HomeMy WebLinkAbout06-13-23 Public Comment - P. Quinn - Public Comment #2 on Site Plan 22047 - Sundance Springs Neighborhood Services Lot #2 DevelopmentFrom:Paul Quinn
To:Agenda
Subject:Public Comment #2 on Site Plan 22047 - Sundance Springs Neighborhood Services Lot #2 Development
Date:Tuesday, June 13, 2023 8:07:22 AM
Attachments:Public Comment #2 on Site Plan 22047 - Sundance Springs Neighborhood Services Lot #2 Development.pdf
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless
you recognize the sender and know the content is safe.
As an adjacent property owner, I insist that the requirements of BMC 38.430.040.A.3.d be
followed by the City and that Application #22047 be disapproved until such time as the
Approved Final Plan is located or there has been an formal process to reconstruction of the
terms of the PUD's Approved Final Plan, including the opportunity for public participation in
such a reconstruction.
Any reconstruction must include a reconstruction of the terms of the Master Plan and the
Development Guidelines. Enforcement of the same is binding upon the City.
Until such time, Site Plan #22047 must be disapproved because the Approved Final Plan is
missing (See BMC 38.430.040.A.3.d), and because Application #22047 violates the PUD's
Master Plan Map, Development Guidelines, and the 1992-era zoning, all enforceable under
modern BMC 38.430.080.A, BMC 38.430.040.A.3.d, BMC 38.100.050, and BMC 38.100.080.
The Sundance Springs PUD
The Sundance Springs PUD is a "Master Plan and Development Guidelines Only" PUD.
Therefore the requirements of the PUD are contained within the "Master Plan" and
"Development Guidelines" contained within the PUD's Approved Final Plan (Document Z-
9812).
The Master Plan and Development Guidelines
BMC 38.430.040.A.3.d forbids City Personnel from issuing development approvals that do not
comply with the terms of a PUD's Approved Final Plan. Therefore, any development under
the PUD must comply with the the PUD's approved final Master Plan and Development
Guidelines.
The missing Approved Final Plan
I recognized that the record of the Approved Final Plan has been lost by the City. Based on
the recent correspondence between the the City and the Applicant for Site Plan #22047, I
also understand that the City is attempting to "reconstruct" the terms of the missing Approved
Final Plan in order to approve Site Plan #22047.
I remind the City that approving a Site Plan in the absence of the PUD's Approved Final Plan
is a violation of the law (BMC38.430.040.A.3.d).
Further, I recognize that the PUD's Approved Preliminary Plan (Document Z-95125) should
contain a draft of the Master Plan and Development Guidelines approved by the City
Commission. However, I understand that the portion of the record describing the the PUD's
preliminary Master Plan (listed the Z-95125's table of contents) is missing from document Z-
95125. The same record is also missing from P-9539 (the Approved Preliminary Plan and
Preliminary Plat for Phase 1 of Sundance Springs). Therefore, the only remaining record of
the PUD's Master Plan is the Master Plan Map found in what remains of Z-9812.
Third, it appears that the City is planning to ignore most of the Development Guidelines and
the all of the Master Plan Map in its attempt to reconstruct the PUD's requirements. Instead,
the City appears ready to assess Site Plan #22047 against only the Commission's
"Conditions of Approval" for the preliminary PUD plan (Z-95125). This is, again, against the
law (BMC 38.430.040.A.3.d) not only because the Approved Final Plan is missing, but
because known elements of the Approved Final Plan (the Master Plan Map and the
Development Guidelines) are being ignored.
In the end, Site Plan #22047 violates virtually all of the Architectural Guidance and many
other requirements included in the PUD's Development Guidelines and Master Plan Map, and
therefore must be disapproved.
Business uses on the Site
In a recent letter, the Applicant argued that the PUD permits any business uses associated
with the modern B-1 zoning district. This is incorrect. The Staff Report for Z-95125 makes
clear that the PUD did not approve ANY business uses on the Neighborhood Services lots
whatsoever, and that approval of ANY proposed business use would be required as part of
the Site Plan application or as a subsequent conditional use approval. Because there are no
uses specified by the Site Plan, the City must conduct a full conditional use approval for any
proposed business use on the site in the future.
Large Outdoor Patios
In reference to the unapproved business uses, the large outdoor patios would create spaces
for outdoor business uses, which have been neither applied for nor approved (see "Business
Uses" above). The size of the patios (3000 sq ft) are disproportionate to the 5000 sq ft
building limit and are not shown on the Master Plan Map and therefore represent
"improvements" that were not approved under the PUD and cannot be allowed by the City
(See BMC38.430.040.A.3.d). The PUD's Development Guidelines (enforceable under BMC
38.100.050.A) forbid occupation of any lot in a manner that will disturb the peaceful
enjoyment of other lots in the subdivision, which outdoor use at this scale surely would. The
proposed patios are therefore fatal to Application #22047; it must be denied.
The 1992 Zoning
In its recent letter, the City has argued that only a subset of the covenant must be enforced.
However, ANY applicable subset of the covenants must be considered in the context of the
covenants' legal declaration. The declaration states that all covenants shall be enforced
beyond the requirements of the zoning and development code that was in effect on the date
the covenants were executed (the zoning in effect in 1998). Therefore because the City
acknowledges that at least some of the covenants must be enforced, they must be enforced
beyond the requirements of the 1992-era zoning (which was in effect in 1998).
Site Plan #22047 violates many of the terms of the 1992-era zoning including setbacks and
building sizes. It must be denied.
Parking
The City's recent letter addressed the City's position on Parking requirements. The Site Plan
has a parking demand of 68 spaces but only provides 41, thereby creating a demand for on-
street parking, which was explicitly prohibited by the City Commission to ensure that
Emergency Response Vehicles can access the subdivision on the 24' wide roads. Because
the demand for on-street parking will create a public safety issue, the Site Plan must be
denied (BMC 38.100.040, BMC 38.100.050).
In the end, the Site Plan violates the 1992-era parking requirements specified in both the
Introduction to the Development Guidelines and in the body of the Development Guidelines.
Therefore, again, Site Plan #22047 must be denied.
Market Study
The City Commission ordered a Market Study. In order for the Commercial Development to
be allowed, the Market Study had to conclude that 50% of the market for Commercial
Development on the Neighborhood Service's lot would come from the surrounding
residences. The Market Study reached this conclusion by assuming that Neighborhood
Services Lot #2 (the subject of Application #22047) would contain a 5000 sq ft convenience
store.
By violating the assumptions of the Market Study, Site Plan #22047 invalidates the Study's
conclusion that 50% of the market would come from the surrounding neighborhood.
Therefore, the proposed commercial development on Lot #2 is disallowed.
Constructive Notice
The Development Guidelines state that the Applicant is on "constructive notice" of the PUD's
requirements, agrees to the same, and is legally bound to them. I expect the City to ensure
the applicant lives up to the terms of the PUD's Master Plan Map and Development
Guidelines, which are requirements of the PUD that are known at this time -- even in the
absence of the Approved Final Plan.
Paul Quinn
467 Peace Pipe Dr
Bozeman, MT 59715