HomeMy WebLinkAbout014_PreliminaryWaterEngineeringReportBlock4Engineering Report
Water Main Extension
South University District
Phase 3 - Block 4
Site Plan Submittal
Updated May 2023
Submitted to:
City of Bozeman Engineering Department
20 East Olive
Bozeman, MT 59715
Prepared by:
Stahly Engineering and Associates
851 Bridger Drive, Suite 1
Bozeman, MT 59715
(406) 522-8594
Water Mains 1 5/19/2023
Engineering Report
Contents
Note: The Engineering Report format follows DEQ-1 organization. Additional
information required by the City of Bozeman Design Standards is added where
required.
Report Narrative
1.1.1 General Information
1.1.2 Extent of water works system
1.1.3 Alternate plans
1.1.4 Site conditions
1.1.5 Water use data
1.1.6 Flow requirements
1.1.7 Sources of water supply
1.1.8 Proposed treatment processes
1.1.9 Sewage system available
1.1.10 Waste disposal
1.1.11 Automation
1.1.12 Project Sites
1.1.13 Financing
1.1.14 Future Extensions
Figures and Tables
Figure 1. Vicinity Map
Figure 2. C2.0 - Water Plan
Table 1. SUD Phase 3 Block 4 Estimated Water Design Flows
Appendices
Hydraulic Analysis Exhibit (To be provided with Infrastructure Submittal)
Water Mains 2 5/19/2023
1.1.1 General Information
The proposed South University District (SUD) Phase 3 Block 4
Development is located southwest of the intersection of South 11th
Avenue and Student Drive. This development will consist of 243
residential units with 655 bedrooms on an 11.89-acre lot.
Six different building types consisting of 20 unique unit configurations
within the buildings is proposed with this development. The intent of this
project is to create a variety of building types to create a diverse
neighborhood in a growing part of town adjacent to the Montana State
University Campus.
The project will be served by extension of City of Bozeman water and
sewer mains throughout the project. Individual service lines will be
provided to each block of units. City of Bozeman water and sewer mains
currently exist along the North side of the project site along Student Drive.
The developer’s contact information is:
Capstone Collegiate Communities
Davis Maxwell
431 Office Park Drive
Birmingham, AL 35223
Water supply and wastewater treatment will be provided by the City of
Bozeman’s municipal systems. The system owner’s contact information is:
City of Bozeman Public Service Department
PO Box 1230
Bozeman, MT 59771-1230
The location of the Block 4 Development is shown on the Vicinity Map in Figure 1
Water Mains 3 5/19/2023
Figure 1. Vicinity Map, Bozeman, Montana
1.1.2 Extent of Water Works System
Water supply to the area is from an existing 8” diameter water main in
Student Dr. and a 12” main on S 11th Ave.
New 8” water mains will be installed in the adjacent portions of S 14th Ave
and Arnold Street as a part of the off-site subdivision improvements to
service the proposed development. Additionally, new on-site water mains
will be extended into the site in combined 30-foot-wide water and sewer
easements.
Each structure will have a single water service from the main to the riser
room, with a curb stop located on the easement or right-of-way line.
Preliminary service sizing indicates a range of 1 ½” to 4” services.
The Block 4 water main extensions have been designed in accordance
with Montana Department of Environmental Quality Circular 1, and the
City of Bozeman Design Standards and Specifications Policy.
Construction specifications will be Montana Public Works Standards and
Specifications (MPWSS), and the City of Bozeman Modifications to
MPWSS.
Water Mains 4 5/19/2023
1.1.3 Alternate Plans
Due to the project’s location within the City of Bozeman, extension of
public mains was the only water supply alternative. Distribution
alternatives were explored, and the proposed design was selected to
increase looping and minimize dead ends. The use of an on-site well as a
source for irrigation usage is not feasible due to the previously-allocated
water rights in the Phase 2 subdivision park.
1.1.4. Site Conditions
The SUD Phase 3 Block 4 site is typical of Bozeman with fine-grained
soils overlying gravel deposits. Geotechnical borings have determined the
depth to gravel ranges from 7.5 to 11 feet. Estimated depth to
groundwater obtained from the geotechnical borings is 8 to 9. If mains are
installed during periods of high groundwater, dewatering may be required.
High groundwater and soil conditions in the area indicate potential for
corrosion of ductile iron pipe. Composite soil samples were collected at
typical depths of water main to test for corrosive soil conditions and found
to be at low risk of corrosion. The full DIPRA Decision Model results and
summary are included in a separate appendix of this submittal.
1.1.5. Water Use Data
The estimated residential water use was based on the City of Bozeman
design standards for wastewater generation. The estimated flow was
determined based on 2.11 people per unit and an average daily flow rate
of 89 gpd/person in accordance with the City of Bozeman Design
Standards Utility Design Criteria.
Site irrigation use was calculated by the Landscape Architect as shown in
the landscaping plans. The following table displays the combined
residential, commercial, and irrigation water design flows.
Water Mains 5 5/19/2023
Table 1: SUD Phase 3 Block 4 Estimated Water Design Flows
The design max day peak hour flow for the proposed Block 4 is 182.03
gpm.
Domestic water will be provided by the City of Bozeman Municipal system.
This project is located within the planned service area of the City’s system.
1.1.6. Flow Requirements
As stated previously, the peak hour water demand is estimated to be
182.03 gallons per min (gpm). Fire flows have not been determined yet
but will be in accordance with the City of Bozeman adopted Uniform Fire
Code. It is anticipated that a fire flow of 1500 gpm will be required. The fire
flow requirement will be the dominant design constraint for system design.
As part of the Phase 3 Subdivision process, a hydraulic analysis was
completed to determine the available fire flow in this area. According to
this analysis, Phase 3 hydrants – including those in Block 4 – will have fire
flows ranging from 3,122 gpm to 3,606 gpm, while maintaining a residual
pressure within the system of 20 psi.
Fire flow requirements are based on the Uniform Fire Code. The required
hydrant flow is determined using Table H.5.1 of the Uniform Fire Code.
For example, a 48,000 sq ft Type V-A building requires a fire flow of 4,000
gpm. In consideration of the planned use of sprinkler systems in future
Phase 3 site developments projects, the fire department is allowing a 75%
SUD Phase 3 Block 4 Estimated Water and Sewer Usage
Site Area (acres)11.89
Bedrooms 655
Residential Occupants 655
Per Capita Use (gpd)89
Residential Flow (gpd)58,295
Commercial Area (sf)0
Commercial Use (gpd/1000 sf)0
Commercial Flow (gpd)0
Commercial and Residential Flows (gpd)58,295
Commercial and Residential Flows (gpm)40
Average Day Water Use [Equal to Commercial & Residntial Flows](gpd) 58,295
Irrigation (annual use in gal)1,047,045.00
Irrigation [based on annual use in a 120 day watering season] (gpd) 8,725
Irrigation per Capita (gpd)13
Max Day Water Use [Average Day Use + Irrigation] (gpd)67,020
Peaking Factor (PF)3.91
Design Water Peak Hour Flow 182.03
Water Mains 6 5/19/2023
reduction in required fire flows, reducing the hydrant flow down to the
anticipated minimum required fire flow of 1500 gpm. The fire flow required
will be determined by the fire department at the time of infrastructure
design. The total fire flow available will allow for the use of the hydrant and
the sprinkler while maintaining the required 20 psi residual pressure.
The Phase 3 Subdivision Engineer’s Water report is available upon
request.
1.1.7. Sources of Water Supply
This section is not applicable.
1.1.8. Proposed Treatment Process
This section is not applicable.
1.1.9 Sewage System Available
Sewer service is provided by new City mains extended through the site
from the existing sewer main running along the northern portion of the
property. Sewers will be approximately 8.5 feet deep and primarily cross
below water mains and services.
1.1.10 Waste Disposal
This section is not applicable.
1.1.11 Automation
This section is not applicable.
1.1.12 Project Sites
This section is not applicable.
1.1.13 Financing
This section is not applicable.
1.1.14 Future Extensions
The water system layout accommodates future water main extensions as
required to complete future system improvements in this area.
SDSDUGE
UGE UGE UGE UGE
UGE UGE
UGE
UGE UGE UGE UGE
UGE UGE SSSSSSSSSSSSW W W
W
W
WWW WWWWWWSSSSSSSSSSSSSSSSSSSSSD SD SD SD SD WWWWSOUTH 11TH AVESTUDENT DRIVESOUTH 14TH AVE
W
SS SS SS
SS
SS
SS
W SSHCHCHC HCHCHC SSSSSSSSWWWWWWWWWWWWWWWWWWSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSD SD
SD SDSD SD
SDSD
SDSD
SD
SDSDSDSDSDSDSDSD
SD
SD
SD SDUGEUGEUGEPUGEUGEUGEUGE UGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGE UGEUGEUGEUGE UGEUGEUGEUGEUGEP
PPPPP
UGEUGEUGEWWWWWWWWWWWWWWWWWWWWWSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSD
S
D
SDSD SSSSSSWWUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGE UGE UGE UGE UGE UGE UGE UGEUGEUGEUGEUGE
UGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEWWWWWWWWWWWWWWWWARNOLD ST(35' WIDTH - 70' ROW) SOUTH 14TH AVESOUTH 13TH AVE
SOUTH 1
2
T
H
A
V
EEXISTINGTRAILS (TYP)SS SS SS SS SS SS SS SS
SDSDSDSDSDSDSDSDSD SD SD SD SD SD SD SD SD SD SD
SSSSSSSSSSSSSSSSSSSSSSSSSSSS(47' WIDTH - 70' ROW)UGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEWWWWWWWWWWWWWWWWWWSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSWWWWWWWWSSSSSSSSSSSSSSSDWWWWWWWWSSSSWWSD
SD
SD
SD SD
SD SD SDSDSSSSSSWWSDSDSDSD SD SDSOUTH DRIVE AISLENORTH DRIVE AISLESOUTH 13TH AVESOUTH 12TH AVEWWSDSSSSSSFUTURE SOUTH13TH AVEMAIL LOAD
INGZONEUNIT1 MULTIFAMILYBUILDING 3CLUBHOUSEUNIT 2UNIT4AUNIT3AUNIT3BUNIT4BUNIT4CUNIT6AUNIT6BUNIT9AUNIT9BUNIT10AUNIT10BUNIT11UNIT14AUNIT14BUNIT26UNIT28AUNIT28BUNIT29UNIT24AUNIT24BUNIT25AUNIT25BUNIT15BUNIT15AUNIT18UNIT19AUNIT19BUNIT20AUNIT20BUNIT20CUNIT21UNIT 30UNIT 42DUNIT 42CUNIT 42BUNIT 42AUNIT 41UNIT 40UNIT39AUNIT38BUNIT38AU
N
I
T
3
7UNIT34 UNIT 31UNIT8AUNIT8BUNIT7UNIT5MULTI-FAMILYBUILDING 2MULTIFAMILYBUILDING 1UNIT12UNIT13AUNIT13BUNIT16UNIT17AUNIT17BUNIT22UNIT23AUNIT23BUNIT32UNIT33AUNIT33BUNIT 35UNIT36AUNIT36BCOVERED PARKING (18)COVERED PARKING (16)COVERED PARKING (18)COVERED PARKINGCOVERED PARKINGCOVERED PARKINGCOVERED PARKINGCOVERED PARKING (22)COVERED PARKING (11)COVERED PARKING (6)MECH.BLDGUNIT27AUNIT27BUNIT39B>>>>C2.0WATER PLAN1 3/23/2022 COB CONCEPT SUBMITTAL ZWL CDP
2 10/17/2022 COB SITE PLAN SUBMITTAL ZWL CDP
3 5/19/2023 COB RC SITE PLAN SUBMIT ZWL CDP PROFESSIONALENGINEERS &SURVEYORSSTAHLYENGINEERING& ASSOCIATESTHE FLATS AT
BOZEMAN
CAPSTONE COLLEGIATE
COMMUNITIES LLC