Randy Visser
From:Walker, Craig <cwalker@mt.gov>
Sent:Thursday, April 15, 2021 7:49 AM
To:R Hudock
Cc:Randy Visser
Subject:RE: Peach & Rouse Project
Ryan,
This is accurate. We will be finishing the sidewalk along Peach in the next couple of weeks. We also have the approach to
complete and the pad for the garbage can structure to complete. If you can meet me at this location either today or
tomorrow, I can show you what we still need to complete.
Craig Walker
Engineering Project Manager
Montana Department of Transportation
100 Nelson Rd.
Po Box: 3028
Bozeman, MT 59772-3028
(406)556-4724 / office
(406)498-2785 / cell
cwalker@mt.gov
zero deaths | zero serious injuries
From: R Hudock <rhudock@chengineers.com>
Sent: Wednesday, April 14, 2021 2:09 PM
To: Walker, Craig <cwalker@mt.gov>
Cc: Randy Visser <randy@visserarchitects.net>
Subject: [EXTERNAL] Peach & Rouse Project
Hi Craig,
Thanks for the call back today. To re-iterate what we discussed, the sidewalk along Rouse is part of the MDT scope of
work and had recently been installed. The sidewalk along Peach Street (extending westward from Rouse) is also part of
the MDT scope. The Peach Street sidewalk will be installed up to the box culvert at Bozeman Creek and will be done by
the MDT over the next several weeks.
Would you be able to confirm that this is accurate? Thanks for taking the time to help us out!
2
Best,
Ryan Hudock, P.E.
www.chengineers.com [chengineers.com]
"This message and/or attachment contains confidential information. Distribution of this
information must be only to those of C&H Engineering and Surveying, Inc employees or
individuals contractually approved to receive this information. If you are not the
addressee and/or are not authorized to receive this for the addressee, you must not use,
copy, disclose,forward, print or take any action based on this message or any information
herein. If you have received this message in error, please advise the sender immediately
by reply e-mail and delete this message."