HomeMy WebLinkAbout022-construction management plan PKG
190 NORTHSTAR LANE
BOZEMAN, MT 59718
406-581-5730
www.headwatersmt.net
Page 1 of 3
February 17, 2023
Urban Villas – Construction Management Plan
The applicant plans to construct the buildings in four phases as shown on the PH-1 sheet. Phase 1 will contain the
majority of the site work; site grading, parking lot construction, storm pond construction, as well as construction of
Buildings #1 and the landscaping associated with building 1 and the retention pond. Phases 2,3 and 4 will mostly
include the construction of buildings and adjacent sidewalks & landscaping. During each step of the construction, the
garbage and materials will be managed. Below is a description of the Construction Management Plan broken down into
the four phases.
PHASE 1
1. Site grading
During site grading, the excess materials (topsoil & fill) will be hauled offsite and disposed of. Garbage will be
minimal in this portion of the construction and will be hauled offsite daily by the contractor. Minimal topsoil
will be stockpiled onsite in the future building 4 site and placed immediately following parking lot and building
completion.
2. Infrastructure Installation
During the installation of the underground water and sewer services, as well as during the installation of the
underground power and phone, the minimal garbage will be hauled offsite daily. The pipe and wire will be
stored at an offsite yard until the time of installation when it will be hauled to the site and stored until it is
installed. Staging areas are shown on the attached construction management exhibit.
3. Parking Lot & Building Pad Construction
The excess fill materials will be hauled offsite during the site grading phase of construction so minimal material
is anticipated to leave the site during the parking lot construction. The gravels and asphalt will be trucked in on
an as-needed basis. Any waste asphalt will be trucked back to the pit after paving has been completed by the
paving contractor. Concrete trucks will be washed out into a washout pit.
4. Building Construction
During the construction of building 1, a 20-30 cubic yard dumpster will be onsite as shown on the attached
exhibit to manage the waste generated by the building construction. A portable toilet will be onsite during all
phases of construction. The building materials will be stored in the staging area during construction.
5. General Management
During this phase of construction, the access will utilize a construction entrance with a cobble runout pad until
the parking lot is paved. As shown on the phasing plan, all parking lots will be paved in Phase 1 to allow for an
all-weather staging/construction area.
The existing hydrant in the center of the project will be utilized for any firefighting needs. Other hydrants are
nearby along Catalyst Street and 27th Avenue. The construction access shall remain open to allow access for
the EMS services.
PHASE 2
1. Site grading
No site grading is planned in Phase 2.
2. Infrastructure Installation
No infrastructure installation will occur in Phase 2.
190 Northstar Lane, Bozeman, MT 59718 (406) 581-5730 www.headwatersmt.net Page 2 of 3
3. Building Pad Construction
The excess fill materials will be hauled offsite during the site grading phase of construction, so minimal
material is anticipated to leave the site during the building pad construction. The gravel will be trucked in on
an as-needed basis.
4. Building Construction
During the construction of building 2, a 20-30 cubic yard dumpster will be onsite as shown on the attached
exhibit to manage the waste generated by construction of the building. A portable toilet will be onsite during
all phases of construction. The building materials will be stored in the staging area during construction.
5. General Management
The construction dumpster and the sanitary facilities will be located away from any occupied buildings in an
attempt to minimize disturbance. A construction fence will be installed to maintain separation of the
construction from existing tenants while allowing existing residents access and adequate parking.
The existing hydrant in the center of the project will be utilized for any firefighting needs. Other hydrants are
nearby along Catalyst Street and 27th Avenue. The construction access shall remain open to allow access for
the EMS services.
PHASE 3
1. Site grading
No site grading is planned in Phase 3.
2. Infrastructure Installation
No infrastructure installation will occur in Phase 3.
3. Building Pad Construction
The excess fill materials will be hauled offsite during the site grading phase of construction, so minimal
material is anticipated to leave the site during the building pad construction. The gravel will be trucked in on
an as-needed basis.
4. Building Construction
During the construction of building 3, a 20-30 cubic yard dumpster will be onsite as shown on the attached
exhibit to manage the waste generated by the building construction. A portable toilet will be onsite during all
phases of construction. The building materials will be stored in the staging area during construction.
5. General Management
The construction dumpster and the sanitary facilities will be located away from any occupied buildings in an
attempt to minimize disturbance. A construction fence will be installed to maintain separation of the
construction from existing tenants while allowing existing residents access and adequate parking.
The existing hydrant in the center of the project will be utilized for any firefighting needs. Other hydrants are
nearby along Catalyst Street and 27th Avenue. The construction access shall remain open to allow access for
the EMS services.
PHASE 4
1. Site grading
No site grading is planned in Phase 4.
190 Northstar Lane, Bozeman, MT 59718 (406) 581-5730 www.headwatersmt.net Page 3 of 3
2. Infrastructure Installation
No infrastructure installation will occur in Phase 3.
3. Building Pad Construction
The excess fill materials will be hauled offsite during the site grading phase of construction, so minimal
material is anticipated to leave the site during the building pad construction. The gravel will be trucked in on
an as-needed basis. Any remaining topsoil will be hauled offsite once the building foundation is backfilled and
graded.
4. Building Construction
During the construction of building 4, a 20-30 cubic yard dumpster will be onsite as shown on the attached
exhibit to manage the waste generated by the building construction. A portable toilet will be onsite during all
phases of construction. The building materials will be stored in the staging area during construction.
5. General Management
The construction dumpster and the sanitary facilities will be located away from any occupied buildings in an
attempt to minimize disturbance. A construction fence will be installed to maintain separation of the
construction from existing tenants while allowing existing residents access and adequate parking.
The existing hydrant in the center of the project will be utilized for any firefighting needs. Other hydrants are
nearby along Catalyst Street and 27th Avenue. The construction access shall remain open to allow access for
the EMS services.
H:\1086\019\DOCS\SITEPLAN\construction management plan.doc
4 W
WSWSWSWSSSSSSSSSSSSS
SS SS
WS
WSWSWSWS4 W4 WWSWSWSWSUUUUUUUU U U
U U 4 W4 WGGGGGGGGGGGGGGGGG G GTTTTTTTT
TTTTTTTTT T TEEEEEEEE
EEEEEEEEE E E
T T T T T T T T
E
T24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS8 SS
SSSS
SS
SSSSSSSSSSSSSS SSSS SSSS SS SS
SSSSSSSS
SS
SS SSSSSSSSSS
SS
SS
SS SS
SS SSSSSSSSSS 12 W12 W12 W12 W12 W12 W12 W12 W12 W12 W8 W8 W8 W8 W8 W8 W8 W 8 W 8 W 8 W 8 W 8 W 8 W 8 W
8 W8 WWS WS WS WSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWS 12 SDN
GRAPHIC SCALE
1 inch = ft.
0
( IN FEET )
25
50
50
DRAWN BY:
DATE:
Plot Date: 2/15/2023 5:01 PM
H:\1086\019\ACAD\SHEETS\CONSTRUCTION MANAGEMENT.dwg
REVISION DATE:
190 NORTHSTAR LANE, BOZEMAN, MT 59718
HEADWATERSMT.NET 406-581-5730
PROJECT #:
LOCATION:
URBAN VILLAS
CONST. MANAGEMENT
PHASE 1
JRM
02/2023
1086.019
BOZEMAN
NOTES:
SPOIL PILES TO BE REMOVED FOLLOWING PHASE 1 PARKING LOT
CONSTRUCTION.
TOPSOIL PILE WILL ONLY CONTAIN TOPSOIL NEEDED FOR FINAL
LANDSCAPING OF BUILDINGS.
PHASE 1
CONSTRUCTION FENCE
CONSTRUCTION FENCE FOR
BUILDING WORK
TOPSOIL
PILE
PHASE 1
STAGING
AREA
TOILET
ROLLOFF DUMPSTER
UTILIZE FOR
CONSTRUCTION
ACCESS
ACTIVE HYDRANT
4 W
WSWSWSWSSSSSSSSSSSSS
SS SS
WS
WSWSWSWS4 W4 WWSWSWSWSUUUUUUUU U U
U U 4 W4 WGGGGGGGGGGGGGGGGG G GTTTTTTTT
TTTTTTTTT T TEEEEEEEE
EEEEEEEEE E E
T T T T T T T T
E
T24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS8 SS
SSSS
SS
SS
SSSSSSSSSSSS
SS
SSSS
SS SS SS
SSSSSSSS
SS
SS SS
SS
SS SS SS
SS
SS
SS SS
SS SSSSSSSSSS 12 W12 W12 W12 W12 W12 W12 W12 W12 W12 W8 W8 W8 W8 W8 W8 W8 W 8 W 8 W 8 W 8 W 8 W 8 W 8 W
8 W8 WWS WS WS WSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWS 12 SDN
GRAPHIC SCALE
1 inch = ft.
0
( IN FEET )
25
50
50
DRAWN BY:
DATE:
Plot Date: 2/15/2023 5:10 PM
H:\1086\019\ACAD\SHEETS\CONSTRUCTION MANAGEMENT.dwg
REVISION DATE:
190 NORTHSTAR LANE, BOZEMAN, MT 59718
HEADWATERSMT.NET 406-581-5730
PROJECT #:
LOCATION:
URBAN VILLAS
CONST. MANAGEMENT
PHASE 2
JRM
02/2023
1086.019
BOZEMAN
NOTES:
TOPSOIL PILE WILL ONLY CONTAIN TOPSOIL NEEDED FOR FINAL
LANDSCAPING OF REMAINING BUILDINGS.
PHASE 2
CONSTRUCTION FENCE
TOPSOIL
PILE
PHASE 2
STAGING
AREA
TOILET
ROLLOFF DUMPSTER
UTILIZE FOR
CONSTRUCTION
ACCESS
ACTIVE HYDRANT
PHASE 2
4 W
WSWSWSWSSSSSSSSSSSSS
SS SS
WS
WSWSWSWS4 W4 WWSWSWSWSUUUUUUUU U U
U U 4 W4 WGGGGGGGGGGGGGGGGG G GTTTTTTTT
TTTTTTTTT T TEEEEEEEE
EEEEEEEEE E E
T T T T T T T T
E
T24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS8 SS
SSSS
SS
SS
SSSSSSSSSSSS
SS
SSSS
SS SS SS
SSSSSSSS
SS
SS SS
SS
SS SS SS
SS
SS
SS SS
SS SSSSSSSSSS 12 W12 W12 W12 W12 W12 W12 W12 W12 W12 W8 W8 W8 W8 W8 W8 W8 W 8 W 8 W 8 W 8 W 8 W 8 W 8 W
8 W8 WWS WS WS WSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWS 12 SDN
GRAPHIC SCALE
1 inch = ft.
0
( IN FEET )
25
50
50
DRAWN BY:
DATE:
Plot Date: 2/15/2023 5:12 PM
H:\1086\019\ACAD\SHEETS\CONSTRUCTION MANAGEMENT.dwg
REVISION DATE:
190 NORTHSTAR LANE, BOZEMAN, MT 59718
HEADWATERSMT.NET 406-581-5730
PROJECT #:
LOCATION:
URBAN VILLAS
CONST. MANAGEMENT
PHASE 3
JRM
02/2023
1086.019
BOZEMAN
NOTES:
TOPSOIL PILE WILL ONLY CONTAIN TOPSOIL NEEDED FOR FINAL
LANDSCAPING OF REMAINING BUILDINGS.
CONSTRUCTION FENCE
TOPSOIL
PILE
PHASE 3
STAGING
AREA
TOILET ROLLOFF DUMPSTER
UTILIZE FOR
CONSTRUCTION
ACCESS
ACTIVE HYDRANT
PHASE 3
4 W
WSWSWSWSSSSSSSSSSSSS
SS SS
WS
WSWSWSWS4 W4 WWSWSWSWSUUUUUUUU U U
U U 4 W4 WGGGGGGGGGGGGGGGGG G GTTTTTTTT
TTTTTTTTT T TEEEEEEEE
EEEEEEEEE E E
T T T T T T T T
E
T24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS24 SS8 SS
SSSS
SS
SS
SSSSSSSSSSSS
SS
SSSS
SS SS SS
SSSSSSSS
SS
SS SS
SS
SS SS SS
SS
SS
SS SS
SS SSSSSSSSSS 12 W12 W12 W12 W12 W12 W12 W12 W12 W12 W8 W8 W8 W8 W8 W8 W8 W 8 W 8 W 8 W 8 W 8 W 8 W 8 W
8 W8 WWS WS WS WSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWSWS 12 SDN
GRAPHIC SCALE
1 inch = ft.
0
( IN FEET )
25
50
50
DRAWN BY:
DATE:
Plot Date: 2/15/2023 5:13 PM
H:\1086\019\ACAD\SHEETS\CONSTRUCTION MANAGEMENT.dwg
REVISION DATE:
190 NORTHSTAR LANE, BOZEMAN, MT 59718
HEADWATERSMT.NET 406-581-5730
PROJECT #:
LOCATION:
URBAN VILLAS
CONST. MANAGEMENT
PHASE 4
JRM
02/2023
1086.019
BOZEMAN
NOTES:
TOPSOIL PILE WILL BE GONE AS SOON AS BUILDING IS
BACKFILLED AND GRADED.
CONSTRUCTION FENCE
PHASE 4
STAGING
AREA
TOILET
ROLLOFF DUMPSTER
UTILIZE FOR
CONSTRUCTION
ACCESS
ACTIVE HYDRANT
PHASE 4