HomeMy WebLinkAbout035 Detention Pond Outfall Permitting03/03/23
22203 Norton
East Ranch Ph.
5B FP
DEPARTMENT OF THE ARMY
CORPS OF ENGINEERS, OMAHA DISTRICT
HELENA REGULATORY OFFICE
100 NEILL AVE SUITE 200
HELENA, MONTANA 59601
Printed on Recycled Paper
January 19, 2022
SUBJECT: 2017 Nationwide Permit Verification; Norton Properties, LLC (Vaughn
Environmental Services) Norton East Subdivision - Various Waterways (Gallatin
County); USACE File No. NWO-2007-01084-MTH
Killday & Stratton Inc.
2880 Technology Blvd
Bozeman, MT 59718
To Whom it may Concern:
We are responding to your request for Nationwide Permit (NWP) verification for the
above-mentioned project. The project is located at Latitude 45.681886°, Longitude -
111.119536°, on Aajker Creek, within Section 9, Township 2 S, Range 5 E, Gallatin
County, Montana.
Specifically, you requested authorization for the following work in waters of the U.S.:
1. Two Stormwater ponds outlet will be constructed in uplands adjacent to Aajker
Creek. One stormwater pond will be constructed at least 30 feet from Aaker Creek.
This storm water drain will consist of a 30-inch PVC culvert with a concrete flared
end section with a rock apron on the immediate end of the concrete section. The
stormwater will drain into a newly constructed vegetated swale leading to Aajker
Creek. No fill is proposed within the stream channel at this location.
2. The other outlet structure will consist of a subsurface 30-inch PVC drainpipe with a
concrete flared end with a rock riprap apron. Approximately 1 cubic yard of 6-inch
minus rock will be used to construct the concrete apron.
3. Approximately 22 linear feet of Aajker Creek will be impacted.
4. The work will be completed as detailed in the drawings entitled “Norton Ranch
Subdivision – Phase 5” and submitted on behalf of the applicant by C&H
Engineering and Survey Inc. Received on December 6, 2021.
Under the authority of Section 404 of the Clean Water Act (CWA), DA permits are
required for the discharge of fill material into waters of the U.S. Waters of the U.S.
include the area below the ordinary highwater mark of stream channels and lakes, or
ponds connected to the tributary system, and wetlands adjacent to these waters.
Isolated waters and wetlands, as well as man-made channels, may be waters of the
U.S. in certain circumstances, which must be determined on a case-by-case basis.
-2-
Printed on Recycled Paper
Based on the information you provided, the proposed activity, permanently affecting
approximately 22 linear feet of Aajker Creek, is authorized by NWP 7, Outfall Structures
found in the January 6, 2017, Federal Register (82 FR 1860), Reissuance and
Modification of Nationwide Permits. Enclosed is a fact sheet that fully describes this
NWP and lists the General and Regional Conditions that must be adhered to for this
authorization to remain valid. Please note that deviations from the original plans and
specifications of your project could require additional authorization from this office.
You are responsible for ensuring that all work is performed in accordance with the
terms and conditions of the NWP. If a contractor or other authorized representative will
be conducting work on your behalf it is strongly recommended that they be provided a
copy of this letter and the enclosed conditions. Failure to comply with the General and
Regional Conditions of this NWP, may result in the suspension or revocation of your
authorization and may be subject to appropriate enforcement action.
The Montana Department of Environmental Quality has provided the enclosed CWA
Section 401 water quality certification for this NWP which includes General Conditions,
all of which must be complied with for that certification to remain valid. This does not
eliminate the need to obtain other permits that may be required by that agency.
This verification is valid until March 18, 2022, when the existing NWPs are
scheduled to be modified, reissued, or revoked. Furthermore, if you commence or are
under contract to commence this activity before the date that the relevant NWP is
modified, reissued or revoked, you will have twelve (12) months from the date of the
modification, reissuance or revocation of the NWP to complete the activity under the
present terms and conditions unless discretionary authority has been exercised on a
case-by-case basis to modify, suspend, or revoke the authorization in accordance with
33 CFR 330.4(e) and 33 CFR 330.5 (c) or (d). Activities completed under the
authorization of an NWP which was in effect at the time the activity was completed
continue to be authorized by that NWP.
In compliance with General Condition 30, we have enclosed a "compliance
certification" form, which must be signed and returned within 30 days of completion of
the project, including any required mitigation. Your signature on this form certifies that
you have completed the work in accordance with the terms and conditions of the NWP.
The Omaha District, Regulatory Branch is committed to providing quality and timely
service to our customers. In an effort to improve customer service, please take a
moment to complete our Customer Service Survey found on our website at:
https://regulatory.ops.usace.army.mil/customer-service-survey/ . If you do not have
Internet access, you may call and request a paper copy of the survey that you can
complete and return to us by mail or fax.
-3-
Printed on Recycled Paper
Please refer to identification number NWO-2007-01084-MTH in any correspondence
concerning this project. If you have any questions, please contact Timothy Mcnew by
email at Timothy.M.McNew@usace.army.mil or telephone at (406) 441-1375.
Sincerely,
Timothy M. McNew
Senior Regulatory Project Manager
3 Enclosures:
1. Compliance Certification
2. Fact Sheet with Regional Conditions
3. CWA Section 401 Water Quality Certification
cc:
Morrison-Maierle Inc./Christine Pearcy
-4-
Printed on Recycled Paper
COMPLIANCE CERTIFICATION
USACE File Number: NWO-2007-01084-MTH
Permit Type: NWP 7, Outfall Structures
Name of Permittee: Kliday & Stratton, Inc
County: Gallatin County, Montana
Date of Issuance: January 19, 2022
Project Manager: Timothy Mcnew
Upon completion of the activity authorized by this permit and any mitigation required by
the permit, sign this certification and return it to Montana.Reg@usace.army.mil or the
following address:
US Army Corps of Engineers
Omaha District
Helena Regulatory Office
100Neill Ave, Suite 200
Helena, Montana 59626
Please note that your permitted activity is subject to a compliance inspection by a U.S.
Army Corps of Engineers representative. If you fail to comply with the conditions of this
permit, you are subject to permit suspension, modification, or revocation.
- - - - - - - - - - - - - - - - - - - - - - - - - - -
I hereby certify that the work authorized by the above referenced permit has been
completed in accordance with the terms and conditions of the said permit, and required
mitigation was completed in accordance with the permit conditions.
_____________________________________
Signature of Permittee
___________________
Date
Effective 19 March 2017
Nationwide Permit 7
Outfall Structures and Associated Intake Structures
Activities related to the construction or modification of outfall structures and associated
intake structures, where the effluent from the outfall is authorized, conditionally
authorized, or specifically exempted by, or otherwise in compliance with regulations
issued under the National Pollutant Discharge Elimination System Program (section 402
of the Clean Water Act). The construction of intake structures is not authorized by this
NWP, unless they are directly associated with an authorized outfall structure.
Notification: The permittee must submit a pre-construction notification to the district
engineer prior to commencing the activity. (See general condition 32.)
(Authorities: Sections 10 and 404)
Nationwide Permit General Conditions
Note: To qualify for NWP authorization, the prospective permittee must comply with the
following general conditions, as applicable, in addition to any regional or case-specific
conditions imposed by the division engineer or district engineer. Prospective permittees
should contact the appropriate Corps district office to determine if regional conditions
have been imposed on an NWP. Prospective permittees should also contact the
appropriate Corps district office to determine the status of Clean Water Act Section 401
water quality certification and/ or Coastal Zone Management Act consistency for an
NWP. Every person who may wish to obtain permit authorization under one or more
NWPs, or who is currently relying on an existing or prior permit authorization under one
or more NWPs, has been and is on notice that all of the provisions of 33 CFR 330.1
through 330.6 apply to every NWP authorization. Note especially 33 CFR 330.5 relating
to the modification, suspension, or revocation of any NWP authorization.
1. Navigation.
(a) No activity may cause more than a minimal adverse effect on navigation.
(b) Any safety lights and signals prescribed by the U.S. Coast Guard, through
regulations or otherwise, must be installed and maintained at the permittee’s expense
on authorized facilities in navigable waters of the United States.
(c) The permittee understands and agrees that, if future operations by the United States
require the removal, relocation, or other alteration, of the structure or work herein
authorized, or if, in the opinion of the Secretary of the Army or his authorized
representative, said structure or work shall cause unreasonable obstruction to the free
navigation of the navigable waters, the permittee will be required, upon due notice from
the Corps of Engineers, to remove, relocate, or alter the structural work or obstructions
caused thereby, without expense to the United States. No claim shall be made against
the United States on account of any such removal or alteration.
Effective 19 March 2017
2. Aquatic Life Movements.
No activity may substantially disrupt the necessary life cycle movements of those
species of aquatic life indigenous to the waterbody, including those species that
normally migrate through the area, unless the activity’s primary purpose is to impound
water. All permanent and temporary crossings of waterbodies shall be suitably
culverted, bridged, or otherwise designed and constructed to maintain low flows to
sustain the movement of those aquatic species. If a bottomless culvert cannot be used,
then the crossing should be designed and constructed to minimize adverse effects to
aquatic life movements.
3. Spawning Areas.
Activities in spawning areas during spawning seasons must be avoided to the maximum
extent practicable. Activities that result in the physical destruction (e.g., through
excavation, fill, or downstream smothering by substantial turbidity) of an important
spawning area are not authorized.
4. Migratory Bird Breeding Areas.
Activities in waters of the United States that serve as breeding areas for migratory birds
must be avoided to the maximum extent practicable.
5. Shellfish Beds.
No activity may occur in areas of concentrated shellfish populations, unless the activity
is directly related to a shellfish harvesting activity authorized by NWPs 4 and 48, or is a
shellfish seeding or habitat restoration activity authorized by NWP 27.
6. Suitable Material.
No activity may use unsuitable material (e.g., trash, debris, car bodies, asphalt, etc.).
Material used for construction or discharged must be free from toxic pollutants in toxic
amounts (see section 307 of the Clean Water Act).
7. Water Supply Intakes.
No activity may occur in the proximity of a public water supply intake, except where the
activity is for the repair or improvement of public water supply intake structures or
adjacent bank stabilization.
8. Adverse Effects from Impoundments.
Effective 19 March 2017
If the activity creates an impoundment of water, adverse effects to the aquatic system
due to accelerating the passage of water, and/or restricting its flow must be minimized
to the maximum extent practicable.
9. Management of Water Flows.
To the maximum extent practicable, the pre-construction course, condition, capacity,
and location of open waters must be maintained for each activity, including stream
channelization, storm water management activities, and temporary and permanent road
crossings, except as provided below. The activity must be constructed to withstand
expected high flows. The activity must not restrict or impede the passage of normal or
high flows, unless the primary purpose of the activity is to impound water or manage
high flows. The activity may alter the pre- construction course, condition, capacity, and
location of open waters if it benefits the aquatic environment (e.g., stream restoration or
relocation activities).
10. Fills Within 100-Year Floodplains.
The activity must comply with applicable FEMA-approved state or local floodplain
management requirements.
11. Equipment.
Heavy equipment working in wetlands or mudflats must be placed on mats, or other
measures must be taken to minimize soil disturbance.
12. Soil Erosion and Sediment Controls.
Appropriate soil erosion and sediment controls must be used and maintained in
effective operating condition during construction, and all exposed soil and other fills, as
well as any work below the ordinary high water mark or high tide line, must be
permanently stabilized at the earliest practicable date. Permittees are encouraged to
perform work within waters of the United States during periods of low-flow or no-flow, or
during low tides.
13. Removal of Temporary Fills.
Temporary fills must be removed in their entirety and the affected areas returned to pre-
construction elevations. The affected areas must be revegetated, as appropriate.
14. Proper Maintenance.
Any authorized structure or fill shall be properly maintained, including maintenance to
ensure public safety and compliance with applicable NWP general conditions, as well as
any activity-specific conditions added by the district engineer to an NWP authorization.
Effective 19 March 2017
15. Single and Complete Project.
The activity must be a single and complete project. The same NWP cannot be used
more than once for the same single and complete project.
16. Wild and Scenic Rivers.
(a) No NWP activity may occur in a component of the National Wild and Scenic River
System, or in a river officially designated by Congress as a ‘‘study river’’ for possible
inclusion in the system while the river is in an official study status, unless the
appropriate Federal agency with direct management responsibility for such river, has
determined in writing that the proposed activity will not adversely affect the Wild and
Scenic River designation or study status.
(b) If a proposed NWP activity will occur in a component of the National Wild and Scenic
River System, or in a river officially designated by Congress as a ‘‘study river’’ for
possible inclusion in the system while the river is in an official study status, the
permittee must submit a pre-construction notification (see general condition 32). The
district engineer will coordinate the PCN with the Federal agency with direct
management responsibility for that river. The permittee shall not begin the NWP activity
until notified by the district engineer that the Federal agency with direct management
responsibility for that river has determined in writing that the proposed NWP activity will
not adversely affect the Wild and Scenic River designation or study status.
(c) Information on Wild and Scenic Rivers may be obtained from the appropriate
Federal land management agency responsible for the designated Wild and Scenic River
or study river (e.g., National Park Service, U.S. Forest Service, Bureau of Land
Management, U.S. Fish and Wildlife Service). Information on these rivers is also
available at: http://www.rivers.gov/.
17. Tribal Rights.
No NWP activity may cause more than minimal adverse effects on tribal rights
(including treaty rights), protected tribal resources, or tribal lands.
18. Endangered Species.
(a) No activity is authorized under any NWP which is likely to directly or indirectly
jeopardize the continued existence of a threatened or endangered species or a species
proposed for such designation, as identified under the Federal Endangered Species Act
(ESA), or which will directly or indirectly destroy or adversely modify the critical habitat
of such species. No activity is authorized under any NWP which ‘‘may affect’’ a listed
species or critical habitat, unless ESA section 7 consultation addressing the effects of
the proposed activity has been completed. Direct effects are the immediate effects on
listed species and critical habitat caused by the NWP activity. Indirect effects are those
effects on listed species and critical habitat that are caused by the NWP activity and are
later in time, but still are reasonably certain to occur.
Effective 19 March 2017
(b) Federal agencies should follow their own procedures for complying with the
requirements of the ESA. If pre- construction notification is required for the proposed
activity, the Federal permittee must provide the district engineer with the appropriate
documentation to demonstrate compliance with those requirements. The district
engineer will verify that the appropriate documentation has been submitted. If the
appropriate documentation has not been submitted, additional ESA section 7
consultation may be necessary for the activity and the respective federal agency would
be responsible for fulfilling its obligation under section 7 of the ESA.
(c) Non-federal permittees must submit a pre-construction notification to the district
engineer if any listed species or designated critical habitat might be affected or is in the
vicinity of the activity, or if the activity is located in designated critical habitat, and shall
not begin work on the activity until notified by the district engineer that the requirements
of the ESA have been satisfied and that the activity is authorized. For activities that
might affect Federally-listed endangered or threatened species or designated critical
habitat, the pre-construction notification must include the name(s) of the endangered or
threatened species that might be affected by the proposed activity or that utilize the
designated critical habitat that might be affected by the proposed activity. The district
engineer will determine whether the proposed activity ‘‘may affect’’ or will have ‘‘no
effect’’ to listed species and designated critical habitat and will notify the non-Federal
applicant of the Corps’ determination within 45 days of receipt of a complete pre-
construction notification. In cases where the non- Federal applicant has identified listed
species or critical habitat that might be affected or is in the vicinity of the activity, and
has so notified the Corps, the applicant shall not begin work until the Corps has
provided notification that the proposed activity will have ‘‘no effect’’ on listed species or
critical habitat, or until ESA section 7 consultation has been completed. If the non-
Federal applicant has not heard back from the Corps within 45 days, the applicant must
still wait for notification from the Corps.
(d) As a result of formal or informal consultation with the FWS or NMFS the district
engineer may add species- specific permit conditions to the NWPs.
(e) Authorization of an activity by an NWP does not authorize the ‘‘take’’ of a threatened
or endangered species as defined under the ESA. In the absence of separate
authorization (e.g., an ESA Section 10 Permit, a Biological Opinion with ‘‘incidental
take’’ provisions, etc.) from the FWS or the NMFS, the Endangered Species Act
prohibits any person subject to the jurisdiction of the United States to take a listed
species, where ‘‘take’’ means to harass, harm, pursue, hunt, shoot, wound, kill, trap,
capture, or collect, or to attempt to engage in any such conduct. The word ‘‘harm’’ in the
definition of ‘‘take’’ means an act which actually kills or injures wildlife. Such an act may
include significant habitat modification or degradation where it actually kills or injures
wildlife by significantly impairing essential behavioral patterns, including breeding,
feeding or sheltering.
(f) If the non-federal permittee has a valid ESA section 10(a)(1)(B) incidental take permit
with an approved Habitat Conservation Plan for a project or a group of projects that
includes the proposed NWP activity, the non-federal applicant should provide a copy of
that ESA section 10(a)(1)(B) permit with the PCN required by paragraph (c) of this
general condition. The district engineer will coordinate with the agency that issued the
ESA section 10(a)(1)(B) permit to determine whether the proposed NWP activity and
Effective 19 March 2017
the associated incidental take were considered in the internal ESA section 7
consultation conducted for the ESA section 10(a)(1)(B) permit. If that coordination
results in concurrence from the agency that the proposed NWP activity and the
associated incidental take were considered in the internal ESA section 7 consultation for
the ESA section 10(a)(1)(B) permit, the district engineer does not need to conduct a
separate ESA section 7 consultation for the proposed NWP activity. The district
engineer will notify the non-federal applicant within 45 days of receipt of a complete pre-
construction notification whether the ESA section 10(a)(1)(B) permit covers the
proposed NWP activity or whether additional ESA section 7 consultation is required.
(g) Information on the location of threatened and endangered species and their critical
habitat can be obtained directly from the offices of the FWS and NMFS or their world
wide Web pages at http://www.fws.gov/ or http:// www.fws.gov/ipac and http://
www.nmfs.noaa.gov/pr/species/esa/ respectively.
19. Migratory Birds and Bald and Golden Eagles.
The permittee is responsible for ensuring their action complies with the Migratory Bird
Treaty Act and the Bald and Golden Eagle Protection Act. The permittee is responsible
for contacting appropriate local office of the U.S. Fish and Wildlife Service to determine
applicable measures to reduce impacts to migratory birds or eagles, including whether
‘‘incidental take’’ permits are necessary and available under the Migratory Bird Treaty
Act or Bald and Golden Eagle Protection Act for a particular activity.
20. Historic Properties.
(a) In cases where the district engineer determines that the activity may have the
potential to cause effects to properties listed, or eligible for listing, in the National
Register of Historic Places, the activity is not authorized, until the requirements of
Section 106 of the National Historic Preservation Act (NHPA) have been satisfied.
(b) Federal permittees should follow their own procedures for complying with the
requirements of section 106 of the National Historic Preservation Act. If pre-construction
notification is required for the proposed NWP activity, the Federal permittee must
provide the district engineer with the appropriate documentation to demonstrate
compliance with those requirements. The district engineer will verify that the appropriate
documentation has been submitted. If the appropriate documentation is not submitted,
then additional consultation under section 106 may be necessary. The respective
federal agency is responsible for fulfilling its obligation to comply with section 106.
(c) Non-federal permittees must submit a pre-construction notification to the district
engineer if the NWP activity might have the potential to cause effects to any historic
properties listed on, determined to be eligible for listing on, or potentially eligible for
listing on the National Register of Historic Places, including previously unidentified
properties. For such activities, the pre- construction notification must state which historic
properties might have the potential to be affected by the proposed NWP activity or
include a vicinity map indicating the location of the historic properties or the potential for
the presence of historic properties. Assistance regarding information on the location of,
Effective 19 March 2017
or potential for, the presence of historic properties can be sought from the State Historic
Preservation Officer, Tribal Historic Preservation Officer, or designated tribal
representative, as appropriate, and the National Register of Historic Places (see 33
CFR 330.4(g)). When reviewing pre-construction notifications, district engineers will
comply with the current procedures for addressing the requirements of section 106 of
the National Historic Preservation Act. The district engineer shall make a reasonable
and good faith effort to carry out appropriate identification efforts, which may include
background research, consultation, oral history interviews, sample field investigation,
and field survey. Based on the information submitted in the PCN and these identification
efforts, the district engineer shall determine whether the proposed NWP activity has the
potential to cause effects on the historic properties. Section 106 consultation is not
required when the district engineer determines that the activity does not have the
potential to cause effects on historic properties (see 36 CFR 800.3(a)). Section 106
consultation is required when the district engineer determines that the activity has the
potential to cause effects on historic properties. The district engineer will conduct
consultation with consulting parties identified under 36 CFR 800.2(c) when he or she
makes any of the following effect determinations for the purposes of section 106 of the
NHPA: no historic properties affected, no adverse effect, or adverse effect. Where the
non-Federal applicant has identified historic properties on which the activity might have
the potential to cause effects and so notified the Corps, the non-Federal applicant shall
not begin the activity until notified by the district engineer either that the activity has no
potential to cause effects to historic properties or that NHPA section 106 consultation
has been completed.
(d) For non-federal permittees, the district engineer will notify the prospective permittee
within 45 days of receipt of a complete pre-construction notification whether NHPA
section 106 consultation is required. If NHPA section 106 consultation is required, the
district engineer will notify the non- Federal applicant that he or she cannot begin the
activity until section 106 consultation is completed. If the non-Federal applicant has not
heard back from the Corps within 45 days, the applicant must still wait for notification
from the Corps.
(e) Prospective permittees should be aware that section 110k of the NHPA (54 U.S.C.
306113) prevents the Corps from granting a permit or other assistance to an applicant
who, with intent to avoid the requirements of section 106 of the NHPA, has
intentionally significantly adversely affected a historic property to which the permit
would relate, or having legal power to prevent it, allowed such significant adverse effect
to occur, unless the Corps, after consultation with the Advisory Council on Historic
Preservation (ACHP), determines that circumstances justify granting such assistance
despite the adverse effect created or permitted by the applicant. If circumstances justify
granting the assistance, the Corps is required to notify the ACHP and provide
documentation specifying the circumstances, the degree of damage to the integrity of
any historic properties affected, and proposed mitigation. This documentation must
include any views obtained from the applicant, SHPO/ THPO, appropriate Indian tribes
if the undertaking occurs on or affects historic properties on tribal lands or affects
properties of interest to those tribes, and other parties known to have a legitimate
interest in the impacts to the permitted activity on historic properties.
Effective 19 March 2017
21. Discovery of Previously Unknown Remains and Artifacts.
If you discover any previously unknown historic, cultural or archeological remains and
artifacts while accomplishing the activity authorized by this permit, you must
immediately notify the district engineer of what you have found, and to the maximum
extent practicable, avoid construction activities that may affect the remains and artifacts
until the required coordination has been completed. The district engineer will initiate the
Federal, Tribal, and state coordination required to determine if the items or remains
warrant a recovery effort or if the site is eligible for listing in the National Register of
Historic Places.
22. Designated Critical Resource Waters.
Critical resource waters include, NOAA-managed marine sanctuaries and marine
monuments, and National Estuarine Research Reserves. The district engineer may
designate, after notice and opportunity for public comment, additional waters officially
designated by a state as having particular environmental or ecological significance,
such as outstanding national resource waters or state natural heritage sites. The district
engineer may also designate additional critical resource waters after notice and
opportunity for public comment.
(a) Discharges of dredged or fill material into waters of the United States are not
authorized by NWPs 7, 12, 14, 16, 17, 21, 29, 31, 35, 39, 40, 42, 43, 44, 49, 50, 51, and
52 for any activity within, or directly affecting, critical resource waters, including
wetlands adjacent to such waters.
(b) For NWPs 3, 8, 10, 13, 15, 18, 19, 22, 23, 25, 27, 28, 30, 33, 34, 36, 37, 38, and 54,
notification is required in accordance with general condition 32, for any activity proposed
in the designated critical resource waters including wetlands adjacent to those waters.
The district engineer may authorize activities under these NWPs only after it is
determined that the impacts to the critical resource waters will be no more than minimal.
23. Mitigation.
The district engineer will consider the following factors when determining appropriate
and practicable mitigation necessary to ensure that the individual and cumulative
adverse environmental effects are no more than minimal:
(a) The activity must be designed and constructed to avoid and minimize adverse
effects, both temporary and permanent, to waters of the United States to the maximum
extent practicable at the project site (i.e., on site).
(b) Mitigation in all its forms (avoiding, minimizing, rectifying, reducing, or compensating
for resource losses) will be required to the extent necessary to ensure that the individual
and cumulative adverse environmental effects are no more than minimal.
(c) Compensatory mitigation at a minimum one-for-one ratio will be required for all
wetland losses that exceed 1⁄10-acre and require pre- construction notification, unless
the district engineer determines in writing that either some other form of mitigation
would be more environmentally appropriate or the adverse environmental effects of the
proposed activity are no more than minimal, and provides an activity-specific waiver of
Effective 19 March 2017
this requirement. For wetland losses of 1⁄10-acre or less that require pre- construction
notification, the district engineer may determine on a case-by- case basis that
compensatory mitigation is required to ensure that the activity results in only minimal
adverse environmental effects.
(d) For losses of streams or other open waters that require pre-construction notification,
the district engineer may require compensatory mitigation to ensure that the activity
results in no more than minimal adverse environmental effects. Compensatory
mitigation for losses of streams should be provided, if practicable, through stream
rehabilitation, enhancement, or preservation, since streams are difficult- to-replace
resources (see 33 CFR 332.3(e)(3)).
(e) Compensatory mitigation plans for NWP activities in or near streams or other open
waters will normally include a requirement for the restoration or enhancement,
maintenance, and legal protection (e.g., conservation easements) of riparian areas next
to open waters. In some cases, the restoration or maintenance/protection of riparian
areas may be the only compensatory mitigation required. Restored riparian areas
should consist of native species. The width of the required riparian area will address
documented water quality or aquatic habitat loss concerns.
Normally, the riparian area will be 25 to 50 feet wide on each side of the stream, but the
district engineer may require slightly wider riparian areas to address documented water
quality or habitat loss concerns. If it is not possible to restore or maintain/protect a
riparian area on both sides of a stream, or if the waterbody is a lake or coastal waters,
then restoring or maintaining/protecting a riparian area along a single bank or shoreline
may be sufficient. Where both wetlands and open waters exist on the project site, the
district engineer will determine the appropriate compensatory mitigation (e.g., riparian
areas and/or wetlands compensation) based on what is best for the aquatic
environment on a watershed basis. In cases where riparian areas are determined to be
the most appropriate form of minimization or compensatory mitigation, the district
engineer may waive or reduce the requirement to provide wetland compensatory
mitigation for wetland losses.
(f) Compensatory mitigation projects provided to offset losses of aquatic resources must
comply with the applicable provisions of 33 CFR part 332.
(1) The prospective permittee is responsible for proposing an appropriate
compensatory mitigation option if compensatory mitigation is necessary to ensure that
the activity results in no more than minimal adverse environmental effects. For the
NWPs, the preferred mechanism for providing compensatory mitigation is mitigation
bank credits or in-lieu fee program credits (see 33 CFR 332.3(b)(2) and (3)). However, if
an appropriate number and type of mitigation bank or in-lieu credits are not available at
the time the PCN is submitted to the district engineer, the district engineer may approve
the use of permittee-responsible mitigation.
(2) The amount of compensatory mitigation required by the district engineer must
be sufficient to ensure that the authorized activity results in no more than minimal
individual and cumulative adverse environmental effects (see 33 CFR 330.1(e)(3)). (See
also 33 CFR 332.3(f)).
(3) Since the likelihood of success is greater and the impacts to potentially
valuable uplands are reduced, aquatic resource restoration should be the first
compensatory mitigation option considered for permittee-responsible mitigation.
Effective 19 March 2017
(4) If permittee-responsible mitigation is the proposed option, the prospective
permittee is responsible for submitting a mitigation plan. A conceptual or detailed
mitigation plan may be used by the district engineer to make the decision on the NWP
verification request, but a final mitigation plan that addresses the applicable
requirements of 33 CFR 332.4(c)(2) through (14) must be approved by the district
engineer before the permittee begins work in waters of the United States, unless the
district engineer determines that prior approval of the final mitigation plan is not
practicable or not necessary to ensure timely completion of the required compensatory
mitigation (see 33 CFR 332.3(k)(3)).
(5) If mitigation bank or in-lieu fee program credits are the proposed option, the
mitigation plan only needs to address the baseline conditions at the impact site and the
number of credits to be provided.
(6) Compensatory mitigation requirements (e.g., resource type and amount to be
provided as compensatory mitigation, site protection, ecological performance standards,
monitoring requirements) may be addressed through conditions added to the NWP
authorization, instead of components of a compensatory mitigation plan (see 33 CFR
332.4(c)(1)(ii)).
(g) Compensatory mitigation will not be used to increase the acreage losses allowed by
the acreage limits of the NWPs. For example, if an NWP has an acreage limit of 1⁄2-
acre, it cannot be used to authorize any NWP activity resulting in the loss of greater
than 1⁄2- acre of waters of the United States, even if compensatory mitigation is
provided that replaces or restores some of the lost waters. However, compensatory
mitigation can and should be used, as necessary, to ensure that an NWP activity
already meeting the established acreage limits also satisfies the no more than minimal
impact requirement for the NWPs.
(h) Permittees may propose the use of mitigation banks, in-lieu fee programs, or
permittee-responsible mitigation. When developing a compensatory mitigation proposal,
the permittee must consider appropriate and practicable options consistent with the
framework at 33 CFR 332.3(b). For activities resulting in the loss of marine or estuarine
resources, permittee- responsible mitigation may be environmentally preferable if there
are no mitigation banks or in-lieu fee programs in the area that have marine or estuarine
credits available for sale or transfer to the permittee. For permittee- responsible
mitigation, the special conditions of the NWP verification must clearly indicate the party
or parties responsible for the implementation and performance of the compensatory
mitigation project, and, if required, its long-term management.
(i) Where certain functions and services of waters of the United States are permanently
adversely affected by a regulated activity, such as discharges of dredged or fill material
into waters of the United States that will convert a forested or scrub-shrub wetland to a
herbaceous wetland in a permanently maintained utility line right-of-way, mitigation may
be required to reduce the adverse environmental effects of the activity to the no more
than minimal level.
24. Safety of Impoundment Structures.
To ensure that all impoundment structures are safely designed, the district engineer
may require non-Federal applicants to demonstrate that the structures comply with
Effective 19 March 2017
established state dam safety criteria or have been designed by qualified persons. The
district engineer may also require documentation that the design has been
independently reviewed by similarly qualified persons, and appropriate modifications
made to ensure safety.
25. Water Quality.
Where States and authorized Tribes, or EPA where applicable, have not previously
certified compliance of an NWP with CWA section 401, individual 401 Water Quality
Certification must be obtained or waived (see 33 CFR 330.4(c)). The district engineer or
State or Tribe may require additional water quality management measures to ensure
that the authorized activity does not result in more than minimal degradation of water
quality.
26. Coastal Zone Management.
In coastal states where an NWP has not previously received a state coastal zone
management consistency concurrence, an individual state coastal zone management
consistency concurrence must be obtained, or a presumption of concurrence must
occur (see 33 CFR 330.4(d)). The district engineer or a State may require additional
measures to ensure that the authorized activity is consistent with state coastal zone
management requirements.
27. Regional and Case-By-Case Conditions.
The activity must comply with any regional conditions that may have been added by the
Division Engineer (see 33 CFR 330.4(e)) and with any case specific conditions added
by the Corps or by the state, Indian Tribe, or U.S. EPA in its section 401 Water Quality
Certification, or by the state in its Coastal Zone Management Act consistency
determination.
28. Use of Multiple Nationwide Permits.
The use of more than one NWP for a single and complete project is prohibited, except
when the acreage loss of waters of the United States authorized by the NWPs does not
exceed the acreage limit of the NWP with the highest specified acreage limit. For
example, if a road crossing over tidal waters is constructed under NWP 14, with
associated bank stabilization authorized by NWP 13, the maximum acreage loss of
waters of the United States for the total project cannot exceed 1⁄3-acre.
29. Transfer of Nationwide Permit Verifications.
If the permittee sells the property associated with a nationwide permit verification, the
permittee may transfer the nationwide permit verification to the new owner by submitting
a letter to the appropriate Corps district office to validate the transfer. A copy of the
Effective 19 March 2017
nationwide permit verification must be attached to the letter, and the letter must contain
the following statement and signature:
When the structures or work authorized by this nationwide permit are still in
existence at the time the property is transferred, the terms and conditions of this
nationwide permit, including any special conditions, will continue to be binding
on the new owner(s) of the property. To validate the transfer of this nationwide
permit and the associated liabilities associated with compliance with its terms
and conditions, have the transferee sign and date below.
_________________________________ (Transferee) ____
________________ (Date)
30. Compliance Certification.
Each permittee who receives an NWP verification letter from the Corps must provide a
signed certification documenting completion of the authorized activity and
implementation of any required compensatory mitigation. The success of any required
permittee-responsible mitigation, including the achievement of ecological performance
standards, will be addressed separately by the district engineer. The Corps will provide
the permittee the certification document with the NWP verification letter. The
certification document will include:
(a) A statement that the authorized activity was done in accordance with the NWP
authorization, including any general, regional, or activity-specific conditions;
(b) A statement that the implementation of any required compensatory mitigation was
completed in accordance with the permit conditions. If credits from a mitigation bank or
in-lieu fee program are used to satisfy the compensatory mitigation requirements, the
certification must include the documentation required by 33 CFR 332.3(l)(3) to confirm
that the permittee secured the appropriate number and resource type of credits; and
(c) The signature of the permittee certifying the completion of the activity and mitigation.
The completed certification document must be submitted to the district engineer within
30 days of completion of the authorized activity or the implementation of any required
compensatory mitigation, whichever occurs later.
31. Activities Affecting Structures or Works Built by the United States.
If an NWP activity also requires permission from the Corps pursuant to 33 U.S.C. 408
because it will alter or temporarily or permanently occupy or use a U.S. Army Corps of
Engineers (USACE) federally authorized Civil Works project (a ‘‘USACE project’’), the
prospective permittee must submit a pre- construction notification. See paragraph
(b)(10) of general condition 32. An activity that requires section 408 permission is not
authorized by NWP until the appropriate Corps office issues the section 408 permission
to alter, occupy, or use the USACE project, and the district engineer issues a written
NWP verification.
32. Pre-Construction Notification.
Effective 19 March 2017
(a) Timing. Where required by the terms of the NWP, the prospective permittee must
notify the district engineer by submitting a pre-construction notification (PCN) as early
as possible. The district engineer must determine if the PCN is complete within 30
calendar days of the date of receipt and, if the PCN is determined to be incomplete,
notify the prospective permittee within that 30 day period to request the additional
information necessary to make the PCN complete. The request must specify the
information needed to make the PCN complete. As a general rule, district engineers will
request additional information necessary to make the PCN complete only once.
However, if the prospective permittee does not provide all of the requested information,
then the district engineer will notify the prospective permittee that the PCN is still
incomplete and the PCN review process will not commence until all of the requested
information has been received by the district engineer. The prospective permittee shall
not begin the activity until either:
(1) He or she is notified in writing by the district engineer that the activity may
proceed under the NWP with any special conditions imposed by the district or division
engineer; or
(2) 45 calendar days have passed from the district engineer’s receipt of the
complete PCN and the prospective permittee has not received written notice from the
district or division engineer. However, if the permittee was required to notify the Corps
pursuant to general condition 18 that listed species or critical habitat might be affected
or are in the vicinity of the activity, or to notify the Corps pursuant to general condition
20 that the activity might have the potential to cause effects to historic properties, the
permittee cannot begin the activity until receiving written notification from the Corps that
there is ‘‘no effect’’ on listed species or ‘‘no potential to cause effects’’ on historic
properties, or that any consultation required under Section 7 of the Endangered Species
Act (see 33 CFR 330.4(f)) and/or section 106 of the National Historic Preservation Act
(see 33 CFR 330.4(g)) has been completed. Also, work cannot begin under NWPs 21,
49, or 50 until the permittee has received written approval from the Corps. If the
proposed activity requires a written waiver to exceed specified limits of an NWP, the
permittee may not begin the activity until the district engineer issues the waiver. If the
district or division engineer notifies the permittee in writing that an individual permit is
required within 45 calendar days of receipt of a complete PCN, the permittee cannot
begin the activity until an individual permit has been obtained. Subsequently, the
permittee’s right to proceed under the NWP may be modified, suspended, or revoked
only in accordance with the procedure set forth in 33 CFR 330.5(d)(2).
(b) Contents of Pre-Construction Notification: The PCN must be in writing and include
the following information:
(1) Name, address and telephone numbers of the prospective permittee;
(2) Location of the proposed activity;
(3) Identify the specific NWP or NWP(s) the prospective permittee wants to use
to authorize the proposed activity;
(4) A description of the proposed activity; the activity’s purpose; direct and
indirect adverse environmental effects the activity would cause, including the anticipated
amount of loss of wetlands, other special aquatic sites, and other waters expected to
result from the NWP activity, in acres, linear feet, or other appropriate unit of measure; a
Effective 19 March 2017
description of any proposed mitigation measures intended to reduce the adverse
environmental effects caused by the proposed activity; and any other NWP(s), regional
general permit(s), or individual permit(s) used or intended to be used to authorize any
part of the proposed project or any related activity, including other separate and distant
crossings for linear projects that require Department of the Army authorization but do
not require pre-construction notification. The description of the proposed activity and
any proposed mitigation measures should be sufficiently detailed to allow the district
engineer to determine that the adverse environmental effects of the activity will be no
more than minimal and to determine the need for compensatory mitigation or other
mitigation measures. For single and complete linear projects, the PCN must include the
quantity of anticipated losses of wetlands, other special aquatic sites, and other waters
for each single and complete crossing of those wetlands, other special aquatic sites,
and other waters. Sketches should be provided when necessary to show that the
activity complies with the terms of the NWP. (Sketches usually clarify the activity and
when provided results in a quicker decision. Sketches should contain sufficient detail to
provide an illustrative description of the proposed activity (e.g., a conceptual plan), but
do not need to be detailed engineering plans);
(5) The PCN must include a delineation of wetlands, other special aquatic sites,
and other waters, such as lakes and ponds, and perennial, intermittent, and ephemeral
streams, on the project site. Wetland delineations must be prepared in accordance with
the current method required by the Corps. The permittee may ask the Corps to
delineate the special aquatic sites and other waters on the project site, but there may be
a delay if the Corps does the delineation, especially if the project site is large or
contains many wetlands, other special aquatic sites, and other waters. Furthermore, the
45 day period will not start until the delineation has been submitted to or completed by
the Corps, as appropriate;
(6) If the proposed activity will result in the loss of greater than 1⁄10-acre of
wetlands and a PCN is required, the prospective permittee must submit a statement
describing how the mitigation requirement will be satisfied, or explaining why the
adverse environmental effects are no more than minimal and why compensatory
mitigation should not be required. As an alternative, the prospective permittee may
submit a conceptual or detailed mitigation plan.
(7) For non-Federal permittees, if any listed species or designated critical habitat
might be affected or is in the vicinity of the activity, or if the activity is located in
designated critical habitat, the PCN must include the name(s) of those endangered or
threatened species that might be affected by the proposed activity or utilize the
designated critical habitat that might be affected by the proposed activity. For NWP
activities that require pre-construction notification, Federal permittees must provide
documentation demonstrating compliance with the Endangered Species Act.
(8) For non-Federal permittees, if the NWP activity might have the potential to
cause effects to a historic property listed on, determined to be eligible for listing on, or
potentially eligible for listing on, the National Register of Historic Places, the PCN must
state which historic property might have the potential to be affected by the proposed
activity or include a vicinity map indicating the location of the historic property. For NWP
activities that require pre-construction notification, Federal permittees must provide
Effective 19 March 2017
documentation demonstrating compliance with section 106 of the National Historic
Preservation Act;
(9) For an activity that will occur in a component of the National Wild and Scenic
River System, or in a river officially designated by Congress as a ‘‘study river’’ for
possible inclusion in the system while the river is in an official study status, the PCN
must identify the Wild and Scenic River or the ‘‘study river’’ (see general condition 16);
and
(10) For an activity that requires permission from the Corps pursuant to 33
U.S.C. 408 because it will alter or temporarily or permanently occupy or use a U.S.
Army Corps of Engineers federally authorized civil works project, the pre-construction
notification must include a statement confirming that the project proponent has
submitted a written request for section 408 permission from the Corps office having
jurisdiction over that USACE project.
(c) Form of Pre-Construction Notification: The standard individual permit application
form (Form ENG 4345) may be used, but the completed application form must clearly
indicate that it is an NWP PCN and must include all of the applicable information
required in paragraphs (b)(1) through (10) of this general condition. A letter containing
the required information may also be used. Applicants may provide electronic files of
PCNs and supporting materials if the district engineer has established tools and
procedures for electronic submittals.
(d) Agency Coordination:
(1) The district engineer will consider any comments from Federal and state
agencies concerning the proposed activity’s compliance with the terms and conditions
of the NWPs and the need for mitigation to reduce the activity’s adverse environmental
effects so that they are no more than minimal.
(2) Agency coordination is required for: (i) All NWP activities that require pre-
construction notification and result in the loss of greater than 1⁄2-acre of waters of the
United States; (ii) NWP 21, 29, 39, 40, 42, 43, 44, 50, 51, and 52 activities that require
pre-construction notification and will result in the loss of greater than 300 linear feet of
stream bed; (iii) NWP 13 activities in excess of 500 linear feet, fills greater than one
cubic yard per running foot, or involve discharges of dredged or fill material into special
aquatic sites; and (iv) NWP 54 activities in excess of 500 linear feet, or that extend into
the waterbody more than 30 feet from the mean low water line in tidal waters or the
ordinary high water mark in the Great Lakes.
(3) When agency coordination is required, the district engineer will immediately
provide (e.g., via email, facsimile transmission, overnight mail, or other expeditious
manner) a copy of the complete PCN to the appropriate Federal or state offices (FWS,
state natural resource or water quality agency, EPA, and, if appropriate, the NMFS).
With the exception of NWP 37, these agencies will have 10 calendar days from the date
the material is transmitted to notify the district engineer via telephone, facsimile
transmission, or email that they intend to provide substantive, site-specific comments.
The comments must explain why the agency believes the adverse environmental effects
will be more than minimal. If so contacted by an agency, the district engineer will wait an
additional 15 calendar days before making a decision on the pre- construction
notification. The district fully consider agency comments received within the specified
time frame concerning the proposed activity’s compliance with the terms and conditions
Effective 19 March 2017
of the NWPs, including the need for mitigation to ensure the net adverse environmental
effects of the proposed activity are no more than minimal. The district engineer will
provide no response to the resource agency, except as provided below. The district
engineer will indicate in the administrative record associated with each pre-construction
notification that the resource agencies’ concerns were considered. For NWP 37, the
emergency watershed protection and rehabilitation activity may proceed immediately in
cases where there is an unacceptable hazard to life or a significant loss of property or
economic hardship will occur. The district engineer will consider any comments received
to decide whether the NWP 37 authorization should be modified, suspended, or revoked
in accordance with the procedures at 33 CFR 330.5.
(4) In cases of where the prospective permittee is not a Federal agency, the
district engineer will provide a response to NMFS within 30 calendar days of receipt of
any Essential Fish Habitat conservation recommendations, as required by section
305(b)(4)(B) of the Magnuson-Stevens Fishery Conservation and Management Act.
5) Applicants are encouraged to provide the Corps with either electronic files or
multiple copies of pre- construction notifications to expedite agency coordination.
Further Information
1. District Engineers have authority to determine if an activity complies with the terms
and conditions of an NWP.
2. NWPs do not obviate the need to obtain other federal, state, or local permits,
approvals, or authorizations required by law.
3. NWPs do not grant any property rights or exclusive privileges.
4. NWPs do not authorize any injury to the property or rights of others.
5. NWPs do not authorize interference with any existing or proposed Federal project
(see general condition 31).
Effective 19 March 2017
2017 NATIONWIDE PERMITS
REGIONAL CONDITIONS
OMAHA DISTRICT
STATE OF MONTANA
1. PCN Requirement. For all NWPs, permittees must notify the Corps in
accordance with General Condition No. 32 (PCN) for regulated activities, located
within or comprised of the following:
a. Wetlands Classified as Peatlands. Peatlands are seasonally waterlogged
areas with a surface accumulation of peat (organic matter) 30 centimeters (12
inches) or more thick. Any peat-covered areas, including fens, bogs, and
muskegs, are all peatlands.
i. PCN required for NWP 3, 5, 6, 20, 27, 32, and 38.
ii. All NWPs not listed above are revoked for use in peatlands.
b. Waters Adjacent to Natural Springs. Any projects located within 100 feet of
the water source in natural spring areas. A spring is defined as any location
where there is groundwater flow emanating from a distinct point. Springs do
not include seeps or other groundwater discharge areas where there is no
distinct point source.
c. Bank Stabilization Activities. Any project that involves bank stabilization
greater than 300 linear feet or includes features that extend out from the
existing bank line greater than 25% of the bankfull channel width.
d. Channel Straightening and Relocation Activities. Any project that involves
straightening, relocating and/or shortening an existing perennial stream
channel.
e. Tribal Reservations and Tribal Trust Lands. Any projects within the
boundaries of any Tribal Reservation or Tribal trust lands.
f. Specific Waterways Requiring PCN. Any projects within the following
waterways and their impoundments:
-Bitterroot River -Flathead Lake
-Clark Fork River (tributary to the -Milk River
Columbia River) -Missouri River
-Flathead River -Yellowstone River
2. Bank and Shoreline Stabilization Activities. The following additional
requirements apply to all bank and shoreline stabilization:
a. The revetment must conform to the existing bankline; must not extend above
the top of the bank (i.e. no new levees); and the slopes must be flatter than
the angle of repose for the selected revetment material (i.e. rock riprap
normally needs to be placed on a slope flatter than 1.5 Horizontal to 1 Vertical
Effective 19 March 2017
(1.5H:1V).
b. The revetment must not wholly or partially block flows from entering a side
channel or an overflow channel.
3. Counter-Sinking Riprap Associated with Culvert Installation. When riprap
inlet and outlet protection is used below the OHWM (OHWM), it must be placed
to match the adjacent culvert bottom elevations. Where culvert bottom elevations
are lower than the stream bed elevation, the riprap must match the culvert
elevation.
4. Placement and Removal of Temporary Fills. Temporary fills in wetlands must
be placed on a horizontal marker layer, such as fabric or certified weed-free
straw, to delineate the pre-project ground elevation and facilitate complete fill
removal and site restoration.
5. Erosion and Sediment Control Blanket. All erosion control blanket or fabric
used in or adjacent to waters of the U.S. must be comprised of degradable
material to ensure decomposition. Do not use material that includes stabilized
netting or stabilized open mesh, as these products take a long time to degrade
and they can trap small animals, birds, amphibians and fish. This prohibition also
applies to mesh materials used for wattles, rolled materials, and bank wraps.
Erosion control blanket or fabrics that break down within 24 months are
acceptable. Non-degradable blankets or fabric may be allowed on a case-specific
basis if it will be buried beneath riprap or structures and it is not likely to be
exposed. Non-degradable blanket or fabric that becomes exposed within waters
of the U.S. must be removed.
6. Suitable Material. NWP General Condition No. 6 prohibits the use of unsuitable
material. Specific criteria can be found in the Omaha District’s “Generic
Prohibitions Regarding the Use of Certain Materials as Fill in Waters of the United
States” and MT Department of Environmental Quality’s (DEQ) “Specifications for
use of Concrete Riprap for Streambank Stabilization,” which apply to proposed
work in jurisdictional waters.
REGIONAL CONDITIONS APPLICABLE TO SPECIFIC NATIONWIDE PERMITS
7. NWP-3 – Maintenance and NWP-45 – Repair of Uplands Damaged by
Discrete Events. The definition of “discrete event,” as used in these permits,
includes, but is not limited to, unexpected natural and human-caused events
such as fires, storms, landslides, avalanches, earthquakes, accidents, debris or
ice jams, and floods. For the purpose of the NWPs, discrete event floods are
stream flow events that overflow the OHWM.
8. NWP-7 – Outfall Structures and Associated Intake Structures and NWP-12 –
Utility Line Activities. Inlet screens for intakes in the Yellowstone River or the
Missouri River in Blaine, Chouteau, Custer, Dawson, Fergus, Garfield, McCone,
Effective 19 March 2017
Petroleum, Phillips, Prairie, Richland, Roosevelt, Valley and Wibaux Counties
must be installed on all pump intakes with a screen mesh opening size no larger
than 0.25 inch. Water intake velocities must not exceed 0.5 foot per second
through the mesh. Intakes must be located in the deepest water available and be
elevated off the bottom of the river bed.
REGIONAL CONDITIONS APPLICABLE ONLY TO THE SPECIAL RIVER
MANAGEMENT ZONE OF THE UPPER YELLOWSTONE RIVER
Special River Management Zone (SRMZ) of the Upper Yellowstone River is defined
within the Special Area Management Plan (SAMP) as the 48-mile reach of the upper
Yellowstone River (River Miles 531.8 to 483.6) from upstream of Emigrant River
downstream to a few miles below the Shields River and Mission Creek confluences (0.7
miles downstream from the bridge at the community of Springdale). It includes
secondary channels, side channels, and the main (primary) channels, and adjacent
wetlands within the channel migration zone (CMZ) or, in absence of a CMZ, within
areas flooded by the 100-year discharge. The SMRZ is located entirely within Park
County.
In addition to Regional Conditions 1 through 8, the following Regional Conditions 9
through 24 apply within the SRMZ described above:
9. SRMZ – Notification – All NWPs. Permittees must notify the Corps in
accordance with General Condition No. 32 (PCN) for any regulated activity in
waters of the U.S. within the SRMZ. This includes all activities within the
Yellowstone River, the portions of tributaries within the SRMZ, and wetlands
within the SRMZ.
10. SRMZ – Emergency Work. Activities requiring a Department of the Army (DA)
Permit that is necessary to prevent imminent loss of life or property is allowed
within the SRMZ. Contact the Corps as soon as reasonably possible by
telephone at 406-441-1375 and/or by Fax at 406-441-1380. Contact may also be
made in person or by sending an e-mail to: CENWO.ODRMT@usace.army.mil.
All such work will be fully reviewed under the SAMP provisions.
11. SRMZ - NWPs Revoked for Use. The following NWPs have been revoked for all
waters and activities within the 48-mile SRMZ:
NWP 17 - Hydropower Projects
NWP 21 - Surface Coal Mining Activities
NWP 29 - Residential Developments
NWP 39 - Commercial and Institutional Developments
NWP 42 - Recreational Facilities
NWP 43 - Stormwater Management Facilities
NWP 44 - Mining Activities
NWP 45 - Repair of Uplands Damaged by Discrete Events
NWP 49 - Coal Remining Activities
Effective 19 March 2017
NWP 50 - Underground Coal Mining Activities
12. SRMZ – Activities Requiring Individual Permit Review. The following project
activities are not authorized under a NWP in the SRMZ. These projects typically
have more than minimal adverse impacts and must be reviewed under standard
(individual) permit procedures.
a. New dams, new diversions, and/or new impoundments for any purpose;
b. Construction of ponds and new artificial stream channels, unless they are
necessary and appropriate elements of a stream or wetland restoration
project;
c. Hydraulic dredging and mining and mechanical excavation to obtain
aggregate, fill material, or minerals, including gold. Processing of material for
the purpose of obtaining select minerals or a specific gradation of material,
where only a portion of the sediment or alluvium is removed and the
remainder returned to the SRMZ, is not allowed under a NWP in the SRMZ.
13. SRMZ - Bank Stabilization Activities - All NWPs. For bank stabilization
activities associated with any NWP, including maintenance of bank stabilization,
the following Regional Conditions apply:
For bank revetments such as riprap, root wads, bioengineered revetments, or
combination revetments, a. through e. apply:
a. Revetments must conform to the existing eroded or eroding bankline, unless
such work is determined by the Corps to be biologically or geomorphically
beneficial for the upper Yellowstone River.
b. Revetment slopes must be flatter than the angle of repose for the selected
revetment material. For example, rock riprap normally needs to be placed on
a slope flatter than 1.5H:1V.
c. Revetments are only permittable under NWPs if they are parallel to and near
the lateral boundaries of the SRMZ.
d. Revetments must not extend above the elevation of the adjacent natural bank
height (i.e., no new levees).
e. Revetments must not wholly or partially block flows from entering a side
channel, secondary channel, or an overflow channel, unless such work is
determined by the Corps to be necessary for maintaining or restoring the
geomorphic integrity of the upper Yellowstone River.
For bank stabilization structures that project into the stream, such as weirs,
barbs, vanes, or hard points, f. through k. apply:
f. Bank stabilization structures must not wholly or partially block flows from
entering a side channel, secondary channel, or an overflow channel, unless
such work is determined by the Corps to be necessary for maintaining or
restoring the geomorphic integrity of the upper Yellowstone River.
Effective 19 March 2017
g. Bank stabilization structures are only permittable under NWPs if they result in
an effective bankline that is approximately parallel to and near the lateral
boundaries of the CMZ.
h. Bank stabilization structures must be keyed into the bank far enough to prevent
flanking.
i. Bank stabilization structures cannot occupy more than 10% of the bankfull
channel area. Bankfull channel area pertains to the specific primary or
secondary channel in question, and is not the aggregate channel area of all
primary and secondary channels in multi-channel reaches.
j. Bank stabilization structures must not present hazardous obstructions to
boating, floating, or other river uses.
k. Bank stabilization structures that are low in elevation, project only a short
distance out from the bank, and angle upstream are more likely to qualify for
NWPs because they typically result in less adverse impact on aquatic
resources than structures that are tall, long, and point downstream.
14. SRMZ – Temporary Bank Stabilization – All NWPs. Temporary bank
stabilization is prohibited during seasonal high flows.
15. SRMZ – Sediment Management – All NWPs. Sediment removal is allowable
only to maintain function of existing facilities and structures, or as necessary to
maintain or restore the geomorphic integrity of the upper Yellowstone River.
Diversion or removal of sediment or alluvium from the river channel and adjacent
wetlands for other purposes is not allowed in the SRMZ under any NWP.
16. SRMZ – Temporary Vegetation Impacts – All NWPs. Limit clearing of riparian
or wetland vegetation to the absolute minimum necessary. Where temporary
riparian or wetland vegetation impacts are unavoidable, mow or cut off the
vegetation above the ground, leaving the topsoil and root mass intact. Restore
temporarily disturbed areas to original contours and use seeding and planting as
necessary to re-establish desirable vegetative cover, utilizing native species in
areas where native species were impacted.
17. SRMZ – NWP-11 – Temporary Recreational Structures. Temporary
recreational structures can be installed no earlier than seven (7) calendar days in
advance of an event and must be removed no later than seven (7) calendar days
after the event concludes.
18. SRMZ – NWP-12 – Utility Line Activities. Trench excavation and backfill for
utility lines is prohibited within the OHWM of main and secondary flow channels
and in adjacent wetlands.
19. SRMZ – NWP-13 – Bank Stabilization. Construction of temporary or permanent
levees is prohibited. Only bank stabilization that is parallel to and adjacent to the
valley wall and/or SRMZ boundary is allowed. All other bank stabilization must be
reviewed under standard (individual) permit procedures. Bank stabilization along
Effective 19 March 2017
existing roads, ditches, fills, and structures already located along the valley wall
is allowed under this Permit.
20. SRMZ – NWP-14 – Linear Transportation Projects. The construction of new
transportation facilities in waters of the U.S. is prohibited under this NWP and
must be reviewed under standard (individual) permit procedures. The expansion,
modification, improvement, replacement, reconstruction, and upgrading of
existing transportation facilities are allowed under this NWP within the SRMZ.
21. SRMZ – NWP- 27 – Aquatic Habitat Restoration, Establishment, and
Enhancement Activities. The construction of water control structures, dikes,
berms, current deflectors, bank stabilization, and ponds is prohibited within the
CMZ of the upper Yellowstone River unless it is demonstrated the proposed
features contribute to the restoration or rehabilitation of previously lost or
impaired functions of the upper Yellowstone River and adjacent aquatic areas.
22. SRMZ – NWP-30 – Moist Soil Management for Wildlife. Fire breaks within the
CMZ of the upper Yellowstone River must be reclaimed and restored within six
(6) months after the fire event ends.
23. SRMZ – NWP-33 – Temporary Construction, Access, and Dewatering.
Construction of temporary levees and other structures or fills in waters of the
U.S. that prevent or reduce overbank flow is prohibited.
24. SRMZ – NWP 40 – Agricultural Activities. Only those activities associated with
the reduction of existing adverse impacts on the upper Yellowstone River may be
authorized by this NWP. Examples of potentially allowable projects include work
associated with livestock management; moving livestock watering areas off the
river or out of the CMZ; removal of irrigation systems from the CMZ; and the
removal or conversion of irrigation systems from flood irrigation to sprinkler
irrigation.