HomeMy WebLinkAbout1-4 GG Departure - rename1
Solara Saad
From:Nakeisha Lyon <nlyon@BOZEMAN.NET>
Sent:Friday, January 20, 2023 11:02 AM
To:Chris Urner; Ross Knapper; Ben Abbey
Cc:Solara Saad; Suzanne Ryan
Subject:RE: T & 27th Building design Review Before Resubmission
Attachments:ATT00001.txt; ATT00002.htm
Hi Chris,
The concurrent review with building permit is likely as long as the resubmittal receives adequacy this round.
I would wait until adequacy is determined before you submit the concurrent review applicant to Ross for approval and
any building permits.
Updates on other outstanding questions from our meeting last week Friday, January 13, 2023:
· Garage dimensions – the garages that have the utility room encroachment would have to be for only one car as
the dimensions for the two car garage must be met. I can still accommodate the internal columns protrusion as
this still meets the minimum 22’ x 20’ required.
· The gear garage
o the redesign is very authentically appeasing and I do believe that the façade transparency departure can
be met with the alternative design, so in the resubmittal, please include a narrative for the departure
and denote who the criteria is met which is - Façade transparency. The proposed alternative design
treatment of façade area between ground level windows provides visual interest to the pedestrian
and mitigates impacts of any blank wall areas. No less than 40 percent of the façade between 30
inches and ten feet above the sidewalk may be approved with a departure;
o From the articulation perspective, this appears to be met with the use of a faux entry, use of weather
protection features and other elements in the design that reinforces the human scale of the building.
Let me know if I am missing anything else,
Thank you,
Nakeisha Lyon, AICP | Associate Planner | Community Development
Pronouns: she, her, hers
City of Bozeman | 20 East Olive St. | P.O. Box 1230 | Bozeman, MT 59771
P: 406.582.2963 | E: nlyon@bozeman.net | W: www.bozeman.net/planning
The City has enhanced our project intake process and will now be receiving all project submittals - New and Revisions,
through ProjectDox. As a result of this transition in process, response times to inquiries may be delayed. We understand
the impacts any delay may create for your site development and we will make every effort to provide you with the highest
level of customer service in a timely manner. We encourage you to review our Development Center webpage and become
familiar with the new intake process. Your patience during this transition is greatly appreciated.
From: Chris Urner <chris.urner@scb.com>
Sent: Thursday, January 19, 2023 10:42 AM
To: Ross Knapper <rknapper@BOZEMAN.NET>; Nakeisha Lyon <nlyon@BOZEMAN.NET>; Ben Abbey
<BAbbey@BOZEMAN.NET>