Landscape Improvements Estimate
6/27/2022
DESCRIPTION QTY UNITS UNIT COST BASELINE COST IIL COST
PHASE 1 - PARK IMPROVEMENTS
Landscape & Material
Prep & Material Topsoil (Existing on Site)1333 CY $5.00 $6,666.67 -
Concrete Flatwork 550 SF $7.50 -$4,125.00
Crusher Fines Trail 470 LF $6.00 -$2,820.00
Fitness & Play Surfacing 1990 SF $4.50 -$8,955.00
Concrete Curb at Play 140 LF $20.00 -$2,800.00
All Round Washed Rock 200 SF $1.50 -$300.00
Landscape Boulders 45 EA $450.00 -$20,250.00
Boulders for Seatwalls 50 EA $450.00 -$22,500.00
Signage Signage - Posts/Totems 10 EA $350.00 $3,500.00 -
Signage - Primary 2 EA $3,500.00 $7,000.00 -
Landscape Deciduous Trees - Boulevard 32 EA $400.00 $12,800.00 -
Deciduous Trees 53 EA $400.00 -$21,200.00
Shrubs at Watercourse 21 EA $75.00 $1,575.00 -
Coniferous Trees 13 EA $800.00 -$10,400.00
Native Seed 50020 SF $0.30 -$15,006.00
Lawn & Boulevard Seed 72000 SF $0.30 $21,600.00 -
Irrigation Plant Material 122020 SF $1.25 $152,525.00 -
Well 1 Install + Power 1 EA $50,000.00 $50,000.00 -
Well 4 Install + Power 1 EA $50,000.00 $50,000.00 -
SubTotal $305,666.67 $108,356.00
Park 4 Improvements & Programming
Material Bridge - Freespan 1 EA $25,852.00 -$25,852.00
Bridge Install 1 EA $2,500.00 -$2,500.00
Play Areas Boulder Rock Dock 6 EA $450.00 -$2,700.00
Furnishings Pet Waste 1 EA $500.00 -$500.00
Bench 2 EA $1,685.00 -$3,370.00
SubTotal $0.00 $34,922.00
Park 12 Improvements & Programming
Material Play Berms Fill (Existing on Site)180 CY $5.00 -$900.00
Furnishings Pet Waste 2 EA $500.00 -$1,000.00
Picnic Table 8' 2 EA $4,000.00 -$8,000.00
Bike Racks 2 EA $250.00 -$500.00
Bench 2 EA $1,685.00 -$3,370.00
Fitness Station 1 EA $2,500.00 -$2,500.00
SubTotal $0.00 $16,270.00
Park 13 Improvements & Programming
Material Play Berms Fill (Existing on Site)150 CY $5.00 -$750.00
Play Equipment Balance & Stepping Logs 1 EA $5,800.00 -$5,800.00
Install & Freight 1 EA $2,200.00 -$2,200.00
Furnishings Pet Waste 1 EA $500.00 -$500.00
Bench 2 EA $1,685.00 -$3,370.00
Bike Racks 2 EA $250.00 -$500.00
Fitness Station 1 EA $2,500.00 -$2,500.00
SubTotal $0.00 $15,620.00
Park 14 Improvements & Programming
Material Play Berms Fill (Existing on Site)450 CY $5.00 -$2,250.00
Play Equipment Log Fort Timber Materials 1 EA $2,900.00 -$2,900.00
Single Swing 1 EA $4,850.00 -$4,850.00
Pony Springer 1 EA $2,260.00 -$2,260.00
Install & Freight 1 EA $1,000.00 -$1,000.00
Furnishings Pet Waste 1 EA $500.00 -$500.00
Bench 3 EA $1,685.00 -$5,055.00
Bike Racks 2 EA $250.00 -$500.00
Trash 1 EA $250.00 -$250.00
Fitness Station 1 EA $2,500.00 -$2,500.00
Square Picnic Table 2 EA $3,000.00 -$6,000.00
SubTotal $0.00 $28,065.00
Park 15 Improvements & Programming
Material Play Berms Fill (Existing on Site)230 CY $5.00 -$1,150.00
SubTotal $0.00 $1,150.00
Park 16 Improvements & Programming
Furnishings Pet Waste 1 EA $500.00 -$500.00
SubTotal $0.00 $500.00
PHASE 1 TOTALS
Baseline IIL
$305,666.67 $204,883.00
Park Improvements Total $510,549.67
City Required Parkland IIL (Based on $2.07/SF)$113,774.16
1
Blackwood Groves
Landscape Improvements Estimate
6/27/2022
DESCRIPTION QTY UNITS UNIT COST BASELINE COST ILL COST
PHASE 2 - PARK IMPROVEMENTS
Phase 1 Additional Improvements
Park 4 Signage Signage - Primary 1 EA $3,500.00 $3,500.00 -
Signage - Posts/Totems 1 EA $350.00 $350.00 -
Park 12 Signage Signage - Primary 0 EA $3,500.00 $0.00 -
Signage - Posts/Totems 2 EA $350.00 $700.00 -
Park 13 Signage Signage - Primary 0 EA $3,500.00 $0.00 -
Signage - Posts/Totems 2 EA $350.00 $700.00 -
Park 14 Signage Signage - Primary 0 EA $3,500.00 $0.00 -
Signage - Posts/Totems 2 EA $350.00 $700.00 -
Park 15 Signage Signage - Primary 0 EA $3,500.00 $0.00 -
Signage - Posts/Totems 2 EA $350.00 $700.00 -
Park 16 Signage Signage - Primary 1 EA $3,500.00 $3,500.00 -
Signage - Posts/Totems 1 EA $350.00 $350.00 -
SubTotal $10,500.00 $0.00
Landscape & Material
Prep & Material Topsoil (Existing on Site)746 CY $5.00 $3,731.48 -
Concrete Flatwork 190 SF $7.50 -$1,425.00
Crusher Fines Trail 665 LF $6.00 -$3,990.00
Fitness Station Surfacing 615 SF $4.50 -$2,767.50
Concrete Curb at Fitness 91 LF $20.00 -$1,820.00
All Round Washed Rock 1550 SF $1.50 -$2,325.00
Boulders for Seatwalls 52 EA $450.00 -$23,400.00
Signage Signage - Posts/Totems 5 EA $350.00 $1,750.00 -
Signage - Primary 2 EA $3,500.00 $7,000.00 -
Landscape Deciduous Trees - Boulevard 27 EA $400.00 $10,800.00 -
Deciduous Trees 101 EA $400.00 -$40,400.00
Coniferous Trees 3 EA $800.00 -$2,400.00
Native Seed 54075 SF $0.30 -$16,222.50
Lawn & Boulevard Seed 40300 SF $0.30 $12,090.00 -
Irrigation Plant Material 94375 SF $1.25 $117,968.75 -
SubTotal $153,340.23 $94,750.00
Park 9 Improvements & Programming
Material Play Berms Fill (Existing On Site)400 CY $5.00 -$2,000.00
Furnishings Pet Waste 1 EA $500.00 -$500.00
SubTotal $0.00 $2,500.00
Park 10 Improvements & Programming
Material Dog Park Fencing 735 LF $65.00 -$47,775.00
Furnishings Bike Racks 2 EA $250.00 -$500.00
Pet Waste 2 EA $500.00 -$1,000.00
Bench 4 EA $1,685.00 -$6,740.00
Fitness Station 1 EA $2,500.00 -$2,500.00
SubTotal $0.00 $58,515.00
Park 11 Improvements & Programming
Material Play Berms Fill (Existing on Site)350 CY $5.00 -$1,750.00
Furnishings Pet Waste 2 EA $500.00 -$1,000.00
Bike Racks 2 EA $250.00 -$500.00
Bike Ramp Features & Install 1 EA $13,905.00 -$13,905.00
Fitness Station 1 EA $2,500.00 -$2,500.00
SubTotal $0.00 $19,655.00
PHASE 2 TOTALS
Baseline IIL
$163,840.23 $175,420.00
Park Improvements Total $339,260.23
City Required Parkland IIL (Based on $2.30/SF)$390,106.68