HomeMy WebLinkAbout010 Geotechnical Report
GEOTECHNICAL REPORT FOR:
Lumber Yard Apartments
Bozeman, Montana
April 2022
Project 22-015
Allied Engineering Services, Inc. Page 1
TABLE OF CONTENTS
INTRODUCTION ............................................................................................................................................. 4
DESCRIPTION OF PROPERTY ......................................................................................................................... 4
SCOPE OF WORK ........................................................................................................................................... 5
EXECUTIVE SUMMARY .................................................................................................................................. 5
GEOLOGY ....................................................................................................................................................... 6
EXPLORATIONS, TESTING, AND SUBSURFACE CONDITIONS ......................................................................... 6
Subsurface Explorations ........................................................................................................................... 6
Soil Conditions .......................................................................................................................................... 7
Groundwater Conditions .......................................................................................................................... 8
Laboratory Testing .................................................................................................................................... 8
GENERAL CONSTRUCTION RECOMMENDATIONS ........................................................................................ 8
Sediment Control ...................................................................................................................................... 8
Topsoil Stripping and Re-Use .................................................................................................................... 8
Moisture Sensitivity of Fine-Grained Soils ................................................................................................ 9
Excavation and Re-Use of On-Site Soils .................................................................................................... 9
Groundwater Dewatering ......................................................................................................................... 9
FOUNDATION, SLAB, AND DRAINAGE RECOMMENDATIONS ....................................................................... 9
Seismic Design Factors.............................................................................................................................. 9
Building Foundation Design .................................................................................................................... 10
Slab and Footing Elevations .................................................................................................................... 10
Foundation Support Under Buildings – Option 1: Over-Excavation and Replacement .......................... 10
Foundation Support Under Buildings – Option 2: Helical Piers .............................................................. 12
Interior Concrete Slabs Under Buildings................................................................................................. 13
Lateral Earth Pressures ........................................................................................................................... 14
Foundation Wall Backfill ......................................................................................................................... 14
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 2
Surface Water Drainage ......................................................................................................................... 15
Subsurface Drainage and Damp-Proofing .............................................................................................. 15
Vapor Barrier .......................................................................................................................................... 15
Exterior Concrete Slabs – Sidewalks ....................................................................................................... 15
Exterior Concrete Slabs and Garage Slabs .............................................................................................. 16
FOUNDATION-RELATED FILL MATERIAL RECOMMENDATIONS .................................................................. 16
Excavated Foundation Soils .................................................................................................................... 16
Sandy (Pitrun) Gravel .............................................................................................................................. 17
Crushed (Road Mix) Gravel ..................................................................................................................... 17
Clean Crushed Rock ................................................................................................................................ 17
Fill Placement and Compaction .............................................................................................................. 17
Granular Structural Fill Under Footings and Interior Slabs: ............................................................... 18
Embankment Fill Under Interior and Exterior Slabs:.......................................................................... 18
Backfill Behind Foundation and Retaining Walls: .............................................................................. 18
UNDERGROUND UTILITY RECOMMENDATIONS ......................................................................................... 18
ASPHALT PAVEMENT RECOMMENDATIONS ............................................................................................... 19
Pavement Section Design ....................................................................................................................... 19
Pavement Section Materials, Placement, and Compaction ................................................................... 21
COLD/WINTER WEATHER CONSTRUCTION ................................................................................................. 21
FUTURE AESI INVOLVEMENT ...................................................................................................................... 22
LIMITATIONS ............................................................................................................................................... 22
REFERENCES ................................................................................................................................................ 23
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 3
SUPPLEMENTAL INFORMATION
• List of Tables
o Table 1. Compaction Recommendations (Application vs. Percent Compaction)
o Table 2. Pavement Section Design – Parking Lots (Stable Subgrade)
o Table 3. Pavement Section Design – Parking Lots (Unstable Subgrade)
o Table 4. Pavement Section Design – Local Roads (Stable Subgrade)
o Table 5. Pavement Section Design – Local Roads (Unstable Subgrade)
• List of Figures
o Figure 1 – Vicinity Map
o Figure 2 – Quadrangle Map
o Figure 3 – Test Pit Location Map
o Figure 4 – Geology Map
o Figure 5 – Groundwater Map
• List of Appendices
o Appendix A – Test Pit Logs and Borehole Logs
o Appendix B – Laboratory Testing Results
o Appendix C – Pavement Section Design
o Appendix D – Limitations of Your Geotechnical Report
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 4
INTRODUCTION
This report presents our geotechnical assessment for the proposed Lumber Yard Apartments
located just north of Kenyon Noble in Bozeman, Montana. Presented herein is a description of
the site’s soil and groundwater conditions and our geotechnical analysis and recommendations
for foundation support and drainage. We are assuming standard construction practices in this
report and suggest AESI remain involved in both the design and construction of structures on
this property to assure the work is completed consistent with our recommendations.
The geotechnical information contained herein is based on an investigation and analysis of the
subsurface conditions, laboratory testing of select soil samples, a review of geologic maps for
the general area, and previous experience on similar projects in Bozeman. The purpose of this
report is to inform all associated parties of the site’s soil and groundwater conditions and its
critical geotechnical issues; and to provide important recommendations that pertain to general
earthwork, foundations, slabs, walls, fill materials, underground utilities, asphalt pavement
sections, and surface and subsurface drainage. Note that this work was completed as a
continuation of earlier work completed by this firm on a much larger parcel, which this property
was once part of.
DESCRIPTION OF PROPERTY
The Lumber Yard Apartments property is comprised of Lots 1, 2, and 3A of Block 3 per Plat J-
498. Lot 1 is approximately 1.64 acres, Lot 2 is approximately 1.19 acres, and Lot 3A is
approximately 9.06 acres. The combined 11.89-acre property is bound by Patrick Street to the
south, the extension of North 15th Avenue to the west, North 11th Avenue to the east, and an
undeveloped field to the north. Please see Figures 1 and 2 for illustrations showing the site
location and property lines. The legal description for the site is Lots 1, 2, and 3A of Block 3, PT
Land Phase 2 Subdivision per Plat J-498, located in a portion of the Northwest One-Quarter of
Section 1, Township 2 South, Range 5 East, Principal Meridian Montana, Gallatin County,
Montana.
We understand the proposed development includes six apartment buildings up to four stories
tall, six carriage buildings, a clubhouse/leasing building, and one commercial building in the
northwest corner of the site. The proposed development will also include associated parking
facilities, the extension of local streets, and the installation of utilities (i.e., water, sewer, storm
sewer, and dry utilities). No plans (beyond the site plan) have been provided to-date, but we
anticipate the buildings will consist of concrete slab-on-grades with associated frost
walls/footings and spread footings. Given the elevated groundwater levels found across much
of the site, slab-on-grade buildings will be the most appropriate option for the development.
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 5
SCOPE OF WORK
The scope of services for this project included:
• Review of available geologic maps and previous AESI geotechnical report from 2016.
• Excavation of four (4) additional test pits across the property and installation of monitor
wells in each test pit.
• Laboratory testing of select samples from the test pits.
• Providing allowable bearing capacity criteria.
• Providing lateral earth pressures.
• Surface and subsurface drainage recommendations.
• Backfill material and compaction recommendations.
• Asphalt pavement section materials and design thickness.
EXECUTIVE SUMMARY
Subsurface conditions were found to be relatively consistent between the March 2022
subsurface explorations and the November 2016 explorations. The 2022 explorations included
four (4) shallow test pits dug with an excavator and the installation of four (4) monitor wells for
future monitoring of water levels. The 2016 explorations consisted of five (5) shallow test pits
and four (4) boreholes extended to depths of up to 30 feet.
The general soil profile consisted of 4.0 to 8.0 feet of very soft, very moist to wet, fine-grain
silt/clay overlying medium dense to very dense alluvial gravels. During our March 2022
explorations, groundwater was measured at depths ranging from 5.0 to 7.5 feet below existing
ground. Weekly groundwater monitoring has shown that groundwater levels have come up
since the time of the explorations. At the time of this report (April 19, 2022), the shallowest
groundwater level recorded is 2.25 feet below the ground surface in MW-3. Please refer to
Figure 3 for the approximate test pit and monitor well locations. AESI will continue monitoring
on a weekly basis through peak groundwater season. During the November 2016 explorations,
groundwater levels ranged from 2.8 to 8.0 feet deep.
Given the shallow depth to groundwater in many areas of the site, we expect the elevation of
many of the proposed buildings will be raised. Raising the finished floor elevation will help
promote positive drainage away from each building. Given the depth to “target” bearing in the
native gravels and the anticipated elevation of the main floors, granular structural fill will most
likely be required to bring the subgrade up from the “target” bearing layer (gravel) to the
footing/slab grades. Depending on the target bearing depth relative to footing elevation, the
required thickness of structural fill could range from approximately 3.0 to 7.0 feet depending on
location. Dewatering will likely be required to install the structural fill.
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 6
Since much of the overlying fine-grain soils are wet and soft, one option is to remove all fine-
grain native material (clay and silt) within the building footprints down to the target bearing
soils (sand and gravel) and replaced with structural fill. The second option is to chase out the
fine-grains soils down to gravel under footings only and leave the fine-grain soil in place under
interior slabs. A significant gravel section with geotextile reinforcement would be required to
support the interior slabs if the fine-grain soil is left in place.
Given the depth to target bearing, a final option to provide foundation support is the
installation of helical piers at regular spacings under the buildings which would eliminate the
need for structural fill. We anticipate the helical piers would be installed at 10-foot spacings
and the footings would be designed as grade beams to span the helical piers. The slabs could
also be supported on helical piers to eliminate the need to remove the soft, fine-grain silt and
clay or sufficient gravel with geotextile reinforcement as described later. We briefly considered
the use of rammed aggregate piers (RAPs) but based on previous experience would be
concerned that the integrity of the RAPs could be compromised if installed in groundwater and
soft fine-grained soils.
The design team could also consider using a combination of these methods across the property
depending on the depth to the gravel and/or the depth to high groundwater.
GEOLOGY
According to the preliminary geologic map prepared by Lonn and English in 2002 for the
eastern part of the Gallatin Valley (Figure 4), the project site is underlain by Quaternary-aged
alluvium of braid plains deposits (Qabo). Based on previous geotechnical experience, the soil
stratigraphy in this general area of Bozeman usually consists of topsoil overlying a mantling of
silt, clay, and/or sand, which in turn overlies alluvial sands and gravels. Consolidated beds of
Tertiary-aged gravels, sands, silts, and clays underlie the Quaternary gravel deposits throughout
the Bozeman area. Our test pit and borehole findings were consistent with the described soil
conditions.
EXPLORATIONS, TESTING, AND SUBSURFACE CONDITIONS
Subsurface Explorations
Subsurface conditions were investigated at the project site on March 10, 2022, under the
direction of Erik Schnaderbeck, a professional geotechnical engineer with Allied Engineering. A
total of four (4) additional test pits were dug in the areas of the proposed improvements. Five
(5) test pits and four (4) boreholes were completed across the property during our original
subsurface explorations in November of 2016. The 2022 test pits (identified as TP-1 through TP-
4) were completed using a Hitachi 130 excavator provided by RLS Construction of Manhattan,
Montana. The test pits were located at various strategic locations across the property to
provide an idea of soil variability within the development. Test pits ranged from 9.0 to 9.5
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 7
feet deep. See Figure 3 for an exhibit showing the approximate test pit locations from 2022, as
well as applicable test pit and borehole locations from 2016.
During the explorations, soil and groundwater conditions were visually characterized,
measured, and logged. The relative densities of the exposed soil profiles were estimated based
on the ease or difficulty of digging and the overall stability of the completed excavations. Copies
of our test pit and borehole logs are attached in Appendix A. Each of the logs provide assorted
field information, such as soil depths and descriptions, groundwater conditions, relative density
data, sample information, and a diagram of the soil stratigraphy. Please be aware that the
detail provided on the logs cannot be accurately summarized in a paragraph; therefore, it is
important to review the logs in conjunction with this report. Following the completion of the
fieldwork, the test pit locations were backfilled with native soils and cleaned up to the extent
possible. Each location was staked with a wooden lathe that identified it accordingly. If any test
pits underlie future site improvements, they should be completely re-excavated and backfilled
in properly compacted lifts to avoid undesirable settlements.
Soil Conditions
Similar soil conditions were encountered in all four test pits. In general, subsurface conditions
consisted of 1.25 to 2.5 feet of topsoil overlying very soft, very moist to wet, fine-grain sandy
silt/clay that extended to 4.0 to 7.0 feet and became softer with depth. Underneath the fine-
grain silt/clay, we encountered dense to very dense alluvial sandy gravel with 3-inch to 6-inch
minus rounded cobbles. The sandy gravel extended to the bottom of all four test pits which
reached 9.0 to 9.5 feet in depth.
Subsurface explorations in 2016 were consistent with the explorations completed in 2022. Five
test pits (identified as TP-4 through TP-8) and four boreholes (identified as BH-5 through BH-8)
were completed across the property during our original subsurface explorations in 2016. The
explorations generally found 0.75 to 2.0 feet of topsoil overlying fine-grain sandy silt/clay that
extended to 4.0 to 8.0 feet. Underneath the fine-grain silt/clay, soil conditions transitioned to
medium dense to very dense alluvial sandy gravel with cobbles up to six inches in diameter. The
sandy gravel extended to the bottom of all test pits and boreholes. The test pits ranged from
5.5 to 9.0 feet in depth while the boreholes ranged from 16.0 to 30.0 feet in depth.
Target bearing for foundations is within the native sandy gravel deposits found at a depth of
4.0 to 8.0 feet depending on location. Foundation support recommendations provided later in
this report are based on excavation to the native sandy gravel and placement of the footings
either directly on the native sandy gravel or on granular structural fill that bears on the native
sandy gravel. Alternative options include the use of helical piers that support footings/slabs
and extend to the native gravel.
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 8
Groundwater Conditions
During our March 2022 explorations, groundwater was encountered at depths of 5.0 to 7.5 feet
below existing grade depending on location. Groundwater levels ranged from 2.8 to 8.0 feet
deep during the November 2016 explorations. The groundwater table throughout the
Bozeman area fluctuates on a seasonal basis depending on the time of year. Groundwater
levels are typically at their lowest during the winter season and at their highest during the
spring and early summer due to runoff from mountain snowmelt and spring rains. We
anticipate groundwater levels to rise well above the 5.0 to 7.5-foot mark as more of the
mountain snowpack melts. Monitoring wells installed in all four test pits in March 2022 and the
two wells installed in 2016 are currently being monitored by AESI on a weekly basis through the
peak groundwater season. The highest groundwater level recorded as of the date of this report
(April 19, 2022) is 2.25 feet below the ground surface in MW-3. Please refer to Figure 3 for
approximate monitor well locations. Groundwater monitoring data can be provided upon
request and results will be issued at the end of monitoring.
Construction of the foundations and utilities will be impacted by high groundwater levels. The
Contractor should be made aware of this prior to construction. We anticipate that
groundwater dewatering will be required during construction.
Laboratory Testing
Multiple soil samples were collected from each test pit during the explorations. All sack
samples were tested in the AESI laboratory for natural moisture content. Laboratory testing
results are found in Appendix B.
GENERAL CONSTRUCTION RECOMMENDATIONS
Sediment Control
Prior to beginning any earthwork construction at the site, adequate sediment control measures
must be in place to prevent disturbed soils/sediment from being carried down slope and off the
site via surface water runoff. According to Montana State Law, all surface waters must be fully
protected from the introduction of sediment by construction-related activities. Most obviously,
sediment protection barriers will need to be placed along/around all established drainages,
waterways, ponds, wetlands, storm water catch basins, etc, that lie within or adjacent the
project area. In addition to protecting these elements, we also believe it is a responsible
practice to install a continuous barrier along the down slope side of the construction limits,
especially on sloping sites. This “minimal level of effort” will help keep disturbed soils as close
to the “source area” as possible and restrict them from being washed of property.
Topsoil Stripping and Re-Use
A majority of the site is covered by some form of topsoil. All organic soils must be adequately
stripped from within each building’s foundation footprint and in all exterior areas that will
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 9
receive asphalt surfacing, concrete slabs, or embankment fills. Final site grading (in landscape
areas) and the reclamation of disturbed construction areas are the only recommended re-uses
for this organic material.
Moisture Sensitivity of Fine-Grained Soils
The fine-grained soils (silt/clay) that underlie the site are moisture sensitive materials that can
be problematic during construction. It should be noted that the fine-grained soils onsite are
already overly moist and excessively wetted by high groundwater levels. It is anticipated that
some drying and re-working of the material will be required to enable the sols to be workable
and suitable for earthwork construction. Assuming the materials can be properly dried, these
soils should be workable and suitable for earthwork construction. However, with only minor
increases in moisture content, compaction of these soils can be difficult, if not impossible, until
they are adequately dried. The air drying of fine-grained soils requires time, warm weather,
and often scarification. For this reason, exposed soils should be protected against precipitation
and infiltration. Excavated and fill surfaces should never be left in a rough condition with
undrained depressions. In addition to becoming hard to compact in wet conditions, the soils
are susceptible to erosion and frost heave. Stormwater pollution prevention (SWPPP) measures
should be considered to minimize erosion as discussed above. Furthermore, care should be
taken to ensure concrete is not poured over frozen ground that is in a frost heaved condition.
Excavation and Re-Use of On-Site Soils
Much of the soil that will be excavated during foundation and general site earthwork will
consist of native silt, clay, sand, and gravel. In general, these soils can be re-used as site fill,
embankment fill, exterior foundation wall backfill, and trench backfill provided they have a
moisture content that is conducive for proper compaction. For a more detailed discussion on
the acceptable re-use of excavated on-site soils, please refer to the foundation-related fill
material section later in this report.
Groundwater Dewatering
As noted earlier, groundwater dewatering will be necessary for nearly all aspects of
construction.
FOUNDATION, SLAB, AND DRAINAGE RECOMMENDATIONS
Seismic Design Factors
Based on our on-site explorations and knowledge of the underlying geology, the seismic site
class for the project should be Site Class D (as per criteria presented in the 2018 IBC). Please
note that is not the Default Site Class D.
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 10
Building Foundation Design
We have assumed the new buildings will be underlain by a concrete slab-on-grade with
conventional frost walls and footings around the perimeter and interior spread footings. The
site’s subsurface conditions will allow for the use of a shallow foundation system (conventional
strip and spread footings) provided all footings are constructed in accordance with our
geotechnical recommendations. The use of helical piers is also an option at the site as
discussed earlier.
We considered the use of crawlspace foundations at the site, but do not have enough
information currently to provide specific recommendations due to the unknown levels that high
groundwater may reach. Proper separation between footing grades and high groundwater
would be required. If possible, we recommend maintaining a minimum of two feet of
separation between high groundwater and the bottom of footings in crawlspace applications.
Note that providing appropriate separation in crawlspace applications will require additional
structural fill to extend from the target bearing sandy gravels encountered at 4.0 to 8.0 feet
below existing grade up to footing grade. Achieving this separation will also result in higher
finished grades across the site to maintain 4 feet of cover for frost protection, increasing costs
associated with fill. Substantial subsurface drainage measures will also likely need to be
implemented in crawlspace applications given the possibility of water intrusion into the
crawlspace. Clean crushed rock would be recommended to infill the crawlspace up to top of
footings. Given the flatness of the site, perimeter footing drains and sub-drains in the
crawlspace will need to connect to an exterior sump to pump out any water. Based on our
experience with other projects in the City of Bozeman and surrounding area, there are
associated challenges with pumping out groundwater and re-routing the water away from the
structures to an acceptable location that does not impact surrounding structures. For these
reasons, we suggest staying away from crawlspace foundations if possible.
Slab and Footing Elevations
Assuming buildings will be constructed on slab-on-grade foundations with finished floor
elevations set two to three feet above existing grade, we anticipate that 3.0 to 7.0 feet of
structural fill may be required to extend from the target bearing gravels up to the bottom of
footings. For frost protection, exterior footings should bear at a depth of four feet below the
lowest adjacent exterior finished grade.
Foundation Support Under Buildings – Option 1: Over-Excavation and Replacement
The native sandy gravel found at a depth of 4.0 to 8.0 feet is the “target” foundation bearing
material for building improvements. All foundation components, including perimeter, interior,
and exterior footings, must bear on the native gravels or granular structural fill that extends
from the native gravels up to the footing grade. Two options are provided below with respect
to the installation of structural fill under footings.
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 11
The first option is to mass-excavate down to the target bearing gravels within the footprint of
the buildings and replace with compacted structural fill. This may be the easiest and quickest
option if there are a significant number of interior spread footings that need to be excavated as
well. For this scenario, the minimum excavated width (beyond the outside edge of perimeter
footings) will depend on the thickness of granular structural fill to be placed under the footing.
The excavation should extend a minimum of one-half (½) the required thickness of structural fill
at any given location beyond the outside edge of the perimeter footing, but at a minimum
should extend 4.0 feet. This dimension is measured at the bottom of the excavation.
An additional option is to excavate only the footing lines down to the native gravels and leave
some of the fine-grained silt/clay under the slab. This option is only acceptable if the upper
fine-grain soils are relatively dry and stable. If this option is selected, we must evaluate the
fine-grain soils at the time of excavation to verify they are relatively dry and stable and
enough gravel and geotextile reinforcement is added to adequately support the slab as
described below. For individual footing lines, the width of the excavation (to ensure load
transfer occurs in the structural fill) is the width of the footing plus the depth from the bottom
of footing to target bearing (essentially 0.5H:1V). For instance, if the width of the footing is 2
feet and the depth to the native gravels below the bottom of footing is 3 feet, the necessary
width of the excavation is 5 feet. The footing is assumed to be centered on the trench. In this
scenario, the slab should be supported directly on six inches of clean crushed rock overlying 15
inches of granular structural fill that in turn bears on the native fine-grained soils. The native
fine-grained soils should be proof rolled to an unyielding condition and covered with a woven
Mirafi 600x geotextile fabric prior to the placement of structural fill. If any wet or soft spots are
identified in the subgrade, they should be completely removed and replaced with lifts of
compacted granular structural fill. Both the structural fill and clean crushed rock should be
vibratory compacted to an unyielding condition with a large smooth drum roller.
For exterior footings outside the building footprint that will be excavated and/or over-
excavated on an individual basis, the minimum excavation dimensions (centered under the
footing) will depend on the thickness of granular structural fill to be placed under the footing,
as well as the footing width. The minimum excavation width is equal to the footing width plus
the thickness of structural fill under the footing. For instance, if the exterior spread footing is 4
feet by 4 feet and the depth to the native gravel from the bottom of footing is three feet, the
dimensions of the over-excavation (measured at the bottom of the excavation) will be 7 feet by
7 feet. The spread footing would need to be centered on the over-excavation. The over-
excavated dimensions will allow footing loads to be transmitted within the structural fill to the
target bearing soils.
If the excavation is only dug to the minimum width dimensions that will satisfy the compacted
structural fill requirement, it is important that proper compaction of the structural fill is
achieved along the edges and in the corners of the excavation. To accomplish this, the use of
small compaction equipment that can “hug” the side of the excavation will be necessary.
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 12
Alternatively, the excavation can be widened beyond the minimum width dimensions to allow
for the use of a larger roller. The compaction of granular structural fill materials can be
accomplished more effectively and efficiently with large, self-propelled, smooth drum rollers.
For this reason, we suggest foundation excavations be made wide enough to accommodate a
large roller.
In the event groundwater is encountered at the bottom of the excavation (at the native gravel
elevation), clean crushed rock may be placed to raise the bottom of the excavation above the
groundwater before switching to more traditional structural fill (pit run or crushed sandy
gravel). Providing separation from groundwater using the non-moisture-sensitive clean crushed
rock will avoid the saturation of the structural fill and subsequent difficulty with compaction.
Clean crushed rock should be placed in lifts not exceeding 12 inches and vibratory compacted.
Clean crushed rock should be covered with a nonwoven geotextile fabric such as a Mirafi 180N
or equal prior to structural fill placement to prevent the migration of fines into the crushed
rock.
Prior to pouring footings or placing structural fill, the native subgrade should be proof-rolled to
an unyielding condition. Any soft or overly moist areas should be removed and replaced with
lifts of structural fill compacted to a dense, unyielding condition. A leveling course of crushed
rock may be used if there are excessive large rocks in the subgrade that would create an
uneven bearing surface.
For a complete description of acceptable import, granular structural fill alternatives, along with
our specifications for the placement and compaction of these materials, please refer to a later
section of this report. In summary, there are only two available options for structural fill under
footings (as well as under the entire building area). These include 4”-minus sandy (pitrun)
gravel or 1.5”-minus crushed (road mix) gravel.
Please recognize that groundwater dewatering will likely be necessary to install the structural
fill given the elevated groundwater levels found across much of the site.
Provided our recommendations are followed (as described above), the allowable bearing
pressure for all perimeter, interior, and exterior footings is 3,000 pounds per square foot (psf).
Allowable bearing pressures from transient loading (due to wind or seismic forces) may be
increased by 50 percent. We estimate that the above-referenced bearing pressure will result in
total settlements of less than one inch, with only minor differential settlements. This bearing
capacity only applies if our recommendations are followed.
Foundation Support Under Buildings – Option 2: Helical Piers
A second option to provide foundation support is the installation of helical piers, which would
eliminate much of the need for structural fill. We anticipate the helical piers would be installed
at regular 10-foot spacings down to the target bearing soils and the footings designed as
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 13
grade beams to span the helical piers. The slabs could also be supported on helical piers to
eliminate the need to remove the soft, fine-grain silt and clay or gravel and geotextile as
described below. The helical piers would penetrate the soils and torque up to the appropriate
level to achieve a working load, design capacity of 25 to 50 kips. Assuming a factor of safety of
2.0, the ultimate capacity of the helical piers would be 50 to 100 kips. The piers may be
battered as necessary to provide uplift and lateral resistance. We recommend that test piers be
completed in this area to determine if the recommended capacities and associated installation
torques can be achieved.
We recommend piers manufactured by AB Chance or an approved equal. All helical piers shall
be galvanized for corrosion protection. In this case, interior and exterior grade beams/footings
should be designed to span between the helical piers with no support provided by the soils.
Alternatively, if the interior slabs and interior footings will not be supported by helical piers, we
recommend supporting the slab directly on six inches of clean crushed rock overlying 15 inches
of granular structural fill. The native subgrade should be proof rolled to an unyielding condition
and covered with a woven Mirafi 600x geotextile fabric prior to the placement of structural fill.
If any wet or soft spots are identified in the subgrade, they should be completely removed and
replaced with additional lifts of compacted granular structural fill. Both the structural fill and
the clean crushed rock should be vibratory compacted to an unyielding condition with a large
smooth drum roller. If this alternative is selected, we recommend we be allowed to evaluate
the condition of the fine-grained subgrade at the time of excavation.
As mentioned previously, the design team could also consider utilizing both the above
discussed options for individual buildings depending on the depth to gravel in that area. We
would be happy to provide additional recommendations/details if helical piers are the chosen
option.
Interior Concrete Slabs Under Buildings
All interior slabs must be supported on at least six inches of clean crushed rock, which in turn
overlies 15 inches (min.) of granular structural fill and geotextile reinforcement. If mass
excavation down to native gravels under the footprint of the buildings is chosen, the geotextile
reinforcement may be eliminated. Based on the 4.0-to-8.0-foot depth to native gravel in the
building areas, and the assumption that finished floor elevations will be set above existing site
grades, multiple feet of granular structural fill will need to be placed in the footprint area to
build back to interior slab grade.
Both the crushed rock and structural fill materials must be compacted to a dense and
unyielding condition by vibratory methods. A large, smooth drum roller should be used to
compact granular structural fill whenever possible. Native subgrade should be compacted to an
unyielding condition prior to the placement of structural fill.
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 14
Lateral Earth Pressures
All foundation walls that will be fixed at the top prior to the placement of backfill should be
designed for an “at rest” equivalent fluid pressure of 60 pounds per cubic foot (pcf). In
contrast, cantilevered retaining walls may be designed for a lower, “active” equivalent fluid
pressure of 45 pcf, provided either some slight outward rotation of the wall is acceptable upon
backfilling or the wall is constructed in such a way that accommodates the expected rotation.
These “at rest” and “active” design values are only applicable for walls that will have backfill
slopes of less than ten percent; and which will not be externally loaded by surface pressures
applied above and/or behind the wall.
Lateral forces from wind, earthquakes, and earth pressures on the opposite side of the
structure will be resisted by passive earth pressure against the buried portion of the foundation
wall and by friction at the bottom of the footing. Passive earth pressures in compacted, fine-
grained backfill should be assumed to have an equivalent fluid pressure of 280 pcf; while a
coefficient of friction of 0.4 is estimated between cast-in-place concrete and granular structural
fill or native gravel. Actual footing loads (not factored or allowable loads) should be used for
calculating frictional resistance to sliding along the base of the footing. Please be aware that
the friction coefficient has no built-in factor of safety; therefore, an appropriate safety factor
should be selected and used in all subsequent calculations for each load case.
The lateral earth pressures summarized above assume that the wall will be backfilled with a
suitable material that is compacted to an unyielding condition. It is also assumed that proper
drainage measures will be taken to prevent the development of hydrostatic pressures. The
lateral earth pressures provided are for static conditions and should be factored accordingly for
seismic conditions.
Foundation Wall Backfill
Exterior foundation wall backfill can consist of any excavated foundation soil, other than
topsoil, provided it is not overly moist, highly plastic, or too rocky in composition. In contrast,
interior foundation wall backfill shall be limited to the use of granular structural fill materials
only. The native soils may require drying prior to re-use as backfill. All select backfill materials
must be placed in multiple, thin lifts and properly compacted to 95 percent of their Standard
Proctor density. Foundation walls intended to be braced should not be backfilled until the
bracing (such as floor joists) is in place to prevent unintended rotation/deflection of the wall. To
prevent damaging foundation walls during the backfilling process, only hand-operated
compaction equipment is recommended within three feet of walls that are not buried on both
sides. To minimize the potential for future settlement problems, the level of care (with respect
to the selection of dry backfill materials and the compactive effort that is used) should be
increased significantly in those areas that will receive concrete/asphalt surfacing or that will
support a retaining wall. Finally, the re-use of topsoil as backfill should be limited to the
uppermost four to six inches in landscaped areas. To reduce the infiltration capacity of the
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 15
topsoil (directly next to the foundation wall), it should be well compacted (especially under rock
or mulch-filled landscape beds).
Surface Water Drainage
No water should be allowed to accumulate against or flow along any exposed foundation walls.
Concrete or asphalt surfacing that abuts the foundation should be designed with a minimum
grade of 2 percent away from all structures, and adjacent landscaped areas should have a slope
of at least 5 percent within 10 feet of the wall (see the IBC building codes). To further reduce
the potential for moisture infiltration along foundation walls, backfill materials should be well-
compacted. The upper 4 to 6 inches of backfill should consist of low permeability topsoil.
Except for the locations that will be surfaced by concrete or asphalt, finished grades next to
foundation walls should be set no less than 6 inches below the top of the sill plate.
We recommend that sediment protection barriers be installed at all points of concentrated
discharge, such as at the end of a ditch/swale, to keep all disturbed soils on the property.
Subsurface Drainage and Damp-Proofing
As noted earlier, there is significant complexity with installing footing drains and interior
subdrains in crawlspace applications. The site is relatively flat with no place to daylight
drainage. Therefore, we anticipate sumps and pumps would be required. However, this option
becomes even more complicated in that the City does not allow dewatering elements that are
routed to storm drainage ponds. For these reasons, we have significant concern with the use of
crawlspaces and would lean more towards slab-on-grade foundations.
Perimeter footing drains for slab-on-grade foundations are not necessary unless the exterior
grade will extend above the top of slab (which is normally not done).
Buried foundation walls should be damp-proofed with an acceptable commercial product as per
the requirements of the International Building Code (IBC 2018).
Vapor Barrier
To control moisture vapor, we recommend installing a heavy-duty vapor barrier directly under
interior slabs. We recommend a vapor barrier with a water vapor transmission rate of 0.006 or
lower as established by ASTM E 96, such as a Stego 15-mil Vapor Barrier. The vapor barrier
should be installed as per the manufacturer recommendations and ASTM E 1643, ensuring it is
properly attached to footings/walls and sealed at the seams.
Exterior Concrete Slabs – Sidewalks
Depending on site grading, exterior concrete sidewalks can either be supported on non-organic,
native soils or on embankment fill material that is placed above the stripped subgrade surface
to raise design elevations. The City of Bozeman standard details for non-traffic and traffic
slabs depict four and six-inch sections of concrete, respectively, overlying three inches of
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 16
clean crushed rock. We believe a three-inch thickness of crushed rock under slabs is a
“minimum value” and, in fact, recommend that it be thickened to at least six inches. The
placement of additional crushed rock will increase the drainage capacity under the sidewalk as
well as provide additional separation from the underlying fine-grained soils. Consequently, the
frost heave potential of the slab should be reduced. Prior to placing embankment fill or
crushed rock, both of which must be adequately compacted, the excavated subgrade surface
should be compacted and proof-rolled to confirm its stability. If soft or wet areas are identified,
these areas should be over-excavated and replaced with suitable, compacted structural fill.
Exterior Concrete Slabs and Garage Slabs
Depending on site grading, exterior concrete slabs can be supported on non-organic native soils
or on compacted on-site soils (see Excavated Foundation Soils section later in this report)
placed above the stripped subgrade surface to raise design elevations. Traffic-loaded exterior
slabs should be underlain by a minimum of six inches of clean crushed rock and 12 inches of
granular structural fill reinforced with woven geotextile fabric (Mirafi 600X or equal).
Thickening the crushed rock layer to greater than six inches will improve the drainage capacity
under the slab as well as provide additional separation from the underlying soils. Consequently,
the frost heave potential of the slab should be reduced. Critical exterior slab areas which
cannot undergo any heaving should be underlain by additional crushed rock and two inches or
more of below-grade insulation extending outward two feet from the edge of the slab to limit
frost penetration. Prior to placing any embankment fill or structural fill, both of which must be
adequately compacted, the subgrade surface should be proof-rolled to confirm its stability. If
soft or wet areas are identified, they should be over-excavated and replaced with suitable,
compacted structural fill.
FOUNDATION-RELATED FILL MATERIAL RECOMMENDATIONS
Provided below are our recommendations for the foundation-related fill materials that may be
used during construction. These include on-site excavated soils, sandy (pitrun) gravel, crushed
(road mix) gravel, and clean crushed rock. General placement and compaction criteria follow
the specifications.
Excavated Foundation Soils
During foundation and site earthwork, excavated soils will include native topsoil, silt, clay, sand,
and gravel. Please refer to an earlier section of the report, along with the attached exploration
logs found in Appendix A, for a detailed description of the site’s subsurface conditions.
Based on the shallow groundwater levels found across the development, some saturation of
the upper fine-grain soils should be expected. For this reason, moisture conditioning (by
drying) will be needed to reuse this material. The acceptable re-uses of this material include
site fill, embankment fill, exterior foundation wall backfill, and trench backfill. Only the driest
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 17
soils should be used for compacted fill, while all wetter soils should be placed in non-critical
areas that do not require compaction or can tolerate some future settlement. Except for some
of the native sand and gravel, none of these soils will qualify for re-use as granular structural fill
under footings and interior slabs. Deleterious materials (fill, topsoil, fat clays, etc) should not
be used as foundation backfill.
Sandy (Pitrun) Gravel
Sandy (pitrun) gravel is a granular structural fill alternative for placement under exterior slabs,
pavements, and behind foundation walls. This material shall be a non-plastic, well-graded,
mixture of clean sand and gravel with 100 percent of its fragments passing a four-inch screen
and less than 10 percent of its particles (by weight) finer than the No. 200 sieve. In addition to
these material and gradation recommendations, it should meet all other applicable
specifications as presented in Section 02234 of the Montana Public Works Standard
Specifications (MPWSS) for uncrushed, sub-base course gravel.
Crushed (Road Mix) Gravel
Crushed (road mix) gravel is another granular structural fill alternative for placement under
and/or behind footings, slabs, and walls. This material shall be a non-plastic, well-graded,
mixture of clean, sand and gravel that is processed (crushed) such that 100 percent of its
fragments pass a 1-1/2-inch screen and less than 5 percent of its particles (by weight) are finer
than the No. 200 sieve. In addition, it should meet all other specifications as presented in
Section 02235 of the MPWSS for crushed, base course gravel.
Clean Crushed Rock
The primary uses for crushed rock include placement under concrete slabs and behind
foundation and retaining walls for drainage-related purposes. Crushed rock shall consist of a
clean assortment of angular fragments with 100 percent passing a one-inch screen and less
than 1 percent (by weight) finer than the No. 100 sieve. This aggregate product needs to be
manufactured by a crushing process and over 50 percent of its particles must have fractured
faces. It is not acceptable to use rock that contains abundant spherical particles for foundation-
related applications.
Fill Placement and Compaction
All fill materials should be placed in uniform, horizontal lifts and compacted to an unyielding
condition. This includes clean crushed rock, which can be compacted and/or consolidated by
vibratory means. The maximum “loose lift thickness” for all fill materials (prior to compaction)
should be limited to 10 inches for large, self-propelled rollers, 6 inches for remote-controlled,
dual drum rollers, and 4 inches for walk-behind plate or jumping jack compactors. The
moisture content of any material to be compacted should be within approximately two (2)
percent (+/-) of its optimum value for maximum compaction.
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 18
Special attention must be paid to the proper compaction of structural fill materials along the
edges and in the corners of the foundation excavation. These areas are usually “tight and
confined” and, as a result, cannot be adequately compacted with large equipment. This is
especially important where footing alignments/locations are only over-excavated to the
minimum width requirements that were presented in an earlier section of this report. There
are two available options for dealing with this issue. Either small compactors must be used that
are able to “hug” the side of the excavation or the limits of the excavation must be increased
such that compaction of the entire minimum structural fill width can be achieved with larger
equipment.
Provided in Table 1 are compaction recommendations for general foundation applications.
These are presented as a percentage of the maximum dry density of the fill material as defined
in ASTM D-698.
Table 1. Compaction Recommendations (Application vs. Percent Compaction)
APPLICATION % COMPACTION
Granular Structural Fill Under Footings and Interior Slabs: 98
Embankment Fill Under Interior and Exterior Slabs: 95
Backfill Behind Foundation and Retaining Walls: 95
Clean Crushed Rock Under Slabs and Behind Walls: N/A (Vibration Required)
Site Fill Around Building and Under Pavement Areas: 95
UNDERGROUND UTILITY RECOMMENDATIONS
All underground utility improvements shall be designed according to City of Bozeman (COB)
standards and constructed in accordance with the Montana Public Works Standard
Specifications (MPWSS) and the COB Modifications to these specifications.
For the most part, water and sewer pipe will most likely be supported in the native gravels.
Given the elevated groundwater levels, dewatering will probably be required. Should utility
lines be supported by the upper fine-grained soils that were very moist and soft, Type 2
bedding may be required by the Engineer to support the lines. We recommend a bid item be
included on the bid form in case Type 2 bedding is deemed necessary.
During utility installation, the trench excavation soils will consist of native topsoil, silt, clay,
sand, and gravel. Much of the material could be very moist to saturated and may need to be
dried prior to re-use. All trench backfill materials should be placed in thin lifts and compacted
to at least 95 percent of the material’s maximum dry density. Given that the native gravels
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 19
contain abundant large cobbles, all utilities should be well-bedded with crushed rock in
accordance with COB and MWPSS standards.
ASPHALT PAVEMENT RECOMMENDATIONS
Pavement Section Design
Presented in Tables 2 through 5 is our recommended asphalt pavement section for all new
parking lots and local road improvements associated with the project. The design sections
assume a 20-year service life and are based on the site’s shallow, fine-grained subgrade soil
conditions, a conservative estimate for traffic loading, and our previous experience with other
similar developments. They were designed in accordance with City of Bozeman, Montana
Department of Transportation (MDT), and American Association of State Highway and
Transportation Officials (AASHTO) guidelines and standards. For a detailed review of our design
calculations and an explanation of design input parameters, please see the documentation
provided in Appendix C.
Tables 2 and 3 provide the recommended design thickness for parking lots assuming stable and
unstable subgrade conditions. As summarized in Table 3, if the subgrade conditions are
unstable, we suggest the addition of a non-woven geotextile fabric and geogrid to the design
section. All fabric and geogrid utilized should be overlapped at seams in accordance with
manufacturer recommendations. Geogrid seams should be zip-tied together.
Table 2. Pavement Section Design – On-Site Parking Lots – Option 1 Stable Subgrade
COMPONENT COMPACTED THICKNESS (IN)
Asphalt Concrete: 3
Base Course - Crushed (road mix) Gravel: 6
Sub-Base Course - Uncrushed Sandy (pitrun) Gravel: 15
Woven Geotextile Fabric (Mirafi 600X or Approved Equal): Yes
Stable Subgrade Soils (Less Topsoil): Compacted to 95%
TOTAL SECTION THICKNESS: 24
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 20
Table 3. Pavement Section Design – On-Site Parking Lots – Option 2 Unstable Subgrade
COMPONENT COMPACTED THICKNESS
Asphalt Concrete: 3
Base Course - Crushed (road mix) Gravel: 6
Sub-Base Course - Uncrushed Sandy (pitrun) Gravel: 15
Tensar TX-190L TriAxial Geogrid (No Approved Equals): Yes
8 oz. Non-Woven Geotextile Fabric (Mirafi 180N or Approved Equal): Yes
Unstable Subgrade Soils (Less Topsoil): Smooth and Rut-Free
TOTAL SECTION THICKNESS: 24
Tables 4 and 5 provide the recommended design thickness for local roads assuming stable and
unstable subgrade conditions.
Table 4. Pavement Section Design – Local Roads – Option 1 Stable Subgrade
COMPONENT COMPACTED THICKNESS (IN)
Asphalt Concrete: 3
Base Course - Crushed (road mix) Gravel: 6
Sub-Base Course - Uncrushed Sandy (pitrun) Gravel: 21
Woven Geotextile Fabric (Mirafi 600X or Approved Equal): Yes
Stable Subgrade Soils (Less Topsoil): Compacted to 95%
TOTAL SECTION THICKNESS: 30
Table 5. Pavement Section Design – Local Roads – Option 2 Unstable Subgrade
COMPONENT COMPACTED THICKNESS (IN)
Asphalt Concrete: 3
Base Course - Crushed (road mix) Gravel: 6
Sub-Base Course - Uncrushed Sandy (pitrun) Gravel: 21
Tensar TX-190L TriAxial Geogrid (No Approved Equals): Yes
8 oz. Non-Woven Geotextile Fabric (Mirafi 180N or Approved
Yes
Unstable Subgrade Soils (Less Topsoil): Smooth and Rut-Free
TOTAL SECTION THICKNESS: 30
Please note, unstable conditions are subgrade that ruts and deflects when proof-rolled with a
loaded truck. In those cases, we recommend switching to the unstable subgrade design section
(i.e., the addition of non-woven geotextile and geogrid).
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 21
Also note that if the subgrade conditions are stable, we still recommend the addition of a
woven geotextile separator fabric to separate the native fine-grain soils and the gravel.
Pavement Section Materials, Placement, and Compaction
The sub-base and base course materials that comprise the granular parts of the pavement
section shall consist of 4-inch minus uncrushed sandy (pitrun) gravel and 1-1/2-inch minus
crushed (road mix) gravel, respectively. Both gravel courses shall meet the material and
gradation specifications as presented in MPWSS, Sections 02234 and 02235. Under normal
circumstances, the gravel products shall be placed in loose lifts not exceeding 10 inches in
thickness (depending on size of the compactor) and compacted to at least 95 percent of the
maximum dry density as defined in ASTM D-698. However, if subgrade soils are found to be
overly soft and the sub-base gravel section needs to be increased to greater than 15 inches, we
recommend placing and compacting this material in one single lift to prevent damaging and
tearing the geotextile fabric and geogrid with the construction equipment.
COLD/WINTER WEATHER CONSTRUCTION
If foundation construction will occur during the cold/winter weather season, the Contractor
shall take all necessary precautions to prevent the earthwork from freezing and/or from being
contaminated with snow. Exposed subgrade and fill materials (under footings, slabs, and walls)
should be adequately covered with concrete insulation blankets to prevent frost penetration
and to protect them from snow. All soils that are used for fill under or around foundation
components should be relatively dry, be free of intermixed snow and frozen clods, and must
not be placed when it is snowing. No fill materials (or footings) should be placed on frozen
soils, which may be in a “frost-heaved condition”, or over layers of snow.
When earthwork will proceed during the non-optimal times of the year, we recommend that it
be performed in an expeditious manner; thereby, minimizing the time that the foundation
excavations are open and exposed to the elements. In addition, positive drainage must be
established away from the excavations to prevent the entry of surface water runoff and the
saturation of the underlying soils. Please be fully aware that carelessness with respect to any of
the above-referenced items can potentially lead to foundation settlement problems in the
spring when the frost thaws and/or the snow melts. Cold weather concrete practices/methods
should be implemented when the conditions dictate.
Virga Capital
April 19, 2022
Lumber Yard Apartments Geotechnical Report
Bozeman, Montana
Allied Engineering Services, Inc. Page 23
REFERENCES
1. International Code Council, 2018, “2018 International Building Code”.
2. Montana Bureau of Mines and Geology, 2014, “Well Logs”, Groundwater Information
Center.
3. Montana Contractors’ Association, April 2010, “Montana Public Works Standard
Specifications”, Sixth Edition.
4. Slagle, Steven E., May 1995, “Geohydrologic Conditions and Land Use in the Gallatin Valley,
Southwestern Montana, 1992-93”, U.S. Department of the Interior, U.S. Geological Survey.
LIST OF FIGURES
FFiigguurree 11 –– VViicciinniittyy MMaapp
FFiigguurree 22 –– QQuuaaddrraannggllee MMaapp
FFiigguurree 33 –– TTeesstt PPiitt LLooccaattiioonn MMaapp
FFiigguurree 44 –– GGeeoollooggyy MMaapp
FFiigguurree 55 –– GGrroouunnddwwaatteerr MMaapp
FIGURECivil Engineering
Geotechnical EngineeringLand Surveying
32 DISCOVERY DRIVE . BOZEMAN, MT 59718PHONE (406) 582-0221 . FAX (406) 582-5770www.alliedengineering.com
LOTS 1, 2, & 3A, BLK 3, PT LAND PH 2 SUB.
VICINITY MAP
BOZEMAN, MONTANA
1
N
FIGURECivil Engineering
Geotechnical EngineeringLand Surveying
32 DISCOVERY DRIVE . BOZEMAN, MT 59718PHONE (406) 582-0221 . FAX (406) 582-5770www.alliedengineering.com
LOTS 1, 2, & 3A, BLK 3, PT LAND PH 2 SUB.
QUADRANGLE MAP
BOZEMAN, MONTANA
2
N
FIGURECivil Engineering
Geotechnical EngineeringLand Surveying
32 DISCOVERY DRIVE . BOZEMAN, MT 59718PHONE (406) 582-0221 . FAX (406) 582-5770www.alliedengineering.com
LOTS 1, 2, & 3A, BLK 3, PT LAND PH 2 SUB.
TEST PIT LOCATION MAP
BOZEMAN, MONTANA
3
TP#MW-#
LOT 1
TP-2MW-2
TP-3MW-3
N
LOT 2
LOT 3A
TP-1
MW-1
TP-4MW-4
TP#
MW-#
BH#
TP-8
TP-4MW-A
TP-5 TP-6
TP-7MW-B
BH-5
BH-6
BH-7
BH-8
FIGURECivil Engineering
Geotechnical EngineeringLand Surveying
32 DISCOVERY DRIVE . BOZEMAN, MT 59718PHONE (406) 582-0221 . FAX (406) 582-5770www.alliedengineering.com
LOTS 1, 2, & 3A, BLK 3, PT LAND PH 2 SUB.
GEOLOGY MAP
BOZEMAN, MONTANA
4
N
FIGURECivil Engineering
Geotechnical EngineeringLand Surveying
32 DISCOVERY DRIVE . BOZEMAN, MT 59718PHONE (406) 582-0221 . FAX (406) 582-5770www.alliedengineering.com
LOTS 1, 2, & 3A, BLK 3, PT LAND PH 2 SUB.
GROUNDWATER MAP
BOZEMAN, MONTANA
5
N
LIST OF APPENDICES
AAppppeennddiixx AA –– TTeesstt PPiitt LLooggss aanndd BBoorreehhoollee LLooggss
AAppppeennddiixx BB –– LLaabboorraattoorryy TTeessttiinngg RReessuullttss
AAppppeennddiixx CC –– PPaavveemmeenntt SSeeccttiioonn DDeessiiggnn
AAppppeennddiixx DD –– LLiimmiittaattiioonnss ooff YYoouurr GGeeootteecchhnniiccaall RReeppoorrtt
APPENDIX A
TTeesstt PPiitt LLooggss 22002200
TTeesstt PPiitt LLooggss 22001166
BBoorreehhoollee LLooggss 22001166
{0.0' - 1.25'}: Native Topsoil:Soft; dark brown to black; organic SILT/CLAY;very moist.{1.25' - 5.0'}: Fine-Grain Deposit:Very soft; brown; sandy SILT/CLAY; very moistto wet.·Pocket Penetrometer @ 2.0' = 1.0 tsf.·Pocket Penetrometer @ 3.0' = 0.5 tsf.·Softer with depth.{5.0' - 9.0'}: Alluvium:Dense; brown; sandy GRAVEL with abundant3"-minus rounded cobbles; wet.·Occasional 6"-minus rounded cobbles.·Groundwater encountered at 6.5'.Notes:·MW-1 installed.·Composite sample collected from all fourtest pits from 4.0 to 6.0 feet.12DEPTH (FT)
SAMPLES
% WATER
CONTENTDESCRIPTION OF MATERIALSHorizontal Distance in FeetCivil EngineeringGeotechnical EngineeringLand Surveying32 DISCOVERY DRIVEBOZEMAN, MT 59718PHONE (406) 582-0221FAX (406) 582-5770www.alliedengineering.comNA22-0159.0'6.5'Test Pit Designation: TP-1 Location:Surface Elevation: Backhoe Type: Hitachi 130 Job Number:Total Depth: Backhoe Operator: John (RLS Construction) Project: Lumber Yard ApartmentsGroundwater: Logged By: EGS (AESI) Date: March 10, 20223S1-A@4.0'See Test Pit Location Map;45.69579, -111.0555630.1%246810GWT at 6.5'108642132Target Bearing at 5.0'
{0.0' - 1.5'}: Native Topsoil:Soft; dark brown to black; organic SILT/CLAY;very moist.{1.5' - 7.0'}: Fine-Grain Deposit:Very soft; brown; sandy SILT/CLAY; very moistto wet.·Pocket Penetrometer @ 2.0' = 1.0 tsf.·Pocket Penetrometer @ 3.0' = 0.5 tsf.·Softer with depth.{7.0' - 9.5'}: Alluvium:Dense; brown; sandy GRAVEL with abundant3"-minus rounded cobbles; wet.·Groundwater encountered at 7.5'.Notes:·MW-2 installed.·Composite sample collected from all fourtest pits from 4.0 to 6.0 feet.12DEPTH (FT)
SAMPLES
% WATER
CONTENTDESCRIPTION OF MATERIALSHorizontal Distance in FeetCivil EngineeringGeotechnical EngineeringLand Surveying32 DISCOVERY DRIVEBOZEMAN, MT 59718PHONE (406) 582-0221FAX (406) 582-5770www.alliedengineering.comNA22-0159.5'7.5'Test Pit Designation: TP-2 Location:Surface Elevation: Backhoe Type: Hitachi 130 Job Number:Total Depth: Backhoe Operator: John (RLS Construction) Project: Lumber Yard ApartmentsGroundwater: Logged By: EGS (AESI) Date: March 10, 20223S2-A@5.0'See Test Pit Location Map;45.69635, -111.0547030.4%246810GWT at 7.5'108642132Target Bearing at 7.0'
{0.0' - 2.5'}: Native Topsoil:Soft; dark brown to black; organic SILT/CLAY;very moist.{2.5' - 4.0'}: Fine-Grain Deposit:Very soft; brown; sandy SILT/CLAY; very moist.·Pocket Penetrometer @ 3.0' = 0.5 tsf.·Softer with depth.{4.0' - 9.0'}: Alluvium:Very dense; brown; sandy GRAVEL withabundant 4"-minus rounded cobbles; wet.·Groundwater encountered at 5.0'.Notes:·MW-3 installed.·Composite sample collected from all fourtest pits from 4.0 to 6.0 feet.12DEPTH (FT)
SAMPLES
% WATER
CONTENTDESCRIPTION OF MATERIALSHorizontal Distance in FeetCivil EngineeringGeotechnical EngineeringLand Surveying32 DISCOVERY DRIVEBOZEMAN, MT 59718PHONE (406) 582-0221FAX (406) 582-5770www.alliedengineering.comNA22-0159.0'5.0'Test Pit Designation: TP-3 Location:Surface Elevation: Backhoe Type: Hitachi 130 Job Number:Total Depth: Backhoe Operator: John (RLS Construction) Project: Lumber Yard ApartmentsGroundwater: Logged By: EGS (AESI) Date: March 10, 20223S3-A@4.0'See Test Pit Location Map;45.69622, -111.0534123.6%246810GWT at 5.0'108642132Target Bearing at 4.0'
{0.0' - 1.25'}: Native Topsoil:Soft; dark brown to black; organic SILT/CLAY;very moist.{1.25' - 4.5'}: Fine-Grain Deposit:Very soft; brown; sandy SILT/CLAY; very moist.·Pocket Penetrometer @ 2.5' = 0.5 tsf.·Softer with depth.{4.5' - 9.0'}: Alluvium:Dense; brown; sandy GRAVEL with abundant3"-minus rounded cobbles; wet.·Groundwater encountered at 5.0'.Notes:·MW-4 installed.·Composite sample collected from all fourtest pits from 4.0 to 6.0 feet.12DEPTH (FT)
SAMPLES
% WATER
CONTENTDESCRIPTION OF MATERIALSHorizontal Distance in FeetCivil EngineeringGeotechnical EngineeringLand Surveying32 DISCOVERY DRIVEBOZEMAN, MT 59718PHONE (406) 582-0221FAX (406) 582-5770www.alliedengineering.comNA22-0159.0'5.0'Test Pit Designation: TP-4 Location:Surface Elevation: Backhoe Type: Hitachi 130 Job Number:Total Depth: Backhoe Operator: John (RLS Construction) Project: Lumber Yard ApartmentsGroundwater: Logged By: EGS (AESI) Date: March 10, 20223S4-A@3.0'See Test Pit Location Map;45.69554, -111.0526127.0%246810GWT at 5.0'1086421Target Bearing at 4.5'32
November 21, 2016Embassy Suites-Hampton Inn16-202John Deere 310 SKCalen - Townsend ExcavatingEGS (AESI)Observed at 6.0'8.0'N/A1Location: 45.697167 N -111.054996 WDEPTH (FT)SAMPLES% WATERCONTENTDESCRIPTION OF MATERIALSSURFACE ELEVATION:TOTAL DEPTH:GROUNDWATER:LOGGED BY:BACKHOE OPERATOR:BACKHOE TYPE:DATE:PROJECT:JOB NUMBER:2016128420161284Test Pit Designation: TP-4 (2016)Horizontal Distance in Feet2{0.0' - 1.5'}: TopsoilSoft; dark brown to black; organic sandy SILT;very moist.{1.5' - 5.0'}: Lean CLAY/SILTMedium stiff to stiff; light brown; leanCLAY/SILT; moist.-Pocket Penetrometer = 1.0 tsf @ 3.0'Atterberg Limits (S4-A @ 3.0')-PL = 24.1-LL = 40.0-PI = 15.9{5.0' - 8.0'}: AlluviumDense to very dense; brown; sandy GRAVELwith rounded rock up to 6" in diameter; wet.Notes:-groundwater monitoring well installed (MW-A)-Test Pit completed in 2016.Civil EngineeringGeotechnical EngineeringLand Surveying32 DISCOVERY DRIVEBOZEMAN, MT 59718PHONE (406) 582-0221FAX (406) 582-5770www.alliedengineering.comS4-A@3'3S4-B@7'7.428.7321Groundwater at 6'Suitable Bearing at 5'
November 21, 2016Embassy Suites-Hampton Inn16-202John Deere 310 SKCalen - Townsend ExcavatingEGS (AESI)8.0'9.0'N/A1Location: 45.695557 N -111.054573 WDEPTH (FT)SAMPLES% WATERCONTENTDESCRIPTION OF MATERIALSSURFACE ELEVATION:TOTAL DEPTH:GROUNDWATER:LOGGED BY:BACKHOE OPERATOR:BACKHOE TYPE:DATE:PROJECT:JOB NUMBER:2016128420161284Test Pit Designation: TP-5 (2016)Horizontal Distance in Feet2{0.0' - 0.75'}: TopsoilSoft; dark brown to black; organic sandy SILTwith small roots; very moist.{0.75' - 8.0'}: Lean CLAY/SILTSoft to stiff; light brown to brown; leanCLAY/SILT; moist.-Pocket Penetrometer = 2.0 tsf @ 3.0'{8.0' - 9.0'}: AlluviumMedium dense; brown; sandy GRAVEL withrounded rock up to 6" in diameter; wet.Notes:-Test Pit completed in 2016.Civil EngineeringGeotechnical EngineeringLand Surveying32 DISCOVERY DRIVEBOZEMAN, MT 59718PHONE (406) 582-0221FAX (406) 582-5770www.alliedengineering.comS5-C@5'3S5-B@2.5'23.124.7321S5-D@8.0'19.7S5-A@1'22.9Groundwater at 8'Suitable Bearing at 8'
November 21, 2016Embassy Suites-Hampton Inn16-202John Deere 310 SKCalen - Townsend ExcavatingEGS (AESI)5.5'5.5'N/A1Location: 45.6695744 N -111.053249 WDEPTH (FT)SAMPLES% WATERCONTENTDESCRIPTION OF MATERIALSSURFACE ELEVATION:TOTAL DEPTH:GROUNDWATER:LOGGED BY:BACKHOE OPERATOR:BACKHOE TYPE:DATE:PROJECT:JOB NUMBER:2016128420161284Test Pit Designation: TP-6 (2016)Horizontal Distance in Feet2{0.0' - 1.5'}: TopsoilSoft; dark brown; organic sandy SILT with smallroots; moist.{1.5' - 4.0'}: Lean CLAY/SILTStiff to very stiff; brown; lean CLAY/SILT; moist.-Pocket Penetrometer = 4.0 tsf @ 3.5'{4.0' - 5.5'}: AlluviumDense to very dense; brown; sandy GRAVELwith rounded rock up to 6" in diameter; wet.Notes:-Test Pit completed in 2016.Civil EngineeringGeotechnical EngineeringLand Surveying32 DISCOVERY DRIVEBOZEMAN, MT 59718PHONE (406) 582-0221FAX (406) 582-5770www.alliedengineering.com3S6-B@5'8.4321S6-A@3'19.5Groundwater at 5.5'Suitable Bearing at 4'
November 21, 2016Embassy Suites-Hampton Inn16-202John Deere 310 SKCalen - Townsend ExcavatingEGS (AESI)7.0'8.5'N/A1Location: 45.695799 N -111.052029 WDEPTH (FT)SAMPLES% WATERCONTENTDESCRIPTION OF MATERIALSSURFACE ELEVATION:TOTAL DEPTH:GROUNDWATER:LOGGED BY:BACKHOE OPERATOR:BACKHOE TYPE:DATE:PROJECT:JOB NUMBER:2016128420161284Test Pit Designation: TP-7 (2016)Horizontal Distance in Feet2{0.0' - 2.0'}: TopsoilSoft; dark brown to black; organic sandy SILTwith occasional small roots; moist.{2.0' - 5.5'}: Lean CLAY/SILTStiff to very stiff; light brown to brown; leanCLAY/SILT; moist.-Pocket Penetrometer = 2.0-3.0 tsf @ 3.0'-Pocket Penetrometer = 1.0 tsf @5.0'Atterberg Limits (S1-B @ 4.0')-PL = 23.7-LL = 36.1-PI = 12.4{5.5' - 8.5'}: AlluviumDense to very dense; brown; sandy GRAVELwith rounded rock up to 6" in diameter; wet.Notes:-Monitoring well installed-TP walls caving-Test pit completed in 2016.Civil EngineeringGeotechnical EngineeringLand Surveying32 DISCOVERY DRIVEBOZEMAN, MT 59718PHONE (406) 582-0221FAX (406) 582-5770www.alliedengineering.com3S7-C@5'28.0321S7-A@1.5'29.0S7-B@3'27.7S7-D@7'9.8Bucket@8'Groundwater at 7'Suitable Bearing at 5.5'
November 21, 2016Embassy Suites-Hampton Inn16-202John Deere 310 SKCalen - Townsend ExcavatingEGS (AESI)4.5'5.5'N/A1Location: 45.696074 N -111.056308 WDEPTH (FT)SAMPLES% WATERCONTENTDESCRIPTION OF MATERIALSSURFACE ELEVATION:TOTAL DEPTH:GROUNDWATER:LOGGED BY:BACKHOE OPERATOR:BACKHOE TYPE:DATE:PROJECT:JOB NUMBER:2016128420161284Test Pit Designation: TP-8 (2016)Horizontal Distance in Feet2{0.0' - 2.0'}: TopsoilSoft; dark brown to black; organic sandy SILT;moist.{2.0' - 4.0'}: Lean CLAY/SILTVery soft to medium stiff; brown; leanCLAY/SILT; moist to very moist.-Pocket Penetrometer < 1.0 tsf @ 3.0'{4.0' - 5.5'}: AlluviumDense to very dense; brown; sandy GRAVELwith rounded rock up to 4" in diameter; wet.Notes:-Test Pit completed in 2016.Civil EngineeringGeotechnical EngineeringLand Surveying32 DISCOVERY DRIVEBOZEMAN, MT 59718PHONE (406) 582-0221FAX (406) 582-5770www.alliedengineering.com3321S8-A@1'41.1S8-B@3'31.0Groundwater at 4.5'Suitable Bearing at 4'
DEPTH (FT)GEOLOGYLOGDESCRIPTIONOF MATERIALS
SAMPLESN(UNCOR)BLOWS/FTMOISTURECONTENTOTHER FIELD ORSAMPLEINFORMATION
10.0
20.0
Geotechnical Engineering
32 DISCOVERY DRIVE
BOZEMAN, MT 59718
FAX (406) 582-5770
PHONE (406) 582-0221Land SurveyingCivil Engineering LOG OF BORING
PROJECT: Embassy Suites - Hampton Inn JOB #: 16-202 BORING: BH-5 (2016) PAGE: 1 of 1
LOCATION: Bozeman, MT. ELEVATION: N/A DEPTH: 30.0' GW: 2.8'
DRILL TYPE: Mobile B-60 FIELD ENGINEER: EGS DATE: 11/22/16
DRILLER: O'Keefe Drilling of Butte, MT CASING/HAMMER/SAMPLER: 3.75"ID/140 lb./SSS
{0.0' - 1.0'}: TopsoilSoft; dark brown; sandy SILT with abundant
roots; moist.
S5-A @ 0.0' - 1.5'(SSS)
S5-B @ 4.0' - 5.5'(SSS)
S5-C @9.0' - 10.5'(SSS)
S5-D @14.0'-15.5'(SSS)
S5-E @19.0'-20.5'(SSS)
S5-F @ 24.0'-25.5'(SSS)
S5-G @ 29.0'-30.5'(SSS)
4
93
37
75
71
94
58
29.2%
12.5%
9.9%
12.4%
15.8%
8.5%
13.9%
General Notes:1. On top of possible rock at4.0'-5.5'2. Drill grinding from 4.0'-15.0'3. Drills slow at 20.0'4. Easy drilling at 28.0'-30.0'
·SSS - 2.0'' O.D. Split SpoonSample
·The beginning and endingdepths of the individual soillayers are approximate.End of Boring @ 30'
{1.0' - 4.0}: Lean CLAY/SILTMedium stiff to stiff; light brown; leanCLAY/SILT; moist.
{4.0' - 30.0'}: AlluviumDense to very dense; brown; sandyGRAVEL; wet.
DEPTH (FT)GEOLOGYLOGDESCRIPTIONOF MATERIALS
SAMPLESN(UNCOR)BLOWS/FTMOISTURECONTENTOTHER FIELD ORSAMPLEINFORMATION
10.0
20.0
Geotechnical Engineering
32 DISCOVERY DRIVE
BOZEMAN, MT 59718
FAX (406) 582-5770
PHONE (406) 582-0221Land SurveyingCivil Engineering LOG OF BORING
PROJECT: Embassy Suites - Hampton Inn JOB #: 16-202 BORING: BH-6 (2016) PAGE: 1 of 1
LOCATION: Bozeman, MT. ELEVATION: N/A DEPTH: 16.0' GW: 5.5'
DRILL TYPE: Mobile B-60 FIELD ENGINEER: EGS DATE: 11/22/16
DRILLER: O'Keefe Drilling of Butte, MT CASING/HAMMER/SAMPLER: 3.75"ID/140 lb./SSS
{0.0' - 1.0'}: TopsoilSoft; dark brown; organic sandy SILT; moist.
S6-A @ 0.0' - 1.5'(SSS)
S6-B @ 4.0' - 5.5'(SSS)
S6-C @9.0' - 10.5'(SSS)
S6-D @14.0'-15.5'(SSS)
S6-E @15.0'-16.5'(SSS)
6
27
47
50+
50+
29.5%
26.6%
15.5%
-
-
General Notes:1. Sandy GRAVEL containsreddish rock fragments2. Seam of dark brown sandyGRAVEL at 10.0'3. Drill grinding at 11.0'4. Significant drill jumping at13.0'5. Very slow/rough drillin at15.0'6. Drilled for 25 minutes with noprogress (drill refusal).7. No sample returned for bothS6-D and S6-E.
·SSS - 2.0'' O.D. Split SpoonSample
·The beginning and endingdepths of the individual soillayers are approximate.
End of Boring @ 16'
{1.0' - 4.0}: Lean CLAY/SILTMedium stiff to stiff; light brown; leanCLAY/SILT; moist.
{4.0' - 16.0'}: AlluviumDense to very dense; brown with traces ofgrey and red; sandy GRAVEL; wet.
DEPTH (FT)GEOLOGYLOGDESCRIPTIONOF MATERIALS
SAMPLESN(UNCOR)BLOWS/FTMOISTURECONTENTOTHER FIELD ORSAMPLEINFORMATION
10.0
20.0
Geotechnical Engineering
32 DISCOVERY DRIVE
BOZEMAN, MT 59718
FAX (406) 582-5770
PHONE (406) 582-0221Land SurveyingCivil Engineering LOG OF BORING
PROJECT: Embassy Suites - Hampton Inn JOB #: 16-202 BORING: BH-7 (2016) PAGE: 1 of 1
LOCATION: Bozeman, MT. ELEVATION: N/A DEPTH: 25.0' GW: 5.1'
DRILL TYPE: Mobile B-60 FIELD ENGINEER: EGS DATE: 11/22/16
DRILLER: O'Keefe Drilling of Butte, MT CASING/HAMMER/SAMPLER: 3.75"ID/140 lb./SSS
{0.0' - 1.0'}: TopsoilSoft; dark brown; sandy SILT with abundant
roots; moist.
5
6
33
27
16
60
25
29
22.1%
25.8%
12.5%
25.0%
27.8%
13.1%
18.0%
29.7%
General Notes:1. Drill grinding at 5.0' andsignificant grinding at 10.0'2. Reddish rock in sample at 5.0'3. Appears to be seam of brownlean CLAY/SILT in samplerat ~20.0'
·SSS - 2.0'' O.D. Split SpoonSample
·The beginning and endingdepths of the individual soillayers are approximate.
End of Boring @ 25'
{1.0' - 4.0}: Lean CLAY/SILTMedium stiff to stiff; light brown; leanCLAY/SILT; moist.
{4.0' - 25.0'}: AlluviumDense; brown; sandy GRAVEL; wet.
S7-A @ 0.0' - 1.5'(SSS)
S7-B @ 2.0' - 3.5'(SSS)
S7-C@4.0'-5.5'(SSS)
S7-C @7.0' - 8.5'(SSS)
S7-D @9.0'-10.5'(SSS)
S7-E @14.0'-15.5'(SSS)
S7-F @ 19.0'-20.5'(SSS)
S7-G @ 24.0'-25.5'(SSS)
DEPTH (FT)GEOLOGYLOGDESCRIPTIONOF MATERIALS
SAMPLESN(UNCOR)BLOWS/FTMOISTURECONTENTOTHER FIELD ORSAMPLEINFORMATION
10.0
20.0
Geotechnical Engineering
32 DISCOVERY DRIVE
BOZEMAN, MT 59718
FAX (406) 582-5770
PHONE (406) 582-0221Land SurveyingCivil Engineering LOG OF BORING
PROJECT: Embassy Suites - Hampton Inn JOB #: 16-202 BORING: BH-8 (2016) PAGE: 1 of 1
LOCATION: Bozeman, MT. ELEVATION: N/A DEPTH: 25.0' GW: 5.9'
DRILL TYPE: Mobile B-60 FIELD ENGINEER: EGS DATE: 11/22/16
DRILLER: O'Keefe Drilling of Butte, MT CASING/HAMMER/SAMPLER: 3.75" ID/140 lb./SSS
{0.0' - 0.5'}: TopsoilSoft; dark brown; sandy SILT with abundant
roots; moist.
General Notes:1. Drill grinding at 5.0' andsignificant grinding at 10.0'2. Reddish rock in sample at 5.0'3. Appears to be seam of brownlean CLAY/SILT in samplerat ~20.0'
·SSS - 2.0'' O.D. Split SpoonSample
·The beginning and endingdepths of the individual soillayers are approximate.
End of Boring @ 25'
{0.5 - 4.0}: Lean CLAY/SILTMedium stiff to stiff; light brown; leanCLAY/SILT; moist.
{4.0' - 25.0'}: AlluviumDense; brown; sandy GRAVEL; wet.
S8-A @ 0.0' - 1.5'(SSS)
S8-B @ 4.0' - 5.5'(SSS)
S8-C @9.0' - 10.5'(SSS)
S8-D @14.0'-15.5'(SSS)
S8-E @19.0'-20.5'(SSS)
S8-F @ 24.0'-25.5'(SSS)
6
40
37
35
43
30
26.4%
3.3%
14.7%
13.2%
12.1%
13.2%
APPENDIX B
LLaabboorraattoorryy TTeessttiinngg RReessuullttss
MOISTURE CONTENT DETERMINATION (ASTM D-2216)
Project: Lumber Yard Apartments
Project Number: 22-015Sample Identification: Varies
Soil Classification: Varies
Date Sampled: March 10, 2022
Date Tested: March 18, 2022
Tested By: HRT
Sample Identification:S1-A S2-A S3-A S4-A
Exploration Location:TP-1 TP-2 TP-3 TP-4
Sample Depth (ft):4.0 5.0 4.0 3.0
Container Number:P AA T R
Weight of Container:49.29 49.07 51.59 50.73
Container + Wet Soil:250.27 354.79 261.37 293.20
Container + Dry Soil:203.80 283.58 221.29 241.72
Weight of Water:46.47 71.21 40.08 51.48
Weight of Dry Soil:154.51 234.51 169.70 190.99
Moisture Content:30.1%30.4%23.6%27.0%
Sample Identification:
Exploration Location:
Sample Depth (ft):
Container Number:
Weight of Container:
Container + Wet Soil:
Container + Dry Soil:
Weight of Water:
Weight of Dry Soil:
Moisture Content:
Reviewed By:
32 Discovery DriveBozeman, MT 59718
Phone (406) 582-0221
Fax (406) 582-5770
APPENDIX C
PPaavveemmeenntt SSeeccttiioonn DDeessiiggnn
PAVEMENT SECTION DESIGN
Project: Lumber Yard Apartments
Project Number: 22-015
Date: April 15, 2022
Prepared By: Jessi Ellingsen
Important Notes:
1) See following pages for an Explanation of the Design Input Parameters.
2) Sub-base course shall be comprised of import sandy pitrun gravel.3) Assumes the subgrade is stable.
4) For unstable subgrade, we recommend the addition of a non-woven geotextile fabric
and geogrid to the design section. Please see geotech report for details.
PARKING LOTS
DESIGN INPUT PARAMETERS
ESALs (total)100,000
Subgrade CBR, (%)2.50
Subgrade Resilient Modulus, MR (psi)3,750
Reliability, R (%)90Standard Normal Deviate, ZR -1.282
Overall Standard Deviation, So 0.45
Initial Serviceability, po 4.2 DESIGN EQUATION
Terminal Serviceability, pt 2.0
Design Serviceability Loss, (PSI)2.2 5 = left side
5.0073 = right side
Required Structural Number, RSN 3.00
(Manipulate RSN such that the left and right side of equation match.)
Asphalt Concrete Layer Coefficient, a1 0.41
Base Course Layer Structural Coefficient, a2 0.14
Base Course Layer Drainage Coefficient, m2 0.90
Sub-Base Course Layer Structural Coefficient, a3 0.09
Sub-Base Course Layer Drainage Coefficient, m3 0.90
DESIGN PAVEMENT SECTION
Asphalt Concrete Thickness, D1 (in)3.0
Granular Base Course Thickness, D2 (in)6.0
Granular Sub-Base Course Thickness, D3 (in)15.0
Calculated Structural Number, CSN 3.20
Pavement Section Design: Page 1 of 1
PAVEMENT SECTION DESIGN
Project: Lumber Yard Apartments
Project Number: 22-015
Date: April 15, 2022
Prepared By: Jessi Ellingsen
Important Notes:
1) See following pages for an Explanation of the Design Input Parameters.
2) Sub-base course shall be comprised of import sandy pitrun gravel.
3) Assumes the subgrade is stable.
4) For unstable subgrade, we recommend the addition of a non-woven geotextile fabric
and geogrid to the design section. Please see geotech report for details.
LOCAL STREETS
DESIGN INPUT PARAMETERS
ESALs (total)400,000
Subgrade CBR, (%)2.50
Subgrade Resilient Modulus, MR (psi)3,750
Reliability, R (%)90Standard Normal Deviate, ZR -1.282
Overall Standard Deviation, So 0.45
Initial Serviceability, po 4.2
Terminal Serviceability, pt 2.0 DESIGN EQUATION
Design Serviceability Loss, (PSI)2.2
5.60206 = left side
Required Structural Number, RSN 3.69 5.6099 = right side
(Manipulate RSN such that the left and right side of equation match.)
Asphalt Concrete Layer Coefficient, a1 0.41
Base Course Layer Structural Coefficient, a2 0.14
Base Course Layer Drainage Coefficient, m2 0.90
Sub-Base Course Layer Structural Coefficient, a3 0.09
Sub-Base Course Layer Drainage Coefficient, m3 0.90
DESIGN PAVEMENT SECTION
Asphalt Concrete Thickness, D1 (in)3.0
Granular Base Course Thickness, D2 (in)6.0
Granular Sub-Base Course Thickness, D3 (in)21.0
Calculated Structural Number, CSN 3.69
(Manipulate layer thicknesses such that CSN matches or exceeds RSN.)
Pavement Section Design: Page 1 of 1
Explanation of Design Input Parameters: Page 1 of 3
PAVEMENT SECTION DESIGN
(EXPLANATION OF DESIGN INPUT PARAMETERS)
Design Life (yr): 20
ESALs (total): Parking Lots – 100,000
Local Streets - 400,000
Subgrade CBR, (%): 2.50
Subgrade Resilient Modulus, MR (psi): 3,750
Reliability, R (%): 90
Standard Normal Deviate, ZR: -1.282
Overall Standard Deviation, So: 0.45
Initial Serviceability, po: 4.2
Terminal Serviceability, pt: 2.0
Design Serviceability Loss, (PSI) 2.2
Asphalt Concrete Layer Coefficient, a1: 0.41
Base Course Layer Structural Coefficient, a2: 0.14
Base Course Layer Drainage Coefficient, m2: 0.90
Sub-Base Course Layer Structural Coefficient, a3: 0.09
Sub-Base Course Layer Drainage Coefficient, m3: 0.90
Design Life: A design life of 20 years is typical for new asphalt projects in Bozeman.
ESALs (total): According to Table 18.12 in Reference 1, the estimated design Equivalent
18,000-lb Single Axle Load (ESAL) value for roadways subjected to light vehicle and
medium truck traffic ranges from 10,000 to 1,000,000. Since we do not anticipate much
for truck traffic in the new parking lot, we believe a value of 100,000 is a reasonable
assumption for the anticipated ESAL loading for parking lots. Light passenger cars, vans,
and pick-up trucks will be the primary users of the new lot. These are classified as Class
1, 2, and 3 vehicles and have an equivalent ESAL value ranging from 0.001 to 0.007 per
trip. Using 0.005 ESALS per trip as a conservative average, this calculates to about 3,000
vehicle trips per day for the next 20 years to get close to the ESAL loading design value.
With respect to local streets, we have conservatively assumed an ESAL value of 400,000,
equivalent to about 11,000 vehicle trips per day.
Subgrade CBR: In our experience, CBR values for fine-grained soils often range from 2.0
to 3.0%. For this reason, we picked a CBR value of 2.5% for design purposes.
Subgrade Resilient Modulus: For fine-grained soils with a CBR of 10.0 or less, an
Explanation of Design Input Parameters: Page 2 of 3
accepted correlation between CBR and resilient modulus is MR = 1500 x CBR. Based on
this equation, the design resilient modulus value shall be 3,750 psi.
Reliability: According to Table 2.2 in Reference 2, the recommended reliability level for
local streets (low volume) in urban settings ranges from 50 to 80 percent; while
collector streets (high volume) should be designed with a level of reliability between 80
and 95 percent. We chose an elevated design reliability level of 90 percent.
Standard Normal Deviate: According to Table 4.1 in Reference 2, a 90 percent reliability
value corresponds to a standard normal deviate of –1.282.
Overall Standard Deviation: According to Sections 2.1.3 and 4.3 in Reference 2, a
design value of 0.45 is recommended for flexible pavements.
Initial Serviceability: According to Section 2.2.1 in Reference 2, a design value of 4.2 is
recommended for flexible pavements.
Terminal Serviceability: According to Section 2.2.1 in Reference 2, a design value of 2.0
is suggested for roads that will be subjected to small traffic volumes; while a value of 2.5
or higher should be used when designing major highways. We selected a terminal
serviceability of 2.0.
Design Serviceability Loss: This is the difference between the initial and terminal
serviceability. Therefore, the design value shall be 2.2.
Asphalt Concrete Layer Coefficient: According to the table with the revised surfacing
structural coefficients in Reference 4, a design value of 0.41 is recommended for all
asphalt plant mix grades. This value replaces the 0.33 asphalt coefficient that was
provided in Table 3-2 of Reference 3.
Base Course Layer Structural Coefficient: According to the table with the revised
surfacing structural coefficients in Reference 4, a design value of 0.14 is recommended
for new 1.5”-minus, crushed base course gravel. This value replaces the 0.12 crushed
gravel coefficient that was provided in Table 3-2 of Reference 3.
Base Course Layer Drainage Coefficient: According to Table 2.4 in Reference 2, a
coefficient of 0.80 to 1.00 should be used when fair to good drainage is anticipated
within the pavement structure. We assume good drainage for this project with a
corresponding drainage coefficient of 0.90 for design.
Sub-Base Course Layer Structural Coefficient: For Pavement Section Design, we are
assuming that imported, uncrushed sandy (pitrun) gravel will be placed for the sub-base
section of the parking lot. This is the standard product used in the Bozeman area for
sub-base. According to pavement design charts for gravelly soils, we estimated that
Explanation of Design Input Parameters: Page 3 of 3
pitrun will have a CBR of between 15.0 and 20.0%, which correlates to a structural
coefficient of 0.09.
Sub-Base Course Layer Drainage Coefficient: The drainage coefficients for sub-base
and base course layers are typically the same; therefore, we selected a value of 0.90 for
the design. See the base course layer drainage coefficient section for an explanation.
Reference List
1) Traffic and Highway Engineering; Nicholas J. Garber and Lester A. Hoel; 1988.
2) Design of Pavement Structures; AASHTO; 1993.
3) Pavement Design Manual; Montana Department of Transportation; 1991.
4) Pavement Design Memo; Montana Department of Transportation; May 11, 2006.
5) Geotechnical Manual; Montana Department of Transportation; July 2008.
APPENDIX D
LLiimmiittaattiioonnss ooff YYoouurr GGeeootteecchhnniiccaall RReeppoorrtt
LIMITATIONS OF YOUR GEOTECHNICAL REPORT
GEOTECHNICAL REPORTS ARE PROJECT AND CLIENT SPECIFIC
Geotechnical investigations, analyses, and recommendations are project and client specific. Each project
and each client have individual criterion for risk, purpose, and cost of evaluation that are considered in
the development of scope of geotechnical investigations, analyses and recommendations. For example,
slight changes to building types or use may alter the applicability of a particular foundation type, as can a
particular client’s aversion or acceptance of risk. Also, additional risk is often created by scope‐of service
limitations imposed by the client and a report prepared for a particular client (say a construction
contractor) may not be applicable or adequate for another client (say an architect, owner, or developer
for example), and vice‐versa. No one should apply a geotechnical report for any purpose other than that
originally contemplated without first conferring with the consulting geotechnical engineer. Geotechnical
reports should be made available to contractors and professionals for information on factual data only
and not as a warranty of subsurface conditions, such as those interpreted in the exploration logs and
discussed in the report.
GEOTECHNICAL CONDITIONS CAN CHANGE
Geotechnical conditions may be affected as a result of natural processes or human activity. Geotechnical
reports are based on conditions that existed at the time of subsurface exploration. Construction
operations such as cuts, fills, or drains in the vicinity of the site and natural events such as floods,
earthquakes, or groundwater fluctuations may affect subsurface conditions and, thus, the continuing
adequacy of a geotechnical report.
GEOTECHNICAL ENGINEERING IS NOT AN EXACT SCIENCE
The site exploration and sampling process interprets subsurface conditions using drill action, soil sampling,
resistance to excavation, and other subjective observations at discrete points on the surface and in the
subsurface. The data is then interpreted by the engineer, who applies professional judgment to render
an opinion about over‐all subsurface conditions. Actual conditions in areas not sampled or observed may
differ from those predicted in your report. Retaining your consultant to advise you during the design
process, review plans and specifications, and then to observe subsurface construction operations can
minimize the risks associated with the uncertainties associated with such interpretations. The conclusions
described in your geotechnical report are preliminary because they must be based on the assumption that
conditions revealed through selective exploration and sampling are indicative of actual
Allied Engineering Services, Inc. ● 32 Discovery Drive. Bozeman, Montana 59718 ● Ph: (406) 582‐0221 Page 2
conditions throughout a site. A more complete view of subsurface conditions is often revealed during
earthwork; therefore, you should retain your consultant to observe earthwork to confirm conditions
and/or to provide revised recommendations if necessary. Allied Engineering cannot assume responsibility
or liability for the adequacy of the report’s recommendations if another party is retained to observe
construction.
EXPLORATIONS LOGS SHOULD NOT BE SEPARATED FROM THE REPORT
Final explorations logs developed by the consultant are based upon interpretation of field logs (assembled
by site personnel), field test results, and laboratory and/or office evaluation of field samples and data.
Only final exploration logs and data are customarily included in geotechnical reports. These final logs
should not be redrawn for inclusion in Architectural or other design drawings, because drafters may
commit errors or omissions in the transfer process.
To reduce the likelihood of exploration log misinterpretation, contractors should be given ready access to
the complete geotechnical report and should be advised of its limitations and purpose. While a contractor
may gain important knowledge from a report prepared for another party, the contractor should discuss
the report with Allied Engineering and perform the additional or alternative work believed necessary to
obtain the data specifically appropriate for construction cost estimating purposes.
OWNERSHIP OF RISK AND STANDARD OF CARE
Because geotechnical engineering is much less exact than other design disciplines, there is more risk
associated with geotechnical parameters than with most other design issues. Given the hidden and
variable character of natural soils and geologic hazards, this risk is impossible to eliminate with any
amount of study and exploration. Appropriate geotechnical exploration, analysis, and recommendations
can identify and reduce these risks. However, assuming an appropriate geotechnical evaluation, the
remaining risk of unknown soil conditions and other geo‐hazards typically belongs to the owner of a
project unless specifically transferred to another party such as a contractor, insurance company, or
engineer. The geotechnical engineer’s duty is to provide professional services in accordance with their
stated scope and consistent with the standard of practice at the present time and in the subject geographic
area. It is not to provide insurance against geo‐hazards or unanticipated soil conditions.
The conclusions and recommendations expressed in this report are opinions based our professional
judgment and the project parameters as relayed by the client. The conclusions and recommendations
assume that site conditions are not substantially different than those exposed by the explorations. If
during construction, subsurface conditions different from those encountered in the explorations are
observed or appear to be present, Allied Engineering should be advised at once such that we may review
those conditions and reconsider our recommendations where necessary.
RETENTION OF SOIL SAMPLES
Allied Engineering will typically retain soil samples for one month after issuing the geotechnical report. If
you would like to hold the samples for a longer period of time, you should make specific arrangements to
have the samples held longer or arrange to take charge of the samples yourself.
NOTES:
If the well is dry, graph shows the groundwater at bottom of the well casing.
Assumed Ground Surface Elevation of 100.0‐ft.
All measurements for this well are in reference to the assumed Ground Surface Elevation.
Dewatering was ongoing from 7/27/2022 through 8/31/2022.
Total Well Well Measure Depth to Top Bottom 4'
Well Casing Casing from T.O.C. GW Depth to Ground of of GW below Measured
Date Time Casing Height Bury to GW Below GW Surface Casing Casing Elev. Ground by
Length Depth Ground Elev. Elev. Elev. Surface
(ft) (feet) (feet) (feet) (feet) (inches) (feet) (feet) (feet) (feet)
3/25/2022 4:30 PM 10.00 2.04 7.96 6.95 4.91 58.90 100.00 102.04 92.04 95.09 96.00 JGE
4/1/2022 1:15 PM 10.00 2.04 7.96 7.09 5.05 60.58 100.00 102.04 92.04 94.95 96.00 JGE
4/6/2022 10:30 AM 10.00 2.04 7.96 7.10 5.06 60.70 100.00 102.04 92.04 94.94 96.00 JGE
4/12/2022 3:00 PM 10.00 2.04 7.96 7.22 5.18 62.14 100.00 102.04 92.04 94.82 96.00 ORB
4/19/2022 2:30 PM 10.00 2.04 7.96 7.22 5.18 62.14 100.00 102.04 92.04 94.82 96.00 ORB
4/26/2022 10:45 AM 10.00 2.04 7.96 6.78 4.74 56.86 100.00 102.04 92.04 95.26 96.00 ORB
5/4/2022 7:10 AM 10.00 2.04 7.96 6.01 3.97 47.62 100.00 102.04 92.04 96.03 96.00 ORB
5/10/2022 12:00 PM 10.00 2.04 7.96 6.22 4.18 50.14 100.00 102.04 92.04 95.82 96.00 ORB
5/17/2022 1:30 PM 10.00 2.04 7.96 6.05 4.01 48.10 100.00 102.04 92.04 95.99 96.00 JGE
5/23/2022 12:10 PM 10.00 2.04 7.96 6.52 4.48 53.74 100.00 102.04 92.04 95.52 96.00 ORB
5/31/2022 11:20 AM 10.00 2.04 7.96 5.46 3.42 41.02 100.00 102.04 92.04 96.58 96.00 ORB
6/8/2022 2:30 PM 10.00 2.04 7.96 5.66 3.62 43.42 100.00 102.04 92.04 96.38 96.00 ORB
6/15/2022 11:30 AM 10.00 2.04 7.96 6.00 3.96 47.50 100.00 102.04 92.04 96.04 96.00 ORB
6/22/2022 12:15 PM 10.00 2.04 7.96 6.38 4.34 52.06 100.00 102.04 92.04 95.66 96.00 ORB
6/29/2022 12:45 PM 10.00 2.04 7.96 6.71 4.67 56.02 100.00 102.04 92.04 95.33 96.00 ORB
7/6/2022 1:45 PM 10.00 2.04 7.96 6.67 4.63 55.54 100.00 102.04 92.04 95.37 96.00 ORB
7/13/2022 11:00 AM 10.00 2.04 7.96 7.02 4.98 59.74 100.00 102.04 92.04 95.02 96.00 HDS
7/20/2022 10:50 AM 10.00 2.04 7.96 7.17 5.13 61.54 100.00 102.04 92.04 94.87 96.00 HDS
7/27/2022 12:00 PM 10.00 2.04 7.96 8.35 6.31 75.70 100.00 102.04 92.04 93.69 96.00 HDS
8/3/2022 10:15 AM 10.00 2.04 7.96 Dry 7.96 95.50 100.00 102.04 92.04 92.04 96.00 HDS
8/10/2022 11:00 AM 10.00 2.04 7.96 Dry 7.96 95.50 100.00 102.04 92.04 92.04 96.00 HDS
8/16/2022 11:00 AM 10.00 2.04 7.96 Dry 7.96 95.50 100.00 102.04 92.04 92.04 96.00 HDS
8/24/2022 12:00 PM 10.00 2.04 7.96 Dry 7.96 95.50 100.00 102.04 92.04 92.04 96.00 HDS
8/31/2022 1:15 PM 10.00 2.04 7.96 Dry 7.96 95.50 100.00 102.04 92.04 92.04 96.00 HDS
9/7/2022 2:00 PM 10.00 2.04 7.96 8.10 6.06 72.70 100.00 102.04 92.04 93.94 96.00 HDS
9/14/2022 12:30 PM 10.00 2.04 7.96 8.44 6.40 76.78 100.00 102.04 92.04 93.60 96.00 HDS
9/21/2022 12:30 PM 10.00 2.04 7.96 8.97 6.93 83.14 100.00 102.04 92.04 93.07 96.00 HDS
9/28/2022 2:40 PM 10.00 2.04 7.96 9.05 7.01 84.10 100.00 102.04 92.04 92.99 96.00 HDS
10/5/2022 11:25 AM 10.00 2.04 7.96 9.21 7.17 86.02 100.00 102.04 92.04 92.83 96.00 ORB
10/12/2022 2:15 PM 10.00 2.04 7.96 8.70 6.66 79.90 100.00 102.04 92.04 93.34 96.00 HDS
10/19/2022 2:20 PM 10.00 2.04 7.96 8.00 5.96 71.50 100.00 102.04 92.04 94.04 96.00 HDS
Installed By: EGS (AESI)
Groundwater Monitoring Results: MW-1
Project: Lumber Yard Apartments
Project Number: 22-015
Location: See well location map
Date Installed: March 10, 2022
90.00
92.00
94.00
96.00
98.00
100.00
102.00
104.00
3/15/2022 4/12/2022 5/10/2022 6/7/2022 7/5/2022 8/2/2022 8/30/2022 9/27/2022 10/25/2022ELEVATION (FT)DATE
LUMBER YARD APARTMENTS (PROJECT 22‐015)
MONITOR WELL 1
Ground Surface Elevation Top oF Casing Elevation Groundwater Elevation Bottom of Casing Elevation 4' of Separation from GSE
NOTES:
If the well is dry, graph shows the groundwater at bottom of the well casing.
Assumed Ground Surface Elevation of 100.0‐ft.
All measurements for this well are in reference to the assumed Ground Surface Elevation.
*MW‐2 obliterated by construction on 7/13/2022.
Total Well Well Measure Depth to Top Bottom 4'
Well Casing Casing from T.O.C. GW Depth to Ground of of GW below Measured
Date Time Casing Height Bury to GW Below GW Surface Casing Casing Elev. Ground by
Length Depth Ground Elev. Elev. Elev. Surface
(ft) (feet) (feet) (feet) (feet) (inches) (feet) (feet) (feet) (feet)
3/25/2022 4:30 PM 10.00 1.50 8.50 7.43 5.93 71.16 100.00 101.50 91.50 94.07 96.00 JGE
4/1/2022 1:15 PM 10.00 1.50 8.50 7.57 6.07 72.84 100.00 101.50 91.50 93.93 96.00 JGE
4/6/2022 10:30 AM 10.00 1.50 8.50 7.62 6.12 73.44 100.00 101.50 91.50 93.88 96.00 JGE
4/12/2022 3:00 PM 10.00 1.50 8.50 7.73 6.23 74.76 100.00 101.50 91.50 93.77 96.00 ORB
4/19/2022 2:30 PM 10.00 1.50 8.50 7.74 6.24 74.88 100.00 101.50 91.50 93.76 96.00 ORB
4/26/2022 10:45 AM 10.00 1.50 8.50 7.19 5.69 68.28 100.00 101.50 91.50 94.31 96.00 ORB
5/4/2022 7:10 AM 10.00 1.50 8.50 6.53 5.03 60.36 100.00 101.50 91.50 94.97 96.00 ORB
5/10/2022 12:00 PM 10.00 1.50 8.50 6.65 5.15 61.80 100.00 101.50 91.50 94.85 96.00 ORB
5/17/2022 1:30 PM 10.00 1.50 8.50 6.59 5.09 61.08 100.00 101.50 91.50 94.91 96.00 JGE
5/23/2022 12:10 PM 10.00 1.50 8.50 7.00 5.50 66.00 100.00 101.50 91.50 94.50 96.00 ORB
5/31/2022 11:20 AM 10.00 1.50 8.50 5.99 4.49 53.88 100.00 101.50 91.50 95.51 96.00 ORB
6/8/2022 2:30 PM 10.00 1.50 8.50 6.22 4.72 56.64 100.00 101.50 91.50 95.28 96.00 ORB
6/15/2022 11:30 AM 10.00 1.50 8.50 6.59 5.09 61.08 100.00 101.50 91.50 94.91 96.00 ORB
6/22/2022 12:15 PM 10.00 1.50 8.50 6.95 5.45 65.40 100.00 101.50 91.50 94.55 96.00 ORB
6/29/2022 12:45 PM 10.00 1.50 8.50 7.31 5.81 69.72 100.00 101.50 91.50 94.19 96.00 ORB
7/6/2022 1:45 PM 10.00 1.50 8.50 7.35 5.85 70.20 100.00 101.50 91.50 94.15 96.00 ORB
7/13/2022 11:00 AM 10.00 1.50 8.50 *N/A #VALUE! #VALUE! 100.00 101.50 91.50 #VALUE! 96.00 HDS
7/20/2022 10:50 AM 10.00 1.50 8.50 *N/A #VALUE! #VALUE! 100.00 101.50 91.50 #VALUE! 96.00 HDS
7/27/2022 12:00 PM 10.00 1.50 8.50 *N/A #VALUE! #VALUE! 100.00 101.50 91.50 #VALUE! 96.00 HDS
8/3/2022 10:15 AM 10.00 1.50 8.50 *N/A #VALUE! #VALUE! 100.00 101.50 91.50 #VALUE! 96.00 HDS
8/10/2022 11:00 AM 10.00 1.50 8.50 *N/A #VALUE! #VALUE! 100.00 101.50 91.50 #VALUE! 96.00 HDS
8/16/2022 11:00 AM 10.00 1.50 8.50 *N/A #VALUE! #VALUE! 100.00 101.50 91.50 #VALUE! 96.00 HDS
8/24/2022 12:00 PM 10.00 1.50 8.50 *N/A #VALUE! #VALUE! 100.00 101.50 91.50 #VALUE! 96.00 HDS
8/31/2022 1:15 PM 10.00 1.50 8.50 *N/A #VALUE! #VALUE! 100.00 101.50 91.50 #VALUE! 96.00 HDS
9/7/2022 2:00 PM 10.00 1.50 8.50 *N/A #VALUE! #VALUE! 100.00 101.50 91.50 #VALUE! 96.00 HDS
9/14/2022 12:30 PM 10.00 1.50 8.50 *N/A #VALUE! #VALUE! 100.00 101.50 91.50 #VALUE! 96.00 HDS
9/21/2022 12:30 PM 10.00 1.50 8.50 *N/A #VALUE! #VALUE! 100.00 101.50 91.50 #VALUE! 96.00 HDS
9/28/2022 2:40 PM 10.00 1.50 8.50 *N/A #VALUE! #VALUE! 100.00 101.50 91.50 #VALUE! 96.00 HDS
10/5/2022 11:25 AM 10.00 1.50 8.50 *N/A #VALUE! #VALUE! 100.00 101.50 91.50 #VALUE! 96.00 ORB
10/12/2022 2:15 PM 10.00 1.50 8.50 *N/A #VALUE! #VALUE! 100.00 101.50 91.50 #VALUE! 96.00 HDS
10/19/2022 2:20 PM 10.00 1.50 8.50 *N/A #VALUE! #VALUE! 100.00 101.50 91.50 #VALUE! 96.00 HDS
Installed By: EGS (AESI)
Groundwater Monitoring Results: MW-2
Project: Lumber Yard Apartments
Project Number: 22-015
Location: See well location map
Date Installed: March 10, 2022
90.00
92.00
94.00
96.00
98.00
100.00
102.00
3/15/2022 4/12/2022 5/10/2022 6/7/2022 7/5/2022 8/2/2022 8/30/2022 9/27/2022 10/25/2022ELEVATION (FT)DATE
LUMBER YARD APARTMENTS (PROJECT 22‐015)
MONITOR WELL 2
Ground Surface Elevation Top oF Casing Elevation Groundwater Elevation Bottom of Casing Elevation 4' of Separation from GSE
NOTES:
If the well is dry, graph shows the groundwater at bottom of the well casing.
Assumed Ground Surface Elevation of 100.0‐ft.
All measurements for this well are in reference to the assumed Ground Surface Elevation.
Dewatering was ongoing from 7/27/2022 through 8/31/2022.
Total Well Well Measure Depth to Top Bottom 4'
Well Casing Casing from T.O.C. GW Depth to Ground of of GW below Measured
Date Time Casing Height Bury to GW Below GW Surface Casing Casing Elev. Ground by
Length Depth Ground Elev. Elev. Elev. Surface
(ft) (feet) (feet) (feet) (feet) (inches) (feet) (feet) (feet) (feet)
3/25/2022 4:30 PM 10.00 2.42 7.58 4.67 2.25 27.04 100.00 102.42 92.42 97.75 96.00 JGE
4/1/2022 1:15 PM 10.00 2.42 7.58 4.80 2.38 28.60 100.00 102.42 92.42 97.62 96.00 JGE
4/6/2022 10:30 AM 10.00 2.42 7.58 4.84 2.42 29.08 100.00 102.42 92.42 97.58 96.00 JGE
4/12/2022 3:00 PM 10.00 2.42 7.58 4.98 2.56 30.76 100.00 102.42 92.42 97.44 96.00 ORB
4/19/2022 2:30 PM 10.00 2.42 7.58 4.97 2.55 30.64 100.00 102.42 92.42 97.45 96.00 ORB
4/26/2022 10:45 AM 10.00 2.42 7.58 4.42 2.00 24.04 100.00 102.42 92.42 98.00 96.00 ORB
5/4/2022 7:10 AM 10.00 2.42 7.58 3.69 1.27 15.28 100.00 102.42 92.42 98.73 96.00 ORB
5/10/2022 12:00 PM 10.00 2.42 7.58 3.67 1.25 15.04 100.00 102.42 92.42 98.75 96.00 ORB
5/17/2022 1:30 PM 10.00 2.42 7.58 3.76 1.34 16.12 100.00 102.42 92.42 98.66 96.00 JGE
5/23/2022 12:10 PM 10.00 2.42 7.58 4.23 1.81 21.76 100.00 102.42 92.42 98.19 96.00 ORB
5/31/2022 11:20 AM 10.00 2.42 7.58 3.29 0.87 10.48 100.00 102.42 92.42 99.13 96.00 ORB
6/8/2022 2:30 PM 10.00 2.42 7.58 3.59 1.17 14.08 100.00 102.42 92.42 98.83 96.00 ORB
6/15/2022 11:30 AM 10.00 2.42 7.58 3.89 1.47 17.68 100.00 102.42 92.42 98.53 96.00 ORB
6/22/2022 12:15 PM 10.00 2.42 7.58 4.24 1.82 21.88 100.00 102.42 92.42 98.18 96.00 ORB
6/29/2022 12:45 PM 10.00 2.42 7.58 4.63 2.21 26.56 100.00 102.42 92.42 97.79 96.00 ORB
7/6/2022 1:45 PM 10.00 2.42 7.58 4.70 2.28 27.40 100.00 102.42 92.42 97.72 96.00 ORB
7/13/2022 11:00 AM 10.00 2.42 7.58 5.01 2.59 31.12 100.00 102.42 92.42 97.41 96.00 HDS
7/20/2022 10:50 AM 10.00 2.42 7.58 5.09 2.67 32.08 100.00 102.42 92.42 97.33 96.00 HDS
7/27/2022 12:00 PM 10.00 2.42 7.58 6.91 4.49 53.92 100.00 102.42 92.42 95.51 96.00 HDS
8/3/2022 10:15 AM 10.00 2.42 7.58 8.02 5.60 67.24 100.00 102.42 92.42 94.40 96.00 HDS
8/10/2022 11:00 AM 10.00 2.42 7.58 8.29 5.87 70.48 100.00 102.42 92.42 94.13 96.00 HDS
8/16/2022 11:00 AM 10.00 2.42 7.58 8.46 6.04 72.52 100.00 102.42 92.42 93.96 96.00 HDS
8/24/2022 12:00 PM 10.00 2.42 7.58 8.75 6.33 76.00 100.00 102.42 92.42 93.67 96.00 HDS
8/31/2022 1:15 PM 10.00 2.42 7.58 8.80 6.38 76.60 100.00 102.42 92.42 93.62 96.00 HDS
9/7/2022 2:00 PM 10.00 2.42 7.58 8.35 5.93 71.20 100.00 102.42 92.42 94.07 96.00 HDS
9/14/2022 12:30 PM 10.00 2.42 7.58 5.97 3.55 42.64 100.00 102.42 92.42 96.45 96.00 HDS
9/21/2022 12:30 PM 10.00 2.42 7.58 7.83 5.41 64.96 100.00 102.42 92.42 94.59 96.00 HDS
9/28/2022 2:40 PM 10.00 2.42 7.58 8.15 5.73 68.80 100.00 102.42 92.42 94.27 96.00 HDS
10/5/2022 11:25 AM 10.00 2.42 7.58 8.86 6.44 77.32 100.00 102.42 92.42 93.56 96.00 ORB
10/12/2022 2:15 PM 10.00 2.42 7.58 7.16 4.74 56.92 100.00 102.42 92.42 95.26 96.00 HDS
10/19/2022 2:20 PM 10.00 2.42 7.58 6.65 4.23 50.80 100.00 102.42 92.42 95.77 96.00 HDS
Installed By: EGS (AESI)
Groundwater Monitoring Results: MW-3
Project: Lumber Yard Apartments
Project Number: 22-015
Location: See well location map
Date Installed: March 10, 2022
90.00
92.00
94.00
96.00
98.00
100.00
102.00
104.00
3/15/2022 4/12/2022 5/10/2022 6/7/2022 7/5/2022 8/2/2022 8/30/2022 9/27/2022 10/25/2022ELEVATION (FT)DATE
LUMBER YARD APARTMENTS (PROJECT 22‐015)
MONITOR WELL 3
Ground Surface Elevation Top oF Casing Elevation Groundwater Elevation Bottom of Casing Elevation 4' of Separation from GSE
NOTES:
If the well is dry, graph shows the groundwater at bottom of the well casing.
Assumed Ground Surface Elevation of 100.0‐ft.
All measurements for this well are in reference to the assumed Ground Surface Elevation.
Dewatering was ongoing from 7/27/2022 through 8/31/2022.
Total Well Well Measure Depth to Top Bottom 4'
Well Casing Casing from T.O.C. GW Depth to Ground of of GW below Measured
Date Time Casing Height Bury to GW Below GW Surface Casing Casing Elev. Ground by
Length Depth Ground Elev. Elev. Elev. Surface
(ft) (feet) (feet) (feet) (feet) (inches) (feet) (feet) (feet) (feet)
3/25/2022 4:30 PM 10.00 2.00 8.00 6.76 4.76 57.12 100.00 102.00 92.00 95.24 96.00 JGE
4/1/2022 1:15 PM 10.00 2.00 8.00 6.88 4.88 58.56 100.00 102.00 92.00 95.12 96.00 JGE
4/6/2022 10:30 AM 10.00 2.00 8.00 6.94 4.94 59.28 100.00 102.00 92.00 95.06 96.00 JGE
4/12/2022 3:00 PM 10.00 2.00 8.00 7.04 5.04 60.48 100.00 102.00 92.00 94.96 96.00 ORB
4/19/2022 2:30 PM 10.00 2.00 8.00 7.08 5.08 60.96 100.00 102.00 92.00 94.92 96.00 ORB
4/26/2022 10:45 AM 10.00 2.00 8.00 6.51 4.51 54.12 100.00 102.00 92.00 95.49 96.00 ORB
5/4/2022 7:10 AM 10.00 2.00 8.00 5.75 3.75 45.00 100.00 102.00 92.00 96.25 96.00 ORB
5/10/2022 12:00 PM 10.00 2.00 8.00 5.78 3.78 45.36 100.00 102.00 92.00 96.22 96.00 ORB
5/17/2022 1:30 PM 10.00 2.00 8.00 5.75 3.75 45.00 100.00 102.00 92.00 96.25 96.00 JGE
5/23/2022 12:10 PM 10.00 2.00 8.00 6.18 4.18 50.16 100.00 102.00 92.00 95.82 96.00 ORB
5/31/2022 11:20 AM 10.00 2.00 8.00 5.28 3.28 39.36 100.00 102.00 92.00 96.72 96.00 ORB
6/8/2022 2:30 PM 10.00 2.00 8.00 5.48 3.48 41.76 100.00 102.00 92.00 96.52 96.00 ORB
6/15/2022 11:30 AM 10.00 2.00 8.00 5.79 3.79 45.48 100.00 102.00 92.00 96.21 96.00 ORB
6/22/2022 12:15 PM 10.00 2.00 8.00 6.08 4.08 48.96 100.00 102.00 92.00 95.92 96.00 ORB
6/29/2022 12:45 PM 10.00 2.00 8.00 6.50 4.50 54.00 100.00 102.00 92.00 95.50 96.00 ORB
7/6/2022 1:45 PM 10.00 2.00 8.00 6.63 4.63 55.56 100.00 102.00 92.00 95.37 96.00 ORB
7/13/2022 11:00 AM 10.00 2.00 8.00 6.94 4.94 59.28 100.00 102.00 92.00 95.06 96.00 HDS
7/20/2022 10:50 AM 10.00 2.00 8.00 7.09 5.09 61.08 100.00 102.00 92.00 94.91 96.00 HDS
7/27/2022 12:00 PM 10.00 2.00 8.00 7.92 5.92 71.04 100.00 102.00 92.00 94.08 96.00 HDS
8/3/2022 10:15 AM 10.00 2.00 8.00 8.60 6.60 79.20 100.00 102.00 92.00 93.40 96.00 HDS
8/10/2022 11:00 AM 10.00 2.00 8.00 8.85 6.85 82.20 100.00 102.00 92.00 93.15 96.00 HDS
8/16/2022 11:00 AM 10.00 2.00 8.00 9.07 7.07 84.84 100.00 102.00 92.00 92.93 96.00 HDS
8/24/2022 12:00 PM 10.00 2.00 8.00 9.10 7.10 85.20 100.00 102.00 92.00 92.90 96.00 HDS
8/31/2022 1:15 PM 10.00 2.00 8.00 9.13 7.13 85.56 100.00 102.00 92.00 92.87 96.00 HDS
9/7/2022 2:00 PM 10.00 2.00 8.00 6.75 4.75 57.00 100.00 102.00 92.00 95.25 96.00 HDS
9/14/2022 12:30 PM 10.00 2.00 8.00 8.05 6.05 72.60 100.00 102.00 92.00 93.95 96.00 HDS
9/21/2022 12:30 PM 10.00 2.00 8.00 8.62 6.62 79.44 100.00 102.00 92.00 93.38 96.00 HDS
9/28/2022 2:40 PM 10.00 2.00 8.00 8.85 6.85 82.20 100.00 102.00 92.00 93.15 96.00 HDS
10/5/2022 11:25 AM 10.00 2.00 8.00 8.80 6.80 81.60 100.00 102.00 92.00 93.20 96.00 ORB
10/12/2022 2:15 PM 10.00 2.00 8.00 8.70 6.70 80.40 100.00 102.00 92.00 93.30 96.00 HDS
10/19/2022 2:20 PM 10.00 2.00 8.00 8.50 6.50 78.00 100.00 102.00 92.00 93.50 96.00 HDS
Installed By: EGS (AESI)
Groundwater Monitoring Results: MW-4
Project: Lumber Yard Apartments
Project Number: 22-015
Location: See well location map
Date Installed: March 10, 2022
90.00
92.00
94.00
96.00
98.00
100.00
102.00
104.00
3/15/2022 4/12/2022 5/10/2022 6/7/2022 7/5/2022 8/2/2022 8/30/2022 9/27/2022 10/25/2022ELEVATION (FT)DATE
LUMBER YARD APARTMENTS (PROJECT 22‐015)
MONITOR WELL 4
Ground Surface Elevation Top oF Casing Elevation Groundwater Elevation Bottom of Casing Elevation 4' of Separation from GSE
NOTES:
If the well is dry, graph shows the groundwater at bottom of the well casing.
Assumed Ground Surface Elevation of 100.0‐ft.
All measurements for this well are in reference to the assumed Ground Surface Elevation.
Dewatering was ongoing from 7/27/2022 through 8/31/2022.
Total Well Well Measure Depth to Top Bottom 4'
Well Casing Casing from T.O.C. GW Depth to Ground of of GW below Measured
Date Time Casing Height Bury to GW Below GW Surface Casing Casing Elev. Ground by
Length Depth Ground Elev. Elev. Elev. Surface
(ft) (feet) (feet) (feet) (feet) (inches) (feet) (feet) (feet) (feet)
3/25/2022 4:30 PM 10.00 2.04 7.96 6.82 4.78 57.34 100.00 102.04 92.04 95.22 96.00 JGE
4/1/2022 1:15 PM 10.00 2.04 7.96 6.93 4.89 58.66 100.00 102.04 92.04 95.11 96.00 JGE
4/6/2022 10:30 AM 10.00 2.04 7.96 6.93 4.89 58.66 100.00 102.04 92.04 95.11 96.00 JGE
4/12/2022 3:00 PM 10.00 2.04 7.96 7.02 4.98 59.74 100.00 102.04 92.04 95.02 96.00 ORB
4/19/2022 2:30 PM 10.00 2.04 7.96 7.03 4.99 59.86 100.00 102.04 92.04 95.01 96.00 ORB
4/26/2022 10:45 AM 10.00 2.04 7.96 6.66 4.62 55.42 100.00 102.04 92.04 95.38 96.00 ORB
5/4/2022 7:10 AM 10.00 2.04 7.96 5.99 3.95 47.38 100.00 102.04 92.04 96.05 96.00 ORB
5/10/2022 12:00 PM 10.00 2.04 7.96 6.20 4.16 49.90 100.00 102.04 92.04 95.84 96.00 ORB
5/17/2022 1:30 PM 10.00 2.04 7.96 6.09 4.05 48.58 100.00 102.04 92.04 95.95 96.00 JGE
5/23/2022 12:10 PM 10.00 2.04 7.96 6.48 4.44 53.26 100.00 102.04 92.04 95.56 96.00 ORB
5/31/2022 11:20 AM 10.00 2.04 7.96 5.39 3.35 40.18 100.00 102.04 92.04 96.65 96.00 ORB
6/8/2022 2:30 PM 10.00 2.04 7.96 5.59 3.55 42.58 100.00 102.04 92.04 96.45 96.00 ORB
6/15/2022 11:30 AM 10.00 2.04 7.96 5.96 3.92 47.02 100.00 102.04 92.04 96.08 96.00 ORB
6/22/2022 12:15 PM 10.00 2.04 7.96 6.32 4.28 51.34 100.00 102.04 92.04 95.72 96.00 ORB
6/29/2022 12:45 PM 10.00 2.04 7.96 6.59 4.55 54.58 100.00 102.04 92.04 95.45 96.00 ORB
7/6/2022 1:45 PM 10.00 2.04 7.96 6.55 4.51 54.10 100.00 102.04 92.04 95.49 96.00 ORB
7/13/2022 11:00 AM 10.00 2.04 7.96 6.88 4.84 58.06 100.00 102.04 92.04 95.16 96.00 HDS
7/20/2022 10:50 AM 10.00 2.04 7.96 7.00 4.96 59.50 100.00 102.04 92.04 95.04 96.00 HDS
7/27/2022 12:00 PM 10.00 1.30 7.96 7.53 6.23 74.76 100.00 101.30 92.04 93.77 96.00 HDS
8/3/2022 10:15 AM 10.00 1.30 7.96 Dry 7.96 95.50 100.00 101.30 92.04 92.04 96.00 HDS
8/10/2022 11:00 AM 10.00 1.30 7.96 Dry 7.96 95.50 100.00 101.30 92.04 92.04 96.00 HDS
8/16/2022 11:00 AM 10.00 1.30 7.96 Dry 7.96 95.50 100.00 101.30 92.04 92.04 96.00 HDS
8/24/2022 12:00 PM 10.00 1.30 7.96 Dry 7.96 95.50 100.00 101.30 92.04 92.04 96.00 HDS
8/31/2022 1:15 PM 10.00 1.30 7.96 Dry 7.96 95.50 100.00 101.30 92.04 92.04 96.00 HDS
9/7/2022 2:00 PM 10.00 1.30 7.96 6.75 5.45 65.40 100.00 101.30 92.04 94.55 96.00 HDS
9/14/2022 12:30 PM 10.00 1.30 7.96 7.32 6.02 72.24 100.00 101.30 92.04 93.98 96.00 HDS
9/21/2022 12:30 PM 10.00 1.30 7.96 7.80 6.50 78.00 100.00 101.30 92.04 93.50 96.00 HDS
9/28/2022 2:40 PM 10.00 1.30 7.96 Dry 7.96 95.50 100.00 101.30 92.04 92.04 96.00 HDS
10/5/2022 11:25 AM 10.00 1.30 7.96 Dry 7.96 95.50 100.00 101.30 92.04 92.04 96.00 ORB
10/12/2022 2:15 PM 10.00 1.30 7.96 Dry 7.96 95.50 100.00 101.30 92.04 92.04 96.00 HDS
10/19/2022 2:20 PM 10.00 1.30 7.96 6.61 5.31 63.72 100.00 101.30 92.04 94.69 96.00 HDS
Installed By: EGS (AESI)
Groundwater Monitoring Results: MW-A
Project: Lumber Yard Apartments
Project Number: 22-015
Location: See well location map
Date Installed: 2016
90.00
92.00
94.00
96.00
98.00
100.00
102.00
104.00
3/15/2022 4/12/2022 5/10/2022 6/7/2022 7/5/2022 8/2/2022 8/30/2022 9/27/2022 10/25/2022ELEVATION (FT)DATE
LUMBER YARD APARTMENTS (PROJECT 22‐015)
MONITOR WELL A
Ground Surface Elevation Top oF Casing Elevation Groundwater Elevation Bottom of Casing Elevation 4' of Separation from GSE
NOTES:
If the well is dry, graph shows the groundwater at bottom of the well casing.
Assumed Ground Surface Elevation of 100.0‐ft.
All measurements for this well are in reference to the assumed Ground Surface Elevation.
Dewatering was ongoing from 7/27/2022 through 8/31/2022.
Total Well Well Measure Depth to Top Bottom 4'
Well Casing Casing from T.O.C. GW Depth to Ground of of GW below Measured
Date Time Casing Height Bury to GW Below GW Surface Casing Casing Elev. Ground by
Length Depth Ground Elev. Elev. Elev. Surface
(ft) (feet) (feet) (feet) (feet) (inches) (feet) (feet) (feet) (feet)
3/25/2022 4:30 PM 10.00 1.96 8.04 6.93 4.97 59.66 100.00 101.96 91.96 95.03 96.00 JGE
4/1/2022 1:15 PM 10.00 1.96 8.04 7.03 5.07 60.86 100.00 101.96 91.96 94.93 96.00 JGE
4/6/2022 10:30 AM 10.00 1.96 8.04 7.09 5.13 61.58 100.00 101.96 91.96 94.87 96.00 JGE
4/12/2022 3:00 PM 10.00 1.96 8.04 7.21 5.25 63.02 100.00 101.96 91.96 94.75 96.00 ORB
4/19/2022 2:30 PM 10.00 1.96 8.04 7.23 5.27 63.26 100.00 101.96 91.96 94.73 96.00 ORB
4/26/2022 10:45 AM 10.00 1.96 8.04 6.61 4.65 55.82 100.00 101.96 91.96 95.35 96.00 ORB
5/4/2022 7:10 AM 10.00 1.96 8.04 5.89 3.93 47.18 100.00 101.96 91.96 96.07 96.00 ORB
5/10/2022 12:00 PM 10.00 1.96 8.04 6.03 4.07 48.86 100.00 101.96 91.96 95.93 96.00 ORB
5/17/2022 1:30 PM 10.00 1.96 8.04 6.01 4.05 48.62 100.00 101.96 91.96 95.95 96.00 JGE
5/23/2022 12:10 PM 10.00 1.96 8.04 6.36 4.40 52.82 100.00 101.96 91.96 95.60 96.00 ORB
5/31/2022 11:20 AM 10.00 1.96 8.04 5.48 3.52 42.26 100.00 101.96 91.96 96.48 96.00 ORB
6/8/2022 2:30 PM 10.00 1.96 8.04 5.73 3.77 45.26 100.00 101.96 91.96 96.23 96.00 ORB
6/15/2022 11:30 AM 10.00 1.96 8.04 6.03 4.07 48.86 100.00 101.96 91.96 95.93 96.00 ORB
6/22/2022 12:15 PM 10.00 1.96 8.04 6.47 4.51 54.14 100.00 101.96 91.96 95.49 96.00 ORB
6/29/2022 12:45 PM 10.00 1.96 8.04 6.66 4.70 56.42 100.00 101.96 91.96 95.30 96.00 ORB
7/6/2022 1:45 PM 10.00 1.96 8.04 6.83 4.87 58.46 100.00 101.96 91.96 95.13 96.00 ORB
7/13/2022 11:00 AM 10.00 1.96 8.04 7.03 5.07 60.86 100.00 101.96 91.96 94.93 96.00 HDS
7/20/2022 10:50 AM 10.00 1.96 8.04 7.20 5.24 62.90 100.00 101.96 91.96 94.76 96.00 HDS
7/27/2022 12:00 PM 10.00 1.96 8.04 7.50 5.54 66.50 100.00 101.96 91.96 94.46 96.00 HDS
8/3/2022 10:15 AM 10.00 1.96 8.04 8.25 6.29 75.50 100.00 101.96 91.96 93.71 96.00 HDS
8/10/2022 11:00 AM 10.00 1.96 8.04 8.65 6.69 80.30 100.00 101.96 91.96 93.31 96.00 HDS
8/16/2022 11:00 AM 10.00 1.96 8.04 Dry 8.04 96.50 100.00 101.96 91.96 91.96 96.00 HDS
8/24/2022 12:00 PM 10.00 1.96 8.04 Dry 8.04 96.50 100.00 101.96 91.96 91.96 96.00 HDS
8/31/2022 1:15 PM 10.00 1.96 8.04 Dry 8.04 96.50 100.00 101.96 91.96 91.96 96.00 HDS
9/7/2022 2:00 PM 10.00 1.96 8.04 8.72 6.76 81.14 100.00 101.96 91.96 93.24 96.00 HDS
9/14/2022 12:30 PM 10.00 1.96 8.04 8.30 6.34 76.10 100.00 101.96 91.96 93.66 96.00 HDS
9/21/2022 12:30 PM 10.00 1.96 8.04 8.29 6.33 75.98 100.00 101.96 91.96 93.67 96.00 HDS
9/28/2022 2:40 PM 10.00 1.96 8.04 8.65 6.69 80.30 100.00 101.96 91.96 93.31 96.00 HDS
10/5/2022 11:25 AM 10.00 1.96 8.04 Dry 8.04 96.50 100.00 101.96 91.96 91.96 96.00 ORB
10/12/2022 2:15 PM 10.00 1.96 8.04 Dry 8.04 96.50 100.00 101.96 91.96 91.96 96.00 HDS
10/19/2022 2:20 PM 10.00 1.96 8.04 Dry 8.04 96.50 100.00 101.96 91.96 91.96 96.00 HDS
Installed By: EGS (AESI)
Groundwater Monitoring Results: MW-B
Project: Lumber Yard Apartments
Project Number: 22-015
Location: See well location map
Date Installed: 2016
90.00
92.00
94.00
96.00
98.00
100.00
102.00
104.00
3/15/2022 4/12/2022 5/10/2022 6/7/2022 7/5/2022 8/2/2022 8/30/2022 9/27/2022 10/25/2022ELEVATION (FT)DATE
LUMBER YARD APARTMENTS (PROJECT 22‐015)
MONITOR WELL B
Ground Surface Elevation Top oF Casing Elevation Groundwater Elevation Bottom of Casing Elevation 4' of Separation from GSE