HomeMy WebLinkAbout018 Appendix Q - Storm Drainage Engineers ReportEngineering Report
Stormwater Design
Aaker Phase 1 Subdivision
Preliminary Report for Preliminary Plat Review
October 2022
Rev. March 2023
Submitted to:
City of Bozeman Engineering Department
20 East Olive
Bozeman, MT 59715
Prepared by:
Stahly Engineering and Associates
851 Bridger Drive, Suite 1
Bozeman, MT 59715
(406) 522-9526
Stormwater Plan 1 3/28/2023
Engineering Report
Table of Contents
General Information and Design Criteria
Existing Site Conditions
Storm Drainage Plan Description
Estimation of Runoff
Retention Facilities
Conveyance Capacity
Flood Conveyance
Aaker Phase 1 Subdivision Stormwater Maintenance Plan
Figures and Tables
Figure 1. Vicinity Map
Table 1 – Storm Runoff Calculations for Retention
Table 2 – Retention and Bio-Retention Basin Capacities
Table 3 – Storm Runoff Calculations for Conveyance
Table 4 – Curb and Gutter Conveyance Calculations
Table 5 – Storm Runoff Rate and Pipe Conveyance Calculations
Table 6 – Retention Pond Overflow Conveyance Calculations
Table 7 – Culvert Conveyance Calculations
Attachments/References
C5.0 Phase 1 Grading and Drainage Plan
C5.1 Phase 1 Stormwater Details
C5.2 Phase 1 Stormwater Details
Geotechnical Report
Aaker Phase 1 Subdivision Flood Hazard Evaluation
Stormwater Plan 2 3/28/2023
11.1 Engineering Report – General Information
The Aaker property consists of approximately 95 acres of vacant land located west of
South 19th Avenue, north of Stucky Road, and extending west and north to the MSU
BART Farm. Concept master planning and initial REMU and B-2M zoning of the Aaker
Property envision a mixed-use development with commercial uses along South 19th
Avenue grading to predominantly residential uses toward the north and west. The
Phase 1 Subdivision includes the extension of Kagy Boulevard and the land to the
north, comprising 31.73 acres, with a 63.68-acre restricted future development lot south
of Kagy Boulevard. Phase 1 will create 7 lots for development with REMU zoning.
Planned land use includes moderate density residential with some commercial uses
integrated into lots adjacent to Kagy Boulevard.
Water and sewer service for the subdivision will be provided by extensions from existing
City of Bozeman water and sewer mains adjacent to the site.
The developer’s contact information is:
West University, LLC
113 East Oak, Suite 4A
Bozeman, MT 59715
Water supply and wastewater treatment will be provided by the City of Bozeman’s
municipal systems. The system owner’s contact information is:
City of Bozeman Public Service Department
PO Box 1230
Bozeman, MT 59771-1230
Figure 1 shows a vicinity map of the Aaker Property and Phase 1 Subdivision.
Figure 1. Vicinity Map, Bozeman, Montana
Stormwater Plan 3 3/28/2023
Existing Site Conditions
The Aaker Phase 1 property was previously used for agriculture. The site slopes
generally to the north and contains a stream and wetland in the western portion of the
site.
A geotechnical investigation was conducted, and the report is provided separately with
the subdivision submittal. In summary, the geotechnical investigation found a variable
depth of fine-grained soils overlying gravel sediments. The depth to gravel varies
between 1 and 4 feet.
Groundwater monitoring was conducted throughout the 2022 season. Depth to
seasonal high groundwater varied from near the surface in the wetlands to about 3-4’
below ground at the proposed lots. Groundwater is generally flowing to the north.
Proposed street and lot grading will raise the developed portions of the site
approximately 2-3’ resulting in a typical depth to seasonal high groundwater in
developed areas of about 5-7’.
Storm Drainage Plan Description
The Storm Drainage Plan for the Aaker Phase 1 Subdivision consists of separate
mitigation systems for subdivision streets (public) and lots (private). The Aaker Phase 1
Subdivision stormwater collection area is divided into 5 separate drainage areas for
evaluation of retention requirements and sizing. Stormwater from drainage areas 1, 2
and 4 is conveyed in curbs and storm drainage pipes to retention basins. Stormwater
from drainage areas 3 and 5 is conveyed in curbs to bio-retention swales in the roadway
boulevards. The City is responsible for maintaining storm piping within City rights-of-
way. The Aaker Subdivision Property Owners’ Association is responsible for monitoring
and maintaining the subdivision stormwater retention and bio-retention facilities. Storm
runoff from individual lots will be mitigated on-site as determined during each lot’s site
design phase and is the responsibility of the individual lot owners to maintain.
The Overall Storm Drainage Plan for Aaker Phase 1 Subdivision is depicted on Plan
Sheet C5.0 Phase 1 Grading and Drainage Plan, attached to this report. The plan
shows proposed grading, drainage areas, stormwater piping, retention basins, and
culverts.
The subdivision stormwater retention systems are sized to contain the storm runoff from
the 10-year, 2-hour storm, in accordance with City of Bozeman Design Standards. All
lots are required to have private on-site stormwater systems to meet the City’s design
standard for stormwater mitigation.
The retention basins will contain 96% of all rainfall events and significantly reduce
discharges from larger events. The retention basins are in areas that facilitate overflow
to natural water ways to prevent property damage during large rainfall events.
Stormwater Plan 4 3/28/2023
The five (5) subdivision storm drainage areas are further divided into 8 reaches or sub-
areas with discrete catchment areas to determine peak flow rates, required pipe sizing,
and curb capacity. Storm drainage curbs, pipes and overflows are sized to convey the
peak flow from a 25-year storm in accordance with City of Bozeman Design Standards.
Stream crossings are sized to convey the 100-year flood flows without causing flooding
of adjacent property.
Estimation of Runoff
Runoff estimates were obtained for each drainage area using City of Bozeman
Standards. The drainage area for the subdivision streets shown on Plan Sheet C5.0
includes a 10’ front yard which typically is sloped toward the street. The runoff
coefficient was selected at 0.65. Runoff coefficients for a local street are 0.58 and for
the full buildout Kagy section are 0.64. Since most drainage basins have a mix of street
sections a value of 0.65 was used for all basins for simplicity. The design storm event is
a 10-year, 2-hour storm. The Bozeman IDF (Intensity, Duration, and Frequency) curves
show a rainfall intensity of 0.41 in/hour for the 10-year, 2-hour storm, totaling a 0.82-
inch storm event. The rainfall event is the 96th percentile event, meaning 96% of
rainstorms are equal to or less than this amount.
Table 1 – Storm Runoff Calculations for Retention
Table 1 shows the 10-year storm runoff calculations for the 5 drainage areas of the
subdivision stormwater collection area.
Retention Facilities
Stormwater from subdivision streets is mitigated by individual stormwater retention
systems for each drainage area as shown on Plan Sheet C5.0 Phase 1 Grading and
Drainage Plan. Stormwater mitigation for drainage areas 1, 2, and 4 is primarily by
ponding retention, with bio-retention media in the pond bottom. The bio-retention
component provides improved infiltration to shorten the duration of standing water and
allows subsurface retention of smaller storms. Drainage areas 3 and 5 utilizes bio-
retention swales in the street boulevard to retain stormwater. All bio-retention areas
consist of an engineered soil media that has consistent permeability but allows for plant
growth. Table 2 shows the storage capacities of each basin exceed the 10-year, 2-hr
storm runoff. Taking into account the improved infiltration provided by the bio-retention
Basin Characteristics 1 2 3 4 5
Mitigation Type Retention Retention Bio-Retention Retention Bio-Retention
Area (sf)159,917 17,320 44,317 222,107 99,849
Area (acre)3.67 0.40 1.02 5.10 2.29
Impervious Area (sf)103946 11258 28806 144370 64902
Pervious Area (sf)55971 6062 15511 77737 34947
Weighted (C)0.65 0.65 0.65 0.65 0.65
Runoff Volume (cf) 10-yr 2-hr storm 7103 769 1968 9865 4435
Stormwater Plan 5 3/28/2023
media, the proposed retention basins will contain storm events considerably larger than
the 10-year, 2-hour storm.
Table 2 – Retention and Bio-Retention Basin Capacities
Construction details of the retention systems are shown on Plan Sheet C5.2. Retention
basins located in City Park have 6:1 side slopes and a maximum ponding depth of 1.5
feet to be compatible with adjacent park uses. Bio-retention basins have concrete inlet
chases designed to capture sediment for easy removal before water enters the bio-
retention basin. To protect groundwater and provide reliable infiltration, retention
systems are situated to provide 3’ of separation between basin bottom and seasonal
high groundwater.
To accommodate discharge from storm events larger than the design event all retention
systems have overflow provisions sized to meet the 25-year peak flow event. The
retention basins will contain a significant amount of the runoff even from large events,
dramatically reducing the actual overflow flow rate and occurrence. To reduce impacts
to the adjacent wetland and stream the retention basins in the City Park have a broad
rip-rap overflow that allows overflows to disperse into the wetlands adjacent to the
stream. The bio-retention basins all include an overflow structure at the downgradient
side that conveys the overflow out of the street. The west bioretention overflow (Basin
3) discharges just outside of the wetlands. The east bio-retention overflow (Basin 5)
discharges directly to the stream crossing culvert beneath the roadway. Overflows are
anticipated to rarely occur, but even so all the basin overflows are situated to minimize
impacts to the adjacent wetlands and stream.
Conveyance Capacity
The peak flow from the 25-year storm event is determined for the purpose of sizing
conveyance facilities. With a time of concentration of 10.9 minutes, the 25-year storm
has an intensity of 2.32 in/hour, but due to its short duration, only represents a 0.32-inch
event.
Drainage Area 1 2 3 4 5
Retention Storage Volume
Ponding Depth (ft)1.50 1.50 N/A 1.50 N/A
Pond Bottom Area (sf)2870 304 N/A 4146 N/A
Pond Top Area (sf)5513 872 N/A 7442 N/A
Retention Storage (cf)6287 882 0 8691 0
Bio-Retention Storage Volume
Media Area 2870 304 5760 4146 7600
Media Depth 1.5 1.5 2 1.5 2
Media Volume 4305 456 11520 6219 15200
Media Porosity 0.30 0.30 0.30 0.30 0.30
Media Storage (cf)1292 137 3456 1866 4560
Total Retention Storage 7579 1019 3456 10557 4560
Stormwater Plan 6 3/28/2023
The peak flow from the 25-year storm shown in Table 3. Note that the two largest
drainage areas, 1 and 4, are broken into sub-areas to identify intermediate flow rates
from pipe branches. Conveyance facilities (curbs, pipes, and overflows) are designed
to have capacities exceeding the 25-year peak flow shown in Table 3.
Table 3 – Storm Runoff Calculations for Conveyance
Curb and gutter collects storm runoff and conveys it to the storm drainage pipe network.
The capacity of a typical City of Bozeman Standard Curb and Gutter at the minimum
slope of 0.5% is shown in Table 4 below. A typical curb and gutter has a conveyance
capacity of 3.47 cfs, and there are two curbs conveying stormwater in each drainage
area (one on each side of the street). The curb capacity of a single curb exceeds >50%
of the 25-year peak flow from any single sub-area as shown in Table 3.
Table 4 – Curb and Gutter Conveyance Calculations
Curb and Gutter Capacity Calcs
Right-side Slope X:1 0.06
Left-side Slope X:1 33.00
Channel Bottom Width (ft) 0
Flow Depth (ft) 0.300
Flow Area (ft^2) 1.488
Wetted Perimeter (ft) 10.205
Width 9.919
Hydraulic Radius (ft) 0.146
Manning's Roughness 0.013
Slope (ft/ft) 0.005
Average Velocity (ft/sec) 2.33
Flow (ft^3/sec) 3.47
Table 5 below shows the stormwater flow in each pipe reach as flow from sub-areas
combine. For drainage area 2, the entire basin is collected in a single pipe. For
drainage areas 1 and 4, the storm drainage pipe collects runoff along its length from
Inlet Subarea Basin #1 1A 1B 2 3 4 4A 4B 4C 5
Drainage Area (acres)3.67 1.20 2.47 0.40 0.93 5.10 3.08 1.11 0.90 2.3
Drainage Area (sf)159917 52195 107722 17321 40428 222107 134256 48441 39410 99850
Slope (%)1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5
Runoff Coefficients 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65
Frequency Adjustment Factor, Cf 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1
Basin Length (ft)300 300 300 300 300 300 300 300 300 300
Time of Concentration (min)10.9 10.9 10.9 10.9 10.9 10.9 10.9 10.9 10.9 10.9
Peak Flow Calculations
Design Storm 25yr 25yr 25yr 25yr 25yr 25yr 25yr 25yr 25yr 25yr
Time of Concentration (min)10.9 10.9 10.9 10.9 10.9 10.9 10.9 10.9 10.9 10.9
Intensity at Tc (Figure I-2 pg. 29) (in/hr)2.32 2.32 2.32 2.32 2.32 2.32 2.32 2.32 2.32 2.3
Peak Runoff Rate at Tc (Q = CIA) (cfs)5.55 1.81 3.74 0.60 1.40 7.70 4.66 1.68 1.37 3.46
Stormwater Plan 7 3/28/2023
contributing sub-areas shown in Table 3, requiring pipe size increases. Table 7 below
also shows the minimum pipe sizes and slopes of each reach required to carry the
storm runoff at that point in the system. For drainage areas 3 and 5, the OF designates
the flow rate and capacity of the overflow pipes for these basins. The capacity of all
pipes and overflows exceeds the flowrate generated by the 25-year storm event in each
basin or subbasin.
Table 5 – Storm Runoff Rate and Pipe Conveyance Calculations
Table 6 below shows the capacity of the overflows for retention basins 1 and 4 in the
City Park. The overflow is 10’ wide to provide a broad shallow overflow condition,
allowing water to dissipate into the wetlands. The capacity of the overflow is 12.63 cfs
which exceeds the peak flow from the 25-year storm runoff of these two drainage areas.
Table 6 – Retention Pond Overflow Conveyance Calculations
Flood Conveyance
A Flood Hazard Evaluation (FHE) was conducted for the Aaker Phase 1 Subdivision
and is included separately with the subdivision submittal. The FHE identified three
Drainage Subarea #1 1A 1B 2 3 OF 4 4A 4B 4C 5 OF
Pipe Material PVC PVC PVC PVC PVC PVC PVC PVC PVC PVC
Pipe Size (in)18.00 15.00 15.00 15.00 15.00 21.00 18.00 15.00 15.00 15.00
Manning's "n" (PVC)0.013 0.013 0.013 0.013 0.013 0.013 0.013 0.013 0.013 0.013
Area (ft2)1.77 1.23 1.23 1.23 1.23 2.41 1.77 1.23 1.23 1.23
Wetted Perimeter (ft)4.71 3.93 3.93 3.93 3.93 5.50 4.71 3.93 3.93 3.93
Hydraulic Radius (ft)0.38 0.31 0.31 0.31 0.31 0.44 0.38 0.31 0.31 0.31
Slope (ft/ft)0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033 0.0033
Full Flow Capacity (cfs)6.05 3.72 3.72 3.72 3.72 9.13 6.05 3.72 3.72 3.72
Velocity (ft/sec)3.42 3.03 3.03 3.03 3.03 3.79 3.42 3.03 3.03 3.03
Contributing Inlet Basin 1A,1B N/A N/A N/A N/A 4A,4B,4C 4A,4C N/A N/A N/A
Stormwater Flow (cfs)5.55 1.81 3.74 0.60 1.40 7.70 6.02 1.68 1.37 3.46
% Capacity 92%49%100%16%38%84%100%45%37%93%
Right-side Slope X:1 4.00
Left-side Slope X:1 4.00
Channel Bottom Width (ft)10
Flow Depth (ft)0.500
Flow Area (ft^2)6.000
Wetted Perimeter (ft)14.123
Width 14.000
Hydraulic Radius (ft)0.425
Manning's Roughness 0.040
Slope (ft/ft)0.010
Average Velocity (ft/sec)2.10
Flow (ft^3/sec)12.63
Pond Overflow Capacity Calcs
Stormwater Plan 8 3/28/2023
channels that convey floodwater through the Aaker property. The three channels are
the East Fork of Catron Creek (near South 22nd Avenue), an irrigation ditch from Middle
Creek Ditch (near South 23rd Avenue), and the West Fork of Catron Creek (west of
South 25th Avenue).
The FHE identified potential future 100-year flood flows for both the east and west forks
of Catron Creek. These flows are 22.1 cfs and 50.7 cfs, respectively. The irrigation
ditch is within the West Fork of Catron Creek drainage basin and represents a potential
flow split of the west drainage basin. The FHE shows the areas of inundation for both
the existing and proposed conditions. The areas inundated by the 100-year flood event
are within the watercourse setback and do not extend into areas proposed for
development.
The Middle Creek Ditch irrigation ditch intercepts the West Fork of Catron Creek south
of the Aaker property and could potentially divert the west drainage flood flows into the
center of the Aaker property. To reduce the flood hazard created by this ditch, the
perennial stream flows, unused irrigation water, and flood flows are proposed to be
returned to the west channel at the south side of the Aaker property. A headgate on
this return pipe is proposed to allow the existing irrigation ditch to continue to supply
downstream users while limiting overflows in a high flow event. Because the proportion
of flood flow split is unknown, the return pipe is sized to carry 100% of the west
drainage basin 100-yr flood flows.
Kagy Boulevard crosses both the east and west forks of Catron Creek. The east fork
crossing will be by an extension of the existing 30” RCAP to the south right-of-way of
Kagy. The west fork crossing is proposed to be a 6’ wide open bottom box culvert, with
a 4’ high opening. Retaining walls at the road right-of-way are proposed to minimize
impacts to existing wetlands at the Kagy crossings.
The hydraulic capacities of the flood conveyance pipes is shown in Table 7. All pipes
have capacity to transmit the 100-year flood flows.
Table 7 – Culvert Conveyance Calculations
Drainage Basin West Drainage West Drainage East Drainage
Location Kagy Crossing W. of 25th Ave.Irrigation Ditch Return Pipe Kagy Crossing E. of 22nd Ave.
Pipe Description 6'x5' Conc. Box - Cobble Bottom 27" x 44" RCAP 23" x 36" RCAP
Pipe Width (ft) (rectangular pipe)6 n/a n/a
Pipe Equalivalent Diameter (in) (arch pipe)n/a 36 30
slope (ft/ft)0.01 0.006 0.005
coefficient of roughness (n)0.05 0.013 0.013
Depth in pipe (in)29 36 30
depth in pipe (ft)2.42 3.00 2.50
pipe radiaus (ft)n/a 1.50 1.25
wetted perimeter (ft)10.83 9.42 7.85
area of flow (sf)14.5 7.07 4.91
hydraulic radius (ft)1.34 0.75 0.63
Avg. Velocity 3.61 7.31 5.91
Flowrate Pipe (cfs)52.3 51.7 29.0
Stormwater Plan 9 3/28/2023
Aaker Phase 1 Subdivision Storm Water Maintenance Plan
General Information
The Aaker Phase 1 Subdivision utilizes storm water retention basins and bio-retention
swales to mitigate storm water impacts from subdivision streets. The stormwater
retention basins are located in City parks, and the bio-retention swales are located in
City rights-of-way. Stormwater is collected and conveyed to the retention systems
through City streets and storm drainage pipes. The City is responsible for maintaining
storm piping within City rights-of-way.
The Aaker Subdivision Property Owners’ Association is responsible for monitoring and
maintaining the subdivision stormwater retention and bio-retention facilities. Stormwater
mitigation for private lots is not part of the subdivision infrastructure and is the
responsibility of the individual lot owners to maintain.
The subdivision storm water facilities are designed to operate without excessive
maintenance. However, like all infrastructure, periodic monitoring and maintenance will
prevent costly repair and replacement. This Maintenance Plan has been prepared in
accordance with City of Bozeman guidelines. Over time, recommended maintenance
guidelines may evolve. Please contact the City of Bozeman Storm Water Division if any
questions arise.
Storm Water Facilities Maintenance Schedule
1. Site Housekeeping. (Continuously as needed)
The main cause of storm water facility damage is poor site housekeeping.
Sediment tracked onto pavement can be washed into storm water bio-retention
basins and conveyance piping and damage these facilities. Trash can clog pipes
and inlet structures causing property damage.
• Keep sidewalk and pavement areas clean
• Pick up trash
• Restore damaged landscaping in order to prevent sediment runoff
2. System Monitoring. (Quarterly, except in winter)
The storm water facilities shall be inspected quarterly to quickly identify small
issues before expensive damage can occur. In addition to regular monitoring,
the best time to inspect the performance of storm water facilities is during runoff
events.
• Observe system during runoff. Look for ponding outside of retention
areas. This can indicate a clogged inlet or pipe.
• Inspect Bio-retention and Retention Basins
• Inspect Inlets, Manholes and Pipes
Stormwater Plan 10 3/28/2023
3. Bio-retention and Retention Basin Maintenance. (Quarterly)
The bio-retention and retention basins are designed to provide long-term
sustainable treatment of storm water. However, with poor housekeeping
sediment can clog these facilities and reduce infiltration capacity. Proper and
timely cleaning of incidental sediment in these basins can prevent these facilities
from being damaged. The bio-retention and retention basins are intended to be
vegetated, since the vegetation provides microbiological communities that can
treat common pollutants in storm water. Unhealthy vegetation can diminish the
performance of these basins. The landscaping of the bio-retention basins shall
follow typical landscape maintenance guidelines. The vegetation on the bottom
of the retention basin should not be regularly mowed, since mowing can cause
plant debris to build up in the basin.
• Remove sediment, trash, and debris
• Inspect for healthy vegetation
• Inspect for uniform ponding and water disappears in 3 days
4. Bio-retention and Retention Basin Maintenance. (Annually)
The vegetation should be maintained annually to reduce plant debris build-up.
The retention basin vegetation should be cut to a height of 6” in the fall with the
clippings removed from the basin.
• Remove dead plant materials from bio-retention basins.
• Cut retention basin vegetation and remove clippings.
• Clean inlet piping or chases, remove sediment if present.
5. Bio-retention and Retention Basin Maintenance. (Long-term)
If regular housekeeping and maintenance is not performed adequately, sediment
and debris can accumulate in the basin and reduce the required storage
capacity. If this occurs the basins should be excavated back down to original
plan grade.
• Hire a contractor to return basin(s) condition to initial design found on City
engineering plans.
• Dredge basin if sediment build-up is greater than 6”.
W W W W W
WWWWWWWWWWWWWWWWWWWWWWWWWWWWW
W
W
WWWWWWWWWW W
SS
SSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSS SS SS SS SSSSSSSSSSSS
SS
SS
SSSSSSSSSSSSSSSSSSUGEUGEUGEUGEUGEUGEUGEUGEUGE UGE UGE UGE UGE UGE UGE UGE UGE UGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGE UGE UGE
UGE
UGE
UGE
UGE
UGE
UGE
UGE
UGE
UGE
WWWWWWWWWWWWWWWWWGASGASGASGASGASGASSS SS SS SS SS SS SS SS SS SS
SS SS SS SS SS SS UGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGCUGCUGCUGCUGCUGCUGCUGCUGCUGCUGC UGCUGCUGCUGEUGEUGEUGEUGEUGEUGE
UGEBB B B BBB8'8'8'
1 5-13-22 PHASE 1 PRE-APP CDP ZWL
2 10/11/2022 PRELIMINARY PRICING CDP ZWL
3 10/26/2022 PRELIMINARY PLAT CDP ZWL
4 2/2/2023 PRELIM PLAT RC1 CDP ZWL
5 3/23/2023 PRELIM PLAT RC2 CDP ZWL PROFESSIONALENGINEERS &SURVEYORSSTAHLYENGINEERING& ASSOCIATESAAKER PHASE 1 SUBDIVISION
LOCATED IN THE SE 14 OFSECTION 14, T2S, R5EWEST UNIVERSITY, LLCBOZEMAN, MONTANAC5.0PH1 DRAINAGEAND GRADINGPLANNOTES:1.SUBDIVISION STORMWATER RETENTION INCLUDES PHASE 1STREETS.2.ALL LOTS TO HAVE ON-SITE RETENTION.