HomeMy WebLinkAbout004 1825 Kagy CCON Request
MONTANA | WASHINGTON | IDAHO | NORTH DAKOTA | PENNSYLVANIA
406.586.0277
tdhengineering.com
234 East Babcock Street
Suite 3
Bozeman, MT 59715
December 13, 2022
City of Bozeman
Attn: Suzy Ryan
Engineering Department
20 E. Olive Street
Bozeman, MT 59715
RE: CONCURRENT CONSTRUCTION REQUEST FOR
1825 KAGY STUDENT HOUSING SITE PLAN
(CONR APP. #22313)
TD&H ENGINEERING JOB NO. B22-025
Dear Suzy,
The purpose of this letter is to formally request concurrent construction for the 1825 Kagy
Student Housing site plan to allow for the construction of buildings to begin prior to the
associated public infrastructure improvements being installed and accepted by the City.
This request is being made pursuant to BMC 38.270.030 – Completion of Improvements.
Specifically, we request that concurrent infrastructure and development construction be
allowed to proceed under the provisions of subsections C.1.b and C.1.c for a single site
plan development.
The proposed public infrastructure improvements associated with this project include:
• Replacement and re-routing of a portion of existing 6” water main with a new 8”
water main that will be north of the new building footprint.
• Relocation of existing Fire Hydrant #1051 approximately 6-feet to the south to be
outside of the new fire lane alignment.
• Relocation of existing Fire Hydrant #495 approximately 21-feet to the west to be
outside of the new fire lane alignment.
• Relocation of existing Sanitary Sewer Manhole #H0701 approximately 25-feet north
along the sewer main line to be outside of the new building footprint and accessible
from the new fire lane access aisle.
The proposed utility relocations will be designed and constructed to City standards and will
be wholly located within publicly dedicated right-of-way or public utility easements. New
domestic water & sewer service lines for this project will be connected to the existing water
& sewer mains existing on the property to serve the proposed development.
Public water mains are already looped within streets and easements around the site. Fire
protection services during building construction can be provided by existing fire hydrant #’s
December 13, 2022 PAGE NO. 2
tdhengineering.com
495, 1051, 1110, 2065, and 3198 with only one fire hydrant being taken out of service at a
time during the water main relocation activities associated with this project. The site can be
readily accessed via S. 19th Avenue, W. Kagy Boulevard, and the privately maintained fire
access drives on the north and east neighboring properties (please see the attached
project map).
Should the DRC initially approve concurrent construction as a purpose of this project, we
will begin compiling the application set materials (Items 1-4) identified on the attached
CCON Form for submittal.
Thank you for considering this request for concurrent construction for this project. Please
let me know if you require any additional information.
Sincerely,
Cody Croskey PE
Civil Engineer
TD&H ENGINEERING
J:\2022\B22-025 1825 Kagy Development\DOCUMENTS\Concurrent Construction\1825 Kagy CCON Request_12.13.22.doc
Miles
0.0 1,128
This product is for informational purposes and may not have been prepared for, or be suitable for legal,engineering, or surveying purposes. Users of this information should review or consult the primary data and
information sources to ascertain the usability of the information. Feet
1310
Legend
66
Location
131
12/13/2022
Created By:
Created For:
Date:
1825 Kagy Student Housing CCON
Manholes
Abandoned Mains
Force Mains
Gravity Mains
Fire Hydrants
Mains
Active
Abandoned
Street Names
City LimitsManhole to be relocated
~25' North
Hydrant to be relocated
~6' South
6" water main to be re-routed and upsized to 8"
Hydrant to be relocated
~21' West
Project Site
CONCURRENT CONSTRUCTION FOR
EXISTING INFRASTRUCTURE OR ON-SITE
CONCURRENT CONSTRUCTION PROCEDURE (BMC 38.270.030.C)
Whenever any building lots or building sites are created inside the city limits, public infrastructure such as: municipal
water distribution systems, municipal sanitary sewer collection systems, streets, and stormwater collection, treatment,
and detention or retention systems must be provided to the lot or site. If a development is proposed on a site with existing
infrastructure and requires public infrastructure extensions or upgrades on site or directly adjacent to the site an applicant
may request to construct the public infrastructure and the building at the same time. This is called concurrent construction.
Concurrent construction requires additional review and approval prior to building permit issuance and must be requested at
the time of the initial planning entitlement such as a site plan or master site plan application. For off-site infrastructure and
subdivision projects follow form CCOFF requirements and process.
CONCURRENT CONSTRUCTION REQUIREMENTS
CCON
Water mains, sewer mains, stormwater system, and streets must meet all of the following requirements:
1. Any required on-site or directly adjacent extensions of water mains, sewer mains, stormwater system, or streets to be
dedicated to the public:
• Must be located entirely within publicly held easements or rights-of-way
• Must serve only a single lot
• Are the subject of an irrevocable offer of dedication to the city upon completion of the project
• The development is under the control of a single developer who must retain control of the entire project until final
completion
• All work is under the supervision of a single general contractor
• No subdivision of land is involved
2. The DRC must determine when the standards of this subsection BMC 38.270.030.C.1 are met
• The fire department must consider whether adequate fire protection services are available from existing hydrants,
and water supply exists to meet needs during construction
3. Approval of the final engineering design, including location and grade, for the infrastructure project must be obtained from
the engineering department, and the Montana Department of Environmental Quality when applicable, prior to issuance of
any building permit for the development
4. A certificate of occupancy must not be issued until all on-site and off-site water, sewer, stormwater, and street
improvements necessary to serve the site are installed and accepted or approved as applicable by the city.
Concurrent Construction Existing or On-Site Page 1 of 2 Revision Date: November 2021
APPLICATION SET
1. Infrastructure Review (City and DEQ)
2. Written approval from Fire Marshall
3. Irrevocable Offer of Dedication (IOOD)
4. Concurrent Construction Plan
Application set must be submitted following Development Review Committee initial approval of concurrent construction:
FORMAL ACKNOWLEDGMENT
By requesting Concurrent Construction (CCON), the applicant is responsible for understanding and adhering to the Bozeman
Municipal Code (BMC Sec. 38.270.030.C) throughout the project development. The applicant understands and accepts the
risk in application approval delays if the Concurrent Construction application does not satisfy all requirements of the BMC.
The applicant acknowledges that by submitting Concurrent Construction he/she agrees:
• Improvements will be designed, constructed, and installed according to the standards and criteria as adopted by the city
• Building permits will not be issued until all improvements are approved by the review authority
Concurrent Construction Existing or On-Site Page 2 of 2 Revision Date: November 2021
This application must be signed by both the applicant(s) and the property owner(s) (if different) before the submittal will be
accepted.
Applicant Signature: Date:
Applicant Printed Name: Date:
Owner Signature: Date:
Owner Printed Name: Date:
SIGNATURES
CONTACT US
Alfred M. Stiff Professional Building
20 East Olive Street
PO Box 1230
Bozeman, MT 59715
phone 406-582-2260
fax 406-582-2263
planning@bozeman.net
www.bozeman.net/planning
C ONCURRENT CONSTRUCTION
EXISTING INFRASTRUCTURE OR ON-SITE
IMPROVEMENTS CHECKLIST
REQUIRED FORMS
CCON, SP
Check each box once each document is reviewed and approved. Concurrent construction cannot be approved until all documents have been completed and approved.
For Official Use Only
Infrastructure Review
Fire
Irrevocable Offer of Dedication
Concurrent Construction Request
Signature:
Print Name:
Approval Denial
Date:
Concurrent Construction Plan