Loading...
HomeMy WebLinkAbout016 Appendix O - Water Engineers ReportEngineering Report Water Main Extension Aaker Phase 1 Subdivision Preliminary Report for Preliminary Plat Review October 2022 Rev. March 2023 Submitted to: City of Bozeman Engineering Department 20 East Olive Bozeman, MT 59715 Prepared by: Stahly Engineering and Associates 851 Bridger Drive, Suite 1 Bozeman, MT 59715 (406) 522-8594 Water Mains 1 3/23/2023 Engineering Report Contents Note: The Engineering Report format follows DEQ-1 organization. Additional information required by the City of Bozeman Design Standards is added where required. Report Narrative 1.1.1 General Information 1.1.2 Extent of Water Works System 1.1.3 Alternate Plans 1.1.4 Site Conditions 1.1.5 Water Use Data 1.1.6 Flow Requirements 1.1.7 Sources of Water Supply 1.1.8 Proposed Treatment Processes 1.1.9 Sewage System Available 1.1.10 Waste Disposal 1.1.11 Automation 1.1.12 Project Sites 1.1.13 Financing 1.1.14 Future Extensions Figures and Tables Figure 1. Vicinity Map Table 1. Aaker Phase 1 Subdivision Estimated Water Use Attachments and Appendices C 2.0. Water Plan Water Mains 2 3/23/2023 1.1.1 Engineering Report – General Information The Aaker property consists of approximately 95 acres of vacant land located west of South 19th Avenue, north of Stucky Road, and extending west and north to the MSU BART Farm. Concept master planning and initial REMU and B-2M zoning of the Aaker property envision a mixed-use development with commercial uses along South 19th Avenue grading to predominantly residential uses toward the north and west. The Phase 1 Subdivision includes the extension of Kagy Boulevard and the land to the north, comprising 31.73 acres, with a 63.68-acre restricted future development lot south of Kagy Boulevard. Phase 1 will create 7 lots for development with REMU zoning. Planned land use includes moderate density residential with some commercial uses integrated into lots adjacent to Kagy Boulevard. Water and sewer service for the subdivision will be provided by extensions from existing City of Bozeman water and sewer mains adjacent to the site. The developer’s contact information is: West University, LLC 113 East Oak, Suite 4A Bozeman, MT 59715 Water supply and wastewater treatment will be provided by the City of Bozeman’s Municipal Systems. The system owner’s contact information is: City of Bozeman Public Service Department PO Box 1230 Bozeman, MT 59771-1230 Figure 1 shows a vicinity map of the Aaker Property and Phase 1 Subdivision. Figure 1. Vicinity Map, Bozeman, Montana Water Mains 3 3/23/2023 1.1.1 Extent of Water Works System This area of town is supplied primarily by an existing 24” water main in South 19th Avenue. Smaller 8” water mains in Kagy Boulevard and Remington Way currently run from South 19th Avenue to the Aaker property. New 8” water mains will be extended in proposed subdivision streets within the Aaker Phase 1 Subdivision. This subdivision will provide approximately 4500 linear feet of 8” water main connecting to existing mains in two locations. In addition, nine (9) new fire hydrants are proposed with the development. Proposed water mains will be extended to the exterior subdivision boundary and planned street alignments, to allow for future extensions and connections to planned future large diameter trunk lines in Stucky Road, Lincoln Street, and South 27th Avenue. The proposed water system improvements are shown on the C2.0 Ph. 1 Water Plan, attached at the end of this report. Due to the large lot size, it is anticipated that future lot development will require on-site main extensions to serve future development. Water main stubs are provided to the lot lines where on-site main extensions are envisioned. Proposed Phase 1 and future phase public parks will be irrigated by wells. The planned total park irrigation is estimated to be approximately 8.68 acre-feet per year, within the 10 acre-feet exemption. Private lots and street boulevard landscaping will be irrigated with City water. Kagy Boulevard and the east side of South 23rd Avenue will be landscaped with the subdivision improvements and are proposed to be irrigated by two dedicated water service/meter pits for the street landscaping. The Aaker Phase 1 Subdivision water main extensions will be designed in accordance with Montana Department of Environmental Quality Circular 1, and the City of Bozeman Design Standards and Specifications Policy. Construction specifications will be Montana Public Works Standards and Specifications (MPWSS), and the City of Bozeman Modifications to MPWSS. 1.1.2 Alternate Plans Due to the project’s location within the City of Bozeman, extension of public mains was the only water supply alternative. Distribution alternatives were explored, and the proposed design was selected to facilitate future extensions and connectivity. Water Mains 4 3/23/2023 1.1.4. Site Conditions The Aaker Phase 1 property was previously used for agriculture. The site slopes generally to the north and contains a stream and wetland in the western portion of the site. A geotechnical investigation was conducted, and the report is provided separately with the subdivision submittal. In summary, the geotechnical investigation found a variable depth of fine-grained soils overlying gravel sediments. The depth to gravel varies between 1 and 4 feet. Groundwater monitoring was conducted throughout the 2022 season. Depth to seasonal high groundwater varied from near the surface in the wetlands to about 3-4’ below ground at the proposed lots. Groundwater is generally flowing to the north. Proposed street and lot grading will raise the developed portions of the site approximately 2-3’ resulting in a typical depth to seasonal high groundwater in developed areas of about 5-7’. Groundwater dewatering may be required during water main installation, depending on groundwater depth at the time of installation. 1.1.5. Water Use Data Domestic and lot irrigation water will be provided by the City of Bozeman Municipal System. This project is located within the planned service area of the City’s System. At the time of subdivision, the ultimate domestic and irrigation water use of the lots are unknown. For the purposes of preliminary design and water main sizing, the water use for the Aaker Phase 1 Subdivision has been estimated in Table 1. Estimated domestic water use for each lot is based on planned use and density, utilizing standard City of Bozeman design values. Because the proposed development is multifamily or mixed use, the domestic water use and irrigation use are calculated separately. The domestic water use is assumed to be the same as the wastewater generation at 89 gpd per capita. Irrigation is estimated based on 25% of the lot and street area being irrigated, at typical irrigation rates of about 1” per week. Public Park irrigation will be provided by exempt well(s) and is within the 10 acre- feet limit of this exemption. Kagy Boulevard street landscaping to be completed with the subdivision improvements will be irrigated with City water. Cash-in-lieu of water rights for Kagy Boulevard and east side of South 23rd street landscaping Water Mains 5 3/23/2023 have been estimated on the landscape plans included with this submittal to be 5.8 acre-feet. Payment for these water rights will be made at Final Plat. Payment of cash-in-lieu of water rights for the individual lots will be made at the time of lot development as determined during each lot’s site plan review. Table 1. Aaker Phase 1 Subdivision Estimated Water Use 1.1.6. Flow Requirements As stated above, the peak hour water demand is estimated to be 313 gpm. The subdivision water mains will also provide fire protection water supplies (fire flow). Final fire flow requirements for each building are unknown at this time, but the 2017 City of Bozeman Water Facility Plan did not identify any fire flow capacity limitations in this area. This peak hour water use and anticipated fire flow is within the typical capacity of a network of looped 8” water mains. Further analysis and modelling will be conducted in final infrastructure design to confirm the availability of fire flows with the proposed design. Aaker Ph. 1 Subdvision Estimated Water Use Residential Commercial Units Capita/Unit Population GPD/Capita Residential Sewer Use (gpd) Commercial Space (sf) GPD/1000 SF Commercial Space Commercial Sewer Use (gpd) Block 1 Lot 1 0 2.11 0 89 - 20,000 100 2,000 Block 2 Lot 1 125 2.11 264 89 23,474 Lot 2 125 2.11 264 89 23,474 Block 3 Lot 1 52 2.11 110 89 9,765 Lot 2 52 2.11 110 89 9,765 Lot 3 68 2.11 143 89 12,770 10,000 100 1,000 Lot 4 68 2.11 143 89 12,770 10,000 100 1,000 Total Units 490 40000 Total Population 1034 Residential Subtotal 92,017 Commercial Subtotal 4,000 Site Area - Lots and ROW (ac)22.89 Average Day Water Use [Equal to Domestic Sewer Use](gpd) 96,017 Irrigated Area = Site Area (ac) * 0.25 5.72 Irrigation (gal/ac/day)4,000 Irrigation (gpd)22,890 Max Day Water Use [Average Day Use + Irrigation] (gpd)118,907 ;P = Pop. ÷ 1,000 Peaking Factor (PF)3.79 Design Water Peak Hour Flow 313 Water Mains 6 3/23/2023 1.1.7. Sources of Water Supply This section is not applicable. 1.1.8. Proposed Treatment Process This section is not applicable. 1.1.9 Sewage System Available Sewer service is provided by new City sewer mains extended through the site from existing sewer mains in Kagy Boulevard and Lincoln Street Sewers will be approximately 9-10 feet deep and primarily cross below water mains and services. 1.1.10 Waste Disposal This section is not applicable. 1.1.11 Automation This section is not applicable. 1.1.12 Project Sites This section is not applicable. 1.1.13 Financing This section is not applicable. 1.1.14 Future Extensions Proposed water mains will be extended to the exterior subdivision boundary and planned street alignments, to allow for future extensions and connections to planned future large diameter trunk lines in Stucky Road, Lincoln Street, and South 27th Avenue. W W W W W WWWWWWWWWWWWWWWWWWWWWWWWWWWWW W W WWWWWWWWWWW SS SSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSS SS SS SS SSSSSSSSSSSS SS SS SSSSSSSSSSSSSSSSSSUGEUGEUGEUGEUGEUGEUGEUGEUGE UGE UGE UGE UGE UGE UGE UGE UGE UGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGESS SS SS SS SS SS SS SS SS SS SS SSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSS SS SS SS SS SS UGE UGE UGE W W W W UGE UGE UGE UGE UGE UGE UGE UGE UGE W SS SS SS SS SS SS SS SS SS SS SSSSSSSSSSSSSSSSSSSSSSWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWW W W W W W W W W W W W W SSSSSSWWWWWWWWWWWWWWWWWGASGASGASGASGASGASSS SS SS SS SS SS SS SS SS SS SS SS SS SS SS SS UGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGEUGCUGCUGCUGCUGCUGCUGCUGCUGCUGCUGCUGC UGCUGCUGCUGEUGEUGEUGEUGEUGEUGE UGEBB BBBBBW8'8'8' 1 5-13-22 PHASE 1 PRE-APP CDP ZWL 2 10/11/2022 PRELIMINARY PRICING CDP ZWL 3 10/26/2022 PRELIMINARY PLAT CDP ZWL 4 2/2/2023 PRELIM PLAT RC1 CDP ZWL 5 3/23/2023 PRELIM PLAT RC2 CDP ZWL PROFESSIONALENGINEERS &SURVEYORSSTAHLYENGINEERING& ASSOCIATESAAKER PHASE 1 SUBDIVISION LOCATED IN THE SE 14 OFSECTION 14, T2S, R5EWEST UNIVERSITY, LLCBOZEMAN, MONTANAC2.0PHASE 1WATER PLAN