HomeMy WebLinkAbout003 Site Plan NarrativeSite Plan Project Narrative
The Boötes
Allison Subdivision 4A, Lots 1 & 2
Multi-Family Residential Development
Project Summary
We are pleased to submit a Site Plan application for The Boötes, a residential project consisting of
rowhomes and apartment homes within the Allison Subdivision 4A. The Boötes is located on the
southeast corner of S. 11th Avenue and Opportunity Way.
VICINITY MAP
The subject property is currently zoned R-3, which permits a variety of medium density residential uses.
The Boötes will include a variety of rowhomes (40) and several apartment buildings (31 units), as
permitted by the Apartment Building, Limited, use-type, under R-3. The Apartment Buildings will
include 3 eight-unit buildings, and 1 seven-unit building. The development will also include a 4,888
square feet clubhouse, a community dog park, while also preserving a trail access easement between the
two lots for the community’s benefit. Pedestrian access is planned to be provided throughout the site and
block frontage will be landscaped. Adjacent land uses included residential and business park districts.
The public infrastructure around the 1.69-acre and 1.94-acre parcels is completely built out. A sewer and
water main extension will be required within the development to service the proposed buildings. Cash-in-
lieu of water rights (CILWR) is proposed. See document 014 CILWR Correspondence for
correspondence regarding the CILWR. Concurrent construction is proposed for this project. A concurrent
construction plan narrative in addition to a Conditional Irrevocable Offer of Dedication is submitted with
this Site Plan application, supplemental documents including written approval from the Fire Marshall will
be obtained once an infrastructure review has been submitted and approved.
Project Overview
Use Type Number of Units Gross Square Feet
Apartment Building, Limited 31 35,539
Rowhomes 40 103,395
Clubhouse - 5,995
Total 71 144,929
Project Density
Use Type Lot area per dwelling Units Required SF
Rowhomes 1,800 40 72,000
Apartment Building,
Limited
2,700 31 83,700
Total - 71 155,700
Additional Project Details
Project Totals Code Standard
Floor Area Ratio .91 / 1 1:1
Lot Coverage 34.14% 40%
Affordable Housing
As part of this application, we intend to comply with certain sections of Division 38.380 of the Bozeman
Unified Development Code and construct affordable homes that meet the standards identified in Table
38.380.020-2 in the same geographically contiguous development as market rate homes. As such, a
minimum of 5% of the project’s rowhomes and multi-household dwellings will be available for rent at 80%
AMI for 30 years. In exchange, we have applied the following incentives to our project application:
• For each single household attached dwelling (townhouse or rowhouse) a minimum lot size of 2,200
square feet, or 1,800 square feet, if the applicant demonstrates that all applicable city regulations
related to lot development, access and utilities can be met.
• For multi-household dwellings and mixed-use buildings:
o Ten percent reduction in lot area for applicable dwelling type in Table 38.320.030.A.
o Minimum vehicle parking requirement of one stall per dwelling for all districts other than
B-3 and bicycle parking standards and requirements of 38.540.050 still apply.
In conjunction with the site plan submittal, an affordable housing plan further outlining the specifics of
how this project implements affordable housing has been submitted and approved by the Economic
Development Department.
Landscaping and Open Space Requirements
Landscaping will be provided throughout the site. Please refer to landscaping plan sheets.
Designated common open space area is provided with the clubhouse which includes amenities such as
fitness area, lounge and an outdoor spa. Private open space will be provided in the form of porches and
balconies for each apartment and rowhouse. Additionally, the five rowhouse complexes along
Opportunity Way have fenced in front yards, providing further protected private open space.
Parkland Requirements
A portion of the parkland was provided with the Allison Subdivision Phase 4A through Cash in lieu of
Parkland (CILP). The Allison Subdivision Phase 4A Parkland Requirements assumed a residential density
of 8 dwelling units per, however the proposed development exceeds this density. For R3 zoning, Cash-in-
lieu values are capped at a maximum of 12 dwelling units per acre. Our calculated CLIP requirement is
based on a difference between these two values and uses a net residential density of 4 dwelling units per
acre. Please refer to 001 C0.0 Cover Sheet to see the CILP calculations in further depth.
Open Space
Code Standard Total Required Total Provided
Rowhouse 10% of Living Space 8,141 sqft -
Apartments 150 sqft/unit 4,650 sqft -
Porches/Balconies - - 3,816 sqft
Rowhouse Front Yards - - 7,400 sqft
Common Open Space - - 2,543 sqft
Total - 12,791 sqft 13,759 sqft
Vehicle Access and Parking Requirements
The development will have three access points, one via Student Drive and two via Bon Ton Avenue. The
sole entrance via Student Drive and the southern entrance via Bon Ton Avenue will lead to a drive lane
with 33 surface parking stalls. Additional parking is provided by 80 rowhouse garage spaces and 32 on-
street parking spaces along Opportunity Way, Bon Ton Avenue, and Student Drive. Adequate ADA
parking is provided onsite. The parking requirements for this project utilize the shallow incentive for
providing affordable housing from section 38.380.30.C.3.d to reduce the minimum vehicle parking
requirement to one stall per dwelling. Bicycle parking is provided by two 8-bicycle racks and additional
bicycle storage is provided in Building A.
Trash and Recycling
Trash and recycling are provided through two main covered trash enclosures adjacent to proposed
buildings. Please refer to 005 C1.0 Site Plan for exact locations and 044 AS410 Site and Clubhouse -
Dumpster Enclosures and 045 AS411 Site and Clubhouse - Dumpster Enclosures for details on the
trash enclosure structures.
Traffic Impact Study
Due to a TIS being completed for the Allison Subdivision Phase 4A, a TIS Waiver has been issued.
Please refer to included document 010 Traffic Impact Study Waiver.
Water and Wastewater Capacity
Water and Wastewater Capacity reports were created as part of the Allison Subdivision Phase IVA
Submittal. Addendum I of each of these reports show the calculations for the increased demand created
by this proposed development and can be found respectively in the following documents 012 Water
Design Report Allison Sub PH IV A Updated Sept 2020 and 013 Sewer Design Report Allison PH IV
A Updated Sept 2020.
Parking
Unit
Count
Per Unit Required Total Required Total Provided
Apartment Building,
Limited
31 1 31 33 surface stalls
Rowhouses 40 1 40 80 garage stalls
On-Street Parking - - - 33
Total 71 - 38 113
Bicycle Parking - - 4 16
Stormwater Report
An updated stormwater report has been prepared for this submittal and can be found in 015
Allison Ph 4 Stormwater Report_Sept 2020 Updated and 016 Stormwater Retention Calculation.
The SWPPP filed with the DEQ will include storm water management to prevent runoff into
adjacent floodplains.
Response to Conceptual Review Comments
All the comments received on the conceptual review of the Boötes site plan were denoted as
‘Info Only’. Each comment was carefully considered and incorporated accordingly into our Site
Plan submittal. Please refer to 021 Concept Plan Comment Responses for specific responses to
comments.