory bodies
established by Ch. 38, Art. 210, BMC, and considering all matters of record presented with the application and during the public
comment period defined by Ch. 38, BMC, the Director finds that the proposed Master Site Plan complies with the requirements
of the BMC if certain conditions are imposed. Therefore, being fully advised of all information comprising the record of review
regarding this application, the Director makes the following decision.
C) The Master Site Plan meets the criteria of Ch. 38, BMC, and is therefore approved, subject to the conditions listed in this
report and the correction of any elements not in conformance with the standards of the Title, as noted in the Code Provisions
section of this document. The evidence contained in the submittal materials, advisory body review, public comment, and this
report, justifies the conditions imposed on this development to ensure that the Site Plan complies with all applicable regulations,
and all applicable criteria of Ch. 38, BMC. On this __14th____ day of ____November____, 2024, Erin George, Interim Director
of Community Development, or her designee, approved with conditions this Master Site Plan for and on behalf of the City of
Bozeman as authorized by Sec. 38.200.010, BMC.
D) This Director of Community Development’s project decision may be appealed by filing a documented appeal with and paying
an appeal fee to the Department of Community Development for the City of Bozeman within 10 working days after the date of
the final decision as evidenced by the Director’s signature, following the procedures of Sec. 38.250.030, BMC.
DIRECTOR OF COMMUNITY DEVELOPMENT OR HER DESIGNEE
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 4 of 26
CONDITIONS OF APPROVAL
1. The applicant is advised that unmet code provisions, or code provisions that are not specifically listed as conditions
of approval, does not, in any way, create a waiver or other relaxation of the lawful requirements of the Bozeman
Municipal Code or state law.
2. The Phase 3 potential parking lot is not approved with the Master Site Plan. The applicant must obtain a Special
Temporary Use Permit (STUP) prior to construction of any parking lot on the northern Phase 3 parcel.
3. The applicant must provide and file with the Gallatin County Clerk and Recorder's office executed Waivers of Right
to Protest Creation of Special Improvement Districts (SIDs) on City standard form for the following:
a. Street improvements to W Peach St between N 11th Ave and N Grand Ave including lighting, signalization,
paving, curb/gutter, sidewalk, and storm drainage.
b. Street improvements to W Tamarack St between N 7th Ave and N Grand Ave including lighting, signalization,
paving, curb/gutter, sidewalk, and storm drainage.
4. The applicant must install a rectangular rapid-flashing beacon pedestrian crossing at the intersection of North 7th
and Aspen Street prior to occupancy. The crossing must be approved by the Montana Department of Transportation
(MDT) through their Systems Impact Action Process. If the MDT does not approve the pedestrian crossing, the
applicant must provide documentation from the MDT as to why the crossing cannot be installed at North 7th and
Aspen.
5. Prior to occupancy, the applicant must work with the Water and Sewer Department to install a sanitary sewer leak
detection system for the portion of sewer in the tunnel under the Northgate Shopping Center.
CODE PROVISIONS
1. BMC 38.270.030.C-D – Exception for concurrent construction. In certain circumstances, the issuance of a building
permit may be allowed prior to completion of the public infrastructure, provided that the criteria listed in this section
are met. The City must approve concurrent construction prior to building permit approval of any phase. Approval
requires a concurrent construction request plan approval, an irrevocable offer of dedication, infrastructure review
and approval, submittal of original executed easements to facility infrastructure, and fire review and approval.
2. BMC 38.380.040.E. Affordable housing plan required. The applicant and owner, if different, must consent to the City
recording the affordable housing plan immediately following conditional approval of the 7th and Aspen Master Site
Plan and Site Plan.
3. BMC 38.380.060.D. Qualification of renters and buyers. The applicant and owner, if different, must record and
provide to the City of Bozeman a Notice of Restrictions for the Affordable Housing Plan and a Declaration of
Restrictive Covenants that implements the affordable housing plan immediately following conditional approval of the
7th and Aspen Master Site Plan and Site Plan. The Affordable Housing plan and the restrictive covenant must be
recorded prior to issuance of a building permit for the 7th and Aspen Master Site Plan or Phase 1 and 2 Site Plan,
application number 24192.
4. BMC 38.410.130. Water Adequacy: Cash-in-lieu of water rights (CILWR) must be paid prior to final plan approval for
each phase.
5. BMC 38.420.030. Cash donation in-lieu of land dedication. The finalized cash donation in-lieu of land dedication
must be paid prior to final site plan approval for each phase.
6. BMC 38.410.060 B 2a. Front setback utility easements. Front setback utility easements must be ten feet wide and
must always be provided unless written confirmation is submitted to the community development department from
all utility companies providing service indicating that front setback easements are not needed.
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 5 of 26
7. BMC 38.520.030.C. Light and air access and privacy alongside and rear property lines. A 20-feet wide No Build
Zone easement shall be recorded on the northern Phase 3 parcel prior to final site plan approval for Phase 1 to
accommodate the required light and air setback.
8. BMC 38.520.070.D Utility meters, electrical conduit, and other service utility apparatus. An easement for the
electrical transformer location must be recorded on the phase 3 property prior to final site plan approval for Phases
1 & 2.
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 6 of 26
Figure 1: Current Zoning Map
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 7 of 26
Figure 2: Phasing Plan
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 8 of 26
Figure 3: Master Site Plan
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 9 of 26
Figure 4: Landscaping Plan Phases 1 & 2
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 10 of 26
Figure 5: Elevations Phase 1
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 11 of 26
Figure 6: Elevations Phase 2
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 12 of 26
ANALYSIS AND FINDINGS
Analysis and resulting recommendations based on the entirety of the application materials, municipal codes, standards,
plans, public comment, and all other materials available during the review period. Collectively this information is the record
of the review. The analysis in this report is a summary of the completed review.
Plan Review, Section 38.230.100, BMC
In considering applications for plan approval under this title, the Director of Community Development shall consider the
following:
1. Conformance with Article 1 - Consistency with the City’s adopted Growth
Policy 38.100.040.D
Meets Code?
Growth Policy
Land Use
Community Commercial Mixed Use Yes
Zoning B-2M, Community Business District-Mixed Yes
Comments: The Bozeman Community Plan 2020, on page 73, discusses how zoning regulations are made
in accordance with a growth policy. “The City must balance many issues in approving urban development.
Therefore, it is not unusual if there is some tension between competing priorities, even if there is no explicit
contradiction in policy.” The adopted regulations in Chapter 38, the Uniform Development Code (UDC), are
the result of the Commission considering and balancing a wide range of issues and the regulations provide
an overall compliance basis of evaluation of the specific development application to the aims and aspirations
of the growth policy. This balancing in crafting regulations means that individual goals or objectives are not
maximized to the exclusion of other priorities and evaluation occurs against the whole of the growth policy.
Applications consistent with the adopted regulations are in accordance with the overall growth policy.
B-2M is an implementing district of the 2020 Community Plan designation of Community Commercial Mixed
Use and is supported by the following goals:
- Goal R-2.4: Social Equity: Provide solutions that are inclusive with consideration to populations that
are most fragile and vulnerable to sudden impacts. Staff Comment: The project proposes 56% of
the total residential units within all 3 phases as affordable housing, with rent proposed under a
mixture of area median income levels. Phase 1 will include 46 units ranging between 50% and 60%
of area median income and Phase 2 will include 50 units with a maximum of 80% area median
income. By including a range of rental percentages, these 96 affordable housing units will provide
greater inclusion for a more diverse range of income levels and housing populations.
- Goal N-1: Support well-planned, walkable neighborhoods. Staff Comment: This project is within
walking distance of the commercial downtown and amenities. The subject property is located
approximately ½ mile from the intersection of N 7th Avenue and Main Street, and less than 1 mile
from the downtown center. Additionally, the site is located within 300-feet of Westlake Park and is
adjacent to N 7th Avenue which is classified as a Principal Arterial supporting public transit and city
sidewalks.
- Goal N-1.1: Promote housing diversity, including missing middle housing. Staff Comment: This
project proposes a total of 171 residential dwelling units over 3 phases of development. The
proposed multi-family building within Phase 1 will contain 46 affordable housing units and the
proposed multi-family building within Phase 2 will contain 50 affordable housing units. The future
Phase 3 building is proposed to include 75 market-rate dwelling units. The number of proposed
units and buildings will provide diversity in the housing types available with the City of Bozeman. As
mentioned previously, the proposed affordable housing units will range between 50%-80% area
median income, specifically targeting the missing middle housing levels.
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 13 of 26
- Goal N-1.11: Enable a gradual and predictable increase in density in developed areas over time.
Staff Comment: The N 7th/Midtown Urban Renewal District was created in 2006 under ordinance
#1685 to remedy blighted areas within the district through rehabilitation and redevelopment. Since
the creation of this urban renewal district, there has been a significant amount of redevelopment
along N 7th Avenue and within the B-2M zoning district including commercial and mixed-use
buildings. The location of the proposed site directly off N 7th Avenue creates a predictable increase
in density by establishing a transition between full commercial uses and standard single family
residential properties.
- Goal N-3.3: Encourage distribution of affordable housing units throughout the City with priority given
to locations near commercial, recreational, and transit assets. Staff Comment: This project is
providing 56% of the residential units as affordable housing within walking distance to the downtown
commercial corridor. Additionally, the site is located directly adjacent to N 7th Street which includes
sidewalks, bus routes and the potential for a future shared use bike path through the City’s Parks,
Recreation and Active Transportation (PRAT) plan.
- Goal N-3.7: Support compact neighborhoods, small lot sizes, and small floor plans, especially
through mechanisms such as density bonuses. Staff Comment: This project proposes to utilize the
deep incentives available through the affordable housing standards in BMC 38.380 to allow for taller
buildings and exemption from the maximum façade widths. By utilizing these deep incentives, the
proposed buildings are able to provide a higher density within the infill site supporting a more
compact neighborhood in close proximity to city services.
- Goal DCD-1: Support urban development within the City. Staff Comment: This project is a
redevelopment of three infill lots providing higher density residential units within close proximity to
commercial uses. The proposed site is located adjacent to N 7th Avenue which is designated as a
Principal Arterial street classification and anticipated for the higher level of density and city services.
- Goal DCD-1.1: Evaluate alternatives for more intensive development in proximity to high visibility
corners, services, and parks. Staff Comment: This project is located approximately 300-feet north
of the intersection of W Peach Street/Durston Road and N 7th Avenue, which is classified as a high
visibility corner. Additionally, the site is within approximately 300-feet of Westlake Park, and as
previously mentioned directly adjacent to N 7th Avenue. Due to the site’s proximity to these city
services, it provides a higher level of potential for more intense redevelopment.
- Goal DCD-2.2: Support higher density development along main corridors and at high visibility street
corners to accommodate population growth and support businesses. Staff Comment: This project
is proposed on three infill lots that have direct access onto N 7th Street. This street is a major
corridor through the City of Bozeman and supports higher density development.
- Goal DCD-2.7: Encourage the location of higher density housing and public transit routes in
proximity to one another. Staff Comment: This project is a mixed-use development with higher
density housing adjacent to an existing public transportation route along N 7th Avenue. Streamline
bus service has an existing Blueline route stop located at the intersection of N 7th Avenue and W
Peach Street, approximately 275-feet south of the subject property.
- Goal DCD-2.9: Evaluate increasing the number of stories allowed in centers of employment and
activity while also directing height transitions down to adjacent neighborhoods. Staff Comment: In
2022, the City Commission adopted the affordable housing ordinance #2105 which created the
deep incentives available to residential and mixed-use developments proposing specific levels of
affordable housing units. One of the available deep incentives is the increase in number of stories
or overall building height on a potential structure. This project proposes to increase the height on
the buildings within Phases 1 and 2 to a maximum of 4 stories, and within Phase 3 to a maximum of
7 stories. As this project site is located along N 7th Avenue and within the Midtown Urban Renewal
District, it is a reasonable location for the use of this incentive while creating a transition area to
adjacent lower density neighborhoods.
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 14 of 26
- Goal M-1.12: Eliminate parking minimum requirements in commercial districts and affordable
housing areas and reduce parking minimums elsewhere. Staff Comment: Through the affordable
housing incentives, an applicant could request a reduction in minimum parking standards, however
this is not a request for this particular project. As this project is located within the Midtown Urban
Renewal District, the requirement for on-site parking is already eliminated. In conjunction with the
connected site plan for Phases 1 and 2, the applicant is voluntarily providing 22 on-site parking
spaces, which is dramatically less than what would normally be required for the proposed number of
dwelling units.
Growth Policy – Community Commercial Mixed Use: “The Community Commercial Mixed Use category
promotes commercial areas necessary for economic health and vibrancy. This includes professional and
personal services, retail, education, health services, offices, public administration, and tourism
establishments. Density is expected to be higher than it is currently in most commercial areas in Bozeman
and should include multi-story buildings. Residences on upper floors, in appropriate circumstances, are
encouraged. The urban character expected in this designation includes urban streetscapes, plazas, outdoor
seating, public art, and hardscaped open space and park amenities. High density residential areas are
expected in close proximity.”
“Developments in this land use area should be located on one or two quadrants of intersections of the
arterial and/or collector streets and integrated with transit and non-automotive routes. Due to past
development patterns, there are also areas along major streets where this category is organized as a
corridor rather than a center. Although a broad range of uses may be appropriate in both types of locations,
the size and scale is to be smaller within the local service areas. Building and site designs made to support
easy reuse of the building and site over time is important. Mixed use areas should be developed in an
integrated, pedestrian friendly manner and should not be overly dominated by any single use. Higher
intensity uses are encouraged in the core of the area or adjacent to significant streets and intersections.
Building height or other methods of transition may be required for compatibility with adjacent development.”
The proposed project also complies with other supporting City plans such as the Affordable Housing Plan
and the Bozeman Climate Plan 2020, which have been expressly incorporated into the Bozeman Community
Plan 2020 in order to cohesively plan for the community’s overall values. The project supports the Bozeman
Climate Plan 2020 through the following goals:
- Solution G. Facilitate Compact Development Patterns: Proactively plan existing and future land
uses to reduce the distance people need to travel for work and to access shopping and services.
Staff Comment: The overall goal of the Bozeman Climate Plan 2020 is to uphold the Paris Climate
Agreement and therefore the City of Bozeman has set goals of reducing the green house gas
emissions 26% by 2025 and to be carbon neutral by 2050. As outlined in the Climate Plan, nearly
70% of Bozeman commuters drive to work and approximately 38% of total emissions came from the
transportation sector. In 2018 alone, Bozeman residents, tourists, commuters, and commercial
vehicles drove over 315 million miles within city limits. (Bozeman Climate Plan 2020, page 22).
This project is proposing 96 affordable housing units available to citizens making less than 80%
area median income and will be located within 1 mile of downtown Bozeman. Additionally, this
location is accessible through public transit, existing sidewalks, and is adjacent to the location of
future shared use paths identified in the PRAT plan. Based on these facts, this project is in an ideal
location to support this goal by reducing the distance residents must travel to reach specific City
amenities.
- Solution J. Increase Walking, Bicycling, Carpooling and Use of Transit. Shift travel modes away
from single-occupancy vehicles and grow the percentage of community members walking, bicycling,
carpooling, avoiding or consolidating vehicle trips, and using transit. Staff Comment: As described
in the Climate Plan, removing barrier to active modes of transportation can enable community
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 15 of 26
members to engage in other types of travel and can expand the mobility and accessibility for
portions of the population that cannot drive due to age, physical abilities, or income. By placing
affordable housing options near facilities such as transit and bike paths, the percentage of the
community members utilizing other forms of travel increases considerably. This project is located
within ½ mile of Main Street, and less than 1 mile of downtown Bozeman. Additionally, as
previously mentioned, this project is located along the Streamline Blueline bus route and a stop is
located less than 300-feet south of the site.
- Action 4.J.7. Leverage Parking Policies to Encourage Other Modes of Transportation. Staff
Comment: The availability and use of parking spaces influences the choices made by the
population on their overall mode of travel. This action described in the Climate Plan reinforces
coordination between other transportation studies and plans to ensure the community’s parking
policies are strengthened and support transit, bicycle, and pedestrian infrastructure. It is directly
correlated to Goal M-1.12 of the Growth Policy which encourages the elimination of parking
minimum requirements in commercial districts and affordable housing areas. As previously
described, this project is located within the Midtown Urban Renewal District and the requirement for
on-site parking is already eliminated.
As an initial part of the 2020 Affordable Housing Plan, the 2019 Bozeman Community Housing Needs
Assessment study showed between 5,400 and 6,340 housing units were needed within 5-years to address
the current housing shortfall for residents and the workforce. The 2020 Affordable Housing Plan went further
stating 5,800 housing units are needed by 2025, ranging between 30% area median income and 180% area
median income. For reference, the ‘missing middle’ housing is classified as between 80% area median
income and 120% area median income. This project supports the 2020 Affordable Housing Plan through the
following strategies:
- Action Strategy – Tax Increment Financing (TIF): Use TIF to incentivize long-term affordable
housing within the districts including incentivizing ADUs and 1-bedroom units in the Downtown BID
and incentivizing tax-credit qualifying projects. Staff Comment: As previously identified, this project
is located within the Midtown Urban Renewal District. In May 2024, the Bozeman City Commission
approved this project as an urban renewal project allowing for the use of TIF funds to help
incentivize the construction of this project.
- On-going Strategy – Flexible Development Standards: Create predictable list of incentives that are
by-right (approved by staff) in exchange for providing community housing benefit. Staff Comment:
Since the adoption of the Affordable Housing Plan 2020, the City Commission adopted the
affordable housing ordinance #2105 in 2022 which created the deep incentives available to
residential and mixed-use developments proposing specific levels of affordable housing units. This
project proposes to utilize the increase in overall building height and the exemptions from residential
block frontage standards, maximum façade width standards, and roofline modulation.
Staff Comment: As described through the above goals and strategies, the proposed project conforms to the
Bozeman Community Plan 2020 designation of Community Commercial Mixed Use by providing urban
density homes within city limits in proximity to existing and developing parks, commercial nodes, centers of
employment, retail, amenities within the midtown and downtown areas, and schools. The Apartment use as
denoted within the master site plan submittal is allowed within the B-2M zoning district and the project
conforms to the requirements of the B-2M zoning district. The property is within the City’s municipal service
area and complies with the goals and objectives of the growth policy and other supporting city plans. No
conflicts between the proposed use, zoning compliance, and the growth policy are identified.
2. Conformance with Article 1 - All other applicable laws, ordinances, and
regulations (38.100.080)
Condominium ownership No
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 16 of 26
Comments: There is no proposed condominium ownership association for this site plan. The proposed use
of the site is consistent with the allowed uses in the B-2M zoning district. As detailed in this report, the
application conforms with all relevant provisions of the UDC and other City regulations. Additional steps will
be required, including but not limited to, review of a site plan for each phase, building permits, and
infrastructure plans. The Building Division of the Department of Community Development will review the
requirements of the International Building Code for compliance at the time of building permit application
following approval of each subsequent site plan.
3. Conformance with Article 2, including the cessation of any current violations
(38.200.160)
Meets Code?
Current Violations None Yes
Comments: There are no current violations on the property.
4. Conformance with Article 2 - Submittal material (38.220) requirements and
plan review for applicable permit types (38.230)
Meets Code?
Site Plan Yes
Submittal requirements 38.220.100 Yes
Phasing of development
38.230.020.B
No. of phases: 3 Yes
Comments: Figure 2 of this report shows the proposed phasing. Phase 1 on the center parcel and Phase
2 on the southern parcel are currently in review under application 24192. Each platted lot is proposed as
an individual phase within the master site plan, containing a single building and a portion of the shared
open space and other site improvements. The shared parking lot between the buildings will be
constructed with Phase 1. The applicant has requested a departure from the light and air setback
required with the Phase 1 building from the northern property line with Phase 3. Instead, the applicant is
proposing a 20-feet wide no build zone easement on the northern lot to accommodate the required
setback. The recording of this easement on the Phase 3 parcel is included as code provision #7 of the
Master Site Plan. Per code provision #4 CILWR must be paid prior to final site plan approval for each
phase. With Phase 1, public infrastructure including water and sewer mains, hardscape, and perimeter
sidewalks are proposed to be constructed. The applicant indicated they are currently exploring the
feasibility of a parking lot on Phase 3 in the interim, although no plan has been formally submitted. This
Master Site Plan report and analysis does not include a parking lot because it is not proposed within this
application. Any proposed parking lot on Phase 3 will be required to obtain a Special Temporary Use
Permit prior to construction for conformance with required city codes.
Special use Permit 38.230.120 NA
Comments: No special uses are proposed.
5. Conformance with Article 3 - Zoning Provisions (38.300) Meets Code?
Permitted uses 38.310 Apartments/Apartment Buildings Yes
Form and intensity standards 38.320
Zoning: B-2M Setbacks
(feet)
Structures Parking / Loading Yes, with
departure for
block
frontage
Front Landscaped Block
Frontage – 10-feet
Landscaped Block
Frontage – 10-feet
Rear 10-feet 5-feet
Side 5-feet 5-feet
Alley 5-feet NA
Comments: Apartments and apartment buildings are permitted uses within the B-2M zoning district. The
proposed structures comply with all B-2M zoning district setbacks and block frontage standards for
building placement with one requested departure. Multi-household buildings are subject to block frontage
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 17 of 26
standards and the block frontage standards will be reviewed and confirmed with the individual site plan
applications for the applicable phase. The block frontage designation is Mixed along N 7th Avenue, and
buildings within Phases 1 and 2 will comply with the Landscaped standards with one departure for the
building placement to be located within 5-feet of the front property line along N 7th Avenue. Since the
requested departure is not related to the entire development, including the Phase 3 future building, the
requested departure will be reviewed for conformance with the applicable criteria within the associated
site plan staff report for Phases 1 and 2, application #24192.
Lot
coverage
40% with Phase
1 and Phase 2
Allowed 100% Yes
Building
height
53-feet for Phase
1 and Phase 2
buildings; 7
stories for future
Phase 3 building
Allowed B-2M district
permits 4-stories
or 50-feet
(whichever is less)
for residential use
and 5-stories or
60-feet for non-
residential or
mixed use
Yes, with
deep
affordable
housing
incentives
Comments: Lot coverage and building height form and intensity standards are met with the proposed design
and affordable housing incentives. In conformance with Sec. 38.380.030.B, the developer has proposed to
construct affordable homes that meet the standards in Table 38.380.020-1 in the same geographically
contiguous development as market rate homes and may apply certain incentives to all primary buildings in the
development in which 50 percent or more of the gross floor area contains residential uses. The applicant has
requested a total of four deep incentives further described under the Affordable Housing Plan in the next
section of this staff report. One of the requested incentives pertains to specific form and intensity standards
as outlined below, while the other three incentives are discussed in Sections 7a – Block Frontage Standards
and 7c – Building Design.
1) Sec. 38.380.030.B.3.c. Four additional stories of height (maximum 15 feet per story) beyond that
allowed in the B-2M zoning district.
The underlying B-2M zoning district (BMC 38.320.050, note 8) permits a maximum building height of 4-stories
or 50-feet (whichever is less) for buildings designed for a single purpose residential use. Buildings designed
for non-residential or a mixed-use (commercial and residential combined) permits a maximum building height
of 5-stories or 60-feet (whichever is less). With the use of the affordable housing deep incentive noted above,
the residential buildings could be a total of 8-stories or 110-feet in total building height. The future Phase 3
building is proposed as a mixed-use building and with the affordable housing deep incentive proposed, could
include a maximum 9-storeis or 120-feet in total building height. This application proposes to construct two 53-
feet tall buildings in Phases 1 and 2 each at 4-stories, and one 7 story building in Phase 3, all of which are
allowable using the deep incentives for affordable housing.
In conjunction with the master site plan approval, an affordable housing plan has been reviewed and approved
by the Economic Development Department. Two code provisions (#2 & #3) must be met prior to final site plan
approval for the execution of this affordable housing plan.
Applicable zone specific or overlay standards 38.330-40 NA
Comments: NA, the proposed project is not subject to zone specific or overlay district standards.
General land use standards and requirements 38.350 Yes
Comments: No setback encroachments are proposed.
Applicable supplemental use criteria 38.360 NA
Supplemental
uses/type
NA NA
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 18 of 26
Comments: NA, the proposed project is not subject to any supplemental use criteria.
Wireless facilities 38.370 NA
Affordable Housing 38.380.010 Yes
Affordable housing plan Yes
Comments: In conformance with Sec. 38.380.030.B, the developer has proposed to construct affordable
homes that meet the standards in Table 38.380.020-1 in the same geographically contiguous development
as market rate homes and may apply certain incentives to all primary buildings in the development in which
50 percent or more of the gross floor area contains residential uses. The applicant has requested four deep
incentives, as follows, with a minimum of 56% (96 units) of the project’s multi-household dwellings will be
available for rent at 50%, 60% and 80% of average median income (AMI) for 30 years.
1) Sec. 38.380.030.B.3.c. Four additional stories of height (maximum 15 feet per story) beyond that
allowed in the B-2M zoning district.
2) Sec. 38.380.030.B.3.f.2. Exemption from Section 38.510.030. E to J block frontage standards,
provided that vehicle parking is prohibited between the front and side of a principal building and a
public or private street.
3) Sec. 38.380.030.B.3.f.3. Exemption from Section 38.530.040.E. maximum façade width
standards.
4) Sec. 38.380.030.B.3.f.4. Exemption from Section 38.530.040.F roofline modulation standards.
In conjunction with the master site plan approval, an affordable housing plan has been reviewed and
approved by the Economic Development Department. The approval memo has been attached to this
staff report and the associated site plan staff report for Phases 1 and 2. Two code provisions (#2 & #3)
must be met prior to final site plan approval for the execution of this affordable housing plan.
6a. Conformance with Article 4 - Community Design Provisions: Transportation
Facilities and Access (38.400)
Meets Code?
Streets 38.400.010 Yes
Street and road dedication 38.400.020 NA
Access easements Yes
Level of Service
38.400.060
Yes Transportation grid adequate to serve site Yes
1. Comments: Adjacent streets exist to serve the site and no additional dedication is needed. The parking lot
between Phases 1 and 2 will be accessed by an existing approach which is a right-in/right-out intersection
due to the center median on N 7th Avenue. Phase 3 would be accessed from either N 7th Avenue or W
Aspen Street, which will be determined at the time of site plan application for that phase. A traffic impact
study was required by the Engineering Division and showed an estimated 1,348 total buildout gross vehicle
trips could be generated by the proposed project daily. Additionally, the traffic impact study identified no
pedestrian crosswalk at the intersection of N 7th Avenue and W Aspen Street, with the nearest protected
crossing approximately 300-feet to the north at the intersection of N 7th Avenue and W Tamarack Street.
As a condition of approval, the applicant must install a rectangular rapid-flashing beacon pedestrian
crossing at the intersection of North 7th and Aspen Street prior to occupancy. The crossing must be
approved by the Montana Department of Transportation (MDT) through their Systems Impact Action
Process. If the MDT does not approve the pedestrian crossing, the applicant must provide documentation
from the MDT as to why the crossing cannot be installed at North 7th and Aspen. Level of service
standards for arterial and collector streets serving the site was evaluated by engineering. N 7th Avenue is a
Montana Department of Transportation controlled National Highway System Route. MDT may require a
review process which could impact the proposed development layout. In the event MDT requires changes,
a modification or resubmittal of the Master Site Plan will be required. Additionally, all work within the MDT
right-of-way must meet MDT standards and specifications. A Waiver of Right to Protest Creation of Special
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 19 of 26
Improvement Districts (SID’s) for future transportation improvements is a required condition of approval
ensuring participation in funding of future infrastructure improvements that may be required to offset
impacts created by development of the property.
Sidewalks 38.400.080 Yes
Comments: Sidewalks currently exist along N 7th Avenue and W Aspen Street. The site plan application
for Phases 1 and 2 proposes to expand portions of the sidewalk on N 7th Avenue in front of the
development to between 6-feet and 11-feet wide. The Landscaped block frontage requires a minimum 6-
feet wide sidewalk adjacent to arterial streets. All other sidewalks proposed within the development will
be a minimum 5-feet wide with the majority closer to 7-feet in total width.
Drive access 38.400.090 Access to site: 3 Yes
Fire lanes, curbs, signage and striping Yes
Comments: Three drive accesses are existing to all three parcels: one from N 7th Avenue between
Phases 1 and 2 (center and southern parcels), one from N 7th Avenue for Phase 3 (northern parcel), and
one shared access from W Aspen Street for Phase 3 (northern parcel). Engineering evaluated the drive
accesses proposed for Phase 1 and 2 for spacing and design standards. Phase 3 access will be
reviewed at the time of site plan approval for the northern parcel. Any required updates to the access
approach for Phases 1 and 2 will be constructed during Phase 1 and the associated parking lot.
Street vision triangle 38.400.100 Yes
Transportation pathways 38.400.110 NA
Pedestrian access easements for shared use pathways and similar transportation
facilities
NA
Public transportation 38.400.120 Yes
Comments: N 7th Avenue is classified as a Principal Arterial and W Aspen Street is classified as a Local
Street. No new pedestrian easements are proposed with this project. As stated above, the applicant will
be required to install a rectangular rapid-flashing beacon pedestrian crossing at the intersection of North
7th and Aspen Street prior to occupancy. Additionally, this project is a mixed-use development with
higher density housing adjacent to an existing public transportation route along N 7th Avenue. Streamline
bus service has an existing Blueline route stop located at the intersection of N 7th Avenue and Peach
Street, approximately 275-feet south of the subject property.
6b. Conformance with Article 4 – Community Design Provisions: Community
Design and Elements (38.410)
Meets Code?
Neighborhood centers 38.410.020 NA
Comments: This project does not trigger neighborhood center requirements.
Lot and block standards 38.410.030-040 NA
Midblock crossing: rights of way for pedestrians alternative block delineation NA
Comments: Requirements of BMC 38.410 such as lot and block standards were previously reviewed for
conformance and satisfied, if necessary, as part of the applicable platting process associated with the
original creation of the lots. Public streets and sidewalks surround the subject property providing adequate
pedestrian connectivity.
If the development is adjacent to an existing or approved public park or public open
space area, have provisions been made in the plan to avoid interfering with public
access to and use of that area
NA
Provisions for utilities including efficient public services and utilities 38.410.050-060 Yes
Easements (City and public utility rights-of-way etc.) Yes
Water, sewer, and stormwater Yes
Other utilities (electric, natural gas, communications) Yes
CIL of water Yes
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 20 of 26
Comments: Utilities, easements, water, sewer, and stormwater have been reviewed by the Engineering
Department, Water/Sewer Division, and Northwestern Energy for functionality and compliance with adopted
standards. The Engineering Department included a condition of approval stating prior to occupancy, the
applicant must work with the Water and Sewer Department to install a sanitary sewer leak detection system
for the portion of sewer in the tunnel under the Northgate Shopping Center. Code provision #5 requires the
front setback utility easement must be ten feet wide and must always be provided unless written confirmation
is submitted to the community development department from all utility companies providing service indicating
that front setback easements are not needed. Sheet 009-C3.1 Site Utility Plan shows the proposed buildings
in Phases 1 and 2 will be provided electrical service along the eastern property line extending from a
proposed electrical transformer located across the northern property line in Phase 3. This location is
considered an off-site improvement for Phases 1 and 2. In order to approve the associated site plan for
Phases 1 & 2, an easement for the electrical transformer location must be recorded on the phase 3 property
and has been included as code provision #7. Cash-in-lieu of water rights (CILWR) is required prior to final
plan approval for each phased site plan per code provision #4. The applicant is encouraged to explore
using a non-municipal source (i.e. groundwater well) to supply irrigation demands.
Municipal infrastructure requirements 38.410.070 Yes
Comments: Municipal water, sanitary sewer, and storm sewer systems proposed with this project have
been reviewed by engineering.
Grading & drainage 38.410.080 Yes
Location, design and capacity of stormwater facilities Yes
Stormwater maintenance plan Yes
Landscaping: native species, curvilinear, 75% live vegetation 38.410.080.H Yes
Comments: Requirements for grading and drainage, design standards for stormwater facilities, stormwater
maintenance and landscaping for the facilities have been reviewed and conform to the City’s standards.
Additional review of the associated landscaping plan can be found in Section 7e of this staff report and will
be analyzed further in the individual staff report for the proposed Phases 1 and 2 site plan.
Watercourse setback 38.410.100 NA
Watercourse setback planting plan 38.410.100.2.f NA
6c. Conformance with Article 4 – Community Design Provisions: Park and
Recreation Requirements (38.420)
Meets Code?
Parkland requirements 38.420.020.A Yes
Cash donation in lieu (CIL) 38.420.030 Yes
Improvements in-lieu NA
Comments: A total of 0.38 acres of equivalent cash donation in lieu of parklands (CILP) is required for
this project. Developments are required to meet parkland requirements when the project proposes more
than 8 dwelling units per acre but not in excess of 12 dwelling units per acre (BMC 38.420.020.A.1). This
project is proposing 96 dwelling units over 1.03 net acres for a net density of 93.2 units per acre.
Because of the cap on the parkland requirement, the CILP does not take into account the total net
density and instead is based on the maximum 12 units per acre for an equivalent of 12.36 dwelling units.
Within the B-2M zoning district the required dedication per dwelling is equivalent to 0.03 acres.
Therefore, the calculation to determine the amount of parkland for this project is 12.36 x 0.03 acres for a
total of 0.38 acres. Additionally, because the net density calculation is greater than 8 dwelling units per
acre, the requirement for dedication must be met with cash donation-in-lieu per BMC 38.420.020.A.1.b.
With 0.38 acres owed for CILP, at an appraisal land value of $2.65 per square foot, the applicant owes
$42,710.05 to provide the necessary cash donation for their proportionate share of parklands
contribution. Per code provision #5, CILP must be paid prior to final site plan approval for each phase.
Park Frontage 38.420.060 NA
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 21 of 26
Park development 38.420.080 NA
Recreation pathways 38.420.110 NA
Park/Recreational area design NA
Comments: No parks are proposed with this application. Westlake public park exists to the east of the
subject property approximately 400-feet down W Aspen Street and can be accessed from sidewalks
along W Aspen Street and N 5th Avenue.
7a. Conformance with Article 5 – Project Design: Block Frontage Standards
(38.510)
Meets Code?
Block frontage classification Mixed – Landscaped Yes, with
deep
affordable
housing
incentives
Departure criteria Yes Yes
Comments: Multi-household buildings are subject to block frontage standards. The block frontage
designation is Mixed along N 7th Avenue and Storefront along W Aspen Street. The block frontage
standards will be reviewed and confirmed with the individual site plan applications for the applicable phase.
The applicant is requesting to utilize the deep incentive BMC 38.380.030.B.3.f.2. Exemption from Section
38.510.030.J block frontage standards regarding special residential standards for ground-floor living spaces
facing a sidewalk or internal pedestrian pathways with the Master Site Plan. With approval of the affordable
housing plan, the proposed development would not be required to comply with these standards for any
ground-floor residential units.
7b. Conformance with Article 5 – Project Design: Site Planning and Design
Elements (38.520)
Meets Code?
Design and arrangement of the elements of the plan (e.g., buildings, circulation, open
space and landscaping, etc.) so that activities are integrated with the organizational
scheme of the community, neighborhood, and other approved development and produce
an efficient, functionally organized and cohesive development
Yes
Relationship to adjacent properties 38.520.030 Yes
Non-motorized circulation and design systems to enhance convenience and safety
across parking lots and streets, including, but not limited to paving patterns, pathway
design, landscaping and lighting 38.420.040
Yes
Comments: Interior sidewalks are proposed along the perimeters and through parking areas that will
allow for direct access to an open space area and trash enclosures. All interior frontages of buildings are
proposed with pedestrian facilities that connect throughout the site and to the public sidewalk network.
The applicant has requested a departure from the light and air setback required with the Phase 1 building
from the northern property line with Phase 3. The criteria states a departure is allowed where it’s
determined based on unique site context the proposed design will not create a compatibility problem in
the near or long term. The applicant is proposing a 20-feet wide no build zone easement on the northern
Phase 3 parcel to accommodate the required setback. The recording of this easement on the Phase 3
parcel is included as code provision #7 of the Master Site Plan.
Design of vehicular circulation systems to assure that vehicles can move safely and
easily both within the site and between properties and activities within the general
community 38.420.050
Yes
Internal roadway design 38.520.050.D NA
Comments: Requirements of BMC 38.520 such as design of vehicular circulation systems have been
met. Pedestrian pathways are provided connecting the residential buildings and parking areas.
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 22 of 26
On-site open space 38.520.060
Total required NA NA
Total provided NA NA
Comments: Required open space will be reviewed and confirmed with the individual site plan applications
for the applicable phases. Since the amount of open space is determined by the proposed use of the site
and the number proposed dwelling units or overall commercial space, it cannot be confirmed with the
Master Site Plan.
Location and design of service areas and mechanical equipment 38.520.070 Yes, with
requested
departure
Comments: Solid waste will be collected in a shared trash enclosure in the middle of the proposed
parking lot. The applicant has requested a departure to BMC 38.520.070.B.3 which requires service
areas visible from sidewalks to be screened with structural and landscaping measures. Due to the site
constraints of the infill lots and the desire to provide as much parking on-site as possible, the applicant is
requesting a departure from providing the required 5-feet wide landscaping to screen the service
enclosure. Instead, the applicant is proposing the use of painted art or graphics applied to the cladding
on the west and east sides of the enclosure to provide visual interest to site users while maximizing the
provided parking.
7c. Conformance with Article 5 – Project Design: Building Design (38.530) Meets Code?
Compatibility with, and sensitivity to, the immediate environment of the site and the
adjacent neighborhoods and other approved development 38.530.030
Yes
Building massing and articulation 38.530.040 Yes, with
deep
affordable
housing
incentives
Building details, materials, and blank wall treatments 38.530.050-070 NA
Comments: In conformance with Sec. 38.380.030.B, the developer has proposed to construct affordable
homes that meet the standards in Table 38.380.020-1 in the same geographically contiguous
development as market rate homes and may apply certain incentives to all primary buildings in the
development in which 50 percent or more of the gross floor area contains residential uses. The applicant
has requested a total of four deep incentives described under the Affordable Housing Plan in previous
sections of this staff report. Two of the requested incentives were discussed previously in Section 3 –
Zoning Provisions and Section 7a – Block Frontage Standards. The other two incentives pertain to
building design standards:
1) Sec. 38.380.030.B.3.f.3. Exemption from Section 38.530.040.E. maximum façade width
standards.
2) Sec. 38.380.030.B.3.f.4. Exemption from Section 38.530.040.F roofline modulation
standards.
In conjunction with the master site plan approval, an affordable housing plan has been reviewed and
approved by the Economic Development Department. Two code provisions (#2 & #3) must be met prior
to final site plan approval for the execution of this affordable housing plan. Review for conformance with
the building design standards will be included in the separate site plan applications for the applicable
phases. The standards for maximum façade width under BMC 38.530.040.E. state that building facades
wider than 150-feet must include features such as vertical building modulation, contrasting building
materials, and/or articulation of the building walls. The apartment buildings proposed for Phases 1 and 2
are approximately 172-feet long, however with approval of the submitted affordable housing plan, the
provisions for maximum façade width would not be required. Additionally, under BMC 38.530.040.F. the
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 23 of 26
7d. Conformance with Article 5 – Parking (38.540) Meets Code?
Parking requirements 38.540.050 NA Yes
Parking requirements residential 38.540.050.A.6 0 required per Midtown
Urban Renewal District
Reductions residential 38.540.050.A.6.c NA
Parking requirements nonresidential
38.540.050.A.6
NA
Reductions nonresidential 38.540.050.A.6.c NA
Provided off-street 22 spaces
Provided on-street 6 on-street available
Bicycle parking 38.540.050.A.6 96 required; 108 provided Yes
Comments: The subject parcels are located within the Midtown Urban Renewal District in the B-2M
zoning district. BMC 38.540.050.A.6.d states the minimum parking requirements do not apply within the
Midtown Urban Renewal District. However, all other requirements of the section, including bicycle
parking and standards where parking is provided, are applicable. The applicant is proposing to provide
22 parking spaces on-site between the buildings in Phases 1 and 2, and 6 spaces on-street located along
N 7th Avenue. Each stall provided off-street meets the stall, aisle, and driveway design requirements of
Section 38.540.020, including one proposed compact space. A total of 96 bicycle parking spaces are
required for the residential units in Phases 1 and 2 according to the B-2M district standards. The
applicant is proposing 8 bicycle parking spaces located outside at racks adjacent to each proposed
building with inverted U racks and another 100 bicycle parking spaces provided indoors. Each proposed
building will include a total of 50 indoor bicycle storage spaces, splitting the 100 bicycle parking spaces
between Phases 1 and 2. Bicycle parking areas meet the length and width dimensions for each stall and
utilize the adjacent sidewalk to meet circulation requirements. The proposed indoor bike parking spaces
can be accessed from an exterior door or through the interior entry lounge and open recreational areas.
Loading and unloading area requirements 38.540.080 NA
First berth – minimum 70 feet length, 12 feet in width, 14 feet in height NA
Additional berth – minimum 45 feet length NA
Comments: NA
7e. Conformance with Article 5 – Landscaping (38.550) Meets Code?
Mandatory landscaping requirements 38.550.050 Yes
Drought tolerant species 75% required Yes
Parking lot landscaping Yes
Additional screening NA
Street frontage Yes
Street median island NA
Acceptable landscape materials Yes
Protection of landscape areas NA
Irrigation: plan, water source, system type Yes
Residential adjacency Yes
Comments: The subject property is zoned B-2M, Community Business District – Mixed and the designation
is considered a commercial zoning district. The surrounding adjacent properties are also zoned B-2M,
however there are existing residential dwelling units located in the southeast corner of the Phase 2 southern
standards for roofline modulation require pitched roofline segments or for flat roofs, the extension of a
parapet or break up the roof to effectively reduce the overall scale of the building and add visual interest.
As mentioned above, the applicant has requested an exemption from the roofline modulation standards
with the submitted affordable housing plan.
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 24 of 26
parcel. Required landscaping provisions for adjacent residential uses will be reviewed during the applicable
site plan application for each phase. Generally, the landscaping plan provided as part of the Master Site
Plan application complies with all provisions of the UDC regarding landscaping because the project proposes
to install 2 street trees along the N 7th Avenue street frontage and 3 trees within the adjacent parking lot area
along with 591 square feet of landscape plantings. The proposed trees within the N 7th Avenue frontage
include one Accolade Elm and one Princess Kay Plum, both deciduous tree varieties. The trees proposed
within the required parking lot landscaping include 2 Harvest Gold Linden and 1 Accolade Elm, again all
deciduous tree varieties. Additionally, the project proposes a mixture of container grown plant coverage,
irrigated lawn and drylawn seed mix for a total landscaped vegetated area of 6,303 square feet between the
Phase 1 and 2 site plan. The submitted landscaping plan will also be reviewed by Water Conservation for
compliance with current standards during the site plan application for each phase. Any required landscaping
conditions or code provisions will be included in the site plan staff report and are not provided within this
Master Site Plan.
Landscaping of public lands 38.550.070 Yes
Comments: Landscaping will be provided along the N 7th Avenue right-of-way compliant with BMC
38.550.070. N 7th Avenue is a Montana Department of Transportation controlled National Highway System
Route. MDT may require a review process which could impact the proposed development layout. In the
event MDT requires changes, a modification or resubmittal of the Master Site Plan will be required.
Additionally, all work within the MDT right-of-way must meet MDT standards and specifications.
Maintenance of landscaping installed within the boulevard portion of the right-of-way is the responsibility of
the adjacent property owner.
7f. Conformance with Article 5 – Signs (38.560) Meets Code?
Allowed SF/building 38.560.060 NA NA
Proposed SF/building NA NA
Comments: No signage is proposed with this application or required for residential uses. Signs permits must
first be obtained prior to the installation of any residential identification signs.
7g. Conformance with Article 5 – Lighting (38.560) Meets Code?
Site lighting (supports, cutoff, footcandles, temperature) 38.570.040 Yes
Building-mounted lighting (supports, cutoff, footcandles, temperature) 38.570.040.B Yes
Comments: Site lighting is proposed at the building entrances and along pedestrian paths surrounding
the internal parking lot. Review for conformance with all lighting standards will be included in the separate
site plan staff reports for the applicable phases.
8. Conformance with Article 6 – Natural Resource Protection Meets Code?
Floodplain regulations 38.600 NA
Wetland regulations 38.610 NA
Comments: Requirements of BMC 38.600 for floodplain regulations and 38.610 for wetland regulations
are not applicable to this development.
9. Relevant Comment from Affected Parties (38.220) Meets Code?
Public Comment Yes
Comments: A public notice period was conducted meeting the requirements of this section and detailed on
page 1 of this report. Five public comments were received during the initial public notice period. Based on
the submitted comments, staff requested additional information from the applicant regarding the existing site
survey with updated tree/vegetation information, a revision to the project narrative, and review of the
Economic Development Staff Report on the submitted Affordable Housing Plan. With the submittal of this
additional information, an additional public comment period was conducted, limited in scope to the additional
information submitted by the applicant as detailed on page 1 of this report. At the close of the limited scope
comment period, an additional five public comments were received. A number of the public comments
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 25 of 26
included topics which are not part of the Master Site Plan or Site Plan criteria. Staff has included responses
to the public comment topics under the Community Development Department’s purview below:
• Requirement for ground floor commercial in every phase: As mentioned in Section 5 of this staff
report, the zoning on the subject parcels is B-2M Community Business District – Mixed. This district
provides for a range of commercial uses and encourages the integration of multi-household
residential. Non-residential uses are only required on the ground floor for properties adjacent to
streets designated storefront block frontage. As discussed in Section 7a of this staff report, N 7th
Avenue has a block frontage designation of Mixed and therefore the project is not required to
provide ground floor commercial along the N 7th Avenue frontage. The northern parcel in Phase 3
will include frontage along W Aspen Street which is listed as a storefront block frontage.
Requirements for ground floor non-residential uses will be reviewed during the future site plan
application for any Phase 3 structure along W Aspen Street.
• Existing mature trees on-site: Multiple public comments addressed concerns over the removal of
mature existing trees on the three parcels. One comment indicated the submitted existing tree
survey was not accurate according to the site plan submittal requirements in BMC 38.220.080. As
mentioned above, this information was conveyed to the applicant and a revised existing tree survey
was resubmitted in conformance with the requirements. Due to the additional information, a second
public comment period with a limited scope occurred allowing for public comment on the
resubmittal. Other comments identified the site plan review criteria in BMC 38.230.100.A.7
regarding conformance with Article 5 and BMC 38.410.010.B stating the design and development of
all land uses must, to the extent possible, preserve the natural terrain, trees, and other existing
vegetation. While these criteria reference existing vegetation, it includes the preservation OR
replacement of natural vegetation. The applicant’s landscaping plan adequately replaces natural
vegetation in conformance with the requirements in code. As identified in Section 1 of this staff
report on the project conformance with the City’s Growth Policy, an action of the Bozeman Climate
Plan is to facilitate compact development which reduce the distance people need to travel for work
and services. This project attempts to work within the existing code provisions to combine
affordable housing options in a desirable location near walkable city services while maintaining the
existing vegetation to the greatest extent possible. The provisions of the Bozeman Unified
Development Code do not state all existing vegetation must be maintain in its entirety. The City of
Bozeman does not have a tree preservation ordinance requiring any private property owner within
city limits to maintain or preserve existing vegetation during any type of project development.
Additionally, applicants are not required to provide information on the health of existing vegetation
from certified arborists during plan review. The provisions of BMC 38.550 Landscaping within
Article 5 include requirements for any specific screening or required tree locations. Section 7.e. of
this report identified general information on the Master Site Plan’s compliance with landscape
provisions in code. The staff report and materials for application #24192 will include specific
information regarding compliance with the landscaping provisions for Phases 1 and 2. Future site
plan applications will also be evaluated against landscaping requirements at the time of submittal.
Finally, many submitted comments requested the applicant to maintain 75% of the trees and
vegetation existing on-site. No such standard exists in code. As stated previously, the existing
code provisions do not provide a specific amount of vegetation or type of vegetation which
applicants are required to maintain.
• Difference between a deviation and departure: One submitted comment stated deviations and
departures can be used interchangeably through the city code. Per the definition of deviation in
BMC 38.700.050, these types of requests only pertain to projects within the Neighborhood
Conservation Overlay District (NCOD). This is also referenced in BMC 38.250.050 Deviations.
This proposed project is not located within the NCOD boundaries and therefore may not request
deviations. Departures are defined in BMC 38.700.050 as provisions where applicants can propose
Staff Report
7th & Aspen Master Site Plan
Application No. 24191
October 30, 2024
Page 26 of 26
alternative means of compliance for a specific standard if they meet the intent of the standard.
Additionally, departure opportunities are only available to those specific standards that allow for a
departure listed within city code (BMC 38.250.060.C). Departures and deviations are not
interchangeable requests and are reviewed through different criteria.
• Site Plan review criteria – Conformance with Growth Policy: As mentioned in Section 1 of this staff
report, projects are reviewed for consistency with the City’s adopted Growth Policy. The Bozeman
Community Plan 2020 articulates goals and objectives that are sometimes in conflict. In reviewing
a development application, the Community Development Division evaluates whether, on balance, a
proposal satisfies the aims of the growth policy. Growth Policies are guiding documents for a
community and are not regulatory standards for specific project development. Projects cannot be
approved or denied based solely on non-conformance with an adopted growth policy. The
standards throughout the entire BMC 38 Unified Development Code were adopted to implement
goals and objectives of the adopted City’s growth policy. Conformance with these standards
ensures consistency with the goals and polices within the growth policy itself. Detailed analysis of
this Master Site Plan’s compliance with the City’s adopted regulations is found throughout this
report.
• Concerns over requested departures: Review of each requested departure was provided within the
applicable sections of this staff report or will be addressed within the specific site plan application
staff reports. As mentioned previously, departures are only available to those specific standards
which allow for a departure within city code and where applicants proposed alternative meets the
intent of the applicable standard.
10. Division of Land Pertaining to Subdivisions (38.240-Part 4) Meets Code?
Subdivision exemptions NA
Required easements Yes
Comments: No lot lines are proposed to be relocated. Required easements have been reviewed and
addressed by the Engineering Department, Northwestern Energy, and Water/Sewer Division. Any
required easements have been included as application conditions or code provisions.
Page | 1
To: Director of Community Development
Fr: Brit Fontenot, Director of Economic Development
Date: September 25, 2024
RE: Approval of Affordable Housing Plan for Project #24191 7th and Aspen Master Site Plan
and Project #24192 7th and Aspen Site Plan
Pursuant to Sec. 38.200.010.H, BMC, as the duly appointed Director of Economic Development,
I am the review authority for an affordable housing plan submitted pursuant to 38.380.040. I
hereby approve the attached Affordable Housing Plan for the 7th and Aspen Master Site Plan and
Site Plan (the “Project”). If you determine the application is appropriate for approval, I request
you include in your approval of 7th and Aspen Master Site Plan and Site Plan the following
conditions:
1. BMC 38.380.040.E. The applicant and owner, if different, must consent to the City
recording a summary of the affordable housing plan immediately following conditional
approval of the 7th and Aspen Master Site Plan and Site Plan.
2. BMC 38.380.060.D. The applicant and owner, if different, must record and provide to the
City of Bozeman a Notice of Restrictions for the Affordable Housing Plan and a
Declaration of Restrictive Covenants that implements the affordable housing plan
immediately following conditional approval of the 7th and Aspen Master Site Plan and Site
Plan. The summary of the Affordable Housing plan and the restrictive covenant must be
recorded prior to issuance of a building permit for the 7th and Aspen Master Site Plan and
Site Plan.
The proposal is utilizing the Deep Incentives allowed pursuant to BMC 38.380.030.B, which were
created to incentivize the increased production of affordable housing to meet the goals of the
adopted Bozeman Community Plan and the Community Housing Action Plan. Deep Incentives
are available to projects for which the minimum percentage of homes meeting the criteria for
affordability is 50 percent. Pursuant to 38.380.030, “Applications for development of affordable
homes that comply with the requirements of this division qualify for and must be awarded the
incentives applicable to the type and tenancy of affordable housing being provided and requested
by the developer. Staff reviewed the Affordable Housing Plan for the 7th and Aspen Master Site
Plan and Site Plan for compliance with every requirement of the Affordable Housing division of
the code and found that it complies with all code requirements. Therefore, the requested incentives
must be awarded.
A compliant Affordable Housing Plan must include the following information.
a. The total number of affordable homes, and market rate homes in the proposed
development.
• The 7th and Aspen Affordable Housing Plan includes 17 affordable units restricted
at 50% AMI, 29 units at 60% AMI in Phase 1, and 50 units restricted at 80% AMI
Page | 2
in Phase 2. Phases 1 and 2 of the project will provide 96 total units, while Phase 3
of the project will provide approximately 75 units, which means that at least 50
percent of the units in all 3 phases meet the affordability criteria for the use of the
Deep Incentives pursuant to Table 38.380.020-1.
b. The table in 38.380.020-1 to be applied to the affordable housing plan.
• The 7th and Aspen Affordable Housing Plan references Table 38.380.020-1 –
Affordable Homes Required for Deep Incentives. To be eligible for Deep
Incentives, the requirements of Table 38.380.020-1, including providing at least 50
percent of the homes within the multi-household dwelling for sale or rent at
percentages of AMI. This project meets the requirements because the development
proposes at least 50 percent of the dwellings be priced at 80 percent of AMI or less,
in accordance with requirements found in the table.
c. The number of bedrooms in each proposed low-income affordable home, and market
rate home in the development.
• The 7th and Aspen Affordable Housing Plan stipulates that Phases 1 and 2 of the
project will have 96 units, 100 percent of those units are proposed as affordable
units. The proposed project meets the code requirement. With the inclusion of 75
market rate units in Phase 3, the overall project will need to meet requirements
related to 38.380.040.2.b requiring that the “mix of bedrooms per unit in affordable
homes must be as similar as possible to the mix of bedrooms per unit of the market-
rate homes in the development.”
d. Whether each affordable home will be offered for rental or for sale.
• The 7th and Aspen Affordable Housing Plan provides that all affordable units will
be offered for rent.
e. The location of affordable lots or units in the development.
• The 7th and Aspen Affordable Housing Plan provides an exhibit (7th & Aspen
Mixed-Use Affordable Housing Action Plan) showing the locations of the 96
affordable units.
f. The applicable AMI and maximum rental or sales price applicable to each low-income
affordable home.
• Because each of the affordable units will be offered for rent, the maximum rental
price allowed is 80 percent of Area Median Income (AMI). The Department of
Housing and Urban Development (HUD) is required by law to set income limits
that determine eligibility for assisted housing programs. These income limits are
set at certain percentages of an area’s median family income (MFI). MFIs are also
often referred to as area median incomes (AMI).
Page | 3
o The 7th and Aspen Affordable Housing Plan provides that 17 of the units
will be offered at 50 percent of AMI. Given the current AMI, a one bedroom
unit will be offered for rent for $986, a two bedroom will rent for $1,183
and a three bedroom will be offered at $1,368 per month.
o The 7th and Aspen Affordable Housing Plan stipulates that 29 of the units
will be offered at 60 percent AMI. A studio unit will be offered for rent for
$1,105, a one bedroom will rent for $1,184, a two bedroom will rent for
$1,420, and a three bedroom will be offered at $1,641 per month.
o The 7th and Aspen Affordable Housing Plan stipulates that 50 of the units
will be offered at 80 percent AMI. A one bedroom will be offered for rent
for $1,684, a two bedroom will rent for $1,893 and a three bedroom will be
offered at $2,103 per month.
g. A description of the requested incentives from section 38.380.040.
• The 7th and Aspen Affordable Housing Plan includes a description of the requested
incentives from section 38.380.040. These incentives include an additional stories
of height, block frontage standards, façade standards, and roofline modulation.
h. Any other information that is reasonably necessary to evaluate the compliance of the
affordable housing plan with the requirements of this division, as determined by the review
authority.
• The information provided with The 7th and Aspen Affordable Housing Plan
satisfies the requirements of 38.380.040.A.1 and is adequate to evaluate the
compliance of the affordable housing plan with the requirements of this division as
explained by this staff report.
i. If the development is to be constructed in phases.
• All of the units meeting the affordability criteria are being provided in the first two
phases of the development with market rate units only being offered in the third
and final phase of the development. Pursuant to 38.380.040.A.i.(2), the Applicant
must update the Affordable Housing Plan to reflect the market rate units in Phase
3. “As the number of low income affordable homes for each later phase is finalized,
the developer must submit an update to the affordable housing plan including or
updating the information required in this section. The review authority shall review
and approve, approve with conditions, or deny the update using the criteria in this
section.”
BMC 38.380.040.A.2. requires that the Applicant meet the following development standards for
affordable homes.
a. The number of affordable homes must meet or exceed the minimum standards needed
to qualify for the applicable incentive in section 38.380.030.
• This application proposes to utilize Deep Incentives. Minimum standards for Deep
Incentives are found in Table 38.380.020-1 and require that a project supply at least
Page | 4
50 percent of the total homes as affordable homes at a price no greater than 80
percent of AMI for a duration of at least 30 years. The 7th and Aspen Affordable
Housing Plan shows 96 units, or more than 50 percent of the project’s units, will be
priced at or below a rent that is affordable for households making at or below 80
percent of the area median income. The duration of the affordability of the units
will be satisfied by recording a deed restriction requiring the affordable units to
remain affordable at rent of no greater than 80 percent AMI for a period of 30 years.
b. The mix of bedrooms per unit in affordable homes must be as similar as possible to
the mix of bedrooms per unit of the market-rate homes in the development.
• The 7th and Aspen Affordable Housing Plan stipulates that the project will have 96
with 100 percent of those units proposed in Phase 1 and Phase 2 as affordable units.
BMC 38.380.040.A.2.b. The proposal meets the requirement that the mix of
bedrooms in the affordable homes is as similar as possible to the mix of bedrooms
in the market-rate homes. Pursuant to 38.380.040.A.i.(2), the Applicant must
update the Affordable Housing Plan to reflect the market rate units in Phase 3. “As
the number of low income affordable homes for each later phase is finalized, the
developer must submit an update to the affordable housing plan including or
updating the information required in this section. The review authority shall review
and approve, approve with conditions, or deny the update using the criteria in this
section.”
c. Access to shared amenities and services by residents of the affordable homes must be
the same as to those in market rate homes in the development.
• The proposal meets the requirement that all units have access to shared amenities.
The Applicant must confirm continued compliance with this criterion with their
updated Affordable Housing Plan for Phase 3.
d. If the development is to be constructed in phases, and the developer has requested
affordable housing incentives, at least 75 percent of the dwelling units in each phase
must be affordable homes, unless the city has received adequate legal or financial
assurance that any shortfall during earlier phases will be constructed before approval
of the final phase of development.
• 100 percent of the affordable housing units will be constructed in Phase 1 and Phase
2 of the project.
The review authority has approved the Affordable Housing Plan for the 7th and Aspen Master Site
Plan and Site Plan and finds that the plan includes all information required for the City to confirm
compliance with the standards and criteria in BMC 38.380, including the standards in
38.380.030.B – Incentives Available. The Applicant requests the following incentives from BMC
38.380.030.B – Incentives Available:
• One additional story of height (38.380.020 – 1.3.c)
• Exemption from the following (38.38.020 – 1.3.f)
▪ Special residential block frontage standards along internal pathways
(38.510.030.J)
▪ Maximum façade width standards (38.530.040.E)
Page | 5
▪ Roofline modulation (380.530.040.F)
The Affordable Housing Plan has been incorporated by reference in the Site Plan documents.