Plan Review - Review Comments Report
Project Name: 22348 Nelson Meadows Business Park INF
Workflow Started: 10/27/2022 7:02:37 AM
Report Generated: 01/23/2023 10:36 AM
REVIEW COMMENTS
REF #CYCLE REVIEWED BY TYPE FILENAME DISCUSSION
1 CD Technician
Jonathan Fuller
11/14/22 8:41 AM
Checklist Item
Incorrect Naming Protocol- Please remove dates from titles as they affect
versioning. A helpful naming protocol info sheet can be found at the
following link:
https://www.bozeman.net/home/showpublisheddocument/11487/63771629
4393064006
Responsed by: Jeremy May - 11/14/22 9:1
Updated plans and docs have been upload
2 1 Solid Waste
Russell Ward
12/14/22 6:06 AM
Changemark
SLD Waste
1. please make sure that island does not encroach into the 50 foot straight
approach
003-C.2-SITE PLAN.pdf
3 1 Solid Waste
Russell Ward
12/14/22 6:11 AM
Changemark
SLD Waste
1.need detailed plan for refuse enclosure
003-C.2-SITE PLAN.pdf
4 1 Water Rights
Griffin Nielson
12/20/22 5:20 PM
Comment
BMC 38.410.130. Water Adequacy - The development will need to satisfy the
water adequacy code requirement prior to future site plan approval. A cash-
in-lieu of water rights (CILWR) fee determination will be completed during
the site plan review process, however, if there are any questions or if a
preliminary review is desired please contact Griffin Nielsen with the
Engineering/Utility Department directly. Email: gnielsen@bozeman.net
Phone: 406 582-2279.
5 1 Engineering
Alicia Paz-Solis
12/23/22 1:22 PM
Comment
City of Bozeman Resolution 5076, Policy 1 - The applicant must provide
and file with the County Clerk and Recorder's office executed Waivers of
Right to Protest Creation of Special Improvement Districts (SID’s) on City
standard form for the following:
Street improvements to Prince Lane between Nelson Road and Frontage
Road including lighting, signalization, paving, curb/gutter, sidewalk, and
storm drainage.
1. Street improvements to Royal Wolf Way between Nelson Road and
northern right-of-way established with the Nelson Meadows
Subdivision plat including lighting, signalization, paving, curb/gutter,
sidewalk, and storm drainage.
2. Street improvements to Nelson Road between Frontage Road and
Prince Lane including lighting, signalization, paving, curb/gutter,
sidewalk, and storm drainage.
3. Street improvements to Frontage Road between Nelson Road and
East Valley Center Spur/Prince Lane including lighting, signalization,
paving, curb/gutter, sidewalk, and storm drainage.
4. Intersection improvements at Prince Lane and Nelson Road including
lighting, signalization/channelization, paving, curb/gutter, sidewalk,
and storm drainage.
5. Intersection improvements at Prince Lane and Royal Wolf Way
including lighting, signalization/channelization, paving, curb/gutter,
sidewalk, and storm drainage.
6. Intersection improvements at Prince Lane and Frontage Road Avenue
including lighting, signalization/channelization, paving, curb/gutter,
sidewalk, and storm drainage. h. Intersection improvements at Royal
Wolf Way and Nelson Road including lighting,
signalization/channelization, paving, curb/gutter, sidewalk, and
storm drainage.
7. Intersection improvements to Nelson Road and Frontage Road
including lighting, signalization/channelization, paving, curb/gutter,
sidewalk, and storm drainage.
8. Intersection improvements to East Valley Center Spur and Frontage
Road including lighting, signalization/channelization, paving,
curb/gutter, sidewalk, and storm drainage.
The document filed must specify that in the event an SID is not utilized for
the completion of these improvements, the developer agrees to participate
in an alternate financing method for the completion of the improvements on
a fair share, proportionate basis as determined by square footage of
property, taxable valuation of the property, traffic contribution from the
development, or a combination thereof. The applicant must provide a copy
of the filed SID waiver prior to the site plan approval. Please use appropriate
template found in the City Documents and Staff Reports folder.
1/23/23, 10:36 AM Report Viewer
https://bozeman-mt-us.avolvecloud.com/ProjectDox/ReportViewer.aspx?ReportPath=%2FReport%2FPlan Review - Review Comments&DataSourceN…2/4
6 1 Engineering
Alicia Paz-Solis
12/23/22 1:25 PM
Comment
Easement Water & Sewer - The applicant must provide a thirty (30) foot
public utility easement to accommodate both water main extension (BMC
38.410.060.C.1). Please use easement template found in the City Documents
and Staff Reports folder.
7 1 Engineering
Alicia Paz-Solis
12/23/22 1:38 PM
Comment
Concurrent Construction - To achieve building permit approvals prior to
completion of (water main extension) the applicant must follow BMC
38.270.030.C.1 options b and c. The following items must be in place prior to
building permit approval as can be seen in 1 through 4 of section c.
8 1 Engineering
Alicia Paz-Solis
12/23/22 1:39 PM
Comment
Water & Sewer Demand - The estimates provided must be certified by a
professional engineer (BMC 38.410.070 and DSSP Section V.A and V.B). The
applicant will need to verify that the reported water and sewer demands are
within the parameters established in the Nelson Meadows Subdivision Water
& Sewer Report.
9 1 Engineering
Alicia Paz-Solis
12/23/22 1:47 PM
Comment
Stormwater Drainage
The applicant will need to confirm runoff produced from this site will not
exceed the runoff volumes assigned to the parcel in the existing Nelson
Meadows Subdivision Drainage Report.
11 1 Engineering
Alicia Paz-Solis
12/23/22 3:16 PM
Comment
Stormwater Drainage
1. Water Quality - The applicant must include a drainage plan with
post-construction stormwater management controls that are
designed to infiltrate, evapotranspire, and/or capture for reuse the
post-construction runoff generated from the first 0.5 inches of
rainfall from a 24-hour storm preceded by 48 hours of no
measurable precipitation. For projects that cannot meet 100% of the
runoff reduction requirement, the remainder of the runoff from the
first 0.5 inches of rainfall must be either: a. Treated onsite using post-
construction storm water management control(s) expected to
remove 80 percent total suspended solids (TSS); b. Managed offsite
within the same sub-watershed using post-construction storm water
management control(s) that are designed to infiltrate,
evapotranspire, and/or capture for reuse; or c. Treated offsite within
the same subwatershed using post-construction storm water
management control(s) expected to remove 80 percent TSS (DSSP
Section II.A.4).
2. Water Quantity - The applicant must provide on-site detention with
release rates limited to predevelopment runoff rates. Retention
ponds must be sized based on a 10-year, 2-hour storm intensity
(DSSP Section II.C).
3. Seasonal High Groundwater - The applicant must demonstrate that
seasonal high groundwater will not impact the function or
maintenance of the proposed facilities. Industry guidance
recommends a three-foot minimum separation from the bottom of
the proposed facility to the underlying groundwater table. The
applicant must provide local seasonal high groundwater elevations
to support the proposed design (Montana Post-Construction Storm
Water BMP Design Guidance Manual).
12 1 Engineering
Alicia Paz-Solis
12/23/22 3:17 PM
Comment
Trip Generation - Please demonstrate that the peak trips generated from
this site match the trips generated metrics assigned to the Park Place
Industrial Park Traffic Impact Study ((BMC 38.220.080.A.2.g).
13 1 Planning
Nakeisha Lyon
12/28/22 10:19 AM
Changemark
PLNG: Phasing in Parking Calculations
Please revise in formal submittal as Phase 1 is repeated twice in this section.
023-PH1-PHASE PLAN.pdf
14 1 Planning
Nakeisha Lyon
12/28/22 10:24 AM
Changemark
PLNG: Grammar
Spelling of manufacturing must be corrected.
023-PH1-PHASE PLAN.pdf
15 1 Building Division
Ben Abbey
12/28/22 10:28 AM
Changemark
BLDG - Adopted 21 Building Codes
2021 International Building Code (IBC) ICC A117.1-2017 Standard for
Accessible and Usable Buildings and Facilities
001-I.1-COVER.pdf
16 1 Stormwater
Division
Russ Smith
12/28/22 11:57 AM
Changemark
Stormflow path
Flowpaths indicate northward drainage into regional stormpond. Inform
storm calculations in grading and drainage plan (BMC 38.410.080) detailing
down-gradient receiving area capacity. (DSSP II.B.) Description of the
ultimate destination of stormwater runoff from the project and an evaluation
of its impact on downslope drainage facilities and water quality. Discuss
erosion control measures for regional pond if used for surface storm flow
(II.A.3.c.)
004-C.3-CIVIL PLAN.pdf
17 1 Fire Department
Scott Mueller
12/28/22 3:48 PM
Comment
Fire Riser rooms meet city standards, have an exterior access door and a
sidewalk from door to public way. Similarly, the Fire Department Connection
(FDC) and horn/strobe shall be located and accessible from building front
with a sidewalk underneath and not blocked by landscaping. Also, any exit
doors from buildings require a sidewalk to public way. Seems some
proposed on Buildings 1 and 2 do not have sidewalks on East side. Similar
for Building 3 on West side. Internal access roads are acceptable maintaining
minimum 20 feet width and circulation without have fire apparatus
turnarounds.
1/23/23, 10:36 AM Report Viewer
https://bozeman-mt-us.avolvecloud.com/ProjectDox/ReportViewer.aspx?ReportPath=%2FReport%2FPlan Review - Review Comments&DataSourceN…3/4
18 1 Northwestern
Energy
Matt Tilstra
1/5/23 10:50 AM
Changemark
NWE
Please submit construction application to begin sizing NWE transformer and
services. If meters are to be screened, there needs to be a 4ft clear zone in
front of them.
003-C.2-SITE PLAN.pdf
19 1 PlanningNakeisha Lyon1/18/23 4:14 PM
ChangemarkPLNG: Parcel and Total Site InformationPlease include location, percentage of parcel and total site, and square footage for the following on the cover sheet: Existing and proposed buildings and structures, driveway circulation and parking areas, semipublic land areas such as recreational, open space, and landscape areas, and public street right-of-way.
001-I.1-COVER.pdf
20 1 Planning
Nakeisha Lyon
1/18/23 4:16 PM
Changemark
PLNG: Plan Index Correction
Please include this cover sheet in the plan index denoted on this page.
001-I.1-COVER.pdf
21 1 PlanningNakeisha Lyon1/18/23 4:16 PM
ChangemarkPLNG: Community Plan DesignationPlease revise the Community Plan Designation to Industrial.
001-I.1-COVER.pdf
22 1 Planning
Nakeisha Lyon
1/18/23 4:17 PM
Changemark
PLNG: Open Space Requirement
Open space is not required for this because it's in an M-1 zoning district.
Please revise that it's based on industrial zoning, not commercial use (which
does require open space).
001-I.1-COVER.pdf
23 1 PlanningNakeisha Lyon1/18/23 4:18 PM
ChangemarkPLNG: Lot Coverage CalculationsPlease include lot coverage calculations per Sec. 38.230.050.
001-I.1-COVER.pdf
24 1 Planning
Nakeisha Lyon
1/18/23 4:49 PM
Library Comment
BMC 38.350.060 - Fences, walls and hedges. If any fences, walls or hedges
are proposed, please ensure conformance with Sec. 38.350.060. and provide
any details of materials and species on the landscape plan and detail sheets.
25 1 PlanningNakeisha Lyon1/20/23 3:37 PM
Library CommentBMC 38.560.060 - Signs permitted upon the issuance of a sign permit. Please note a separate sign and building permit must be obtained prior to the construction, placement, erection or modification of any signage in conformance with this section of the BMC.
26 1 Planning
Nakeisha Lyon
1/20/23 3:37 PM
Library Comment
BMC 38.560.080 - Comprehensive sign plan. A comprehensive sign plan is
required for industrial buildings or centers consisting of two or more
tenants. This must be approved prior to the request for any signage related
to the buildings in this development. Dependent on the future tenant(s) on
the subject property, this must be approved prior to the submittal of a sign
permit. Unless otherwise approved in the comprehensive sign plan, Sec.
38.560.090. - Multi-tenant complexes with less than 100,000 square feet of
ground floor area would apply to the signage in this application.
27 1 PlanningNakeisha Lyon1/20/23 3:37 PM
Library CommentBMC 38.570. Lighting. Please provide a detailed lighting plan, if applicable, in accordance with this section of the BMC.
28 1 Planning
Nakeisha Lyon
1/20/23 3:52 PM
Library Comment
BMC 38.540.080 - Off-street loading berth requirements. Please provide
loading ramp details and specifications for the proposed loading berths and
necessary screening as denoted for service areas per Sec. 38.520.070. Based
on the gross floor area of each building, it appears a loading berth(s) is not
required.
29 1 PlanningNakeisha Lyon1/20/23 3:52 PM
Library CommentBMC 38.550. Landscaping. Please provide a detailed landscaping plan in accordance with this section of the BMC and Sec. 38.220.100 during the formal submittal. Please ensure conformance with Sec. 38.550.050.B. in reference to the required drought tolerant species. Please ensure conformance with Sec. 38.550.050.C.2.d. in reference to planting requirements of trees from the back of curb/edging. Please ensure conformance with Sec. 38.550.050.C.2.e.(3) in reference to the minimum width and/or length requirements for parking lot landscaping islands. Please provide mandatory landscaping provisions as applicable for parking lot screening, street frontage trees, etc as denoted in this section of code. An irrigation plan is required as denoted in this division of the BMC.
30 1 Planning
Nakeisha Lyon
1/20/23 3:55 PM
Comment
Sec. 38.540.050.A.4. Please provide bicycle parking calculations, and
proposed bicycle rack details (rack type, dimensions, etc). in conformance
with this section and Sec. 38.540.040.A.5.
31 1 PlanningNakeisha Lyon1/20/23 4:02 PM
CommentSec. 38.540.010.A.4. Stacking of off-street parking spaces. Required parking spaces must be located so as to preclude stacking of off-street parking
spaces, with the exception of single-household dwellings and individual
townhouse, rowhouse, and multi-household units, and two unit structures
with physically separated individual drive aisles. Physical separation is
provided when at least one of these options are employed: individual garage
doors for each interior parking space; a vegetated planter not less than four
feet in width between the parking spaces in the driveway area, or a wall not
less than four feet in height and length, is provided between the parking
area in the driveway and divides the garage entrance. Generally, not more
than two cars may be stacked. When stacking is allowed, not more than two
vehicles may be stacked within an enclosed parking area. Commercial and
industrial parking spaces cannot stack which appears to be occurring along
the buildings via the parking spaces in front of the overhead door and the
1/23/23, 10:36 AM Report Viewer
https://bozeman-mt-us.avolvecloud.com/ProjectDox/ReportViewer.aspx?ReportPath=%2FReport%2FPlan Review - Review Comments&DataSourceN…4/4
space denoted in the building. Parking may only occur in this area if it is a
parking garage or has separation from the manufacturing use as the space
may only be for the vehicle. Internal spaces must meet the Garage
Dimensions of Sec. 38.540.010.A.4. If this occurs, the direct space in front of
this must be removed.
32 1 Planning
Nakeisha Lyon
1/20/23 4:09 PM
Comment
Sec. 38.540.050.A.1.a.(1) On street parking spaces only applies to the
required parking for residential development. Please remove these spaces
from the calculations. Parallel on street parking is not allowed for any of the
uses indicated in this informal submittal.
33 1 Planning
Nakeisha Lyon
1/20/23 4:12 PM
Comment
Sec. 38.540.010.2.b. If maximum use on the subject property is 100%
manufacturing, the parking is in excess of the allowed parking maximum
which is 125%.
34 1 Planning
Nakeisha Lyon
1/20/23 4:14 PM
Comment
Table 38.540.050-3. Please include the 1 space per 2 employees at maximum
working shift in the calculations for the manufacturing use. Please revise the
parking space requirements accordingly.
35 1 Planning
Nakeisha Lyon
1/20/23 4:27 PM
Comment
Please provide clarity in the uses in regards to parking calculations and other
requirements that may be imposed if this is an office and manufacturing use
versus strictly manufacturing. With the maximum parking percentage in
code, approving 150% over this maximum is not something the code can
accommodate.
36 1 Planning
Nakeisha Lyon
1/20/23 4:51 PM
Comment
Please ensure striping, lighting, and signs for the parking lot are met per Sec.
38.540.010.G-I.
37 1 Planning
Nakeisha Lyon
1/20/23 5:09 PM
Library Comment
BMC 38.530.060 - Building materials. Please demonstrate conformance with
Sec. 38.530.060. for all building materials.
38 1 Planning
Nakeisha Lyon
1/20/23 5:09 PM
Library Comment
BMC 38.530.070 - Blank wall treatments. Please demonstrate conformance
with Sec. 38.530.070 for any blank wall areas.
39 1 Planning
Nakeisha Lyon
1/20/23 5:39 PM
Library Comment
Sec. 38.520.040.D.2. Pathway design. Where a pathway is adjacent to
perpendicular or angled parking, an extra two feet of walkway width must
be provided to mitigate for parked vehicles overhanging the walkway. If
changes occur to the landscaped and paved areas along Building 1 and 2
that would lead to the parking spaces being perpendicular to the pathway,
these pathways must meet this provision.