HomeMy WebLinkAbout012 - NPWH - DEQ Email Solvent Site Source Area1
Bryana Zuiderweg
From:Fry, Kate <kfry@mt.gov>
Sent:Thursday, July 13, 2023 9:06 AM
To:Mike Russell; Bryana Zuiderweg
Cc:Jim Sullivan; Christopherson, Sarah
Subject:RE: Construction Requirements - Solvent Site Source Area - Groundwater data attached
Hi Bryana and Mike,
Thank you for reaching out about the Bozeman Solvent Site and providing the additional
information. Construction requirements related to the Bozeman Solvent Site in this area are not
identified in the Record of Decision (DEQ 2011).
Please let me know if you have questions.
Regards,
Kate
Kate Fry | Senior Project Officer
Superfund, AML, and Construction Bureau
Waste Management and Remediation Division
Montana Department of Environmental Quality
Office: 406-444-6426
From: Mike Russell <Mike.Russell@djanda.com>
Sent: Thursday, July 13, 2023 8:37 AM
To: Fry, Kate <kfry@mt.gov>; jsullivan@tasman-geo.com
Cc: Bryana Zuiderweg <Bryana.Zuiderweg@djanda.com>
Subject: [EXTERNAL] RE: Construction Requirements - Solvent Site Source Area - Groundwater data attached
Just a teensy bit of data to add to Bryana’s excellent email. I’ve attached the groundwater monitoring that has been
taken this spring (during a very wet spring with a year with a strong snowpack. Neither our stormwater (nor other
utilities) nor our foundation excavations are anticipated to go as deep as groundwater has been found (about ~12-13
feet deep… which should represent peak groundwater). To give some perspective, we believe our utilities will be about
6-7’.
CAUTION: This email originated from outside the organization. Do not click links or open attachments
unless you recognize the sender and know the content is safe.
2
[djanda.com]
Mike Russell, PE, MBA
Senior Project Manager at DJ&A
Phone: 406.200.9768 Mobile: 801.712.7396
Email: mike.russell@djanda.com
[linkedin.com] [facebook.com]
From: Bryana Zuiderweg <Bryana.Zuiderweg@djanda.com>
Sent: Thursday, July 13, 2023 8:30 AM
To: Fry, Kate <kfry@mt.gov>; jsullivan@tasman-geo.com
Cc: Mike Russell <Mike.Russell@djanda.com>
Subject: RE: Construction Requirements - Solvent Site Source Area
Hi Kate and Jim,
I am following up on a proposed commercial development (hotel) project in Bozeman. The City requires us to contact
you both for construction requirements regarding construction within the solvent site source area. Attached is the figure
Kate previously sent of the DNRC Controlled Groundwater Area. I added a red rectangle to the figure in cell B7 that
roughly represents the development location located at the NW corner of the Mandeville Lane and Wheat Drive
intersection. Since I last reached out a few months ago, we have confirmed that construction for this project is not
anticipated to require dewatering, per recent groundwater monitoring investigations and further design development.
If we are not anticipating needing a dewatering permit for construction of this project, I wanted to confirm there are no
further construction requirements that we need to be considering for this project to satisfy City and State requirements
related to the solvent site source area.
Thank you,
Bryana
[nam10.safelinks.protection.outlook.com]
Bryana Zuiderweg, PE
Project Engineer at DJ&A
Phone: 720.768.6385 Mobile: 614.570.9995
Email: bryana.zuiderweg@djanda.com
[nam10.safelinks.protection.outlook.com]