HomeMy WebLinkAbout001 - Turnrow MSP NarrativeMaster Site Plan - RC 2
August 2024
August 2024 Turnrow Master Site Plan RC 2 | 2
Table of Contents
1. Project Team
2. Project Narrative
a. REMU Zoning Analysis
b. Project History
3. Project Design
a. Land use analysis
b. Streetscape
d. Landscape
e. Parkland
f. Neighborhood Centers
g. Infrastructure & Utilities
4. Entitlement Period
5. Phasing
6. Design Regulations
7. Departures
Appendices
Appendix A - Vicinity Map
Appendix B - Land Use Diagram
Appendix C - Block Frontage Diagram
Appendix D - Parks Master Plan
Appendix E - Environmental Assessment
Appendix F – Subdivision Green Plan
Appendix G - CCR's
Appendix H – Articles of Incorporation
Appendix I – Bylaws
Appendix J - Design Regulations
Appendix K - Traffic Impact Study
Appendix L – Wetland Delineation Report
Appendix M - Water Design Report
Appendix N - Sewer Design Report
Appendix O - Stormwater Management Report
Appendix P – Geotechnical Reports
Appendix Q - Concurrent Construction request
Appendix R - DNRC Intent to Issue Well Permit - Letter
Appendix S - Weed Management Plan
Appendix T- Agricultural Water Users Notifications
Appendix U - Commercial Area Tracking Table
Appendix V - Existing Easements
Appendix W – Warranty Deeds
Appendix X – Water Rights Information
Appendix Y – Correspondence with Adjacent Neighbor (Westlake Alignment)
August 2024 Turnrow Master Site Plan RC 2 | 3
1. Project Team
Owner & Applicant:
Virga Capital
Attn: Rob Lateiner
211 East Oak Street Suite 2B
Bozeman, MT 59715
Ph: 406-599-9419
Email: rob@virgacapital.com
Representative:
Intrinsik Architecture, Inc
Attn: Tyler Steinway
106 East Babcock Street, Suite 1A
Bozeman, MT 59715
Ph: 406-582-8988
Email: tsteinway@intrinsikarchitecture.com
Planning:
KTGY
Attn: Casey Roberts
17911 Von Karman Avenue, Suite 200
Irvine, CA 92614
Ph: 949-268-8545
Email: croberts@ktgy.com
Engineering:
Morrison – Maierle
Attn: Matt Ekstrom
2880 Technology Blvd W
Bozeman, MT 59718
Ph: 406-922-6784
Email: mekstrom@m-m.net
Landscape Architecture:
Design 5
Attn: Troy Scherer
111 North Tracy Ave
Bozeman, MT 59715
Ph: 406-587-4873
Email: troy@design5la.com
August 2024 Turnrow Master Site Plan RC 2 | 4
2. Project Narrative
Executive Summary
The project team is submitting a Master Site Plan for all of the land the Turnrow Development project.
This Master Site Plan will establish the framework for the development of the Turnrow Neighborhood.
Submitted concurrently with this application is a Preliminary Plat application to divide the 114.68-acre
parcel into 145 buildable lots, 2 park lot, 4 common open space lots, road Right-of-Way and 23
restricted future development lots also referred to as “remainder parcel” or “future phase”. It is
understood that further subdivision review will be required prior to these lots being developed.
Community Vision
Turnrow (“Project” or the “Development”) is a large undeveloped 114.68-acre parcel located in the
northwest side of Bozeman. The proposed project consists primarily of residential housing units (rental
and for sale product) with accompanying parkland and commercial uses to support the residential
neighborhood and adjacent areas. The location provides a unique opportunity for Bozeman to connect
this newly emerging northwestern side via a well-planned addition to the City. The subdivision will
support the area’s natural amenities to create a unique framework that fosters walkability and a sense
of place with a variety of offered housing options and supporting commercial spaces. Turnrow is
envisioned to have a diverse set of residents with a range of income and demographics to create an
energic and active community that also enhances the surrounding neighborhoods and developments.
Turnrow will be built in multiple phases over several years, based on market demand and logical
extension of supporting infrastructure. This Master Plan creates the framework for each phase within,
ensuring adequate access to vehicular, bicycle and pedestrian networks. Maintaining flexibility in the
plating process is important to the success of Turnrow. This flexibility will allow lots to respond to
current market conditions and provide a needed mix of housing and commercial uses. By putting a focus
August 2024 Turnrow Master Site Plan RC 2 | 5
on the parkland and shared community areas, Turnrow will create opportunities for the community to
gather and move through the site. The overall neighborhood’s design reflects the REMU zoning district’s
intent to “preserve and integrate the natural amenities into the development.”
Site Analysis
The Turnrow project site has several on-site challenges that had to be considered during the design
process. The results of these considerations are reflected in the overall design of the project. For
example, the street grid is slightly tilted to minimize street crossings and align with an existing high
pressure gas line. Additionally, the Ferguson Road alignment is shifted to the east to fulfill a requirement
from MDT. Lastly, in order to preserve maintain an existing irrigation stream/ditch located on the
property, the land associated with this ditch will be dedicated as park. This linear parkway will also serve
as the location of the required PROST/PRAT planned trail.
The overall vision for the parks system prioritizes green space and off-street trail connections
throughout the neighborhood and to adjacent communities. The proposed park amenities in this master
plan look to serve a wide range of users, with areas for passive recreation in the form of a hammock tree
grove and shade pavilions, to active recreation with a trail loop, bike pump track, sand volleyball courts,
and skate dots. This holistic vison for the parks system will create recreation opportunities for all types
of users.
Project History
This project formally began back in November of 2021 with the submittal of an Annexation and Initial
Zoning Application. The City Commission approved the Annexation and initial Zoning July 26, 2022,
authorizing the REMU Zoning designation. The ordinance formally adopting the Zoning was finalized in
December of 2023. Following the ZMA, Subdivision Pre-Application was submitted to outline the vision
and framework for phase 1 of this project.
August 2024 Turnrow Master Site Plan RC 2 | 6
3. Project Design
Land Use Analysis
Turnrow’s vision hinges on the underlying REMU zoning districted. The range of land uses permitted in
REMU allows for a dynamic mix of residential and commercial uses. The commercial/mixed uses are
anticipated to range from retail establishments to offices & daycares. The residential uses are
anticipated to range from single households to multifamily. This neighborhood is planned to be compact
and walkable, to promote and support an active lifestyle. There are several lots shown as restricted lots
and will be subject to a future subdivision and site plan review application, but the intension with all of
the restricted lots is that they will be residential in nature. All commercial mixed use areas are
envisioned to be along East Valley Center Road and Davis Lane.
As outlined in UDC section 38.310.060 non-residential uses must not exceed 30% of the total gross
building square footage of all the uses within the master planned area. The specific buildings designs are
in early stages and exact square footages are unknown, so for this reason a commercial tracking table
has been included as a separate appendix (Appendix U). This table will track the residential square
footage and the percentage of commercial built. It is envisioned that this will be monitored and
administered by the to be formed Property Owners Association.
Hypothetically, if you use the total land area designated for residential and mixed use in this Master Plan
and a minimum density of 12 units an acre (anticipated to be in the 12-30 U/A range) the number of
units created would be approximately 738 units. If each unit is a 600 SF, one bedroom unit, the square
footage created would be 442,872 SF. In this scenario the maximum amount of commercial area that
could be created is 132,861 SF which is significantly more than the commercial anticipated with this
REMU zoned area. These numbers will be accurately tracked in the commercial tracking table (Appendix
U).
The REMU zoning district envisions a balance of both residential at a variety of shapes and scales,
coupled with a small amount of neighborhood commercial. At this time the total number of dwelling
units is still in flux, but more concrete numbers will be submitted with each site plan application. the
goal is to achieve an average density between 12-25 DU/A. Please see the Land use table below:
Streetscape
Area (in Acres) Percent of Total
Area in Residential Lots 10.63 9.3%
Area in Commercial Lots 5.01 4.4%
Area In Restricted Lots 60.13 52.4%
Area in ROWs 26.27 22.9%
Area In Park 11.16 9.7%
Area in Open Space 0.85 0.7%
Area allocated for lift station 0.64 0.6%
Total Site Area 114.68 100%
August 2024 Turnrow Master Site Plan RC 2 | 7
The streetscape and block frontage will take the shape in variety of different ways in Turnrow. The
majority of the public streets will utilize the block frontage landscape with the exception of the
commercial lots. The commercial lots are proposed to be mixed to allow for the possibility of a more
storefront condition to arise. The buildable lots adjacent to parks will have a secondary “Park” block
frontage. These block frontages are depicted on the Community Design Framework Master Plan
included as Appendix C. These lots are somewhat large, so additional block frontages (Special
Residential Block Frontage) may be identified as each lot goes through site plan review.
Landscape
All landscaping will comply with the mandatory landscaping provision of the UDC, include the use of
drought tolerant plants, use of appropriately sized landscape plant material, coordination with utilities,
use of permanent irrigation and perpetual maintenance in a health condition. Furthermore, all required
ROW landscaping will comply with the UDC regulations. All mature trees and significant vegetation will
be preserved where possible, as they are a direct enhancement of the pedestrian streetscape
environment. All site development will go through a future site plan application to verify all on site
landscaping meets the intent of the UDC.
Parkland
The site’s location and proximity between I-90 and downtown make it an excellent location for
expanded park amenities and recreational opportunities to North Bozeman. The subdivision layout also
prioritizes green space and off-street trail connections throughout the neighborhood and to adjacent
communities. Turnrow is designed and envisioned from several key guiding ideas:
▪ Promote pedestrian circulation and walkability by providing connections between residential
neighborhoods and park / open space areas.
▪ Provide a variety of experiences and opportunities for recreation and play.
▪ Provide areas for passive and active recreation.
▪ Minimize hard or impervious surface.
▪ Allow the surrounding land uses, needs of existing users, and needs of proposed users to
▪ inform all park design and programming.
These guiding ideas translate into the dedication and development of 11.16 acres of parks & open
space. These spaces contain trails, playgrounds, manicured lawns, pavilions, and other park amenities.
The Cash-In-Lieu required will be proposed as Improvements-in-Lieu to the parks totaling 10.01 acres or
$1,130,075.31 worth of improvements.
Neighborhood center
The size and scale of the Property, along with the proposed zoning designations, allow for the creation
of a diverse and dynamic focal point for all the residents and adjacent neighborhoods. The primary
neighborhood centers will be the neighborhood park system. This larger park network is planned to
have a variety of amenities that will serve a wide audience.
The park area dedicated in phase 1 will aim to be the central focal point highlighting amenities centered
around all ages. It is proposed to have a wide range of both passive and active recreation opportunities.
Some of the proposed amenities are sand volleyball courts, cornhole boards, picnic pavilion area.
August 2024 Turnrow Master Site Plan RC 2 | 8
Future phases of Turnrow will meet the neighborhood center requirements through a future subdivision
application. It is anticipated that the park system will act as the neighborhood center for each phase.
This is documented in the Parks Master Plan on Page 8 (Appendix D).
Please see the Parks Master Plan Appendix D for more information about the phasing of park
improvements and amenities. The qualifying criteria for this location are described below:
38.410.020.A.1 - The proposed neighborhood center is within 600’ of the geographical center of the site.
38.410.020.A.2 – This park is proposed to be developed in one phase. each future phase will be within
600’ of an existing neighborhood center or will develop another neighborhood center.
38.410.020.A.3&4 - This neighborhood center has less than 100% frontage but more than 50%.
Maintenance of this neighborhood center is further described in the Parks Master Plan Appendix D.
38.410.020.A.5&6 - This neighborhood center is also being used to meet our parkland requirements for
the project. There is significant area in land used as open space with enhanced natural features and a
nice gathering space in the middle.
Infrastructure & Utilities
Common subdivision infrastructure improvements are critical to the Property utility, transportation, and
parkland networks. The construction of these improvements will be installed in accordance with a
subdivision application for each phase of development. These common subdivision improvements will
need to be installed or financially guaranteed prior to occupancy of any structures within each phase.
Furthermore, a request to construct site improvements including residential structures, concurrently
with these common subdivision infrastructure improvements is included in this application.
Due to the size of the first phase, it has been broken down into subphases to allow for the possibility of
concurrent construction (requested under Section 38.270.030.B.1.b.(2)) on the four lots in Block 1. All
the associated public improvements with phase 1.1 will be installed or financially guaranteed prior to
the occupancy of any structure in Block 1. Please see the specific list below for more information on
those improvements. Additionally, please see Appendix Q.2. Each lot in Block one will be subject to a
further site plan review and will be evaluated under that application for conformance with the UDC and
the approved MSP. The concurrent construction request letter has more information on this request.
Please see the list below for a more detailed outline of improvements to be installed in each phase. for a
visual representation please see the Concurrent Construction Infrastructure Phasing Plan (Appendix
Q.2).
Phase 1.1 Required Concurrent Construction Infrastructure & Snow Removal
Infrastructure which shall be completed prior to building permit issuance and would permit concurrent
construction on Phase 1.1, Block 1 include the following items. Please note that the items related to
water main and fire hydrant installations shall all be tested and activated prior to building permit
issuance. If interior utilities are activated by the City of Bozeman for concurrent construction purposes,
this shall not mean they have been deemed formally accepted by the City of Bozeman. The owner is
August 2024 Turnrow Master Site Plan RC 2 | 9
responsible for any damage that may occur to active utilities during concurrent construction activities
and prior to final acceptance by the City.
• East Valley Center Road
• East Valley Center Road improvements are being permitted with the Montana
Department of Transportation (MDT). These improvements include:
• Symmetrical expansion of the existing road to a 3-lane section from Quicksilver
Road to Davis Lane with tapers on each end to accommodate a southbound
turning lane onto Davis Lane and Quicksilver Road
• Installation and maintenance of temporary striping and signage to
accommodate the new configuration, at minimum
• Final striping shall be completed at the time of signal installation
• Installation of utility culverts for dry utilities and electrical conduit required for
the traffic signal
• MDT Access Permit for Quicksilver Road
• Additional approvals being coordinated:
• Traffic Signal
• Culverts
• Davis Lane
• Road Reconstruction
• Remove the existing Davis Lane section through the entire Turnrow Subdivision
east frontage (at minimum) and further south as required to blend design
grades.
• Construct Davis Lane to a 3-lane arterial section from East Valley Center Road
along the eastern boundary of the Subdivision, to accommodate a northbound
turning lane into Turnrow Trail
• Includes installation of road structure aggregates, curb, gutter, asphalt,
lighting
• Temporary signage and striping, at minimum, if final striping cannot be
performed
• A curbed taper section shall be designed to provide positive protection
for vehicles and direct traffic to the existing 2-lane county section. The
design meets design guidance per Section 9.2.2.4 from Chapter 9 of the
MDT Road Design Manual.
• A tapering section which matches the existing country road section shall be
installed south of the property to channelize traffic to the existing 2-lane section
at the southern boundary of the project near Westlake Road.
• Final signage and striping shall be installed prior to issuance of any building
permits for buildings within Phase 1.1.
• Utilities
• Storm Drain
• Install storm drain main within Davis Lane for capture and treatment of
stormwater
• Sewer
August 2024 Turnrow Master Site Plan RC 2 | 10
• Remove and replace the existing manhole and existing 15” stub to Block
1.
• The sewer main shall convey the estimated 2,265 gpm force
main discharge in addition to the upstream gravity sewer flows
from the properties to the south, as outlined in the figure from
the VCLS PER (drafted by HDR).
• Install 18” sewer main into Block 1 to the proposed outfall
manhole where gravity and force main discharge will be
combined.
• Water
• Install two live taps and extensions to the property
• Block 1 secondary feed loop (8”)
• Turnrow Trail water main (12”)
• Culverts
• Upsize the existing culvert for Cattail Creek to 60” embedded RCP
• Replace existing 30” culvert beneath Davis Lane for conveyance of
water from the existing irrigation ditch
• Extend the existing culvert beneath Valley Center to a point south of the
proposed 10’ shared use path
• Access Construction to Existing Roads
• The following accesses shall be constructed in their final configuration and surfacing to
comply with necessary stormwater permitting and ensure safety, traffic control, and fire
and emergency access to the site.
• This shall be completed beyond the curb return and a minimum of 25’ (or as
required by the City of Bozeman) beyond any depressed stormwater inlets
required for capture, conveyance, and treatment of stormwater originating
from these accesses
• Quicksilver Road
• Installation of access to Valley Center from Quicksilver Road
• Turnrow Trail
• Installation of access point to Davis Lane from Turnrow Trail
• Turnrow Trail Improvements
• The installation extents shall be from Davis Lane to the western boundary of Phase 1
• Road Improvements
• Includes installation of road structure aggregates
• Utilities
• Installation of water, sewer, & stormwater facilities within the right-of-
way
• Hydrants
• Installation of all hydrants along the road within the boundary shown
for Phase 1.1
• Gunsmoke Avenue Improvements
• The installation extents shall be from Turnrow Trail north and west to the boundaries of
Phase 1
August 2024 Turnrow Master Site Plan RC 2 | 11
• Road Improvements
• Includes installation of road structure aggregates
• Utilities
• Installation of water, sewer, & stormwater facilities within the right-of-
way
• Installation of run-on stormwater drain
• Hydrants
• Installation of all hydrants along the road within the boundary shown
for Phase 1.1
• Quicksilver Road Improvements
• The installation extents shall be from Turnrow Trail to the intersection with East Valley
Center Road
• Road Improvements
• Includes installation of road structure aggregates
• Utilities
• Installation of water, sewer, & stormwater facilities within the right-of-
way
• Includes force main extension beneath Gunsmoke Avenue
• Hydrants
• Installation of all hydrants along the road within the boundary shown
for Phase 1.1
• Additional Utility Improvements
• Block 1 Utilities
• The utilities below shall have adequate cover installed and be provided with
accessible route for maintenance, but shall not have final surfacing (curb,
gutter, asphalt, etc.)
• Secondary Water Supply Loop
• Constructing a secondary supply water main through the
proposed easement within Block 1
• Block 1 Hydrant
• Install the planned hydrant within Block 1
• Pressure Reducing Valves
• The following pressure reducing valves will be installed with Phase 1.1
• Primary PRV (near Turnrow Trail & Davis Lane intersection)
• Secondary PRV (near Quicksilver Road and East Valley Center Road
intersection)
• Stormwater Treatment Structures
• Stormtech Structures
• Treatment system U-1 shall be constructed which serves Quicksilver
Road between Gunsmoke Avenue and East Valley Center Lane
• Treatment system U-2 shall be constructed which serves Davis Lane and
a small portion of Block 2
• Surface Pond P-1
August 2024 Turnrow Master Site Plan RC 2 | 12
• Pond P-1 will be constructed as it provides stormwater treatment for
internal roads for Phases 1.1-1.4
• Snow Removal
• Snow removal shall be performed during the winter to provide access for fire
and emergency service vehicles.
• Two points of access to the subdivision shall be cleared of snow and any
main roads where fire hydrants are provided nearest to the lots
undergoing concurrent construction.
• This shall include on the eastern portion of Turnrow Trail
(between Quicksilver Rd and Davis Lane), Gunsmoke Avenue
(between Turnrow Trail and Quicksilver), and the northern
portion of Quicksilver Road (between Gunsmoke Avenue and
East Valley Center Road).
• Sewer Service Inspections
• Buildings within lots that are eligible for concurrent construction shall have a
sewer service video inspection completed by the owner of the building to verify
that no damage occurred during construction activities.
• The video shall be required to be submitted to the City of Bozeman, and
occupancy shall not be granted for the building until received and
approved by the City.
Phase 1.1 Subdivision Infrastructure Not Required for Concurrent Construction
The following infrastructure items, if not already completed, will be financially guaranteed through an
improvements agreement when applying for a building permit for commercial lots within Block 1.
• Block 1 Sewer Infrastructure
• The utilities below shall have adequate cover installed and be provided with accessible
route for maintenance, but shall not have final surfacing (curb, gutter, asphalt, etc.)
• Gravity Sewer Outfall
• Extend the existing 15” sanitary sewer gravity main through Block 1 for
conveyance of all sanitary sewer for Phase 1
• Install a manhole on this outfall line that will receive discharge from the
future Valley Center Lift Station
• Sewer Force Main
• The sewer force main shown through Block 1 shall be constructed for
future connection to the City of Bozeman’s force main from the Valley
Center Lift Station
• The force main shall be capped west of the Quicksilver Road and East Valley
Center Road intersection as shown
• Alleys 3.1 & 3.2
• Road Improvements
• Includes installation of road structure aggregates, concrete valley gutters (if
applicable), and asphalt per the proposed road section
• Utilities
• Installation of water, sewer, & stormwater facilities within the rights-of-way
August 2024 Turnrow Master Site Plan RC 2 | 13
• Alley 6.1 Improvements
• Road Improvements
• Includes installation of road structure aggregates and asphalt
• Park Improvements
• All park improvements within Park 1
• Shared Use Path Construction
• East Valley Center (Onsite)
• Installation of shared use path on East Valley Center Road from Quicksilver Road
to Davis Lane
• Includes installation of 60” RCP culvert for Cattail Creek
• East Valley Center (Offsite)
• Installation of shared use path east of Davis Lane to Westlake Road
• Davis Lane
• Installation of a 10’ shared use path along the western side of Davis Lane
• Final Surfacing of Roadways
• Includes curb, gutter, and asphalt installation within the following roadways:
• Turnrow Trail
• Gunsmoke Avenue
• Quicksilver Road
• Sidewalks
• Installation of all common open space and park frontage sidewalks
• Signing and Striping
• The final signing and striping may be deferred provided that temporary striping and
signage is provided and acceptable to the agencies having jurisdiction
• East Valley Center Road
• Final striping for East Valley Center shall be concurrent with the traffic
signal installation.
• Interior Roads
• Turnrow Trail
• Gunsmoke Avenue
• Quicksilver Road
• Street Lighting
• Street lighting proposed for Phase 1.1 shall not be required for concurrent construction
• Traffic Signal
• Final installation and activation of the proposed traffic signal at the Davis Lane and
Valley Center Road intersection shall be performed when warrants are met for the
Traffic Signal.
• Temporary signage and control shall be in place and maintained.
• Access Permit
• MDT Access Permit for Maintenace Access Permit to future Valley Center Lift Station
Phase 1.2
August 2024 Turnrow Master Site Plan RC 2 | 14
No infrastructure within Phase 1.2 is proposed to be deferred, or financially guaranteed for
concurrent construction activities. These items shall only be required for final plat of this phase.
• Gunsmoke Avenue Improvements
• The installation extents shall be from Turnrow Trail south to the boundary of Phase 1.2
• Road Improvements
• Includes installation of road structure aggregates, curb, gutter, asphalt,
lighting, and signage and striping
• Utilities
• Installation of water, sewer, & stormwater facilities within the right-of-
way
• Installation of run-on stormwater drain
• Hydrants
• Installation of all hydrants along the road within the boundary
shown for Phase 1.2
• Alleys 2.1, 2.2, and 2.3
• Road Improvements
• Includes installation of road structure aggregates, concrete valley gutters (if
applicable), and asphalt per the proposed road section
• Utilities
• Installation of water and facilities within the rights-of-way
• Installation of all common open space sidewalks, parking spaces, and other common
improvements
• Durango Lane Improvements
• The installation extents shall be from Gunsmoke Avenue to the western boundary of
Phase 1.2
• Road Improvements
• Includes installation of road structure aggregates, curb, gutter, asphalt,
lighting, and signage and striping
• Utilities
• Installation of water, sewer, & stormwater facilities within the right-of-
way
• Hydrants
• Installation of all hydrants along the road within the boundary
shown for Phase 1.2
• Alley 4.2
• Road Improvements
• Includes installation of road structure aggregates, concrete valley gutters (if
applicable), and asphalt per the proposed road section
• Installation of all common open space sidewalks, parking spaces, and other common
improvements.
Phase 1.3
No infrastructure proposed within Phase 1.3 is proposed to be deferred, or financially guaranteed for
concurrent construction activities. These items shall only be required for final plat of this phase.
• Durango Lane Improvements
August 2024 Turnrow Master Site Plan RC 2 | 15
• The installation extents shall be from the Phase 1.2 boundary to the western boundary
of Phase 1.3
• Road Improvements
• Includes installation of road structure aggregates, curb, gutter, asphalt,
lighting, and signage and striping
• Utilities
• Installation of water, sewer, & stormwater facilities within the right-of-
way
• Installation of temporary stormwater pond.
• Hydrants
• Installation of all hydrants along the road within the boundary
shown for Phase 1.3
• Alleys 4.1, 4.3, and 4.4
• Road Improvements
• Includes installation of road structure aggregates, concrete valley gutters (if
applicable), and asphalt per the proposed road section
• Utilities
• Installation of water and facilities within the rights-of-way
• Installation of water main and services through common open space lot.
• Installation of all common open space sidewalks, parking spaces, and other common
improvements
Phase 1.4
No infrastructure proposed within Phase 1.4 is proposed to be deferred, or financially guaranteed for
concurrent construction activities. These items shall only be required for final plat of this phase.
• Durango Lane Improvements
• The installation extents shall be from the Phase 1.3 boundary to the western boundary
of Phase 1.4
• Road Improvements
• Includes installation of road structure aggregates, curb, gutter, asphalt,
lighting, and signage and striping
• Utilities
• Installation of water, sewer, & stormwater facilities within the right-of-
way
• Installation of temporary stormwater pond
• Hydrants
• Installation of all hydrants along the road within the boundary
shown for Phase 1.4
• Alleys 5.1, 5.2, 5.3, 5.4, 5.5 and 5.6
• Road Improvements
• Includes installation of road structure aggregates, concrete valley gutters (if
applicable), and asphalt per the proposed road section
• Utilities
• Installation of water and facilities within the rights-of-way
August 2024 Turnrow Master Site Plan RC 2 | 16
• Installation of all common open space sidewalks, parking spaces, and other common
improvements
• Quicksilver Road Improvements
• The installation extents shall be from the southern property boundary to Turnrow Trail
• Road Improvements
• Includes installation of road structure aggregates, curb, gutter, asphalt,
lighting, and temporary signage and striping
• Utilities
• Installation of water, sewer, & stormwater facilities within the right-of-
way
• Hydrants
• Installation of all hydrants along the road within the boundary
shown for Phase 1.4
• Gunsmoke Avenue Improvements
• The installation extents shall be from the southern property boundary to Durango Lane
• Road Improvements
• Includes installation of road structure aggregates, curb, gutter, asphalt,
lighting, and signage and striping
• Utilities
• Installation of water, sewer, & stormwater facilities within the right-of-
way
• Installation of run-on stormwater drain
• Hydrants
• Installation of all hydrants along the road within the boundary
shown for Phase 1.4
• Westlake Road Improvements
• The installation extents shall be from Quicksilver Road to Gunsmoke Avenue.
• Road Improvements
• Includes installation of road structure aggregates, curb, gutter, asphalt,
lighting, and signage and striping
• Utilities
• Installation of water, sewer, & stormwater facilities within the right-of-
way
• Hydrants
• Installation of all hydrants along the road within the boundary
shown for Phase 1.4
-
All infrastructure design reports have also been included as Appendices (Appendix M-O).
Conformance with the REMU Supplimental Standards
The project site is entirely designated as REMU and as such please see the responses below to the
supplemental standards outlined for the REMU district.
August 2024 Turnrow Master Site Plan RC 2 | 17
A. The special standards set forth in this section are minimum standards for a development review
application. Standards not specifically addressed by this section are subject to the standards set
forth in this chapter.
Response: Understood.
B. Street and circulation standards.
1. The policies and standards of the city's long-range transportation plan apply to REMU districts.
New streets within REMU districts must be complete streets that accommodate pedestrians,
bicycles, buses, automobiles and wintertime snow storage, and work in concert with internal
property accesses and adjacent development to create a connected and vibrant public realm.
REMU street standards also include the following stipulations:
2. Natural storm drainage systems are allowed within street rights-of-way.
3. Boulevard strips and medians may incorporate natural drainage technologies.
4. Buildings must be oriented with front facades facing the street as specified in the block frontage
standards of division 38.510 of this chapter.
5. Shared drive accesses must be used to reduce the need for additional curb cuts, when feasible.
6. On-street parking should be maximized wherever feasible.
7. Front-loaded local streets. To ensure that front-loaded streets are community-oriented and
pedestrian-friendly, adjacent buildings, garages and drive aisles must comply with the following
specific standards of this chapter.
a. Section 38.350.070, parking and garages (for single to four-household dwellings).
b. Section 38.400.090.C.2.a, drive access requirements—Residential.
c. Division 38.510, block frontage standards (for all development except single to four-household
dwellings)
d. Section 38.540.010.A.4, stacking of off-street parking spaces.
e. Section 38.540.010.A.5, no parking permitted in required front or side setbacks.
f. Section 38.540.010.A.6, parking permitted in rear setbacks.
8. Woonerfs. Woonerfs, or streets where pedestrians and cyclists have priority over motorists, are
encouraged on private drive accesses or properties in the REMU district. Woonerfs may be
permitted on public local streets or alleys through the subdivision variance or PUD process.
9. Alleys. Alleys are encouraged, but not required, in the REMU district.
a. Apply standards of section 38.400.060.B (street improvement standards—alleys) where
applicable.
Response: The overall flow and circulation of this site has been carefully studied to help promote
the overall goals of this project. The goal of this project is to create a hub or gathering space for the
neighborhood, so access via all methods of transportation is important. Pedestrian pathways
surround the site on all sides and weave throughout the master plan. One major goal of this
neighborhood is to provide adequate off-street pathways to make the pedestrian experience more
enjoyable. These components will be further evaluated through each site plan application.
August 2024 Turnrow Master Site Plan RC 2 | 18
All buildings will be designed to front the street. The master plan for this neighborhood introduces a
variety of home styles including front loaded sing households, alley loaded single households, small
lot single households, townhouses/rowhouses and apartments.
C. Site planning and design element standards. See division 38.520 for applicable standards for all
development types, except single to four-household dwellings. See section 38.360.220 for applicable
standards for single to four-household dwellings.
Response: This is understood. All proposed buildings will be designed with these standards in mind.
These components will be verified in future site plan applications.
D. Open space standards. The REMU district is urban in nature. Public parks and recreational areas and
publicly accessible private open spaces are likewise expected to be urban in nature. This may include
elements such as plazas or other hardscaping, or landscaping with planters and furniture. Such areas
may be more concentrated in size and development than anticipated in a less urban setting. Public
spaces must be designed to facilitate distinct types of activities to encourage consistent human
presence and activity.
1. Public parks and recreational areas. The requirements of this section must give direction in the
development of park plans and the application of the standards of division 38.420 of this
chapter.
2. Publicly accessible private open space in commercial developments. See section 38.520.060 of
this chapter for the minimum amount and design of pedestrian-oriented open space.
3. Private residential open space. See section 38.520.060 of this chapter for the minimum amount
and design of usable residential open space.
Response: Open space is proposed to be provided in a variety of ways, both publicly and privately.
This application is to create a subdivision. Each of these components will be further evaluated in
future site plan applications. This project site has a great network of parks (to be built in phases), so
each home will be within a short walk. One of the goals of the park system is to create a series of
loop trails that allow residents to get around the neighborhood off the road.
E. Building standards.
1. See division 38.520 for applicable standards for all development types, except single to four-
household dwellings.
2. Parking structures must not have more than one two-way vehicle entrance or two one-way
vehicle entrances facing any public way. Fifty percent of a parking structure's ground floor linear
frontage along the primary street must be retail, commercial, office, civic, residential, or
live/work.
3. Building encroachments are permitted in accordance with section 38.350.050, subject to any
and all applicable International Building Codes.
4. All projects in the REMU district are exempt from the rear setback lot coverage requirements of
section 38.360.030.I.
August 2024 Turnrow Master Site Plan RC 2 | 19
Response: Understood. All future site plan applications will show each building complying with the
standards of 38.520. Furthermore, each application will be studied for any encroachments. This
application is to divide the land, so each of these building components will be further studied and
documented in future site plan applications.
F. Landscape and planting standards. Developments are subject to the landscaping standards in
division 38.550 of this chapter and the provisions herein. Table 38.330.020-1 lists the minimum
number of points needed for landscape plan approval for development types within REMU districts.
Response: This is understood. All the landscape plans will be designed with these requirements in
mind.
G. Lighting standards. See division 38.580 for applicable standards.
Response: This project has been designed to meet all the applicable street lighting standards for
each street. Additionally, each site plan application will be studied to show an adequate balance of
the need for light on the pathways and circulation corridors, and the desire to not create light
pollution.
4. Entitlement period
The project is to be constructed over a period of longer than 5 years. For a site of this size, construction
on every lot could take up to 10-15 years to complete. It is likely that extension to the Master Site Plan
will be sought, as necessary.
Following approval of the Master Site Plan, the applicant will submit subsequent subdivision applications
for each phase of the project. Following the approval of those phases site plans and sketch plans will be
developed for each lot. Each subsequent application shall be consistent with the approved Master Site
Plan and subject to the review criteria of Section 38.230.100.A BMC.
5. Phasing
The projected entitlement period for this Master Site Plan is five (5) years; however, based on the size
and scale of this project, extension(s) may be requested. Phasing beyond the first phase is still largely in
flux. It is understood per the development agreement with the city that the second phase will include
the land for the lift station and the parcel dedicated to city for affordable housing. Additionally, there
are several restricted lots which will be subject to further subdivision review. Sequencing of phases is
dependent on phasing of the overall development and subdivision review of individual planning areas.
6. Draft Design Guidelines
The design guidelines have been included herein as Appendix J.
7. Departures
At this time, no departures are requested. Each lot will be required to go through the site planning
process, at that time departures may also be requested.