HomeMy WebLinkAbout012_Construction Staging PlanTRAIL EASEMENT25' - 0"BRIDGER VIEW
CONNECTION TO EXISTING
TRAIL AT FLANDER'S MILL
PRE-MANUFACTURED
PEDESTRIAN BRIDGE;
RE: LANDSCAPE
SPANISH PEAKS VIEW10' WIDE ASPHALT
SHARED USE PATH
PAVED PEDESTRIAN BIKE TRAIL
(EXISTING)
BENCH
CONNECTION TO TRAIL
FOR TRAIL MAINTANENCE
DURSTON ROAD FERGUSON AVEKimball AveFlander's Mill Subdivision
Christ the King
Lutheran Church ACCESS EASEMENT60' - 0"FLEXIBLE
LAWN
SPACE
BB
COURT
SNOW | RETENTIONFULL
ACCESS
OFFICES
MINISTRY
CENTER
UTILITY EASEMENT
20' - 0"UTILITY EASEMENT20' - 0"4
10 11
11 11
6
8
8 8
UTILITIES VISION TRIANGLEUTILITY EASEMENT10' - 0"CTK TRAIL EASEMENT
15' - 0"
STAFF
ENTRY
MAIN
ENTRY
Heritage Christian School
PARKING CALCULATIONS:
PHASE TWO:
A-3: CHURCH
Parking Requirement = 1 Stall per 6 persons of Max. Occ. Load
Main Assembly Space: 648 Occupants
Fellowship Hall: 171 Occupants
All Classrooms: 334 Occupants
MAX OCCUPANT LOAD = 1,153 Occupants
Required Phase Two Stalls: 1,153/6 = 192.1667 (193 Stalls)
Phase 2 Required Parking per UDO: 193 Stalls
Total Phase 2 Parking Provided: 191 Stalls (Additional Stalls provided in Phase 1)
Masterplan Parking Required per UDO: 51 + 193 = 244 Stalls
Total Masterplan Parking Provided: 86 + 191 = 277 Stalls
EXISTING WATER MAIN
EXISTING GAS LINE
EXISTING COMM. FIBER LINE
EXISTING COMM. CABLE LINE
NEW 8" WATER LINE
NEW SANITARY SEWER
MANHOLE
FIRE HYDRANT
50' - 0"
5 0 ' - 0 "
WA TE RC O U R S E S E T B AC K 7' - 0"ELECTRICAL
TRANSFORMER;
RE: ELECT.
JUNCTION CAN;
RE: ELECT.
80' - 8" ROLLDOWN CURB 80' - 8" ROLLDOWN CURB
10' - 0"
5' - 0"
NEW CONCRETE
SIDEWALK, CONNECT TO
EXISTING 5' SIDEWALK
26' - 0"42' - 0"26' - 0"TYP. UNO18' - 0"8' - 0" 72' - 0" 8' - 0"
TYP.
26' - 0"
820' - 0"SNOW | RETENTION SNOW | RETENTIONSD1.2
4
COLLECTOR // LANDSCAPE BLOCK FRONTAGEMINOR ARTERIAL // LANDSCAPE BLOCK FRONTAGE
EXISTING
STREET
LIGHTING
EXISTING
STREET
LIGHTINGEXISTING MANHOLE
AND TRAIL EASEMENT
10' - 0" UTILITY EASEMENT
TRAIL EASEMENT
25' - 0"
PROPOSED CROSSWALK CONNECTING TO
MEADOWLARK ELEMENTARY N-S SIDEWALK; RE: CIVIL
9' - 0"
TYP.
9' - 0"
CL
ALIGN CL OF
ACCESS W/
DIAMOND
STREET
MONUMENT
SIGN
SITE LIGHTING;
RE: ELECT.
GAGA
BALL
(9) BIKE RACKS
PHASE ONE:
A-3: COMMUNITY CENTER
Parking Requirement = 1 Stall per 200 SF
Area: 7,492 SF Gross
Required Stalls: 7,492/200 = 37.46 (38 Stalls)
B: OFFICE
Parking Requirement = 1 Stall per 250 SF
Area: 3,600 SF Gross
Required Stalls: 3,600/250 = 14.4 (15 Stalls)
Phase 1 Parking Required per UDO: 53 Stalls
Total Phase 1 Parking Provided: 85 Stalls
FIRE
HYDRANT50' - 0"30' - 0"42' - 0"
LANDSCAPING EXTENTS OF PHASE 1
5
SD1.2
Sim
STORMWATER RETENTION
SNOW RETENTIONSD1.2
1 Sim
WILLIAM A.
HANSON
1898
FOETATS MONT
A
N
AEMANZOB
T A N ANOM
A R C H IT ECTDES
N
ECIL
COPYRIGHT 2019
12/1/2021 10:40:37 AMSD1.0
Site Plan Review
12.1.21
1811TRINITY CHURCHMINISTRY CENTER701 North Ferguson Ave. Bozeman, MT 59718SITE PLAN -PHASE 11" = 40'-0"SD1.0
1 SITE PLAN_Phase 1 Extents
NORTH
ISSUE DATE DESCRIP.
Primary Construction
Entrance/Exit - FODS track Pad
Secondary Construction
Entrance/Exit - FODS track Pad
Construction Trailers
10x40 typical.
Construction Dumpsters &
Recycling Containers - 40 yard typ.
Staging & Laydown Areas. Active Spring
2022 thru summer 2023. Areas to be
phased according to construction activity.
Construction Traffic will access the site via
one of the two entrances from Ferguson Ave.
Construction Traffic will exit the site via one
of the two exits onto Ferguson Ave.
Site Security Fencing