HomeMy WebLinkAbout24 - Amendments Amendment Number Unknown - Morrison-Maierle - Fire Station 1 Ice Well Relocation
First Amendment to Professional Services Agreement for the Fire Station 1 Ice Well Relocation Project
Page 1 of 2
FIRST AMENDMENT TO PROFESSIONAL SERVICES AGREEMENT
THIS FIRST AMENDMENT TO THE PROFESSIONAL SERVICES AGREEMENT FOR
Fire Station 1 Ice Well Relocation Project dated April 26, 2022 (the “Agreement”) is made and
entered into this _____ day of ____________, 2024, by and between the CITY OF BOZEMAN,
MONTANA, a self governing municipal corporation organized and existing under its Charter and
the laws of the State of Montana, 121 North Rouse Street, Bozeman, Montana, with a mailing
address of PO Box 1230, Bozeman, MT 59771, hereinafter referred to as “City,” and
_________________, hereinafter referred to as “Contractor.”
In consideration of the mutual covenants and agreements herein contained, the receipt and
sufficiency whereof being hereby acknowledged, the parties hereto agree to amend the Agreement
as follows:
1. Scope of Services. Section 3 of the Agreement is amended to include the scope of services
attached to this amendment as Exhibit 1A. The services included in Exhibit 1A are in
addition to and supplement the Scope of Services in the Original Agreement.
2. Payment. Section 4 of the Agreement is amended to include payment for the scope of
services attached to this amendment as Exhibit 1A. Payment for these services shall not
exceed the amount of Sixty-Seven Thousand Three Hundred and Seventy-Nine Dollars
& 42/100ths ($67,379.42) and will be paid based on time and materials at the rates included
in Exhibit 1A. The amount is in addition to the Original Agreement amount.
3. Agreement still valid. All remaining terms and provisions of the Agreement remain valid.
**** END OF AGREEMENT EXCEPT FOR SIGNATURES ****
DocuSign Envelope ID: 1D506BA5-D5F3-4FCC-8651-D9A6C3FF89C4
Morrison-Maierle, Inc.
6th February
First Amendment to Professional Services Agreement for the Fire Station 1 Ice Well Relocation Project
Page 2 of 2
IN WITNESS WHEREOF, the parties hereto have executed this instrument the day and
year first above written.
CITY OF BOZEMAN, MONTANA MORRISON-MAIERLE, INC.
By________________________________ By_____________________________
Jeff Mihelich, City Manager Print Name:
Title:
APPROVED AS TO FORM
By_______________________________
Greg Sullivan, Bozeman City Attorney
DocuSign Envelope ID: 1D506BA5-D5F3-4FCC-8651-D9A6C3FF89C4
Vice President
Travis EickmanXXXXXXXXXXXXXXXXXXXXXXXXXXXX
Chuck Winn, Acting City Manager
EXHIBIT 1A
Ice Control Well Project
Scope of Work – Engineering Services
December 19, 2023
The project is for engineering services related to construction oversight of the replacement Ice
Control Well located as shown in the project documents. This includes oversight and testing of
the well, water line installation, electrical service/controls and rebuild of the retaining wall. A
replacement well notice will be filed with the Department of Natural Resources and Conservation
(DNRC) upon project completion.
Work will be completed based on actual effort spend on the work based on the hourly rate
schedule and expense schedule attached to and made part of this Exhibit A. The total estimated
compensation for the work is $67,379.42 which is a combination of amended tasks (6a) –
($8,608.92) and future work as identified on the fee estimate that is attached to and made part of
this Exhibit A1 ($58,770.50).
Task 1a – Project management
• Project management
• Progress meetings
• Construction meetings
• DNRC coordination
• NW Energy Coordination
Task 6a – Electrical redesign and Well abandonment task completed to date that was out of
scope. Total out of scope effort is $8,608.92.
• Letter from 10/27/2022 on abandonment work completed - $5,666.92
• Additional Electrical Engineering re-design due to design changes from Northwest Energy
- $2,942
Task 7 - Well Construction
This task includes services during well construction. These tasks include:
• Contractor coordination and scheduling prior to arrival on-site.
• Well drilling oversight to provide final well design will include:
o Well construction material oversight
o Formation Sampling
o Preparation of lithologic log
o Identify water bearing intervals
o Preliminary well design
o Sediment control plan oversight
• Provide a final well design to the contractor with recommended screen intervals.
• Oversight of screen install and well development including oversight of discharge water
plan.
DocuSign Envelope ID: 1D506BA5-D5F3-4FCC-8651-D9A6C3FF89C4
• Aquifer test oversight will include a six hour well performance test (stepped rate test)
followed by a 24-hour minimum constant rate test.
• Aquifer test analysis to determine final pumping rate and potential effects to adjacent Ice
Control Wells.
Task 8 – Civil Construction
This task includes services during civil construction including inspection of waterline, power and
reclamation of the site including final grading and paving if necessary. Compaction testing
services will also be provided.
Task 9 – Final Project Closeout
This task will provide a final well completion and testing memorandum, as-builts, O&M Manual
and filing of DNRC form 643. Preparation of beneficial use or change authorization application is
not anticipated for this project and is outside of the current scope.
Quality Assurance
Quality assurance budget for senior staff is provided for review of the work products in all work
phases.
END
DocuSign Envelope ID: 1D506BA5-D5F3-4FCC-8651-D9A6C3FF89C4
City of Bozeman - Ice Control ProjectDescription Units Rate Task 1a Task 2 Task 3 Task 4 Task 5 Task 6a Task 7 Task 8 Task 9 Total Hours Total Cost ($)LaborProject ManagerPat EllerHrs $202.00 2480 4 20 128 $25,856.00Staff GeologistDean Snyder Hrs $143.0020 24 44 $6,292.00Senior EngineerJames Nickleson Hrs $257.00 82 4 14 $3,598.00Design EngineerBJ Cope Hrs $216.00 88 20 20 56 $12,096.00Senior ScientestChristine Pearcy Hrs $186.0016 16 $2,976.00Electrical EngineerRyan Maroney Hrs $216.00 24 8 4 18 $3,888.00SurveyingJon Wilkensen Hrs $164.004 4 8 $1,312.00DraftsmanHrs $133.008 8 $1,064.00SecretarySecretary II Hrs $90.000 $0.00Subtotal, Labor 4200000132 38 80$57,082.00Materials Reports/Specifications Pg $0.100 $0.00Color Photos Ea. $0.550 $0.00Travel Mileage Mile $0.75 50100 100 250 $188.50Lodging LS $150.000 $0.00Per Diem LS $52.000 $0.00EquipmentPump Day $75.000 $0.00Hermit Week $150.000 $0.00Minitroll/Leveltroll Week $250.002 2 $500.00Sampling & AnalysisSeive Analysis - Lab Ea. $100.0010 10 $1,000.00Water Quality Ea. $800.000 $0.00Description Units Rate Task 1 Task 2 Task 3 Task 4 Task 5 Task 6 Task 7 Task 8 Task 9 Total Cost ($)TOTAL$9,101.70 $0.00 $0.00 $0.00 $0.00$0.00 $26,819.40 $8,101.40 $14,748.00$58,770.50h:\water resources\3017\031\xost estimate12/19/2023 11:12 AMDocuSign Envelope ID: 1D506BA5-D5F3-4FCC-8651-D9A6C3FF89C4
Standard Billling Rate Schedule
Effective Thru
June 30, 2024
Standard Rate Overtime Rate
Engineer Supervising Engineer V $287.00 $287.00Supervising Engineer IV $280.00 $280.00Supervising Engineer III $257.00 $257.00Supervising Engineer II $246.00 $246.00Supervising Engineer I $233.00 $233.00Senior Engineer II $216.00 $216.00Senior Engineer I $197.00 $197.00Design Engineer II $186.00 $186.00Design Engineer I $172.00 $172.00Engineer Intern II $142.00 $142.00Engineer Intern I $125.00 $125.00
Planner Supervising Senior Planner $225.00 $225.00Senior Planner $195.00 $195.00Planner III $151.00 $151.00Planner II $138.00 $138.00Planner I $121.00 $121.00
Scientist Supervising Environmental Scientist $234.00 $234.00Environmental Scientist III $186.00 $186.00Environmental Scientist II $142.00 $142.00Environmental Scientist I $121.00 $121.00Environmental Technician $106.00 $106.00Supervising Geologist $265.00 $265.00Senior Geologist $222.00 $222.00Geologist III $202.00 $202.00Geologist II $164.00 $164.00Geologist I $140.00 $140.00
Designer and Technician Senior Communications Designer $239.00 $239.00Communications Designer $125.00 $125.00CAD Designer III $164.00 $164.00CAD Designer II $143.00 $143.00CAD Designer I $133.00 $199.50CAD Tech III $130.00 $195.00CAD Tech II $111.00 $166.50CAD Tech I $98.00 $147.00Senior Engineering Designer $183.00 $183.00Engineering Designer $125.00 $125.00
Resident Project Representative Senior Resident Project Representative $185.00 $185.00Resident Project Representative IV $175.00 $175.00Resident Project Representative III $166.00 $166.00Resident Project Representative II $140.00 $210.00Resident Project Representative I $126.00 $189.00
Administrative Administrative Manager $126.00 $126.00Administrative Coordinator III $116.00 $116.00Administrative Coordinator II $110.00 $165.00Administrative Coordinator I $90.00 $135.00Project Coordinator III $113.00 $113.00Project Coordinator II $102.00 $153.00Project Coordinator I $92.00 $138.00Technical Intern $85.00 $127.50Senior Communication Specialist $134.00 $134.00Graphic Designer $106.00 $106.00Health & Safety Administrator $140.00 $140.00
Survey Senior Survey Manager $226.00 $226.00Survey Manager $176.00 $176.00Land Surveyor IV $170.00 $170.00Land Surveyor III $164.00 $164.00Land Surveyor II $148.00 $148.00Land Surveyor I $134.00 $134.00Remote Sensing Specialist II $149.00 $149.00Remote Sensing Specialist I $139.00 $139.00Survey Technician IV $129.00 $129.00Survey Technician III $114.00 $171.00Survey Technician II $98.00 $147.00Survey Technician I $84.00 $126.00
Expert Witness
Recommended rate for expert witness services (depositions and/or time in court) is charged at an
hourly rate of 150-200% of the standard billing rate.
12/14/2023
DocuSign Envelope ID: 1D506BA5-D5F3-4FCC-8651-D9A6C3FF89C4