August 4, 2022
Bozeman City Planning & Engineering
20 E. Olive Street
Bozeman, MT 59715
Re: BG Mill – Site Plan Application (No. _________)
Concurrent Construction Request
Dear Planning & Engineering Staff:
This letter is being submitted as a supplement to the BG Mill Site Plan Application. Specifically,
this letter serves as a request for concurrent construction to be permitted of the public infrastructure
improvements required for this project while the private on-site improvements are being
constructed. This request is being made per the BMC Section 38.270.030.C.1. which states that any
municipal water system, sewer system, stormwater system and streets shall be constructed and
accepted by the City prior to the issuance of any building permits.
The required public infrastructure for this project includes replacing the existing 13”x13” square
concrete storm drain manhole and grate along the E. Mendenhall project frontage, with a new city
standard 36” diameter storm drain inlet.
The provisions of subsections 38.270.030.C.1.b & c are met as follows:
b. The storm drain to be replaced is located entirely within public right-of-way; it shall be
designed and constructed according to city standards; it is adjacent to the subject property; it
shall be installed and accepted by the city; and it will be adequate in capacity to provide
necessary service to the project.
c.(1) There are no on or off-site public extensions required for the project.
c.(2) There is an existing fire hydrant located at the intersection of E. Mendenhall and N.
Broadway providing adequate fire protection. A copy of the hydrant flow test is included
with this application. Existing water supply to the property is from the city municipal
system and shall provide adequate supply during construction.
c.(3) The final engineering design plans shall be approved by the City Engineering
Department prior to the issuance of any building permits.
c.(4) No occupancy permit shall be issued prior to the completion and final acceptance of
the stormwater improvements.
BG MILL||
SPR SUBMITTAL
BG MILL | NORTHERN PACIFIC ADD, S07, T02 S, R06 E, LOT 1, PLAT C-23-A11 | BOZEMAN, MT, 59715
013CCON
CCON - CONCURRENT CONSTRUCTION FOR
EXISTING INFRASTRUCTURE OR ON-SITE
BRIDGER ENGINEERS, INC. Page 2
We believe this to be a reasonable request since the work can easily be accomplished during the
construction timeframe of the on-site improvements; and the approval of this request would allow
for scheduling the construction at a desirable time without delaying project approval and
construction.
Thank you for your time and consideration of this request.
Sincerely,
Melanie Dyba, P.E.
Bridger Engineers, Inc.
cc: File