2304 N. 7TH AVENUE | SUITE L | BOZEMAN, MT 59715 | (406) 587-2781
Professional Consulting Engineers and Land Surveyors
Equal Opportunity Employer | www.hyaliteeng.com
September 6, 2022
City of Bozeman- Community Development Department
PO Box 1230
Bozeman, MT 59771
Attn: Danielle Garber, Associate Planner
RE: May Fly Townhomes
Pre-Application Response
Gallatin County, Montana
Dear Danielle:
The purpose of this letter is to provide you with the additional information/responses requested in
your letter dated 06/09/2022. The following is in response to your comment letter following the
pre-application submittal for this project:
Reference #1:
Noted, pedestrian corridors will include a city standard sidewalk, trees and ground cover designed
to create an inviting & safe walkway.
Reference #2:
Noted, any lot that does not have street frontage will face the proposed pedestrian corridors. The
landscape sheet includes a proposed path for the sidewalk with connections to the front of each
lot.
Reference #3:
Noted, all utilities will run through the proposed alleys and not through the open space lots.
Reference #4:
Noted, no response necessary.
Reference #5:
Noted, no response necessary.
Reference #6:
Noted, no response necessary.
Reference #7:
Noted, no response necessary.
Reference #8:
Noted, no response necessary.
Reference #9:
Noted, no response necessary.
Reference #10:
Noted, no response necessary.
Letter to City of Bozeman Community Development
Re: May Fly Townhomes Major Subdivision
Pre-Application Response
September 6, 2022
Page 2 of 4
L:\203430\_Preliminary Plat\May Fly Townhomes\1.C PRE-APP COMMENT RESPONSE.doc
Reference #11:
Noted, no response necessary.
Reference #12:
Noted, no response necessary.
Reference #13:
Noted, no response necessary.
Reference #14:
Noted, no response necessary.
Reference #15:
Noted, street boulevard tree locations are included on the landscape sheet as required.
Reference #16:
Noted, pedestrian rights of way include a 5 ft wide sidewalk and landscaped elements.
Reference #17:
Noted, no response necessary.
Reference #18:
The water main will no longer be run through the open space lot, see the included preliminary
plans.
Reference #19:
Noted, all existing 2-inch water services will be utilized while the 4-inch fire services and 8-inch
main stub will be terminated at the main.
Reference #20:
All existing sewer mains will now be utilized in some form; therefore, no sewer main termination
will be necessary.
Reference #21:
The storm water plan is shown within the preliminary plat submittal as well as the stormwater
engineering report.
Reference #22:
Noted, a parkland tracking table is included on the landscape sheet.
Reference #23:
Noted, no IILP are proposed for this project.
Reference #24:
Noted, see the included plans for the existing utilities and drain tile.
Reference #25:
See the overall layout, there are no proposed dead-end roads (alley connections to the
surrounding roadways), thus turn arounds are not necessary.
Letter to City of Bozeman Community Development
Re: May Fly Townhomes Major Subdivision
Pre-Application Response
September 6, 2022
Page 3 of 4
L:\203430\_Preliminary Plat\May Fly Townhomes\1.C PRE-APP COMMENT RESPONSE.doc
Reference #26:
Noted, no response necessary.
Reference #27:
There are no proposed dead-end roads, thus turn arounds are not necessary. See the overall lot
layout for the alley connections to the surrounding roadways.
Reference #28:
Noted, with the new sewer alignment, no easement is necessary/
Reference #29:
Noted, the existing water main stub in May Fly will be abandoned at the main.
Reference #30:
The proposed western trail will have proper lighting, striping, and ADA ramps for the mid-block
crossing.
Reference #31:
Noted, and agreed.
Reference #32:
Noted, please see the included stormwater design documents.
Reference #33:
Noted, no response necessary.
Reference #34:
Noted, we are working with HDR & Norton Ranch for the design & construction of future NRLS
upgrades.
Reference #35:
Noted, the full TIS is included with the application.
Reference #36:
Noted, see the included documentation for the request for ‘Modification of Property Access
Standards’.
Reference #37:
Noted, no response necessary.
Reference #38:
Noted, the appropriate corrosion protection wrap will be utilized based on the soil testing that has
taken place.
Reference #39:
Noted, no response necessary.
Reference #40:
Noted, no response necessary.
Letter to City of Bozeman Community Development
Re: May Fly Townhomes Major Subdivision
Pre-Application Response
September 6, 2022
Page 4 of 4
L:\203430\_Preliminary Plat\May Fly Townhomes\1.C PRE-APP COMMENT RESPONSE.doc
Reference #41:
The lots adjacent to the open space will have sidewalks to directly access the trail.
Reference #42:
Noted, please see the included stormwater design components for the subdivision.
Reference #43:
Noted, no response necessary.
Reference #44:
Noted, the existing system will stay in place.
I hope that the enclosed information allows you to approve this submittal. If for any reason you
have questions or need any additional information during the review of this project, please call me
at 587-2781 or send an email to bmegaard@hyaliteeng.com.
Sincerely,
__________________________
Brett Megaard, P.E.
Project Engineer
Cc: File: 203430
Enclosures: As Noted