July 31, 2023 – Transmitted via Project Dox Only
Tim Stefan
Stefan Associates
1209.5 East Main Street
Bozeman, MT 59715
RE: Gallatin County Regional Park Maintenance Shed Site Plan, Application 22331
Dear Applicant,
The Site Plan for the above-referenced project has received Conditional Approval. Please
review all Conditions of Approval & Code Requirements as listed in the Staff Report and copy
and pasted below. Once all Conditions have been satisfied, you will receive Final Plans Approval
and the submittal will be batch stamped as the approved documents and drawings.
As the applicant, you must comply with all provisions of the Bozeman Municipal Code, which
are applicable to this project. All unmet code provisions, or code provisions that are not
specifically listed as conditions of approval, does not, in any way, create a waiver or other
relaxation of the lawful requirements of the Bozeman Municipal Code or state law.
CODE REQUIREMENTS
1. The Applicant is advised that unmet code provisions or code provisions that are not
specifically listed as conditions of approval does not, in any way, create a waiver or
other relaxation of the lawful requirements of the Bozeman Municipal Code (BMC) or
State law.
2. Pursuant to section 38.570, BMC. Lighting. Exterior wall lighting must meet all
applicable standards for intensity, color, cut-off, aiming, and other applicable standards.
Prior to final occupancy a finalized specification sheet detailing building-mounted
lighting (supports, cutoff, footcandles, temperature) 38.570.040.B must be submitted to
the Planning Department for review and approval.
Future Impact Fees - Building permit applications will require payment of the required
transportation, water, sewer and fire impact fees according to the City of Bozeman adopted
impact fee schedule in place at the time of building permit issuance. If you desire an estimate of
the required impact fees according to current rates please contact the Department of Community
Development.
Please be informed that ANY changes from the final plan or final building elevations will
need to be reviewed by the Department of Community Development. This Director of
Community Development project decision may be appealed by filing a notice of appeal with the
Clerk of the Commission for the City of Bozeman, within ten working days after the date of
approval as evidenced by the Director’s signature, by following the procedures of Section
38.250.030, BMC.
If you have questions, or if the Department of Community Development can be of further
assistance, please do not hesitate to contact myself or your development review coordinator.
Regards,
Tom Rogers, Senior Planner