HomeMy WebLinkAbout001 - Narrative 2023112 EAST MAIN BUILDING
CCOA/SITE PLAN APPLICATION
September 2023
TABLE OF CONTENTS
1. Commercial Certificate of Appropriateness Application, Site Plan Forms & Checklists
2. Project Team
3. Narrative
a. General site information
b. Site considerations
c. Parkland
d. Building design
e. Landscaping
f. Site Lighting
g. Traffic
h. Water rights
i. Departures
j. CCOA Checklist Items
k. DEM Checklist Items
4. Appendices
Appendix A – Vicinity Map
Appendix B – Existing Zoning
Appendix C – Existing Plat
Appendix D – Existing Site Photos
Appendix E – Property Record Form 2016
Appendix F – SID 565 Space data
Appendix G – Waiver of TIS Request Letter
Appendix H – Water, Sewer and Stormwater Design Report
Appendix I – Stormwater Maintenance Plan
Appendix J – CILWR Determination Request
1. Site Plan Application Information, Forms & Checklists
The Site Plan form has been included per City requirements, and the applicant will submit the
required fee once the application has been deemed adequate for review. Please see the
estimated site plan fee amount below:
Component Fee Quantity Total
Base $3,069 $3,069
Dwelling Units $125 per unit 7 $875
Commercial Area $400 Per 1,000 SF 12,447 $4,978.9
Total $8,922.8
2. Project Team
OWNER / APPLICANT 112 E. Main, LLC
(Attn: Randy Scully)
randy@scullywestproperties.com
5073 Patterson Road
Bozeman, Montana 59718
p. 914.450.8803
PROJECT CONSULTANTS
ARCHITECT/PLANNER Intrinsik Architecture
(Attn. Tyler Steinway)
Tsteinway@intrinsikarchitecture.com
106 East Babcock, Suite 1A
Bozeman, Montana 59715
p. 406.582.8988
CIVIL ENGINEER TD&H Engineering
(Attn: Kyle Scarr)
Kyle.scarr@tdhengineering.com
234 East Babcock Street, Suite 3
Bozeman, Montana 59715
p. 406.586.0277
LANDSCAPE Design 5
ARCHITECT (Attn: Troy Scherer)
Troy@design5la.com
111 North Tracy Avenue
Bozeman, Montana 59715
p. 406.5874873
3. Site Plan Narrative
A. General site information
This Site Plan Application is for the redevelopment of the current eastern portion of US Bank
site (112 East Main Street) that is located directly adjacent to The National building (104 East
Main Street) and is currently under construction. This application proposes to demolish the
existing one-story building, which currently houses US Bank, and build a 4-story mixed-use
structure in its place. The proposed program seeks to create commercial spaces on the ground
floor, offices on the second floor and residential units on floors three and four. The existing
building on this site was originally built in the 1970s as part of the overall makeover of the site.
The property record form for this property designated this building as non-contributing to the
Main Street Historic District.
The Main Street Historic District Nomination from 1986 notes that while the Main Street District
was incredibly intact at the time of its historic designation, it suffered from significant visual gaps
created by architectural sheathing that covered the historic facades of landmark buildings like
The National. The US Bank building was also called out in this report as being the “one other
major gap” within this historic commercial district. While these aspects of the Main Street
Historic District were lamented in the past, today work is underway to improve this district by
repairing these previously identified gaps. The National building has had its sheathing removed
and is being renovated to showcase its original historic beauty. Seeking to continue this
momentum, this proposal will repair one of the other major gaps that was identified in the 1986
Historic District Nomination, the rest of the US Bank site. This will be accomplished by
constructing a new building with a design that consciously responds to the context of the site,
with regard to architectural design, traditional building materials, scale, and use.
B. Site Considerations
1. Setbacks & Utilities
Setbacks
This building will front along Main Street and will take advantage of the Storefront Block frontage
which puts the fact of the building at the back of the 12’ sidewalk. Currently, the single level
portion of the US Bank building is located on the same lot as The National building but there are
extra parcel lines located on other portions of the site. A subdivision exemption will be applied
for to establish this as a stand-alone parcel prior to occupancy of the structure. Due to the
ongoing coordination of the foundation design and seismic concerns, the exact location of the
proposed property lines is still being determined. This building is located in the B-3 core and will
have 0’ setbacks off the sides of the building. This building complies with all of the B-3 and block
frontage setbacks.
Infrastructure
New water, fire sprinkler and sewer services will be constructed off the Main Street main lines to
service this building. It is understood that proper permits will be required from MDT for any work
in the Main Street ROW.
2. Block Frontage
The project is located on Main Street. The vision for this project is to maintain the active
streetscape and as such will utilize the Storefront Block Frontage. The proposal is to construct
ground level commercial space(s) with residential and office space on the 3 floors above. The
uppermost level will be setback to create a layered design and add to the historic downtown
aesthetic.
3. Accessible Provision
This development will be designed in compliance with the IBC, including its accessible
requirements; as well as ANSI 117.1 & ADA standards for accessible design. Specifically
pertaining to this site plan, the site design provides three (3) accessible parking spaces across
the whole site. All resident building entries, the refuse areas, and landscaped open space, are
connected via an accessible pathway system which is in compliance with the requirements for
an accessible route.
4. Parking
The 112 East Main Building is currently located on the same lot as The National building and as
such the parking calculations for the project can be challenging to follow. In an effort to avoid
any double counting and confusion the approved parking numbers for The National (22-147)
have been included for reference.
Parking for this site is proposed in two ways. Seven parking spaces are proposed in the
basement of the proposed building. The balance of the spaces will be in the form of the existing
SID 565 spaces. In 1976 this property paid for 156.0 SID spaces which are still in use today.
The redevelopment of this site is within the paid for spaces and does not require any additional
spaces on site. Furthermore, the draft new UDC indicates that there will be no parking
requirements in the B-3 Core district. Please see the Parking Calculations included below and
Appendix F for more information on the SID 565 Spaces.
Parking Calculations Table
The National (Approved under 22-147)
Level Program Square
Footage
3,000 SF
Exempt
(B-3)
Square
Footage
After
Reduction
Number of
Residential
Units
Parking
Factor
Required
Number
of Spaces
Blanket
Reductions
Required
Parking
after
reduction
Basement Storage &
Mechanical
– Exempted
7,387
- 6,279 - - - 0% 0
Ground Bank 7,206 - 3,125 - 300 10 30% 7
Level 2 Office 6,345 3,000 5,393 - 250 22 20% 17
Level 3 Office 7,236 - 6,151 - 250 25 20% 20
Level 4 Office 7,233 - 6,148 - 250 25 20% 20
Level 5 Office 7,232 - 6,147 - 250 25 20% 20
TOTAL 80
Other Reductions
Within 800’ of Transit Stop – 10% 8
Within 800’ of Structured Parking – 15% 13
TOTAL REQUIRED AFTER REDUCTIONS 63
Number of Spaces in Basement Garage 58
Number of SID Spaces Used (of 151 Available) 5
TOTAL PROVIDED 63
Scully Building
Level Program Square
Footage
3,000 SF
Exempt
(B-3)
Square
Footage
After
Reduction
Number of
Residential
Units
Parking
Factor
Required
Number
of Spaces
Blanket
Reductions
Required
Parking
after
reduction
Basement Parking
Garage,
Mechanical
& Tennant
Storage –
Exempt
6,788 - - - N/A N/A N/A N/A
Ground Retail/
Commercial
6,248 3,000 3,248 - 300 10.827 40% 6
Level 2 Office 6,199 - 6,199 - 250 25 20% 20
Level 3 Residential 5,883 - - 3 1 3 - 3
Level 4 Residential 4,654 - - 7 1 4 - 4
TOTAL 29,772 3,000 7 33
Other Reductions
Within 800’ of Transit Stop – 10% 3
Within 800’ of Structured Parking – 15% 5
TOTAL REQUIRED AFTER REDUCTIONS 25
Number of Spaces in Basement Garage 7
Number of SID Spaces Used (of 151 Available) 18
*Note: 5 of 156 SID Spaces Used in The National Site Plan (22-147) *
TOTAL PROVIDED 25
Total Combined
TOTAL REQUIRED PARKING 117
TOTAL REQUIRED PARKING AFTER REDUCTIONS 88
Total Parking On-Site 58
Total Parking in Building 7
Total SID Spaces Used (of Available 156) 23
TOTAL PROVIDED 88
5. Bike Parking
The required number of parking spaces, before any reductions, for the site is 33 spaces, which
then requires 3.3 (rounded up to 4) bike parking spaces (10% of total parking). There is an
existing bike rack located at the front of the site that offers 2 bike parking spaces. Additionally, in
the basement of the building there are 7 storage facilities (one for each residential unit) that
each have the space for one bike. This allows the site to provide a total of 9 bike parking
spaces.
6. Trash Enclosure
The project site features an alley that has an unconventional form due to a former partial
vacation of the Right-of-Way behind The National building that occurred many years prior to this
submittal. The vacating of this Right-of-Way resulted in an alley easement being adjusted to
provide access from Babcock St. rather than S. Black Ave. See Appendix C - PLAT C-1-V for
additional information. Refuse and recycling containers will be located in the rear of the site
adjacent to this alley located behind a steel wall/enclosure. It is important to note that while the
garbage & recycling containers are located behind a wall, the wall is not required to meet any
UDC design standards for service area because it is located on an alley (38.520.070.B.3.).
While a screening wall/trash enclosure is not required, this screening element is proposed to
reduce the visual impact of the trash & recycling area. Please refer to Sheets SP100 & SP102
for location and access.
7. Open Space
The on-site open space for this project is proposed to be provided through a combination of
areas both on-site and private balconies. This project proposes 7 residential units that are a mix
of two one-bedroom, four two-bedroom, and one three-bedroom units. In total this project is
required to provide 850 SF of residential open space. This will be accomplished through private
balcony spaces and a common plaza area at ground level. Please see the table below for the
open space calculations and the plan set for the proposed open space locations.
OPEN SPACE CALCULATIONS
Program Number of Units Open Space Factor Required Open Space
1 Bedrooms 2 100 SF 200 SF
2 Bedrooms 4 150 SF 600 SF
3 Bedrooms 1 150 SF 150 SF
TOTAL REQUIRED 950 SF
Provided Open Space
Private Balcony Open Space 475 SF (1,521 SF TOTAL PROVIDED)
Level One Plaza Open Space 480 SF (480 SF TOTAL PROVIDED)
TOTAL PROVIDED 955 SF (2,001 SF TOTAL PROVIDED)
9. Construction Management
To provide a safe working environment for adjacent properties, the project will utilize temporary
construction fencing around the project extents which generally follows the perimeter of the
property. A 40-CY dumpster will be located near the site in an easily accessible and clearly
defined area to provide easy disposal of construction waste. The dumpsters will typically be
placed near the alley to allow for easy pick up. Construction staging areas will likely be in the
adjacent parking lot owned by the property owner on East Babcock. See C2.2 Construction
Management Plan for more information.
C. Parkland
This application proposes to pay Cash-in-Lieu (CIL) of Parkland rather than on-site dedication
due to it being located within the commercial core of Bozeman. CIL of Parkland is also
supported by Resolution 4784. It states, “CIL will always be accepted for development within the
B-3 District.” Additionally, Resolution 4784 indicates areas less than 5,300 sf are more favorable
for CIL. Please see the calculations below for the required CIL amount.
23243 Cooper
Block SP
Park and Recreation
Requirements
Total site area (ac) 0.20
(s) school or park
sites (ac) 0.0
Total excluded
(ac) 0.01
(D) Net residential
density 37
(c) commercial lot
area (ac) 0.0
(a) ROW &
easements (ac) 0.0
(N) Net
residential lot
area (ac) 0.19 Zoning District Other
(i) industrial lot
area (ac) 0.0
(d) Open
space/Park (ac) 0.01
(du) Number of
units 7
(M) Max density
by zone 12
Required land dedication.
Required cash-in-lieu
Adjustments to Parkland
Requirements Approved Parkland Dedication
Net residential
land area (ac) 0.20
Net residential
land area (ac) 0.20
Parkland
dedication
required (ac) 0.05
Land dedication
(ac) 0.00
Dwellings/acre
(du) 8 Dwelling/acre (du) 4
Land already
provided (ac) 0.00 Cash-in-lieu ($) $3,397.68
Acre/du of land 0.03 Acre/du of land 0.03
Land dedication
proposed (ac) 0
Additional in-lieu
($) $5,662.80
Land dedication
(ac) 0.05
Equivalent land
area (ac) 0.03
Land equivalent
required (ac) 0.05 Total CILP/IILP $9,060.48
land appraisal
value ($/sf) $2.60
Land appraisal
value ($/sf) $2.60
Cash-in-lieu ($) $3,397.68
In-lieu fee
equivalent ($) $5,662.80
D. Building Design
The 112 East Main Building aims to blend into the existing urban fabric, while simultaneously
respecting The National building’s status in the architectural hierarchy. The form of the proposed
building is a unique individual design that has been developed with the same goal in mind.
While the proposed building is large and similar in scale to The National, its top floor is stepped
back approximately 12 feet and will complement the pattern of the existing 2 & 3 story building
facades along Main Street; this allows the visual prominence of The National building to remain,
protecting the views of the National’s cornice from both East and West elevations. The brick
material has been selected to complement the color and texture of the nearby buildings and is
intentionally different from the beige brick of the National building.
F. Site Lighting
There are minimal accent lights proposed on the rear of the building and plaza, as well as the
top story of the front elevation. Please see plan set sheets ES1.1 - ES1.9 for more information
on the proposed locations, photometrics and details.
G. Traffic
A memo requesting a waiver to provide a TIS has been provided with this application (Appendix
G). Included in that request is a trip generation report. That report shows that the net weekday
trips ends at the site are expected to increase by 271 average daily trips while the net peak hour
trips are expected to increase by 5 and 24 trips ends during the AM and PM peak hours,
respectively. It is our request given the limited net increase in trips and built out nature of the
existing transportation network that a waiver to providing a traffic impact study be granted.
H. Water Rights
The City of Bozeman Engineering Department (Griffin Neilson) has been contacted to determine
what cash-in-lieu of water rights are required for the site. The preliminary determination shows
that the annual net demand is 0.03 AF which falls below the 0.25 AF threshold for required
CILWR. Currently, the preliminary determination shows no CILWR are required. This will be
revisited with this site plan application. If a final determination indicates CILWR are required, the
fee will be paid by the owner prior to site plan approval. Please see Appendix J documenting the
Preliminary Determination.
I. Departures
There are no departures necessary or included in this application.
J. CCOA Checklist Items
If demolition is proposed, provide a complete submittal with checklist items in form DEM.
Applicant Response: The current proposal is to demolish the existing US Bank building
on site. The demolition of this non-contributing structure is necessary in order to be able
to construct the new building that is being proposed. Please see Sheet C2.1 for
additional information on demolition.
Date of construction of structure if known.
Applicant Response: The existing structure was built in 1972 when the First National
Bank expanded to the east. Prior to this structure, the Cooper/Black building occupied a
portion of the lot. This building originally consisted of 11 bays of arch windows, but 4 of
those bays on the west end were removed to make way for the previously mentioned
expansion of First National bank, which today houses the single level US Bank.
Property record form, both original and updated.
Applicant Response: Please see the property record form attached as Appendix E &E.2.
Project narrative providing a thorough description of what is being proposed including a list of all
alterations/changes proposed on the property.
Applicant Response: Please see Site Plan Sheets SP100-800 and Section 3 above for our
project narrative outlining the proposed changes.
Historical information such as pictures, plans, authenticated verbal records and similar research
documentation that may be relevant to the proposed changes to the property.
Applicant Response: Please see Appendix E& E.2 for Historic Property Records.
Appendix E contains a set of site photos for reference.
One current picture of each elevation of each structure planned to be altered that will clearly
express the nature and extend of the changes planned. All pictures should include elevation
direction and relevant information on the proposed changes.
Applicant Response: The drawing set contains detailed elevations for each face of the
building. Additionally, please see Appendix D for site photos that depict each elevation.
Include a separate site plan displaying existing conditions such as lot boundaries, dimensions,
setbacks, existing easements, access points, vehicular and pedestrian circulation, buildings,
natural features, and topography.
Applicant Response: Please see Plan Set Sheet C2.1 for an existing site plan and sheet
SP100 for our proposed Site Plan.
Site plan depending on project complexity with north narrow, property dimensions, location of
buildings, parking, driveways, fencing, landscaping, setbacks, utilities, access, pedestrian
facilities, and location of changes proposed.
Applicant Response: Please see Plan Set Sheet C2.1 for an existing site plan and sheet
SP100 for our proposed Site Plan.
Front, rear and side elevations of all buildings, structures, fences and walls with height
dimensions and roof pitches if new construction or changes to elevations are proposed. Show
existing and proposed changes.
Applicant Response: We have included proposed elevations in the drawing set, please
see sheets SP301-302. Proposed changes are indicated on the drawings.
Building elevations shall include proposed exterior building materials, windows and doors
including a color and building material palette for all proposed features keyed to the building
elevations.
Applicant Response: Please see sheets SP301-302 for the building elevations and
proposed materials. Additionally, please see the Architectural Plan Set.
One exhibit or illustration shall include all the internal and external elements of a structure to be
removed or altered by a project. All elements to be removed or altered, and to what extent, shall
be clearly identified and shall include those elements to be removed and reinstalled.
Applicant Response: Please see the included drawing set for this information.
For any non-conforming structure, an analysis of demolition to determine whether the threshold
for loss of protected nonconforming status per Section 38.280.040.B BMC has been met or
surpassed.
Applicant Response: At this time there are no known non-conformities, and the proposed
building will comply with the Unified Development Code.
For minor screen, storefront or window/door changes or replacements, and other minor
changes: pictures, specifications and other information that will clearly express the proposed
changes or alterations to the property.
Applicant Response: Please see the finish selections on SP301-302. Additionally, lighting
plan set sheet ES1.9 for cutsheet information.
Cutsheets or brochure pages for proposed windows, doors, exterior lighting or other detailed
alterations if building elevations are not detailed enough to depict features accurately.
Applicant Response: Please see the finish selections on SP301-302. Additionally, lighting
plan set sheet ES1.9 for cutsheet information.
Floor plans showing floor layout including square footage and proposed use for each room and
area within the building clearly showing areas to be changed or added to. Suggested scale of
1/4” = 1’-0”.
Applicant Response: Floor plans have been included in the architectural plan set. Please
see sheets SP200-205. Detailed plans will follow for Building Permit Applications.
Parking plan and calculation for all uses, if proposed changes to the property require review of
parking requirements.
Applicant Response: Please see the Parking Calculations included above. Parking for
this site is proposed in two ways. First, in the basement of the building (accessed via a
car elevator in rear of building) there are 7 spaces. Secondly, given the small downtown
nature of this lot parking for this building will be provided in the form of the existing SID
565 Spaces. In 1976 this property paid for 156.0 SID spaces which are still in use today.
The redevelopment of this site stays within the paid for spaces and does not require any
additional spaces on site. Furthermore, the draft new UDC indicates that there will be no
parking requirements in the B-3 Core district.
A schedule for the proposed changes to the property if to be phased or if applicable.
Applicant Response: The Applicant is not going to phase the improvements proposed in
this application. Any additional modifications will be submitted and approved through a
MOD Application, and subsequent Building Permit Applications where required.
K. Demolition Checklist
1. Project narrative providing a thorough description of what is being proposed including a list of
all alterations proposed to buildings, structures and site layouts on the property.
Application Response: Please see Appendix E & E.2 for Historic Property Records.
Appendix E contains a set of historic photos for reference. The proposal is to demolish
the underutilized one-story building, which currently houses US Bank, and build a 4-
story mixed-use structure in its place.
2. Historical information, such as pictures, plans, authenticated verbal records and similar
research documentation which describe the property’s historic significance that may be relevant
to the proposed changes to the property. A current Montana Property Record Form may be used
to document the existing conditions on the site and determine the property’s historic
significance.
Application Response: Please see Appendix E & E.2 for Historic Property Records.
Appendix E contains a set of historic photos for reference.
3. One current picture of each elevation of each structure planned to be altered that will clearly
express the nature and extent of the changes planned. All pictures should include elevation
direction and relevant information on the proposed changes.
Applicant Response: Please See Appendix D for reference pictures of the building.
4. Site plan showing), parking, driveways, fencing, landscaping, setbacks.
a. Property dimensions
b. Location of building(s) and changes proposed
c. Setbacks
d. Pedestrian and vehicular circulation
e. Location of utilities
Application Response: Please see plan set sheet C2.1 and SP200-201 for this
information.
5. One exhibit or illustration shall include all the internal and external elements of a structure to
be removed or altered by a project. All elements to be removed or altered, and to what extent,
shall be clearly identified and shall include those elements to be removed and reinstalled.
Application Response: Please see plan set sheet C2.1 for this information.
6. For any non-conforming structure, an analysis of demolition to determine whether the
threshold for loss of protected non-conforming status per Section 38.280.040 BMC has been
met or surpassed.
Application Response: At this time there are no known non-conformities, and the
proposed building will comply with the Unified Development Code.
7. If the property is classified as historic, whether by listing on the National Register of Historic
Places, identification as “eligible” or “contributing,” identification as a Landmark or in a local
district, definitive evidence shall be provided in support of demolishing the structure under
Section 38.340.090.C and Section 38.340.100 including:
a. The structure or site has no viable economic or useful life remaining, based on evidence
supplied by the applicant. This may include a structural analysis and cost comparison
evaluating the cost to repair and/ or rehabilitate versus the cost of demolition and
redevelopment using the International Existing Buildings Code.
b. The structure or site is a threat to public health or safety, and that no reasonable repairs or
alterations will remove such threat; any costs associated with the removal of health or safety
threats must exceed the value of the structure.
Application Response: This building is not classified as historic by the National Register
of Historic Places. Additionally, it is identified as a non-contributing structure to the
historic district.