HomeMy WebLinkAbout22192 Approval
HISTORIC NEIGHBORHOOD CERTIFICATE OF
APPROPRIATENESS DECISION
APPLICATION
Date: July 27, 2022
File Number: 22192
Address: 119 S. 7th Avenue Townhomes
Alterations:
This is a Neighborhood Certificate of Appropriateness (NCOA) application to construct a two-unit
townhouse with an accessory structure that has a garage on the first floor and accessory living
space on the second floor on a vacant lot. The property is located in the Cooper Park Historic
District within the Neighborhood Conservation Overlay District (NCOD) and zoned R-2.
Public
Notice: The public notice period took place from June 17-July 1. No public comment was received.
FINDINGS
Project meets City of Bozeman Design Guidelines for Historic Preservation and the Neighborhood
Conservation Overlay and Section 38.340.050 Bozeman Municipal Code.
Project meets City of Bozeman Design Guidelines for Historic Preservation and the Neighborhood
Conservation Overlay and Section 38.340.050 Bozeman Municipal Code with conditions, see
below.
Project meets City of Bozeman Design Guidelines for Historic Preservation and the Neighborhood
Conservation Overlay and Section 38.340.050 Bozeman Municipal Code, see attachment.
PLANNER SIGNATURE
Sarah Rosenberg, AICP, Associate Planner
DIRECTOR SIGNATURE
Brian Krueger, Development Review Manager
CODE PROVISIONS
Per Section 38.100.080 & 38.200.110, the proposed project shall be completed as approved and conditioned in
the Certificate of Appropriateness application. Any modifications to the submitted and approved application
materials shall invalidate the project's legitimacy, unless the applicant submits the proposed modifications for
review and approval by the Department of Community Development prior to undertaking said modifications. The
only exception to this law is repair
Per Section 38.200.100.A.3, the applicant shall obtain a building permit within one year of Certificate of
Appropriateness approval, or said approval shall become null and void. Please call the Building Division at 406-
582-2375 for more information on the building permit process.
APPEALS
You have the right to appeal this decision of the Community Development Director pursuant to the provisions of
Article 38.250 of the Bozeman Municipal Code.
Please note that this decision is also subject to appeal by other aggrieved parties as defined by Sec. 38.700.020 of
the Bozeman Municipal Code. Such appeals must be filed pursuant to the provisions of Sec. 38.250.030 of the
Bozeman Municipal Code. An appeal must be filed within 10 working days following the date of this decision. If a
valid appeal is filed, no further action on the project may proceed until a decision on the appeal is made by the City
Commission, and the Community Development Department and Building Division will not be able to approve any
building permits or to perform any inspections related to this COA.
IMPACT FEES
Future building permit applications may require payment of the required transportation, water, sewer and fire
impact fees according to the City of Bozeman adopted impact fee schedule in place at the time of building permit
issuance. If you desire an estimate of the required impact fees (according to current rates) please contact the
Department of Community Development.
CONTACT US
Alfred M. Stiff Professional Building
20 East Olive Street 59715 (FED EX and UPS Only)
PO Box 1230
Bozeman, MT 59771
phone 406-582-2260
fax 406-582-2263
planning@bozeman.net
www.bozeman.net
DISPLAY THE FRONT OF THIS DOCUMENT IN A
PROMINENT LOCATION FACING THE STREET
DURING CONSTRUCTION
NO WORK MAY COMMENCE PRIOR TO BUILDING
PERMIT ISSUANCE