ATTENDEES:David Tolliver and Kat Belendiuk 2023 August 7
Jesse Brown,Josh Aarestad –Hyalite Custom Building
Suzanne McGee,Marit Lueth –Thruline Partners
Attendees met at the Thruline Partners Office at 4 PM.Meeting intent was to review HCB agenda items
and update from site.TLP Agenda:kitchen layout options.
ACTION ITEMS:
●TLP:
○Submit structural details to city
○Contact surveyor for plat and utility maps,alert to curb stop
○Investigate with city the potential of utilizing both water lines
○Confirm lower level egress window sill heights 44”max.
○Provide window R.O.framing Thursday 8/10
○Provide site plan to K&D for negotiating purchase of sliver of adjacent lot
○Follow up with Geotech Engineer re:foundation waterproofing approach and sump pump
○Send K&D WOH bedroom light alternatives
●HCB:
○Review trusses and roof framing once exposed,attn:above dining and kitchen
○Begin working w/Xypex waterproofing rep.Derek
○Salvage concrete slabs and stone fountain pieces
○Look into sump pump performance and drainage solutions
SCHEDULE
●TLP,HCB w/Structural engineer 10 AM,8/10 @ BSB.
●Next OAC meeting 4 PM,8/14 @ BSB or TLP
●HCB to complete demo this week (8.7 -8.11)
●Plan to begin window RO Thursday 8/10
MEETING NOTES:
BASEMENT BEAM
●Demo revealed compromised joists and awkward,jogged beam condition at media room/rec.
room ceiling beams.
●K&D approved moving forward with recessing new beam solution in floor pack.
●Team will review on site with structural engineer 8/10.
THRULINE PARTNERS ||212 S WALLACE AVE STE 301 BOZEMAN MT 59715 ||(406)282-4411
thrulinepartners.com
1
Per Table 38.570.040-2. Entrance requires 2.5 - 5 foot candles
Product Lumens / Feet squared above pavement = Foot candles
800 lm / (6 ft) sq = 22.22 foot candles
(2) fixtures @ new entry exceed requirements