HomeMy WebLinkAbout21341 Staff Report Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 1 of 23
Application No. 21341 Type Site Plan for one of two buildable lots within the 6.23-acre Preliminary Plat of the
Bozeman Gateway Subdivision PUD Phase 5. Lot 1 is to be developed as a 113-
room hotel. Abutting Open Space Lots OS-1 and OS-1A must be improved with
the development of the hotel on Lot 1. Lot 2 to remain undeveloped at this time.
Project Name The Everhome Hotel.
Summary This is a Site Plan for the 2.97-acre Lot 1 and 1.34-acres of Lots OS-1 and OS-1A of the 6.23-acre
Preliminary Plat of the Bozeman Gateway Subdivision PUD Phase 5 subdivision that lies within the
Bozeman Gateway Planned Unit Development (PUD) area. The property owner/Applicant
submitted a preliminary plat application to create five lots that includes two developable lots and
three open space lots.
Phase 5 is part of the Bozeman Gateway Planned Unit Development (PUD) Master Plan that
consists of a 72-acre mixed-use development. This Phase 5 is the final phase of the Bozeman
Gateway development. It is located directly south and west of the Huffine Lane/Fallon Avenue
intersection and is north of Technology Boulevard West. Phase 1, 2, and 3 are currently being
development in accordance with the PUD. Phase 4 received preliminary plat approval on July 20,
2021. Phase 5 land is undeveloped. Full development of Phase 5 would include two commercial
buildings and a 2.85-acre open space corridor that runs north-south along the Site’s eastern edge.
Two water bodies border the hotel Site: (1) A tributary to the Baxter Border Ditch (irrigation ditch)
that flows south to north along the west side of Fowler Avenue; and (2) a portion of the Farmers’
Canal irrigation ditch that borders its southern boundary. As irrigation ditches, these two water
bodies do not meet the definition of a watercourse per the Bozeman Municipal Code (BMC) Section
38.700.210.
The 2.97-acre Lot 1 Site Plan would be for a 4-story, 61-feet tall, 62,000 gross square foot (gsf),
113-guest room hotel with associated parking, landscaping and open space. The approved
Bozeman Gateway PUD Master Plan, which includes this Phase 5 Site, requires the three abutting
open space lots, Lots OS-1, OS-1A and OS-1B, to be improved concurrently with the development
of Lots 1 and 2. Lots OS-1 and OS-1A are to be improved with the Lot 1 hotel Site (see Condition
of Approval No. 9). The remaining Lot OS-1B would be improved with the development of Lot 2. A
proposal for development of Lot 2 would require a separate Site Plan application per Condition No.
3 below.
This application evaluates the development of the hotel on Lot 1 and the landscape plans of
the abutting open space Lots OS-1 and OS-1A. Accessory parking, landscaping and open
space for the Lot 1 hotel are also addressed herein.
The Bozeman Gateway PUD Phase 5 Subdivision Preliminary Plat was conditionally approved
in August 2021 and the Findings of Fact document was signed on September 14, 2021. A
Final Plat for this subdivision has not yet been submittal for review. Pursuant to BMC
38.230.140.D, a Final Plat for this subdivision must be approved within one year of the signing
of the Preliminary Plat Finding of Fact, which was September 14, 2021. Condition No. 2 below
requires the Final Plat to be approved and recorded with the Gallatin County Clerk and
Recorder prior to final approval of this hotel and open space Site Plan.
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 2 of 23
Zoning B-2 with
Bozeman
Gateway
PUD
Growth Policy Regional Commercial & Services Parcel Size 2.97-ac Lot 1 buildable
area & 1.34-ac
combined open space
lots OS-1 and OS-1A.
Overlay District(s) Bozeman Gateway Planned Unit Development (PUD); Sanitary sewer Payback Area; Street Lighting
Improvement District;
Street Address Unaddressed property located at the southwest corner of Huffine Lane and Fowler Avenue.
Legal Description Currently: Tract 2A of the Amended Plat of West College Minor Subdivision No. 195A. The hotel
Site is proposed to be subdivided as Lots 1 and Open Space Lots OS-1 and OS-1A of the
Bozeman Gateway Subdivision PUD Phase 5 subdivision situated in the NW ¼ of S14, T5 S, R5
E, PPM, City of Bozeman, Gallatin County, Montana
Owner Ted Mitchell, Mitchell Development Group, LLC
Applicant Ted Mitchell, Mitchell Development Group, LLC
Representative Jim Ullman, Morrison-Maierle
Staff Planner Susana Montana Engineer Mikaela Shultz
Noticing Public Comment Period Site Posted Adjacent Owners Mailed Newspaper Legal Ad
June 3 to June 17, 2022 June 3, 2022 June 3, 2022 NA
Advisory Boards Board Date Recommendation
Development Review
Committee (DRC)
The application is adequate, conforms to
standards, and is sufficient for approval with
conditions and code provisions as noted below.
Community Development
Board acting as the Design
Review Board
NA The May 2021 PUD Modification (Project #
20051) exempts any development proposal within
the Bozeman Gateway PUD area from review by
the Design Review Board (now Community
Development Board).
Recommendation The application is adequate, conforms to standards, and is sufficient for approval with conditions and
code provisions as noted below.
Decision Authority Director of Community Development Date
Full application and file of record: Community Development Department, 20 E. Olive St., Bozeman, MT 59715
After the public comment period is closed, the Director of Community Development would review the DRC recommendation,
any public comment, and staff evaluations and would make the final decision on this application.
FINDINGS OF FACT AND APPEAL PROVISIONS CERTIFICATE
A) PURSUANT to Chapter 38, Article 2, Bozeman Municipal Code (BMC), and other applicable sections of Ch.38, BMC, public
notice was given, opportunity to submit comment was provided to affected parties, and a review of the Site Plan described in
this report was conducted. The Applicant proposed to the City a Site Plan to construct a hotel plus associated parking,
landscaping and open space areas for a 2.97-acre Lot 1 Site. The development of the hotel Lot 1 Site requires the concurrent
development of the abutting 1.34-acre open space lots OS-1 and OS-1A. The purposes of the Site Plan review was to consider
all relevant evidence relating to public health, safety, welfare, and the other purposes of Ch. 38, BMC; to evaluate the proposal
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 3 of 23
against the criteria of Sec. 38.230.100 BMC, and the standards of Ch. 38, BMC; and to determine whether the application
should be approved, conditionally approved, or denied.
B) It appeared to the Director that all parties and the public wishing to examine the proposed Site Plan and offer comment were
provided the opportunity to do so. After receiving the recommendation of the relevant advisory bodies established by Ch. 38,
Art. 210, BMC, and considering all matters of record presented with the application and during the public comment period
defined by Ch. 38, BMC, the Director has found that the proposed Site Plan would comply with the requirements of the BMC if
certain conditions were imposed. Therefore, being fully advised of all matters having come before them regarding this
application, the Director makes the following decision.
C) The Site Plan has been found to meet the criteria of Ch. 38, BMC, and is therefore approved, subject to the conditions listed
in this report and the correction of any elements not in conformance with the standards of the Title. The evidence contained in
the submittal materials, advisory body review, public testimony, and this report, justifies the conditions imposed on this
development to ensure that the Site Plan complies with all applicable regulations, and all applicable criteria of Ch. 38, BMC.
On this 28th day of June, 2022, Anna Bentley, Interim Director/Deputy Director of Community Development, approved with
conditions this Site Plan for and on behalf of the City of Bozeman as authorized by Sec. 38.200.010, BMC.
D) This Director of Community Development’s project decision may be appealed by filing a documented appeal with and paying
an appeal fee to the Clerk of the Commission for the City of Bozeman within 10 working days after the date of the final decision
as evidenced by the Director’s signature, following the procedures of Sec. 38.250.030, BMC.
DIRECTOR OF COMMUNITY DEVELOPMENT
CONDITIONS OF APPROVAL
Please note that these conditions are in addition to any required code provisions identified in this report. Additional
conditions of approval and code corrections may be required and would be included with the final report provided to
the Director of Community Development.
1. The Applicant is advised that unmet code provisions, or code provisions that are not specifically listed as conditions
of approval, does not, in any way, create a waiver or other relaxation of the lawful requirements of the Bozeman
Municipal Code (BMC) or state law.
2. This Site Plan is not approved until the Bozeman Gateway Subdivision PUD Phase 5 Final Plat is approved and
recorded with the Gallatin County Clerk and Recorder and a digital copy of the recorded plat is delivered to the
Director of Community Development.
3. The details of proposed development of Lot 2 within this Phase 5 PUD subdivision have not been
submitted with this application. Any development of Lot 2 requires a subsequent Site Plan submittal and
review of those plans within one year of approval of this Site Plan. The Site Plan for Lot 2 shall include
details of improvements to the adjacent open space Lot OS-1B.
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 4 of 23
4. Prior to final Site Plan approval, a 10-foot utility easement must be recorded with the County Clerk and Recorder
for the electrical line from Technology Boulevard West to a new transformer. The Applicant must coordinate with
Northwestern Energy on the transformer location (located at least 10 feet from the building).
5. Prior to final Site Plan approval, a public access easement must be recorded for the proposed sidewalk outside
the right-of-way on the west side of Fowler Ave extending through the OS-1 lot to the hotel Lot 1.
6. Prior to final Site Plan approval, a revised Traffic Impact Study addressing the hotel development on the Phase 5
Lot 1 must be provided to and accepted by the City Engineer.
7. Prior to Site Plan approval, the Cash-in-lieu of water rights (CILW) must be paid to the City.
8. Prior to final Site Plan approval, per City of Bozeman Resolution 5076, Policy 1, the Applicant must provide and
file with the County Clerk and Recorder's office executed Waivers of Right to Protest Creation of Special
Improvement Districts (SID’s) on City standard form for the following:
a. Street improvements to Fowler Avenue between West Garfield Street and West Babcock Street including
lighting, signalization, paving, curb/gutter, sidewalk, and storm drainage.
b. Street improvements to Huffine Lane between 19th Avenue and Cottonwood Road including lighting,
signalization, paving, curb/gutter, sidewalk, and storm drainage.
c. Street improvements to West Garfield Street between 19th Avenue and Fowler Avenue including lighting,
signalization, paving, curb/gutter, sidewalk, and storm drainage.
d. Street improvements to West College Street between 19th Avenue and Huffine Lane including lighting,
signalization, paving, curb/gutter, sidewalk, and storm drainage.
e. Intersection improvements at Huffine Lane and Fowler Avenue including lighting, signalization/channelization,
paving, curb/gutter, sidewalk, and storm drainage.
f. Intersection improvements at West Garfield Street and Fowler Avenue including lighting,
signalization/channelization, paving, curb/gutter, sidewalk, and storm drainage.
g. Intersection improvements at Huffine Lane and West College Street including lighting,
signalization/channelization, paving, curb/gutter, sidewalk, and storm drainage.
h. Intersection improvements at Huffine Lane and Cottonwood Road including lighting,
signalization/channelization, paving, curb/gutter, sidewalk, and storm drainage.
i. Intersection improvements at Fowler Avenue and Babcock Street including lighting, signalization/channelization,
paving, curb/gutter, sidewalk, and storm drainage.
The document filed must specify that in the event an SID is not utilized for the completion of these improvements, the
developer agrees to participate in an alternate financing method for the completion of the improvements on a fair share,
proportionate basis as determined by square footage of property, taxable valuation of the property, traffic
contribution from the development, or a combination thereof. The Applicant must provide a copy of the filed SID
waiver to the City Engineer prior to final Site Plan approval.
9. The open space Lots OS-1 and OS-1A must be improved concurrently with the development of Lot 1. A Certificate of
Occupancy for the hotel on Lot 1 shall not be issued until the improvements to those open space lots are completed.
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 5 of 23
CODE PROVISION
1. Per BMC 38.100.080 and 38.200.110, the proposed project shall be completed as approved and conditioned in
the approved Site Plan. Any modifications to the final approved submittals and approved application materials shall
invalidate the project's legitimacy, unless the Applicant submits the proposed modifications for review and
approval by the Director of the Community Development Department and this approval is granted prior to undertaking
said modifications. The only exception to this law is repair.
Figure 1: Location and Zoning Map; PUD area shown in red; Phase 5 shown in yellow.
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 6 of 23
Figure 2: Bozeman Gateway Master Site Plan/PUD with Phase 5 Lot 1 hotel Site highlighted
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 7 of 23
Figure 3: Bozeman Gateway Phase 5 Preliminary Plat (Project # 20094)
[Final Plat not yet submitted]
Lot 1
Lot 2
Lot OS-1
Lot OS-1A
Lot OS-1B
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 8 of 23
Figure 4: Baxter Border Ditch on Site (view east from Site)
Figure 5: Baxter Border Ditch through the Site
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 9 of 23
Figure 6: Farmers Canal non-US-jurisdictional watercourse (irrigation ditch) south of Site
Farmers’ Canal
Baxter Border Ditch
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 10 of 23
Figure 7: Lots 1, OS-1 and OS-1A Site Plan
Lot OS-1
Lot OS-1A
Lot 1
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 11 of 23
Figure 8: Lot 1 hotel Site Plan
Lot A hotel
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 12 of 23
Figure 9: Hotel—southeast corner at Huffine Lane addressing High Intensity Street Corner Block Frontage
Figure 10: Hotel—facing Fowler Avenue
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 13 of 23
Figure 11: Shared parking area
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 14 of 23
ANALYSIS and findings
Analysis and resulting recommendations based on the entirety of the application materials, municipal codes, standards,
plans, public comment, and all other materials available during the review period. Collectively this information is the record
of the review. The analysis in this report is a summary of the completed review.
Plan Review, Section 38.230.100, BMC
In considering applications for plan approval under this title, the Director of Community Development shall consider the
following:
1. Conformance with Article 1 - Consistency with the City’s adopted Growth
Policy 38.100.040.D
Meets Code?
Growth Policy
Land Use
Regional Commercial and Services Yes
Zoning B-2 with the Bozeman Gateway PUD overlay Yes
Comments: Purpose of the Regional Commercial and Services land use designation:
“Regionally significant developments in this land use category may be developed with physically large and
economically prominent facilities requiring substantial infrastructure and location near significant transportation
facilities. Due to the scale of these developments, location, and transition between lower density uses is
important. Residential space should be located above the first floor to maintain land availability for necessary
services. Development within this category needs well-integrated utilities, transportation, and open space
networks that encourage pedestrian activity and provide ready-access within and adjacent to development. Large
community scale areas in this land use category are generally 75 acres or larger and are activity centers for several
surrounding square miles. These are intended to service the overall community as well as adjacent neighborhoods
and are typically distributed by a one-to two-mile separation.”
The Bozeman Gateway PUD land area was designated “Regional Commercial and Services” Future Land Use Designation
with the update in the 2020 Community Plan. The proposed hotel conforms to this designation.
The B-2 District is an implementing zoning district of the Regional Commercial and Services future land use designation. The
hotel use is a principal permitted use in the B-2 zone as well as in the Bozeman Gateway PUD designation. Relevant
Community Plan/Growth Policies are noted below for this development.
N-1.11 Enable a gradual and predictable increase in density in developed areas over time.
THEME 3 | GOALS, OBJECTIVES, AND ACTIONS
Goal DCD-1: Support urban development within the City.
DCD-1.1 Evaluate alternatives for more intensive development in proximity to high visibility corners, services and
parks.
DCD-1.12: Prioritize the acquisition and/or preservation of open space that supports community
values, addresses gaps in functionality and needs, and does not impede development of the community.
Goal DCD-2: Encourage growth throughout the City, while enhancing the pattern of community development
oriented on centers of employment and activity. Support an increase in development intensity within developed
areas.
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 15 of 23
DCD-2.2 Support higher density development along main corridors and at high visibility street
corners to accommodate population growth and support businesses.
Goal EPO-2: Work to ensure that development is responsive to natural features.
EPO-2.1 Where appropriate, activate connections to waterways by creating locations, adjacent trails, and
amenities encouraging people to access them.
EPO-2.3 Identify, prioritize, and preserve key wildlife habitat and corridors.
2. Conformance with Article 1 - All other applicable laws, ordinances, and
regulations (38.100.080)
Meets Code?
Condominium ownership NA
Comments: The Applicant will own the hotel.
3. Conformance with Article 2, including the cessation of any current violations
(38.200.160)
Meets Code?
Current Violations NA
Comments: There are no known violations on this vacant property.
4. Conformance with Article 2 - Submittal material (38.220) requirements and
plan review for applicable permit types (38.230)
Meets Code?
Site Plan Yes with conditions and code
provisions
Submittal requirements 38.220.100 Yes
Phasing of development 38.230.020.B No. of phases: 1 Yes
Comments: The Applicant has requested that only the Lot 1 hotel development be included in the evaluation and approval
of this Site Plan. The second Lot 2 remains undeveloped on the Phase 5 Site; it would be developed at a later date and,
therefore, its development is not included with this Site Plan. The Director agreed to move forward with the hotel
development on Lot 1 as a stand-alone Site Plan rather than require a Master Site Plan addressing both Lots 1 and 2 with
the condition that the Applicant submit a separate Site Plan for Lot 1 within the one-year time-period of the hotel Site Plan.
Pursuant to BMC 38.230.140.D, an approved Site Plan is valid for up to one year. The Director may extend such approval
for an additional approval provided the relevant terms of the initial approval have not significantly changed during the initial
approval period. In this case, per Condition of Approval Number 3, the Applicant must submit a separate Site Plan for the
development of Lots 2 and OS-1B within one year of the date of Director approval of this Lot 1 hotel Site Plan.
It is also noted that no lot exists on this Site until the subdivision final plat is submitted, approved and recorded per Condition
of Approval No. 2.
Any additional use permit (Conditional Use Permit) 38.230.120 or (Special use
Permit) 38.230.120
NA
Comments: NA
5. Conformance with Article 3 - Zoning Provisions (38.300) Meets Code?
Permitted uses 38.310 Hotel Yes
Form and intensity standards 38.320
Zoning: Setbacks
(feet)
Structures Parking / Loading Yes
Front 10’ from the
Huffine Lane
property line for
5’ setback from the
Lot 1 property line
for the parking lot.
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 16 of 23
the Lot 1 hotel
building.
Rear 20’ for Lot 1
20’ for Lot 1
Side 20’ for Lot 1
20’ for Lot 1
Alley NA NA
Comments: The Phase 5 PUD Design Guidelines establish setbacks for Lots 1 and 2. Both lots front on street corners but
are separated from their respective streets by open space lots. Nonetheless, the lots “front” on their respective streets and
the building on each of the lots must address the Block Frontage designations of those streets as measured from the lot
boundary/property line.
The hotel Lot 1 is a corner lot fronting on Huffine Lane and Fowler Avenue. This corner is designated a High Visibility
Intersection and the Huffine Lane frontage is designated a Gateway Block Frontage (BF). The Lot 1 High Visibility
Intersection (38.530.050.C) and Gateway BF (38.510.030.E) designations require the hotel building to be located within 20-
feet of the street corner and include design features that accentuate the street corner [BMC 38.530.050.C]. However, the
OS-1 lot separates Lot 1 from the street by a distance of 50 feet. Therefore, the High Visibility Intersection setback distance
of less than 21 feet from the Huffine and Fowler intersection cannot be met. However, per 38.530.050.C, alternative designs
for the building corner allow a plaza, entry feature and façade articulation to satisfy this requirement. The ground floor plaza
and façade treatments of the northeast corner of the hotel building satisfy this High Visibility Intersection requirement (see
Figure 14).
The required 10-feet PUD setback for the Huffine Lane frontage is met by a 25-foot-wide fire lane. The Gateway BF setback
of 25 feet is met by that fire lane. The landscaping of the open space Lot OS-1 that “frames” Lot 1 along the Huffine and
Fowler frontages feature trees, turf and wetlands-appropriate native grasses which, combined, allow for visibility of the
hotel’s corner architectural and landscaping elements which meet the High Visibility Intersection standards. Along the
Fowler Avenue frontage, the hotel parking lot and architectural features at ground level would be largely obscured from view
by the landscaping of that portion of the OS-1 lot.
Lot
coverage
Lot 1: 76%
Allowed: 100% Meets Code?
Yes
Building
height
Lot 1 hotel: 61’ to
tower element
Allowed:
85.8 feet Yes
Comments: Meets BMC and PUD standards.
Applicable zone specific or overlay standards 38.330-40 Yes
Comments: the PUD allows an 85.8 feet height limit Yes
General land use standards and requirements 38.350 Yes
Comments: Hotel use is a principal permitted use.
Applicable supplemental use criteria 38.360 NA
Supplemental
uses/type
NA
Comments: NA
Wireless facilities 38.370 Meets Code?
NA
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 17 of 23
Affordable Housing 38.380.010 NA
Affordable housing plan NA
Comments: This is a wholly commercial development.
6a. Conformance with Article 4 - Community Design Provisions: Transportation
Facilities and Access (38.400)
Meets Code?
Streets 38.400.010 Yes
Street and road dedication 38.400.020 Yes
Access easements Yes with Condition No. 5
Level of Service
38.400.060
TBD Transportation grid adequate to serve Site Yes with Condition 6 and
subsequent required
mitigation.
Comments:
Per Condition No. 5, a public access easement is required for the proposed sidewalk outside of the right-of-way on the west
side of Fowler Avenue that extends through open space Lot OS-1 to the hotel Site.
BMC 38.220.060 A 12 - Traffic Generation – The Applicant submitted with this application a January 2021 PUD Phase 4
Traffic Impact Study (TIS); this evaluation needs to be updated due to new development in the vicinity. Per Condition No.
6, prior to final Site Plan approval, the Applicant must submit a TIS update specific to the proposed Phase 5 Lot 1
development which will discuss how much daily traffic will be generated on existing and planned streets and intersections
when the subject Site is fully developed. This TIS update must discuss the following topics: 1) Study and report findings on
all collector and arterial intersections within a 1/2 mile of the Site; and 2) Simulate/study the subject Sites peak hour trip
generations with respect to the directly adjacent/planned intersections of Technology Boulevard and Fowler Avenue, and
Fowler Avenue and Huffine Lane.
Sidewalks 38.400.080 Yes
Comments: Trails along the Huffine Lane and Fowler Avenue frontages are provided within the abutting open space lots.
However, the subdivision Preliminary Plat did not clearly show a public access easement from the Fowler Avenue
sidewalk through Lot OS-1 to the hotel Site; Condition No. 5 would correct that deficiency. Sidewalks are provided along
the Technology Blvd. frontage.
Drive access 38.400.090 Access to Site: Two vehicular access points are
provided along the Technology Blvd. frontage.
Pedestrian access is provided along the Huffine
Lane, Fowler Avenue and Technology Blvd.
frontages.
Yes
Fire lanes, curbs, signage and striping Yes
Comments: The northernmost vehicular lane, on the north side of the hotel, is a fire lane. No parking is permitted thereon.
Street vision triangle 38.400.100 Yes
Transportation pathways 38.400.110 Yes with Condition 5.
Pedestrian access easements for shared use pathways and similar transportation
facilities
Yes with Condition 5.
Public transportation 38.400.120 Yes
Comments: The Streamline bus service has a stop at Huffine and Fowler.
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 18 of 23
6b. Conformance with Article 4 – Community Design Provisions: Community
Design and Elements (38.410)
Meets Code?
Neighborhood centers 38.410.020 NA
Comments: The Bozeman Gateway PUD is a commercial development providing a number of destinations of interest to
nearby residents, workers and visitors.
Lot and block standards 38.410.030-040 Yes
Midblock crossing: rights of way for pedestrians alternative block delineation NA
Comments: The December 12, 2005 PUD relaxation allows blocks to be longer and wider than 400 feet. The 591-foot-long
Lot 1, in a north/south orientation, has pedestrian connections in the abutting open space lots, in sidewalks surrounding the
hotel and throughout the parking lot.
If the development is adjacent to an existing or approved public park or public open
space area, have provisions been made in the plan to avoid interfering with public
access to and use of that area
NA
Comments: Per the Bozeman Gateway PUD and subdivision conditions, the open
space lots that abut the Site to the north, east and south are private but publicly-
accessible open space lots to be developed/improved by the Applicant and
maintained in perpetuity by the Bozeman Gateway property owners’ association.
Yes
Provisions for utilities including efficient public services and utilities 38.410.050-060 Yes
Easements (City and public utility rights-of-way etc.) Meets Code?
Yes per Conditions 4 and 5.
Water, sewer, and stormwater Yes
Other utilities (electric, natural gas, communications) Yes
CIL of water rights (CILWR) Yes per Condition 7.
Comments: NA
Municipal infrastructure requirements 38.410.070 Yes
Comments: NA
Grading & drainage 38.410.080 Yes
Location, design and capacity of stormwater facilities Yes
Stormwater maintenance plan Yes
Landscaping: native species, curvilinear, 75% live vegetation 38.410.080.H Yes
Comments: Meets code.
Watercourse setback 38.410.100 Yes
Watercourse setback planting plan 38.410.100.2.f Yes
Comments: Pursuant to the definition of “watercourse” in BMC 38.700.210, the Baxter Border Ditch that lies within the
eastern portion of the Site is an irrigation ditch that is not “naturally-occurring” and therefore, is not a “watercourse” within
the Site. The Farmers’ Canal along the southern boundary of Lot 1 is also an irrigation ditch and not a “watercourse”.
Agricultural water user facilities on the Site include these two irrigation ditches that provide irrigation water to downstream
users. The Baxter Border tributary, shown on Figure 5, lies in a north/south orientation on the east side of the Site. The
Farmer’s Canal, shown on Figure 6, is a tributary to the Baxter Border stream, Section Line Ditch, and Upper Cattail Creek
(Harmon Stream), and transports irrigation water bordering the property in an east/west orientation along the Technology
Blvd. West right-of-way (ROW). According to the U.S. Army Corps of Engineers (ACOE) Jurisdictional Determination
Report of March 20, 2021, these irrigation ditches do not relocate or capture a navigable water of the U.S. They are
operational ditches whose sole function is to supply water for agricultural purposes. The ACOE has determined that the
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 19 of 23
ditches do not relocate a natural tributary and were not constructed in an otherwise adjacent wetland. Water is diverted
downstream and is controlled through a headgate structure from a natural tributary. However, it does not capture the entire
tributary and meets the exclusions for ditches within the Navigable Waters Protection Rule.
No modifications to existing agricultural water facilities by this development would reduce the ability of the downstream users
to divert water from these facilities and the ability of these facilities to deliver water to downstream users would be protected.
The 72-acre Bozeman Gateway PUD was amended in 2005 (Project # Z-05217) which allowed, among other relaxations,
(1) encroachment into a BMC 38.410.100.A.2.c.(3) required 50-foot minimum setback along waterways, and (2) allowed a
required watercourse setback to not include adjacent wetlands. The 2005 PUD does not establish a minimum watercourse
setback in the PUD. Nonetheless, since the irrigation ditch through the Site is not a wetlands or watercourse, the
proposed landscape plan meets code.
Figure 12: Six-foot watercourse setback on Lot OS-1
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 20 of 23
Figure 13: Site Plan Sheet L103 shows turf and pavement 35 feet from Ditch
6c. Conformance with Article 4 – Community Design Provisions: Park and
Recreation Requirements (38.420)
Meets Code?
Parkland requirements 38.420.020.A .52 ac. X 10 units/ac. X 0.03 ac.= .3 ac. NA
Cash donation in lieu (CIL) 38.420.030 NA
Improvements in-lieu NA
Comments: No residential development is proposed. NA
Park Frontage 38.420.060 NA
Park development 38.420.080 NA
Recreation pathways 38.420.110 Yes
Park/Recreational area design Yes
Comments: The private open space Lots OS-1 and OS-1A would provide “passive” recreation, sitting and walking facilities
throughout those lots. Those lots would be owned and maintained by the PUD property owners’ association.
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 21 of 23
7a. Conformance with Article 5 – Project Design: Block Frontage Standards
(38.510)
Meets Code?
Block frontage classification Types: Gateway along the Huffine Lane
frontage and Mixed along the Fowler
Avenue frontage
Yes
Departure criteria No Departures were requested. NA
Comments: The intersection of Huffine Lane and Fowler Avenue is designated a “high visibility intersection” and the northeast
corner of the hotel building has been designed to address Block Frontage (BF) standards for this type of intersection. The
Fowler frontage has been designed to address the Mixed BF standards.
Figure 14: High-visibility design of the northeast corner of the hotel
7b. Conformance with Article 5 – Project Design: Site Planning and Design
Elements (38.520)
Meets Code?
Design and arrangement of the elements of the plan (e.g., buildings, circulation, open
space and landscaping, etc.) so that activities are integrated with the organizational
scheme of the community, neighborhood, and other approved development and produce
an efficient, functionally organized and cohesive development
Yes, per PUD
Relationship to adjacent properties 38.520.030 Yes
Non-motorized circulation and design systems to enhance convenience and safety
across parking lots and streets, including, but not limited to paving patterns, pathway
design, landscaping and lighting 38.520.040
Yes, with Condition 5.
Comments: The open space lots OS-1 and OS-1A have trails connecting the Site to Fowler Avenue, Huffine Lane and
Technology Blvd. However, the Preliminary Plat failed to note on the plat map a public access easement on the trail
connecting Fowler Avenue to the hotel Lot 1; Condition No. 5 would correct that error. The Final Plat for the subdivision
can show such an easement.
Design of vehicular circulation systems to assure that vehicles can move safely and
easily both within the Site and between properties and activities within the general
community 38.520.050
Yes
Internal roadway design 38.520.050.D Yes
Comments: The fire lane on the northern side of the hotel provides exclusive access for Fire and emergency service
vehicles.
On-Site open space 38.520.060 Yes.
Total required 2% (2,590 sf)
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 22 of 23
7d. Conformance with Article 5 – Parking (38.540) Meets Code?
Parking requirements 38.540.050 Yes
Parking requirements residential 38.540.050.A.1 NA
Reductions residential 38.540.050.A.1.b NA
Parking requirements nonresidential
38.540.050.A.2
135
Reductions nonresidential 38.540.050.A.2.c NA
Provided off-street 170
Provided on-street None
Bicycle parking 38.540.050.A.4 10% or 13 required; 16
provided
Yes
Comments: All parking spaces on Lot 1 are to be shared with the future Lot 2 development per the PUD shared parking
agreement throughout the PUD area. Since access to and vehicular circulation for the “landlocked” Lots 1 and 2 are
shared, the parking for both lots, and the abutting open space lots, are provided with this Site Plan.
Loading and uploading area requirements 38.540.080 Not required
First berth – minimum 70 feet length, 12 feet in width, 14 feet in height NA
Additional berth – minimum 45 feet length NA
Comments: This hotel does not have a restaurant or conference rooms and, therefore, does not require loading zones.
The Applicant does not wish to provide loading facilities for the hotel operation or for guests.
7e. Conformance with Article 5 – Landscaping (38.550) Meets Code?
Mandatory landscaping requirements 38.550.050 Yes
Drought tolerant species 75% required Yes
Parking lot landscaping Yes
Additional screening Yes of mechanical equipment
Street frontage NA
Total provided 2.3% Meets Code?
Yes
Comments: Two areas of open space are provided on the hotel Lot 1 including a 1,989 sf plaza at the north end of the
building with tables and seating and a 1,080 sf seating area plaza at the east side entrance for a total of 3,069 sf.
Location and design of service areas and mechanical equipment 38.520.070 Yes
Comments: The trash enclosure is screened and landscaped. Electrical panels are interior to the building. The gas meter
on the southwest stair is screened by landscaping.
7c. Conformance with Article 5 – Project Design: Building Design (38.530) Meets Code?
Compatibility with, and sensitivity to, the immediate environment of the Site and the
adjacent neighborhoods and other approved development 38.530.030
Yes, per PUD Development
Manual
Building massing and articulation 38.530.040 Yes, per PUD Dev. Manual
Building details, materials, and blank wall treatments 38.530.050-070 Yes
Comments: This is a 4-story, 61’ tall building lying at the edge of a commercial neighborhood characterized by 2-story
buildings. However, it is consistent with the adopted Master Site Plan/PUD for this neighborhood. The building meets
Block Frontage design standards as well as High Visibility Intersection standards for the treatment of the northeast corner
facing Fowler and Huffine.
Staff Report
Bozeman Gateway Phase 5 Development Site Plan:
Hotel and Open Space lots
Application No. 21341
June 28, 2022
Page 23 of 23
Street median island NA
Acceptable landscape materials Yes
Protection of landscape areas Yes
Irrigation: plan, water source, system type Yes
Residential adjacency NA
Comments: The Huffine and Fowler street frontages are separated from Lot 1 by landscaped open space lots OS-1 and OS-
1A which, per the PUD Master Plan, must be developed/improved by the developer at the time Lot 1 is developed (see
Condition No. 9).
Landscaping of public lands 38.550.070 Yes
Comments: The Huffine and Fowler boulevard greens would be improved to City standards by the developer of Lot 1 as part
of the landscape plans of lots OS-1 and OS-1A.
7f. Conformance with Article 5 – Signs (38.560) Meets Code?
Allowed SF/building 38.560.060 NA
Proposed SF/building NA
Comments: Signage is not included in this application or review.
7g. Conformance with Article 5 – Lighting (38.560) Meets Code?
Site lighting (supports, cutoff, footcandles, temperature) 38.570.040 Yes
Building-mounted lighting (supports, cutoff, footcandles, temperature) 38.570.040.B Yes
Comments: The lumens of the Site lighting remains below the 3000K LED limit of the PUD standards and otherwise meets
BMC standards.
8. Conformance with Article 6 – Natural Resource Protection Meets Code?
Floodplain regulations 38.600 Yes
Wetland regulations 38.610 Yes
Comments: As noted earlier, there are no “watercourses” on the Site as the Baxter Border Ditch and the Farmers Canal
are irrigation ditches and are not deemed “watercourses” requiring setbacks from development. However, it is noted that
the December 2005 PUD relaxations allow encroachment into the BMC standard 50-foot minimum watercourse setback.
The re-aligned Baxter Ditch on Lot OS-1 is setback 35 feet from the hotel parking lot drive aisle.
9. Relevant Comment from Affected Parties (38.220) Meets Code?
Public Comment Yes
Comments: Public notice was sent from June 3rd through the 17th and no comments were received.
10. Division of Land Pertaining to Subdivisions (38.240-Part 4) Meets Code?
Subdivision exemptions NA
Required easements Yes, with Condition 5
Comments: The Bozeman Gateway Phase 5 Major Subdivision Final Plat has not been submitted for review. The
Preliminary Plat was approved by the City Commission on September 14, 2021 and is valid for two years from that date.
This Site Plan cannot be approved until Lot 1 is formally created by a final plat recordation as noted in Condition of
Approval No. 2.