HomeMy WebLinkAbout23- Project Specificationsi
(MPWSS) – Montana Public Works Standard Specifications
PROJECT SPECIFICATIONS
STORY MILL ROAD LANDFILL, BOZEMAN, MONTANA
2023 LFG AND LEACHATE / CONDENSATE SYSTEM IMPROVEMENTS REBID
BIDDING REQUIREMENTS, CONTRACT FORMS AND CONDITIONS OF THE
CONTRACT
00100 Invitation to Bid
00200 Instructions to Bidders
00300 Bid Form
EJCDC C-430 Bid Bond
00500 Agreement Form
EJCDC C-610 Performance Bond
EJCDC C-615 Payment Bond
EJCDC C-700 Standard General Conditions of the Construction Contract
00810 Supplementary Conditions to the General Conditions
DIVISION 1 – GENERAL REQUIREMENTS
01010
01029
01030
01041
01050
01052
01095
01300
01310
01410
01500
01570
01620
01630
01700
01710
Summary of Work
Measurement and Payment
Special Instructions
Coordination (MPWSS)
Field Engineering
Layout of Work and Surveys
Definitions and Standards
Submittals
Construction Work Plan and Schedule
Quality Assurance Testing, Quality Control Testing
Temporary Facilities and Controls (MPWSS)
Traffic Control (MPWSS)
Transportation, Handling, and Storage
Product Options and Substitutions
Contract Close-Out (MPWSS)
Final Cleaning
Nondiscrimination and Equal Pay Affirmation
EJCDC C942 Field Order
EJCDC C625 Certificate of Substantial Completion
Work Change Directive
Change Order Form
Order to Contractor to Suspend Work
Order to Contractor to Resume Work
Montana Prevailing Wage Rates
ii
(MPWSS) – Montana Public Works Standard Specifications
PROJECT SPECIFICATIONS
STORY MILL ROAD LANDFILL, BOZEMAN, MONTANA
2023 LFG AND LEACHATE / CONDENSATE SYSTEM IMPROVEMENTS REBID
DIVISION 15 – MECHANCIAL AND PLUMBING
15010
15100
15900
General Piping Specifications
High Density Polyethylene Piping
Pressure Testing of Pipe
Structures (MPWSS)
Trench Excavation and Backfill for Pipelines and Appurtenant 02221
DIVISION 2 – SITE WORK
CITY OF BOZEMAN, MONTANA
C A L L F O R B I D S
NOTICE IS HEREBY GIVEN that the City of Bozeman, Montana, is accepting sealed bids for:
2023 LFG and Leachate/Condensate System Improvements Rebid
The City of Bozeman will receive online electronic sealed Bids for Construction of the 2023
LFG and UST System Improvements Project until 2:00 p.m. (local time) on February 8, 2023,
and then publicly opened and read aloud.
Project Description: Installation of three Landfill Gas (LFG) wells, providing and installing
buried piping for transmission of LFG gas to the existing gas handling system, providing, and
installing buried pipeline for transmission of leachate/condensate, and removal of an existing UST
as specified in the contract documents.
For this project, bids will only be received and accepted via the online electronic bid service
through QuestCDN. A contractor may view the contract documents at no cost prior to becoming a
Planholder. Project bid documents and addenda must be downloaded from QuestCDN, which will
add your company to the Planholder List and allow access to vBid online bidding, for the submittal
of your bid. QuestCDN may be located using the link in the left-hand navigation menu on the City
of Bozeman’s Bids\RFPs\RFQs page or at www.bozeman.net/QuestCDN. The specific project
can be found by referencing the eBidDoc number (eBidDoc #8371550). Plans may be
downloaded for a non-refundable charge of $15.00. Bidders will be charged an additional fee of
$30.00 to submit a bid electronically. Contact QuestCDN Customer Support at
952-233-1632 or info@questcdn.com for assistance in membership registration,
downloading digital project information and vBid online bid submittal.
There will be a Pre-Bid Conference at 2:00 p.m. on February 1, 2023. Interested
CONTRACTORS are encouraged to attend and should email Cody Flammond
at cflammond@bozeman.net for a meeting invitation.
CONTRACTOR and any of the CONTRACTOR’S subcontractors bidding or doing work on this
project will be required to be registered with the Montana Department of Labor and Industry (DLI).
Forms for registration are available from the DLI, PO Box 8011, 1805 Prospect, Helena, Montana
59604-8011. Information on registration can be obtained by calling (406) 444-7734.
CONTRACTOR is not required to have registered with the DLI prior to bidding on this project
but must have registered prior to execution of the Construction Agreement. All laborers and
mechanics employed by CONTRACTOR or subcontractors in performance of the construction
work shall be paid wages at rates as may be required by the laws of Gallatin County and the state
of Montana. Discrimination in the performance of any agreement awarded under this project on
the basis of race, color, religion, creed, sex, age, marital status, national origin, or actual or
perceived sexual orientation, gender identity or disability is prohibited. This prohibition shall apply
to the hiring and treatment of the awarded entity’s employees and to all subcontracts.
INVITATION TO BID
Page 1 of 2
As such, each entity submitting under this notice shall include a provision wherein the submitting
entity, or entities, affirms in writing it will not discriminate on the basis of race, color, religion,
creed, sex, age, marital status, national origin, or because of actual or perceived sexual orientation,
gender identity or disability and which also recognizes the eventual contract will contain a
provision prohibiting discrimination as described above and that this prohibition on discrimination
shall apply to the hiring and treatment of the submitting entity’s employees and to all subcontracts.
In addition, pursuant to City Commission Resolution 5169, the entity awarded a contract under
this project and any subcontractors must abide by the Equal Pay Act of 1963 and Section 39-3-
104, MCA (the Montana Equal Pay Act), and affirm it will abide by the above and that it has
visited the State of Montana Equal Pay for Equal Work “best practices” website,
https://equalpay.mt.gov/BestPractices/Employers, or equivalent “best practices publication and
has read the material.
Each Bid or proposal must be accompanied by a Certified Check, Cashier’s Check, or Bid Bond
payable to the City of Bozeman, Montana, in an amount not less than ten percent (10%) of the
total amount of the Bid. Successful BIDDERS shall furnish an approved Performance Bond and a
Labor and Materials Payment Bond, each in the amount of one hundred percent (100%) of the
contract amount. Insurance as required shall be provided by the successful BIDDER(s) and a
certificate(s) of that insurance shall be provided.
No Bid may be withdrawn after the scheduled time for the public opening of bids.
BIDDERS should email Cody Flammond at cflammond@bozeman.net for a meeting invitation to
the bid opening.
The City of Bozeman reserves the right to reject any or all proposals received, to waive
informalities to postpone the award of the contract for a period not to exceed sixty (60) days, and
to accept the lowest responsive and responsible bid which is in the best interest of the City
of Bozeman.
The Contractor is required to be an Equal Opportunity Employer.
DATED at Bozeman, Montana, this 12th day of January 2023.
Mike Maas,
Bozeman City Clerk
Published Legal Ad, Bozeman, Montana
Sunday, January 22, 2023
Sunday, January 29, 2023
INVITATION TO BID
Page 2 of 2
Section 00200
INSTRUCTIONS TO BIDDERS
Page 1 of 9
SECTION 00200
INSTRUCTIONS TO BIDDERS
1.BIDS
a.The Bid Form included within the Bidding Documents is for reference only. The City of
Bozeman will only accept online electronic bids through QuestCDN. Project bid
documents and addenda must be downloaded from QuestCDN, which will add your
company to the Planholder List and allow access to vBid online bidding, for the submittal
of your bid. QuestCDN may be located using the link in the left-hand navigation menu on
the City of Bozeman’s Bids\RFPs\RFQs page or at www.bozeman.net/QuestCDN. The
specific project can be found by referencing the eBidDoc number provided above.
(eBidDoc #8371550) Bid documents are available for download for a non-refundable
charge of fifteen dollars ($15). Bidders will be charged an additional fee of thirty dollars
($30) to submit a bid electronically. For electronic bids, scans of required electronic bid
documents will be accepted. Bids shall be strictly in accordance with the prescribed form.
Any modifications thereof or deviations therefrom may be considered as sufficient cause
for rejection. Bids carrying riders or qualifications to the bid being submitted may be
rejected as irregular.
b.A bid shall be submitted no later than the date and time prescribed and as indicated in
the Invitation to Bid and shall be submitted online through QuestCDN. The bid shall
include the name and address of the Bidder and shall be accompanied by the Bid
Security, Nondiscrimination Affirmation Form, and other required documents.
c.Contract Documents may be viewed at the following locations:
City of Bozeman
20 East Olive
Bozeman, MT 59771
Phone: (406) 582-2200
2.BID SECURITY
The Bid must be accompanied by a Bid Security which shall not be less than 10 percent of the amount of
the bid. At the option of the Bidder, the security may be in the form of a cashier's check, certified check,
bank money order, or bank draft drawn and issued by a national banking association located in the State
of Montana or by any banking corporation incorporated under the laws of the State of Montana or Bid
Bond (EJCDC C-430) executed by a surety corporation authorized to do business in the State of Montana.
No bid will be considered unless it is accompanied by the required guaranty. Cashier's checks, certified
checks, bank money orders, or bank drafts must be made payable to the City of Bozeman. The Bid
Security shall insure the execution of the Agreement and the furnishing of the surety bond or bonds by the
successful Bidder, all as required by the Contract Documents.
Should the Bidder fail to furnish the properly executed Performance Bond, Labor and Material Payment
Bond, Insurance Certificates, and signed Agreement within the time specified, he/she shall forfeit this Bid
Security to the Owner. The Bid Security (negotiable instruments other than bonds) will be returned to un-
successful Bidders when the successful Bidder has signed the Agreement and furnished satisfactory
Performance and Labor and Material Payment Bonds. At the option of the Owner, bid security with bids
that are not competitive may be returned prior to signature of the Agreement.
Section 00200
INSTRUCTIONS TO BIDDERS
Page 2 of 9
Revised Bids submitted before the opening of bids, if representing an increase in the original bid, must
have the Bid Security adjusted accordingly; otherwise, the bid will not be accepted.
If the Bidder elects to furnish a Bid Bond, he shall use the Bid Bond form (EJCDC C-430)
bound herewith.
3.SUBSTITUTE AND “OR-EQUAL” ITEMS
The Contract, if awarded, will be on the basis of materials and equipment specified or described in the
Bidding Documents without consideration of possible substitute or “or-equal” items. Whenever it is
indicated in the Bidding Documents that a substitute or “or-equal” item of material or equipment may be
furnished or used by Contractor if acceptable to Engineer, application for such acceptance will not be
considered by Engineer until after the Effective Date of the Agreement.
4.INTERPRETATIONS AND/OR ADDENDA
All questions about the meaning or intent of the Contract Documents are to be directed to the Engineer.
Interpretations or clarifications considered necessary by the Engineer in response to such questions will
be issued by Addenda emailed to all parties recorded by QuestCDN as having downloaded the Bidding
Documents. Questions received less than ten days prior to the date for opening of Bids may not be
answered. Only questions answered by formal written Addenda will be binding. Oral and other
interpretations or clarifications will be without legal effect. It shall be the responsibility of the Bidder to
download such Addenda prior to submitting his online bid.
5.EXAMINATION OF CONTRACT DOCUMENTS AND CONDITIONS OF WORK SITE
a.It is the responsibility of each Bidder before submitting a Bid, to (a) examine the Contract
Documents thoroughly, (b) visit the site to become familiar with local conditions that
may affect cost, progress, performance or furnishing of the Work, (c) consider federal,
state and local Laws and Regulations that may affect cost, progress, performance or
furnishing of the Work, (d) study and carefully correlate Bidder's observations with the
Contract Documents, and (e) notify Engineer of all conflicts, errors or discrepancies in
the Contract Documents.
1.Each Bidder should visit the site of the proposed work and fully acquaint himself
with the existing conditions there relating to construction and labor and should fully
inform himself as to the facilities involved, and the difficulties and restrictions
attending the performance of the Contract. In submitting a bid for this project, the
Bidder is thereby acknowledging that he is capable of performing the specified work
on the site. The Bidder should thoroughly examine and familiarize himself with the
Drawings, Technical Specifications, and all other Contract Documents, and shall
verify the accuracy of the estimated quantities in the Bid Proposal. Failure to do so
will not relieve the successful Bidder of his obligations to carry out the provisions of
this Contract.
2.The submission of a Bid will constitute a representation of familiarization by the
Bidder. There will be no subsequent financial adjustment for lack of such
familiarization.
Section 00200
INSTRUCTIONS TO BIDDERS
Page 3 of 9
b.The Contractor may refer to the following for information regarding site conditions:
1.Those reports, if any, of explorations and tests of subsurface conditions at the site
which have been prepared by the Owner and are included as part of the Contract
Documents. Bidder may rely upon the accuracy of the technical data contained in
such reports but not upon the completeness thereof for the purposes of bidding or
construction.
2.Those drawings of physical conditions in or relating to the existing surface and
subsurface conditions which are at or contiguous to the site (except Underground
Facilities) which have been utilized by Engineer in preparation of the Contract
Documents. Bidder may rely upon the accuracy of the technical data contained in
such drawings but not upon the completeness thereof for the purposes of bidding or
construction.
c.Information and data reflected in the Contract Documents with respect to Underground
Facilities at or contiguous to the site is based upon information and data furnished to
Owner and Engineer by owners of such Underground Facilities or others, and Owner
does not assume responsibility for the accuracy or completeness thereof unless it is
expressly provided otherwise in the Special Provisions.
d.Provisions concerning responsibilities for the adequacy of data furnished to prospective
Bidders on subsurface conditions, Underground Facilities and other physical conditions,
and possible changes in the Contract Documents due to differing conditions appear in
Paragraphs 4.02 and 4.03 of the General Conditions.
e.Before submitting a Bid, each Bidder will, at Bidder's own expense, make or obtain any
additional examinations, investigations, explorations, tests and studies and obtain any
additional information and data which pertain to the physical conditions (surface,
subsurface and Underground Facilities) at or contiguous to the site or otherwise which
may affect cost, progress, performance or furnishing of the Work which Bidder deems
necessary to determine its Bid for performing and furnishing the Work in accordance
with the time, price and other items and conditions of the Contract Documents.
f.On request in advance, Owner will provide each Bidder access to the site to conduct such
explorations and tests as each Bidder deems necessary for submission of a Bid. Bidder
shall fill all holes, clean up and restore the site to its former condition upon completion of
such explorations.
g.The lands upon which the Work is to be performed, rights-of-way and easements for
access thereto are designated for use by Contractor in performing the Work. All
additional lands and access thereto required for temporary construction facilities or
storage of materials and equipment are to be provided by Contractor. Easements for
permanent structures or permanent changes in existing structures are to be obtained and
paid for by Owner unless otherwise provided in the Contract Documents.
h.The submission of a Bid will constitute representation by Bidder that Bidder has
complied with every requirement of this Article 4, that without exception the Bid is
premised upon performing and furnishing the Work required by the Contract Documents
and such means, methods, techniques, sequences or procedures of construction as may be
indicated in or required by the Contract Documents, and that the Contract Documents are
Section 00200
INSTRUCTIONS TO BIDDERS
Page 4 of 9
sufficient in scope and detail to indicate and convey understanding of all terms and
conditions for performance and furnishing of the Work.
6.TIME FOR RECEIVING BIDS
Bids received prior to the advertised time of opening will be securely kept sealed. The officer whose duty
it is to open them will decide when the specified time has arrived, and no bid received thereafter will be
considered.
7.OPENING OF BIDS
At the time for the opening of bids, the Owner will cause to be opened and publicly read aloud every bid
received within the time set for receiving Bids, irrespective of any irregularities therein, except bids that
do not contain either the bid bond or non-discrimination affirmation, which will not be read. Bidders and
other persons properly interested may be present, in person or by representative.
BIDDERS must email Cody Flammond at cflammond@bozeman.net for a meeting invitation to the
bid opening.
8.WITHDRAWAL OF BIDS
Bids may be withdrawn at any time prior to the scheduled closing time for the receipt of bids if through
written confirmation or in person. The Bid Security of any Bidder withdrawing his bid in accordance with
the foregoing conditions shall be returned promptly. No bids shall be withdrawn for a period of 60 days
after the scheduled closing time for receipt of bids.
9.METHOD OF AWARD
a.Award of the contract shall be to the lowest “responsible” Bidder whose total base
bid (if within the funds available) is the lowest “responsible” bid for the work.
b.If such lowest bid exceeds the budget, the Owner may reject all bids.
c.The Owner reserves the right to reject any or all bids or to waive any irregularity or
informality in any bid received. The Owner reserves the right to determine what
constitutes material and/or immaterial informalities and/or irregularities.
d.The Owner shall award such contract to the lowest “responsible” bidder (18-1-102
MCA). The term “responsible” does not refer to pecuniary ability only, or the ability to
tender sufficient performance and payment bonds. The term “responsible” includes, but is
not limited to:
1.Having adequate financial resources to perform the contract or the ability to
obtain them;
2.Being able to comply with the required delivery, duration, and performance schedule;
3.Having a satisfactory record of integrity and business ethics;
Section 00200
INSTRUCTIONS TO BIDDERS
Page 5 of 9
4.Having the necessary production, construction, technical equipment, and
facilities, and;
5.Having the technical skill, ability, capacity, integrity, performance, experience, lack
of claims and disputes, lack of actions on bonds, lack of mediations, arbitrations
and/or lawsuits related to construction work or performance, and such like.
e.Unless otherwise stated in the Special Provisions, all contracts will be awarded in
conformance with the laws of the State of Montana. Pursuant to Section 18-1-102,
Montana Code Annotated, the Owner, in awarding public contracts for construction,
repair, and public works of all kinds, shall award such contract to the lowest responsible
Bidder without regard to residency. However, a resident bidder must be allowed a
preference on a contract against the bid of any non-resident bidder from any state or
country that enforces a preference for resident bidders. The preference given to resident
bidders of this state must be equal to the preference given in the other state or country.
f.The Owner may make such investigations as it deems necessary to determine the ability
of the Bidder to perform the Work, and the Bidder shall furnish to the Owner all such
information and data for this purpose as the Owner may request. The Owner reserves the
right to reject any Bid if the evidence submitted by, or investigation of, such Bidder fails
to satisfy the Owner that such Bidder is properly qualified and responsible to carry out
the obligations of the Agreement and to complete the Work contemplated therein.
10.PRE-AWARD CONFERENCE
The Bidder submitting what appears to be the lowest “responsible” bid may be required to meet with the
Engineer prior to the award of the contract for the purpose of discussing pertinent details pertaining to the
proposed Work. The following points will be considered in particular:
a.The Contractor's organization and equipment available for work and the Contractor's
proposed sources of materials or installed equipment.
b.Contractor's financial status and capability to execute the contract.
c.The Contractor's proposed schedule of operations.
d.The interpretation of the Specifications.
e.The Contractor's proposed wage rates for use on the project.
f.Bidder status concerning “responsibility”.
g.Approval of subcontractors.
h.Unbalanced bids, either in excess or below the reasonable cost analysis value.
Should the conference indicate that the Contractor does not appear to be in a position to properly
undertake the Work or that he has not properly familiarized himself with the Plans and Specifications, the
Owner reserves the right to reject the bid of this Contractor and to consider the next Bidder.
Section 00200
INSTRUCTIONS TO BIDDERS
Page 6 of 9
11.EXECUTION OF AGREEMENT
a.Subsequent to the award and within 10 days after the date of the Notice of Award, the
successful Bidder shall execute and deliver to the Owner an Agreement, the Performance
Bond, Labor and Material Payment Bond, Insurance Certificates, and an Approval of
Subcontractors form in such number of copies as the Owner may require. The standard
Agreement form as issued by the Owner shall be used as the contracting instrument.
b.The Agreement form shall be signed in longhand by the proper representatives of the
contracting firm as follows:
1.The principal of the single-owner firm.
2.A principal of the partnership firm.
3.An officer of the incorporated firm, or an agent whose signature is accompanied by a
certified copy of the resolution of the Board of Directors authorizing the agent
to sign.
4.Other persons signing for a single-owner firm or a partnership shall attach a Power of
Attorney evidencing his authority to sign for that firm.
c.The Owner within 30 days of receipt of acceptable Performance Bond, Labor and
Material Payment Bond, required Insurance Certificates, and Agreement signed by the
party to whom the Agreement was awarded shall sign the Agreement and return to such
party an executed duplicate of the Agreement. Should the Owner not execute the
Agreement within such period, the Bidder may by written notice withdraw his signed
Agreement. Such notice of withdrawal shall be effective upon receipt of the notice by
the Owner.
12.PERFORMANCE, LABOR AND MATERIAL PAYMENT BONDS AND INSURANCE
a.The Owner will require the successful Contractor to furnish a Performance Bond (EJCDC
C-610) in the amount of 100 percent of the contract price as security for the faithful
performance of his Contract.
b.The Owner will require the successful Contractor to furnish a Labor and Material Payment
Bond (EJCDC C-615) in the amount of 100 percent of the contract price as security for the
payment of all persons performing labor and furnishing materials in connection therewith.
c.The bonds will be signed by the Attorney-in-fact and countersigned by a Montana
Resident Agent.
d.Prior to beginning work, Insurance Certificates as proof of insurance coverage shall be
filed with the Owner. The specifications for the Workers' Compensation, Commercial
General Liability, Separate Owner's and Contractor's Protective Policy, and other related
insurance are listed in these Contract Documents.
Section 00200
INSTRUCTIONS TO BIDDERS
Page 7 of 9
13.POWER OF ATTORNEY
a.Attorneys-in-fact who sign bid bonds or contract bonds must file with each bond a
certified and effectively dated copy of their Power of Attorney.
b.One original shall be furnished with each set of bonds.
c.Additional copies furnished with a set of bonds may be copies of that original.
14.LABOR AND WAGES
a.For public projects in excess of $25,000 let, the Contractor(s) shall pay the standard
prevailing rate of wages, including fringe benefits for health and welfare and pension
contributions and travel allowance provisions in effect and applicable in the county or
locality in which the work is being performed (18-2-403, Montana Code Annotated).
b.On any state construction project funded by state or federal funds, except a project
partially funded with federal aid money from the United States Department of
Transportation or when residency preference laws are specifically prohibited by federal
law and to which the state is a signatory to the construction contract, each Contractor
shall ensure that at least 50 percent of the Contractor’s workers performing labor on the
project are bona fide Montana residents, as defined in 18-2-401, (18-2-409, MCA).
c.Montana Prevailing Wage Rates. The Montana Commissioner of Labor and Industry has
established the standard prevailing rate of wages in accordance with 18-2-401 and
18-2-402, Montana Code Annotated. A copy of the wage rates is bound herein. It is the
Contractor’s responsibility to classify their workers in accordance with the craft of trade
to be performed and pay the appropriate established prevailing wage rate.
d.The Contractor shall classify all workers on the project in accordance with the
Department of Labor Wage Rate Determinations. In the event the Contractor is unable to
classify a worker in accordance with these rates, the Contractor shall contact the
Department of Labor and Industry, Labor Standards Bureau, Wage and Hour Unit,
Helena, Montana 59604, for a determination of the prevailing wage rate to be paid that
particular worker.
e.Should the prevailing rate of wages change during the life of the contract, the wage rates
included in the Contract Documents at the time of the bid opening shall be the prevailing
wage rate for the life of the contract.
f.Section 18-2-406, Montana Code Annotated, provides that Contractors, subcontractors,
and employers who are performing services under public works contracts as provided in
this part shall post in a prominent and accessible site on the project or work area, not later
than the first day of work, a legible statement of all wages and fringe benefits to be paid
to employees on such site or work area.
g.Travel allowance, if applicable, may or may not be all-inclusive of "travel" and/or
subsistence and travel time due employees. It is incumbent on the employer to determine
the amounts due for each craft employed according to the method of computation
outlined for each craft where applicable.
Section 00200
INSTRUCTIONS TO BIDDERS
Page 8 of 9
h.Any notice of infraction of the labor laws of the State of Montana received by the Owner
or Engineer will be forwarded to the State of Montana, Department of Labor and
Industry, Wage and Hour Unit, Helena, Montana.
i.Safety Training. Contractor shall comply with the Occupational Safety and Health
Act (OSHA).
15.EQUAL EMPLOYMENT OPPORTUNITY
Attention of Bidders is particularly called to the requirement for ensuring that employees and applicants
for employment are not discriminated against because of their race, color, religion, national origin, sex,
marital status, age, or political ideas. The Owner is an equal opportunity employer.
16.MONTANA CONTRACTOR'S TAX (GROSS RECEIPTS TAX)
All Bidders are reminded that a Gross Receipts Tax in the amount of 1 percent of the total bid will
be withheld from all payments, for projects over $5,000.00, due to Contractor pursuant to
Section 15-50-205, MCA.
17.PAYROLLS AND BASIC RECORDS
Payrolls and basic records relating thereto shall be maintained by the Contractor during the course of the
work and preserved for a period of three years thereafter for all laborers and mechanics working at the site
of the work, or in the development of the project. Such records will contain the name and address of each
employee, his correct classification, rates of pay, daily and weekly number of hours worked, deductions
made, and actual wages paid.
In addition, the Contractor will submit weekly a copy of all payrolls to the Owner and Engineer. The
copy shall be accompanied by a certification signed by the employer or his agent indicating that the
payrolls are correct and complete, that the wage rates contained therein are not less than those determined
by the Montana Department of Labor and Industry, and that the classifications set forth for each laborer or
mechanic conform with the work he performed. The prime Contractor will make the record required
under the labor standards clause of the Contract available for inspection by authorized representatives of
the Owner and the Montana Department of Labor and Industry and will permit such representatives to
interview employees during working hours on the job.
Payroll reports and certificates of compliance shall be submitted to the Owner and Engineer prior to or
with each Payment Request. The copies sent to the Owner and Engineer are for archive purposes only,
because neither the Owner or Engineer are trained in the interpretation of payroll reports, and thus will
rely on the Contractor’s certification that all employees are being classified and paid appropriately.
18.MAINTENANCE OF RECORDS
Contractor shall maintain all required records for three years after the Owner makes final payment and all
other pending matters are closed.
Section 00200
INSTRUCTIONS TO BIDDERS
Page 9 of 9
19.NOTICE TO PROCEED
The Notice to Proceed will normally be issued within 30 days of the execution of the Agreement by the
Owner. Should there be reasons why the Notice to Proceed cannot be issued within such period, the time
may be extended by mutual written agreement between the Owner and Contractor.
20.CONTRACT TIME
The Contract Time will be as set forth in the Special Provisions.
21.LIQUIDATED DAMAGES
Liquidated damages will be as set forth in the Special Provisions.
22.MONTANA CONTRACTOR’S REGISTRATION
Each bidder will be required to be registered with the State of Montana, Department of Labor and
Industry prior to execution of the contract.
Attachment A
NONDISCRIMINATION AND EQUAL PAY AFFIRMATION
____________________________________(name of entity submitting) hereby affirms it will not
discriminate on the basis of race, color, religion, creed, sex, age, marital status, national origin,
or because of actual or perceived sexual orientation, gender identity or disability and
acknowledges and understands the eventual contract will contain a provision prohibiting
discrimination as described above and this prohibition on discrimination shall apply to the hiring
and treatments or proposer’s employees and to all subcontracts.
In addition, ____________________________________(name of entity submitting) hereby
affirms it will abide by the Equal Pay Act of 1963 and Section 39-3-104, MCA (the Montana Equal
Pay Act), and has visited the State of Montana Equal Pay for Equal Work “best practices” website,
https://equalpay.mt.gov/BestPractices/Employers, or equivalent “best practices publication and
has read the material.
______________________________________
Name and title of person authorized to sign on behalf of submitter
Work Change Directive
No. _____
Date of Issuance: _____________________ Effective Date: _____________________
Project: Owner: City of Bozeman Owner’s Contract #:
Contract: Date of Contract:
Contractor: Engineer’s Project #:
You are directed to proceed promptly with the following change(s):
Item No. Description
Attachments (list documents supporting change):
Purpose for Work Change Directive:
Authorization for Work described herein to proceed on the basis of Cost of the Work due to:
Nonagreement on pricing of proposed change.
Necessity to expedite Work described herein prior to agreeing to changes on Contract Price and Contract Time.
Other:
Estimated change in Contract Price and Contract Times:
Contract Price $___________________ (increase/decrease) Contract Time ___________(increase/decrease)
If the change involves an increase, the estimated amounts are not to be exceeded without further authorization.
Recommended for Approval by Engineer: Date:
Authorized by Owner: Date:
Accepted for Contractor by: Date:
Approved by Funding Agency (if applicable): Date:
Page 1 of 2
O:\A-G\Bozeman City of\114-710326H - 2022-2023 GW & METHANE BOZ LF\05-Deliverables\Draft\LFG_UST pipelines\specs\16-COB
Change Order Form.doc
CHANGE ORDER No. DATE OF ISSUANCE EFFECTIVE DATE OWNER CONTRACTOR Contract: Project: OWNER's Contract No. ENGINEER ENGINEER's Contract No.
You are directed to make the following changes in the Contract Documents: Description: Reason for Change Order: Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIMES:
Original Contract Price $
Original Contract Times: Substantial Completion: Ready for final payment:
(days or dates)
Net Increase (Decrease) from previous Change Orders No. to : $
Net change from previous Change Orders No. to No. : Substantial Completion: Ready for final payment: (days)
Contract Price prior to this Change Order: $
Contract Times prior to this Change Order: Substantial Completion: Ready for final payment: (days or dates)
Net increase (decrease) of this Change Order: $
Net increase (decrease) this Change Order: Substantial Completion: Ready for final payment: (days)
Contract Price with all approved Change Orders: $
Contract Times with all approved Change Orders: Substantial Completion: Ready for final payment: (days or dates)
Contractor certifies and agrees that there are no additional costs or claims for extra work, additional time, delays or omitted items, of any nature whatsoever, associated with the subject change order items, except as identified and set forth herein and unless expressly stated otherwise in the Change Order. And further, that the price agreed-upon herein represents the full cost and value for the subject work performed and the materials supplied under the terms of the contract and that the work quantities and value were properly determined and are correct. CONTRACTOR (Authorized Signature) Date RECOMMENDED BY: APPROVED BY: (ENGINEER - Signature) Date OWNER (Authorized Signature) Date EJCDC 1910-8-B (1996 Edition Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America and the Construction Specifications Institute.
Page 2 of 2
O:\A-G\Bozeman City of\114-710326H - 2022-2023 GW & METHANE BOZ LF\05-Deliverables\Draft\LFG_UST pipelines\specs\16-COB
Change Order Form.doc
CHANGE ORDER INSTRUCTIONS A. GENERAL INFORMATION
This document was developed to provide a uniform format for handling contract changes that affect Contract Price or
Contract Times. Changes that have been initiated by a Work Change Directive must be incorporated into a subsequent
Change Order if they affect Price or Times.
Changes that affect Contract Price or Contract Times should be promptly covered by a Change Order. The practice of
accumulating Change Orders to reduce the administrative burden may lead to unnecessary disputes.
If Milestones have been listed in the Agreement, any effect of a Change Order thereon should be addressed.
For supplemental instructions and minor changes not involving a change in the Contract Price or Contract Times, a
Field Order should be used.
B. COMPLETING THE CHANGE ORDER FORM
Engineer normally initiates the form, including a description of the changes involved and attachments based upon
documents and proposals submitted by Contractor, or requests from Owner, or both.
Once Engineer has completed and signed the form, all copies should be sent to Owner or Contractor for approval,
depending on whether the Change Order is a true order to the Contractor or the formalization of a negotiated
agreement for a previously performed change. After approval by one contracting party, all copies should be sent to
the other party for approval. Engineer should make distribution of executed copies after approval by both parties.
If a change only applies to price or to times, cross out the part of the tabulation that does not apply.
Order to Contractor to Suspend Work – Page 1 of 1
O:\A-G\Bozeman City of\114-710326H - 2022-2023 GW & METHANE BOZ LF\05-Deliverables\Draft\LFG_UST pipelines\specs\17-
suspend_wrk.doc
11/9/22
ORDER TO CONTRACTOR TO SUSPEND WORK
Federal/State Project Number Suspend Work Order No.
DATE:
City of Bozeman Project Number
TO: PROJECT AND LOCATION
OWNER:
By reason of
which renders it impracticable for you to secure specified results on the work required by your
contract, you are hereby directed to suspend work (minor operations excepted), at the close of work
on .
You will resume major operations only when authorized to do so in writing by a Resume Work
Order.
Under the terms of your contract for the above subject project, Contract Time will (will not) continue
to be charged during the period work is suspended. (See General Conditions, Articles 12 and 15
and applicable Supplementary Conditions). calendar days are allowed to complete this
project and calendar days have been allowed for approved extra and/or additional work.
At the close of work on the date specified above, of the calendar days have been
used and there remain calendar days in which to complete the contract.
Please sign all five copies in the space provided and return them to this office. One approved copy
will be returned for your files.
CONTRACTOR OWNER
Receipt Acknowledged, Date: BY:
BY: TITLE:
TITLE: Address for Correspondence:
Order to Contractor to Resume Work – Page 1 of 1
ORDER TO CONTRACTOR TO RESUME WORK
Federal/State Project Number Resume Work Order No.
DATE:
City of Bozeman Project Number
TO: PROJECT AND LOCATION
OWNER:
The Suspend Work Order, dated , directed you to suspend work on your contract, for the
reasons and conditions described therein. Conditions are now favorable to the continuation of the work, you are
hereby directed to resume major operations on this project effective .
Under the terms of your contract for this project, Contract Time was (was not) charged during the period work was
suspended.
At the close of work on the date specified in the last Suspend Work Order, of the calendar days
Contract Time had been used. calendar days were charged during the period work was suspended,
therefore, on the date this resume work order is effective, calendar days of Contract Time remain.
The (revised) contract completion date is 20 .
Please sign all five copies in the space provided and return them to this office. One approved copy will be returned for
your file.
CONTRACTOR OWNER
Receipt Acknowledged, Date: BY:
BY: TITLE:
TITLE: Address for Correspondence:
MONTANA
PREVAILING WAGE RATES FOR HEAVY CONSTRUCTION SERVICES 2022
Effective: January 1, 2022
Greg Gianforte, Governor
State of Montana
Laurie Esau, Commissioner
Department of Labor & Industry
To obtain copies of prevailing wage rate schedules, or for information relating to public works projects and payment of prevailing
wage rates, visit ERD at erd.dli.mt.gov/labor-standards or contact:
Employment Relations Division
Montana Department of Labor and Industry
P. O. Box 8011
Helena, MT 59620-1503
Phone 406-444-6543
The department welcomes questions, comments, and suggestions from the public. In addition, we’ll do our best to provide
information in an accessible format, upon request, in compliance with the Americans with Disabilities Act.
MONTANA PREVAILING WAGE REQUIREMENTS
The Commissioner of the Department of Labor and Industry, in accordance with Sections 18-2-401 and 18-2-402 of the
Montana Code Annotated (MCA), has determined the standard prevailing rate of wages for the occupations listed in this
publication.
The wages specified herein control the prevailing rate of wages for the purposes of Section 18-2-401, et seq., MCA. It is required
each employer pay (as a minimum) the rate of wages, including fringe benefits, travel allowance, zone pay and per diem
applicable to the district in which the work is being performed as provided in the attached wage determinations.
All Montana Prevailing Wage Rates are available on the internet at erd.dli.mt.gov/labor-standards or by contacting the
department at (406) 444-6543.
In addition, this publication provides general information concerning compliance with Montana’s Prevailing Wage Law and the
payment of prevailing wages. For detailed compliance information relating to public works contracts and payment of prevailing
wage rates, please consult the regulations on the internet at erd.dli.mt.gov/labor-standards or contact the department at (406)
444-6543.
LAURIE ESAU
Commissioner
Department of Labor and Industry
State of Montana
2
TABLE OF CONTENTS
MONTANA PREVAILING WAGE REQUIREMENTS:
WAGE RATES:
A.Date of Publication ……………………………………………………………………………………………………………………………………………….……. 3
B.Definition of Heavy Construction …………………………………………………………………………………………………………………..…............. 3
C.Definition of Public Works Contract ………………………………………………………………………………………………………………………….... 3
D.Prevailing Wage Schedule ……………………………………………………………………………………………………………………………….………… 3
E.Rates to Use for Projects ………………………………………………………………………………………………………………………………..…………… 3
F.Wage Rate Adjustments for Multiyear Contracts ……………………………………………………………………………………………….………… 3
G.Fringe Benefits ……………………………………………………………………………………………………………………………………………………………. 4
H.Dispatch City ………………………………………………………………………………………………………………………………………………………….……. 4
I.Zone Pay …………………………………………………………………………………………………………………………………………………………………….. 4
J.Computing Travel Benefits ……………………………………………………………………………………………………………….………………………… 4
K.Per Diem …………………………………………………………………………………………………………………………………………………………………….. 4
L.Apprentices ………………………………………………………………………………………………………………………………………..……………………….. 4
M.Posting Notice of Prevailing Wages ……………………………………………………………………………………………………………………………. 5
N.Employment Preference …………………………………………………………………………………………………………….…………………………....... 5
O.Projects of a Mixed Nature ............................................................................................................................................................ 5
P.Occupations Definitions Website ................................................................................................................................................... 5
Q.Welder Rates ……………………………………………………………………………………………………………………………………………………………. 5
R.Foreman Rates …………………………………………………………………………………………………………………………………………………..……. 5
S Proper Classification for Pipefitter and Laborer/Pipelayer Work on Water and Waste Water Treatment Plants ……………..… 5
BOILERMAKERS ……………………………………………………………………………………………………………………………………………..………………….. 6
BRICK, BLOCK, AND STONE MASONS ……………………………………………………………………………………….......................................... 6
CARPENTERS …………………………………………………………………………………………………………………………………………………………………….. 6
CEMENT MASONS AND CONCRETE FINISHERS …………………………………………………………………………………………………………… 6
CONSTRUCTION EQUIPMENT OPERATORS
OPERATORS GROUP 1 ………………………………………………………………………………………………………….............................................. 7
OPERATORS GROUP 2 ………………………………………………………………………………………………………………………………………………….. 7
OPERATORS GROUP 3 ………………………………………………………………………………………………………………………………………………….. 8
OPERATORS GROUP 4 ………………………………………………………………………………………………………………………………………………….. 8
OPERATORS GROUP 5 ………………………………………………………………………………………………………………………………………………….. 8
OPERATORS GROUP 6 ………………………………………………………………………………………………………………………………………………….. 8
OPERATORS GROUP 7 ………………………………………………………………………………………………………………………………………………….. 9
CONSTRUCTION LABORERS
LABORERS GROUP 1 ………………………………………………………………………………………………………………………………………………….. 9
LABORERS GROUP 2 ………………………………………………………………………………………………………………………………………………….. 9
LABORERS GROUP 3 ………………………………………………………………………………………………………………………………………………….. 10
LABORERS GROUP 4 ………………………………………………………………………………………………………………………………………………….. 10
DIVERS ………………………………………………………………………………………………………………………………………………………………………………. 10
DIVER TENDERS ……………………………………………………………………………………………………………………………………………………………….. 11
ELECTRICIANS …………………………………………......................................................................................................................................... 11
INSULATION WORKERS - MECHANICAL (HEAT AND FROST) ………………………………………………………………............................ 11
IRONWORKERS - STRUCTURAL STEEL AND REBAR PLACERS …………………………………………………………………………………. 12
LINE CONSTRUCTION
EQUIPMENT OPERATORS …………………………………………………………………………………..........…………………………………………………. 12
GROUNDMAN ………………………………………………………………………………………………...........……………………………………………………….. 12
LINEMAN ……………………………………………………………………………………………...........………………………………………………………………….. 12
MILLWRIGHTS …………………………………………………………………………………………………………………………………………………………………….. 13
PAINTERS ……………………………………………………………………………..............….......................................................................................... 13
PILE BUCKS ……………………………………………………………………………………………………………………………………………………………………….. 13
PLUMBERS, PIPEFITTERS, AND STEAMFITTERS …………………………………………………………………………………………………………… 13 SPRINKLERFITTERS …………………………………………………………………………………………………………………............................................... 14
TRUCK DRIVERS ..................................................................................................................................................................................... 15
3
A. Date of Publication January 1 2022
B. Definition of Heavy Construction
The Administrative Rules of Montana (ARM), 24.17.501(4) – (4)(a), states “Heavy construction projects include, but
are not limited to, those projects that are not properly classified as either ‘building construction’, or ‘highway
construction.’
Heavy construction projects include, but are not limited to, antenna towers, bridges (major bridges designed for
commercial navigation), breakwaters, caissons (other than building or highway), canals, channels, channel cut-offs,
chemical complexes or facilities (other than buildings), cofferdams, coke ovens, dams, demolition (not incidental to
construction), dikes, docks, drainage projects, dredging projects, electrification projects (outdoor), fish hatcheries,
flood control projects, industrial incinerators (other than building), irrigation projects, jetties, kilns, land drainage
(not incidental to other construction), land leveling (not incidental to other construction), land reclamation, levees,
locks and waterways, oil refineries (other than buildings), pipe lines, ponds, pumping stations (prefabricated drop-in
units – not buildings), railroad construction, reservoirs, revetments, sewage collection and disposal lines, sewers
(sanitary, storm, etc.), shoreline maintenance, ski tows, storage tanks, swimming pools (outdoor), subways (other
than buildings), tipples, tunnels, unsheltered piers and wharves, viaducts (other than highway), water mains,
waterway construction, water supply lines (not incidental to building), water and sewage treatment plants (other
than buildings) and wells.”
C. Definition of Public Works Contract
Section 18-2-401(11)(a), MCA defines “public works contract” as “…a contract for construction services let by the
state, county, municipality, school district, or political subdivision or for nonconstruction services let by the state,
county, municipality, or political subdivision in which the total cost of the contract is in excess of $25,000...”.
D. Prevailing Wage Schedule
This publication covers only Heavy Construction occupations and rates in the specific localities mentioned herein.
These rates will remain in effect until superseded by a more current publication. Current prevailing wage rate
schedules for Building Construction, Highway Construction and Nonconstruction Services occupations can be found
on the internet at https://erd.dli.mt.gov/labor-standards/ or by contacting the department at (406) 444-6543.
E. Rates to Use for Projects
ARM, 24.17.127(1)(c), states “The wage rates applicable to a particular public works project are those in effect at the
time the bid specifications are advertised.”
F. Wage Rate Adjustments for Multiyear Contracts
Section 18-2-417, MCA states:
“(1) Any public works contract that by the terms of the original contract calls for more than 30 months to fully
perform must include a provision to adjust, as provided in subsection (2), the standard prevailing rate of wages to
be paid to the workers performing the contract.
(2) The standard prevailing rate of wages paid to workers under a contract subject to this section must be adjusted
12 months after the date of the award of the public works contract. The amount of the adjustment must be a 3%
increase. The adjustment must be made and applied every 12 months for the term of the contract.
(3) Any increase in the standard rate of prevailing wages for workers under this section is the sole responsibility of
the contractor and any subcontractors and not the contracting agency.”
4
G. Fringe Benefits
Section 18-2-412, MCA states:
“(1) To fulfill the obligation...a contractor or subcontractor may:
(a) pay the amount of fringe benefits and the basic hourly rate of pay that is part of the standard prevailing rate of
wages directly to the worker or employee in cash;
(b) make an irrevocable contribution to a trustee or a third person pursuant to a fringe benefit fund, plan, or
program that meets the requirements of the Employee Retirement Income Security Act of 1974 or that is a bona
fide program approved by the U. S. department of labor; or
(c) make payments using any combination of methods set forth in subsections (1)(a) and (1)(b) so that the
aggregate of payments and contributions is not less than the standard prevailing rate of wages, including fringe
benefits and travel allowances, applicable to the district for the particular type of work being performed.
(2) The fringe benefit fund, plan, or program described in subsection (1)(b) must provide benefits to workers or
employees for health care, pensions on retirement or death, life insurance, disability and sickness insurance, or
bona fide programs that meet the requirements of the Employee Retirement Income Security Act of 1974 or that
are approved by the U. S. department of labor.”
Fringe benefits are paid for all hours worked (straight time and overtime hours). However, fringe benefits are not to
be considered a part of the hourly rate of pay for calculating overtime, unless there is a collectively bargained
agreement in effect that specifies otherwise.
H. Dispatch City
ARM, 24.17.103(11), defines dispatch city as “...the courthouse in the city from the following list which is closest to the
center of the job: Billings, Bozeman, Butte, Great Falls, Helena, Kalispell, Miles City, Missoula and Sidney.”
I. Zone Pay
Zone pay is not travel pay. ARM, 24.17.103(24), defines zone pay as “...an amount added to the base pay; the combined
sum then becomes the new base wage rate to be paid for all hours worked on the project. Zone pay must be determined
by measuring the road miles one way over the shortest practical maintained route from the dispatch city to the center of
the job.” See section H above for a list of dispatch cities.
J. Computing Travel Benefits
ARM, 24.17.103(22), states “ ‘Travel pay,’ also referred to as ‘travel allowance,’ is and must be paid for travel both to
and from the job site, except those with special provisions listed under the classification. The rate is determined by
measuring the road miles one direction over the shortest practical maintained route from the dispatch city or the
employee's home, whichever is closer, to the center of the job.” See section H above for a list of dispatch cities.
K. Per Diem
ARM, 24.17.103(18), states “ ‘Per diem’ typically covers costs associated with board and lodging expenses. Per diem is
paid when an employee is required to work at a location outside the daily commuting distance and is required to stay at
that location overnight or longer.”
L. Apprentices
Wage rates for apprentices registered in approved federal or state apprenticeship programs are contained in those
programs. Additionally, Section 18-2-416(2), MCA states, “…The full amount of any applicable fringe benefits must
be paid to the apprentice while the apprentice is working on the public works contract.” Apprentices not registered
in approved federal or state apprenticeship programs will be paid the appropriate journey level prevailing wage rate
when working on a public works contract.
5
M. Posting Notice of Prevailing Wages
Section 18-2-406, MCA, provides that contractors, subcontractors, and employers who are “…performing work or
providing construction services under public works contracts, as provided in this part, shall post in a prominent and
accessible site on the project or staging area, not later than the first day of work and continuing for the entire
duration of the project, a legible statement of all wages and fringe benefits to be paid to the employees.”
N. Employment Preference
Sections 18-2-403 and 18-2-409, MCA require contractors to give preference to the employment of bona fide
Montana residents in the performance of work on public works contracts.
O.Projects of a Mixed Nature
Section 18-2-408, MCA states:
“(1) The contracting agency shall determine, based on the preponderance of labor hours to be worked, whether the
public works construction services project is classified as a highway construction project, a heavy construction project, or
a building construction project.
(2) Once the project has been classified, employees in each trade classification who are working on that project must be
paid at the rate for that project classification”
P.Occupations Definitions
You can find definitions for these occupations on the following Bureau of Labor Statistics website:
https://erd.dli.mt.gov/labor-standards/state-prevailing-wage-rates/building-construction-occupations
Q.Welder Rates
Welders receive the rate prescribed for the craft performing an operation to which welding is incidental.
R.Foreman Rates
Rates are no longer set for foremen. However, if a foreman performs journey level work, the foreman must be paid
at least the journey level rate.
S. Proper Classification for Pipefitter and Laborer/Pipelayer Work on Water and Waste Water Treatment Plants The
proper classification for the following work is Pipefitter, when it is performed inside a building structure or performed
at a location which will later be inside of a building: Joining steel pipe larger than 12 inches in diameter with bolted
flange connections that has been pre-fabricated off site and does not require any modification such as cutting,
grinding, welding, or other fabrication in order to be installed. All other work previously classified as pipefitter
remains in that classification. The proper classification for that work when it is at a location that will always be
outside a building is Pipelayer, which is under the Laborer Group 3 classification.
6
WAGE RATES
BOILERMAKERS
Wage Benefit
$34.12 $31.68
Duties Include:
Construct, assemble, maintain, and repair stationary steam
boilers, boiler house auxiliaries, process vessels, pressure
vessels and penstocks. Bulk storage tanks and bolted
steel tanks.
Travel:
All Districts
0-120 mi. free zone
>120 mi. federal mileage rate/mi.
Special Provision:
Travel is paid only at the beginning and end of the job.
Per Diem:
All Districts
0-70 mi. free zone
>70-120 mi. $65.00/day
>120 mi. $80.00/day
↑ Back to Table of Contents
BRICK, BLOCK, AND STONE MASONS
Wage Benefit
$35.95 $18.52
Travel:
0-20 mi. free zone
>20-35 mi. $30.00/day
>35-55 mi. $35.00/day
>55 mi. $78.00/day
↑ Back to Table of Contents
CARPENTERS
Wage Benefit
$32.75 $13.82
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $4.00/hr.
>60 mi. base pay + $6.00/hr.
↑ Back to Table of Contents
CEMENT MASONS AND CONCRETE FINISHERS
Wage Benefit
$22.85 $12.85
Duties Include:
Smooth and finish surfaces of poured concrete, such as
floors, walks, sidewalks, or curbs. Align forms for
sidewalks, curbs, or gutters. Rates for rebar workers can
be found under the Ironworkers classification.
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $2.95/hr.
>60 mi. base pay + $4.75/hr.
↑ Back to Table of Contents
7
CONSTRUCTION EQUIPMENT OPERATORS GROUP 1
Wage Benefit
$28.21 $13.65
This group includes but is not limited to:
Air Compressor; Auto Fine Grader; Belt Finishing; Boring
Machine (Small) 12 inch and under; Cement Silo; Crane, A-
Frame Truck Crane; Crusher Conveyor; DW-10, 15, and 20
Tractor Roller; Farm Tractor; Forklift; Form Grader; Front-
End Loader, under 1 cu. yd; Oiler, Heavy Duty Drills;
Herman Nelson Heater; Mucking Machine; Oiler, All Except
Cranes/Shovels; Pumpman.
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $3.50/hr.
>60 mi. base pay + $5.50/hr.
↑ Back to Table of Contents
CONSTRUCTION EQUIPMENT OPERATORS GROUP 2
Wage Benefit
$30.04 $13.65
This group includes but is not limited to:
Air Doctor; Backhoe\Excavator\Shovel, up to and incl. 3 cu.
yds; Bit Grinder; Bitunimous Paving Travel Plant; Boring
Machine, Large; Broom, Self-Propelled; Concrete Travel
Batcher; Concrete Float & Spreader; Concrete Bucket
Dispatcher; Concrete Finish Machine; Concrete Conveyor;
Distributor; Dozer, Rubber-Tired, Push, & Side Boom;
Elevating Grader\Gradall; Field Equipment Serviceman;
Front-End Loader, 1 cu. yd up to and incl. 5 cu. yds; Grade
Setter; Heavy Duty Drills, All Types; Hoist\Tugger, All;
Hydralift Forklifts & Similar; Industrial Locomotive; Motor
Patrol (except finish); Mountain Skidder; Oiler,
Cranes\Shovels; Pavement Breaker, EMSCO; Power Saw,
Self-Propelled; Pugmill; Pumpcrete\Grout Machine; Punch
Truck; Roller, other than Asphalt; Roller, Sheepsfoot (Self-
Propelled); Roller, 25 tons and over; Ross Carrier; Rotomill,
under 6 ft; Trenching Machine; Washing /Screening Plant
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $3.50/hr.
>60 mi. base pay + $5.50/hr.
↑ Back to Table of Contents
8
CONSTRUCTION EQUIPMENT OPERATORS GROUP 3
Wage Benefit
$29.75 $13.65
This group includes but is not limited to:
Asphalt Paving Machine; Asphalt Screed;
Backhoe\Excavator\Shovel, over 3 cu. yds; Cableway
Highline; Concrete Batch Plant; Concrete Curing Machine;
Concrete Pump; Cranes, Creter; Cranes, Electric Overhead;
Cranes, 24 tons and under; Curb Machine\Slip Form Paver;
Finish Dozer; Front-End Loader, over 5 cu. yds;
Mechanic\Welder; Pioneer Dozer; Roller Asphalt
(Breakdown & Finish); Rotomill, over 6 ft; Scraper, Single,
Twin, or Pulling Belly-Dump; YO-YO Cat Haul Truck,
Articulating Trucks, Vac Truck.
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $3.50/hr.
>60 mi. base pay + $5.50/hr.
↑ Back to Table of Contents
CONSTRUCTION EQUIPMENT OPERATORS GROUP 4
Wage Benefit
$30.75 $13.65
This group includes but is not limited to:
Asphalt\Hot Plant Operator; Cranes, 25 tons up to and incl.
44 tons; Crusher Operator; Finish Motor Patrol; Finish
Scraper.
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $3.50/hr.
>60 mi. base pay + $5.50/hr.
↑ Back to Table of Contents
CONSTRUCTION EQUIPMENT OPERATORS GROUP 5
Wage Benefit
$31.75 $13.65
This group includes but is not limited to:
Cranes, 45 tons up to and incl. 74 tons.
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $3.50/hr.
>60 mi. base pay + $5.50/hr.
↑ Back to Table of Contents
CONSTRUCTION EQUIPMENT OPERATORS GROUP 6
Wage Benefit
$32.75 $13.65
This group includes but is not limited to:
Cranes, 75 tons up to and incl. 149 tons; Cranes, Whirley
(All).
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $3.50/hr.
>60 mi. base pay + $5.50/hr.
↑ Back to Table of Contents
9
CONSTRUCTION EQUIPMENT OPERATORS GROUP 7
Wage Benefit
$33.75 $13.65
This group includes but is not limited to:
Cranes, 150 tons up to and incl. 250 tons; Cranes, over
250 tons—add $1.00 for every 100 tons over 250 tons;
Crane, Tower (All); Crane Stiff-Leg or Derrick; Helicopter
Hoist.
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $3.50/hr.
>60 mi. base pay + $5.50/hr.
↑ Back to Table of Contents
CONSTRUCTION LABORERS GROUP 1/FLAG PERSON FOR TRAFFIC CONTROL
Wage Benefit
$23.08 $11.77
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $3.05/hr.
>60 mi. base pay + $4.85/hr.
↑ Back to Table of Contents
CONSTRUCTION LABORERS GROUP 2
Wage Benefit
$25.90 $11.77
This group includes but is not limited to:
General Labor; Asbestos Removal; Burning Bar; Bucket
Man; Carpenter Tender; Caisson Worker; Cement Mason
Tender; Cement Handler (dry); Chuck Tender; Choker
Setter; Concrete Worker; Curb Machine-lay Down; Crusher
and Batch Worker; Heater Tender; Fence Erector;
Landscape Laborer; Landscaper; Lawn Sprinkler Installer;
Pipe Wrapper; Pot Tender; Powderman Tender; Rail and
Truck Loaders and Unloaders; Riprapper; Sign Erection;
Guardrail and Jersey Rail; Spike Driver; Stake Jumper;
Signalman; Tail Hoseman; Tool Checker and Houseman
and Traffic Control Worker.
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $3.05/hr.
>60 mi. base pay + $4.85/hr.
↑ Back to Table of Contents
10
CONSTRUCTION LABORERS GROUP 3
Wage Benefit
$26.07 $11.77
This group includes but is not limited to:
Concrete Vibrator; Dumpman (Grademan); Equipment
Handler; Geotextile and Liners; High-Pressure Nozzleman;
Jackhammer (Pavement Breaker) Non-Riding Rollers;
Pipelayer; Posthole Digger (Power); Power Driven
Wheelbarrow; Rigger; Sandblaster; Sod Cutter-Power and
Tamper.
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $3.05/hr.
>60 mi. base pay + $4.85/hr.
↑ Back to Table of Contents
CONSTRUCTION LABORERS GROUP 4
Wage Benefit
$26.76 $11.77
This group includes but is not limited to:
Hod Carrier***; Water Well Laborer; Blaster; Wagon Driller;
Asphalt Raker; Cutting Torch; Grade Setter; High-Scaler;
Power Saws (Faller & Concrete);
Powderman; Rock & Core Drill; Track or Truck Mounted
Wagon Drill and Welder incl. Air Arc
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $3.05/hr.
>60 mi. base pay + $4.85/hr.
***Hod Carriers will receive the same amount of travel
and/or subsistence pay as bricklayers when requested to
travel.
↑ Back to Table of Contents
DIVERS
Wage Benefit
Stand-By $44.98 $17.84
Diving $89.96 $17.84
Depth Pay (Surface Diving)
0-20 ft. free zone
>20-100 ft.$2.00 per ft.
>100-150 ft.$3.00 per ft.
>150-220 ft.$4.00 per ft.
>220 ft.$5.00 per ft.
Diving In Enclosures
0-25 ft. free zone
>25-300 ft.$1.00 per ft.
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $4.00/hr.
>60 mi. base pay + $6.00/hr.
↑ Back to Table of Contents
11
DIVER TENDERS
Wage Benefit
$43.98 $17.84
The tender shall receive 2 hours at the straight time pay
rate per shift for dressing and/or undressing a Diver when
work is done under hyperbaric conditions.
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $4.00/hr.
>60 mi. base pay + $6.00/hr.
↑ Back to Table of Contents
ELECTRICIANS
Wage Benefit
$35.59 $16.39
Travel:
No mileage due when traveling in employer’s vehicle.
The following travel allowance is applicable when traveling
in employee’s vehicle:
0-08 mi. free zone
>08-50 mi. federal mileage rate/mi. in excess of the
free zone.
>50 mi. $60.57/day
↑ Back to Table of Contents
INSULATION WORKERS - MECHANICAL (HEAT AND FROST)
Wage Benefit
$37.97 $21.87
Duties Include:
Insulate pipes, ductwork or other mechanical systems.
Travel:
0-30 mi. free zone
>30-40 mi. $25.00/day
>40-50 mi. $35.00/day
>50-60 mi. $45.00/day
>60 mi. $60.00/day plus
▪$0.56/mi. if transportation is not provided.
▪$0.20/mi. if in company vehicle.
>60 mi. $100.00/day on jobs requiring an overnight stay
plus
▪$0.56/mi. if transportation is not provided.
▪$0.20/mi. if in company vehicle.
↑ Back to Table of Contents
12
IRONWORKERS - STRUCTURAL STEEL AND REBAR PLACERS
Wage Benefit
$29.38 $27.05
Duties Include:
Structural steel erection; assemble prefabricated metal
buildings; cut, bend, tie, and place rebar; energy producing
windmill type towers; metal bleacher seating; handrail
fabrication and ornamental steel.
Travel:
0-45 mi. free zone
>45-60 mi. $45.00/day
>60-100 mi. $70.00/day
>100 mi. $90.00/day
Special Provision:
When the employer provides transportation, travel will not
be paid. However, when an employee is required to travel
over 70 miles one way, the employee may elect to receive
the travel pay in lieu of the transportation.
↑ Back to Table of Contents
LINE CONSTRUCTION – EQUIPMENT OPERATORS
Wage Benefit
$36.00 $16.92
Duties Include:
All work on substations
Travel:
No Free Zone
$60.00/day
↑ Back to Table of Contents
LINE CONSTRUCTION – GROUNDMAN
Wage Benefit
$29.09 $16.09
Duties Include:
All work on substations
Travel:
No Free Zone
$60.00/day
↑ Back to Table of Contents
LINE CONSTRUCTION – LINEMAN
Wage Benefit
$48.65 $18.03
Duties Include:
All work on substations
Travel:
No Free Zone
$60.00/day
↑ Back to Table of Contents
13
MILLWRIGHTS
Wage Benefit
$39.68 $14.27
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $4.00/hr.
>60 mi. base pay + $6.00/hr.
↑ Back to Table of Contents
PAINTERS
Wage Benefit
$25.00 $0.00
Travel:
No travel or per diem established.
↑ Back to Table of Contents
PILE BUCKS
Wage Benefit
$32.75 $13.82
Duties Include:
Set up crane; set up hammer; weld tips on piles; set leads;
insure piles are driven straight with the use of level or plum
bob. Give direction to crane operator as to speed, and
direction of swing. Cut piles to grade.
Zone Pay:
0-30 mi. free zone
>30-60 mi. base pay + $4.00/hr.
>60 mi. base pay + $6.00/hr.
↑ Back to Table of Contents
PLUMBERS, PIPEFITTERS, AND STEAMFITTERS
Wage Benefit
$39.98 $20.26
Duties Include:
Assemble, install, alter, and repair pipe-lines or pipe
systems that carry water, steam, air, other liquids or gases.
Testing of piping systems, commissioning and retro-
commissioning. Workers in this occupation may also
install heating and cooling equipment and mechanical
control systems.
Travel:
0-70 free zone
>70 mi.
▪On jobs when employees do not work consecutive
days: $0.55/mi. if employer doesn’t provide
transportation. Not to exceed two trips.
▪On jobs when employees work any number of
consecutive days: $105.00/day.
↑ Back to Table of Contents
14
SPRINKLER FITTERS
Wage Benefit
$35.66 $24.29
Duties Include:
Duties Include but not limited to any and all fire protection
systems: Installation, dismantling, inspection, testing,
maintenance, repairs, adjustments, and corrections of all
fire protection and fire control systems, including both
overhead and underground water mains, all piping, fire
hydrants, standpipes, air lines, tanks, and pumps used in
connection with sprinkler and alarm systems.
Travel
All Districts
The following travel allowance is applicable when traveling
in employee’s vehicle.
0-60 mi. free zone
>60-80 mi. $19.00/day
>80-100 mi. $29.00/day
>100 mi. $105.00/day.
Special Provision
When traveling >100 miles, mileage at $0.54/mi. + $8.59
for every 15 miles traveled at beginning and end of job.
The following travel allowance is applicable when traveling
in employer’s vehicle.
0-100 mi. free zone
>100 mi. $105.00/day
Special Provision
When traveling >100 miles, $8.59 for every 15 miles
traveled, at beginning and end of job.
Per Diem:
All Districts
No per diem is applicable when traveling in employee’s
vehicle
The following per diem is applicable when traveling in
employer’s vehicle.
0-100 mi. free zone
>100 mi. $105.00/day
↑ Back to Table of Contents
15
TRUCK DRIVERS
Pilot Car Driver No Rate Established
Wage Benefit
Truck Driver $31.28 $9.37
Truck drivers include but are not limited to:
Combination Truck and Concrete Mixer and Transit Mixer;
Dry Batch Trucks; Distributor Driver; Dumpman; Dump
Trucks and similar equipment; Dumpster; Flat Trucks;
Lumber Carriers; Lowboys; Pickup; Powder Truck Driver;
Power Boom; Serviceman; Service Truck/Fuel
Truck/Tireperson; Truck Mechanic; Trucks with Power
Equipment; Warehouseman, Partsman, Cardex and
Warehouse Expeditor; Water Trucks.
Zone Pay:
All Districts
0-30 mi. free zone
>30-60 mi. base pay + $3.05/hr.
>60 mi. base pay + .$4.85/hr.
Special Provision:
Zone pay only applies to the Truck Driver classification. No
zone pay was established for Pilot Car Driver.
↑ Back to Table of Contents
1 BID FORM
TO: City Clerk
P.O. Box 1230
Bozeman, Montana 59771-1230
THE UNDERSIGNED BIDDER, having familiarized himself with the Work required by the Contract
Documents, the site(s) where the work is to be performed, local labor conditions and all laws,
regulations, municipal ordinances and other factors which may affect the performance of the Work, and
having satisfied himself of the expense and difficulties attending performance of the work:
HEREBY PROPOSES and agrees, if this bid is accepted, to enter into an Agreement, in the form attached,
to perform all Work for the construction of Landfill Gas (LFG) Wells and buried underground piping, and
related items including the assumption of all obligations, duties, and responsibilities necessary for the
successful completion of the contract and the furnishing of all materials and equipment required to be
incorporated in, and form a permanent part of, the work; tools, equipment, supplies, transportation,
facilities, labor, superintendence, and services required to perform the Work; Bonds, Insurance and
Submittals; all as indicated or specified in the Contract Documents to be performed or furnished by
Contractor within the time and for the prices set forth in the following schedules.
The undersigned bidder agrees to be bound by this Bid for a period not to exceed that specified in the
Invitation to Bid.
The undersigned Bidder agrees to furnish the required Bonds and to enter into a contract within fifteen
(15)calendar days after Owner's acceptance of this Bid, and further agrees to complete all Work within
the time specified per schedule after commencement of the contract time as defined in the General
Conditions.
The allowed contract time is 90 calendar days.
Where multiple schedules are awarded under a single Contract, the Contract times shall run
concurrently unless separate notices to proceed are issued for the awarded schedules.
Liquidated Damages shall be as specified in Article 2.2 of the Agreement Form.
The undersigned Bidder agrees that the unit prices shall govern in checking the Bid, and should a
discrepancy exist in the total prices and total amount of Bid as listed above, after extensions are checked
and corrections made, if any, the total amount of the Bid as corrected shall be used in awarding the
contract.
The undersigned Bidder agrees that he has been afforded access to the construction site and has
performed those independent site investigations as he deemed necessary.
This Bid Form is included for reference only. The City of Bozeman will only accept online electronic bids
through QuestCDN. Project bid documents and addenda must be downloaded from QuestCDN, which will
add your company to the Planholder List and allow access to vBid online bidding, for the submittal of your
bid. Refer to the instructions to bidders for additional information.
BID FORM
2023 LFG and LEACHATE/CONDENSATE SYSTEM IMPROVEMENTS REBID
CITY OF BOZEMAN
BOZEMAN, MONTANA 59771
2 BID FORM
The undersigned Bidder hereby certifies the following:
A)That this Bid is genuine and is not made in the interest of, or on behalf of, any undisclosed
person, firm, or corporation, and is not submitted in conformity with any agreement or rules of any
group, association, organization, or corporation;
B)That he has not directly or indirectly solicited any other Bidder to put in a false or sham Bid;
C)That he has not solicited or induced any person, firm, or corporation to refrain from bidding;
D)That he has not sought by collusion to obtain for himself any advantage over any other Bidder or
over the Owner.
E)That he is not currently operating beyond the contract time on any previously awarded public
works contract as defined and required by Article 15-50-203, MCA, as amended.
The undersigned Bidder(s) either singularly or as a joint venture hereby certifies (certify) pursuant to
Article 37-71-203, MCA, that he (they) is (are) duly and regularly licensed.
Bidder agrees to perform all the Work described in the following unit prices or lump sums:
BID SCHEDULE
See the attached Bid Schedule
The undersigned Bidder acknowledged receipt of the following Addenda, which have been considered in
preparation of this Bid.
No. _______________________________
No. _______________________________
No. _______________________________ Dated __________________________
No. _______________________________
Submitted this __________day of ____________________, 2023.
SIGNATURE OF BIDDER:
Montana Contractor Registration Number ____________________________
Special Fuel User Permit Number ___________________________________
If an individual: __________________________________________________
doing business as ________________________________________________
3 BID FORM
If a Partnership: _________________________________________________ by
______________________________________________________________, partner
If a Corporation: _________________________________________________
(a)____________________________________________ Corporation
by ____________________________________________________________
Business Address of Bidder: _______________________________________
If Bidder is a joint venture, other party must sign below:
Montana License Number and Class
If an individual: __________________________________________________
doing business as ________________________________________________
If a Partnership: __________________________________________________
by _____________________________________________________________
Partner _________________________________________________________
If a Corporation: __________________________________________________
(a)_____________________________________________ Corporation
By
Title __________________________________________________ Seal & Attest
CITY OF BOZEMAN LANDFILL
LFG AND LEACHATE/CONDENSATE SYSTEM IMPROVEMENTS REBID
DRILLING AND FIELD PIPING CONSTRUCTION
BID SHEET
PAY
ITEM DESCRIPTION UNITS APPROX.
QTY.
UNIT
PRICE AMOUNT
LFG DRILLING
1 Drill Rig Mobilization/Demobilization LS -
2 LFG Well Vertical Drilling and Completion VF 225
DRILLING TOTAL:
FIELD CONSTRUCTION
3 Piping Crew Mobilization/Demobilization LS -
4 8" SDR 17 HDPE LFG Pipe and Fittings LF 880
5 Corrugated 12" HDPE Sleeve LF 20
6 Waste Excavation and Disposal Ton 2
7 Type 2 Pipe Bedding LF 50
8 2" SDR 17 HDPE Drainpipe LF 60
9 8" SDR 17 Leachate/Condensate Drainpipe LF 744
10 48" Diameter Manholes EA 2
FIELD CONSTRUCTION TOTAL:
LFG DRILLING TOTAL:
FIELD CONSTRUCTION TOTAL:
TOTAL BID:
TOTAL AMOUNT OF BID: ________________________________
WRITTEN WORDS
825 West Custer Ave. Checked By: LC
Helena, MT 59602
Prepared By:
SNA Job No.
Updated: 01/23
AGREEMENT FORM
THIS AGREEMENT is dated as of the day of ________ in the year 2023, by and between
CITY OF BOZEMAN, hereinafter called OWNER, and ______________________ hereinafter
called CONTRACTOR.
OWNER AND CONTRACTOR, in consideration of the mutual covenants hereinafter set forth,
agree as follows:
Article 1. WORK.
CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents. The
project work is generally described as follows:
The installation of LFG wells and buried piping for transmission of collected LFG and Leachate / Condensate.
The project for which the Work under the Contract Documents may be the whole or only a part is
generally described as follows: LFG & Leachate / Condensate System Improvements Rebid.
Article 2. CONTRACT TIME.
2.1 The Work will be completed within 90 days after the date when the contract time
commences to run as provided in the General Conditions. Final payment will be withheld
until final completion and acceptance of the Work, as stipulated in this Agreement.
2.2 Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the essence in
this Agreement and that OWNER will suffer financial loss if the Work is not substantially
complete within the time specified above, plus any extensions thereof allowed in accordance
with the General Conditions. They also recognize the delays, expense and difficulties
involved in proving, in a legal or arbitration proceeding, the actual loss suffered by OWNER
if the Work is not substantially complete on time. Accordingly, instead of requiring any
such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay (but
not as a penalty) CONTRACTOR shall pay OWNER one thousand dollars ($ 1,000.00) for
each day that expires after the time specified herein until the Work is substantially complete.
Article 3. CONTRACT PRICE.
3.1 OWNER shall pay CONTRACTOR for performance of the Work in accordance with the
Contract Documents the sum (subject to adjustment as provided in the Contract Documents)
of _________________________________________________________ ($__________).
Article 4. PAYMENT PROCEDURES.
CONTRACTOR shall submit applications for payment in accordance with the General Conditions.
Applications for payment will be processed as provided in the General Conditions.
4.1 Progress Payments. OWNER will make progress payments monthly on account of the
contract price on the basis of CONTRACTOR'S application for payment as recommended by
ENGINEER. All progress payments will be on the basis of the progress of the Work
measured by the schedule of values provided for in the General Conditions.
4.1.1 The OWNER may retain five (5) percent of the amount due the CONTRACTOR in
accordance with the General Conditions and as outlined herein.
4.2 Final Payment. Upon final completion and acceptance of the Work in accordance with the
General Conditions, OWNER shall pay the remainder of the contract price as recommended
by ENGINEER.
Article 5. INTEREST.
All monies not paid when due hereunder shall bear interest at the simple rate established by
the Federal Cost of Money Rate commencing at the time of a claim.
Article 6. CONTRACTOR'S REPRESENTATIONS.
In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the
following representations:
6.1 CONTRACTOR has familiarized himself with the nature and extent of the Contract
Documents, Work, locality, and with all local conditions and federal, state and local laws,
ordinances, rules and regulations that in any manner may affect cost, progress or
performance of the Work.
6.2 CONTRACTOR has studied carefully all reports of investigations and tests of subsurface
and latent physical conditions at the site or otherwise affecting cost, progress or performance
of the Work which were relied upon by ENGINEER in the preparation of the drawings and
specifications and which have been identified in the modifications to the General Conditions.
6.3 CONTRACTOR has made or caused to be made examinations, investigations and tests and
studies of such reports and related data in addition to those referred to above as he deems
necessary for the performance of the Work at the contract price, within the contract time and
in accordance with the other terms and conditions of the Contract Documents, and no
additional examinations, investigations, tests, reports or similar data are or will be required
by CONTRACTOR for such purposes.
6.4 CONTRACTOR has correlated the results of all such observations, examinations,
investigations, tests, reports and data with the terms and conditions of the Contract
Documents.
6.5 CONTRACTOR has given ENGINEER written notice of all conflicts, errors or
discrepancies that he has discovered in the Contract Documents and the written resolution
thereof by ENGINEER is acceptable to CONTRACTOR.
6.6 CONTRACTOR hereby affirms it will not discriminate on the basis of race, color, religion,
creed, sex, age, marital status, national origin, or because of actual or perceived sexual
orientation, gender identity or disability in the performance of work performed for the city of
Bozeman. This prohibition shall apply to the hiring and treatment of the CONTRACTOR’S
employees and to all subcontracts it enters into in performance of the agreement with the city
of Bozeman.
Article 7. CONTRACT DOCUMENTS.
The Contract Documents which comprise the entire Agreement between OWNER and
CONTRACTOR are attached to this Agreement, made a part hereof and consist of the following:
7.1 This Agreement.
7.2 Exhibits to this Agreement (if any).
7.3 Performance Bond, Payment Bond, and Bid Bond.
7.4 Invitation to Bid.
7.5 Instructions to Bidders and Bid Form.
7.6 Certificate(s) of Insurance.
7.7 General Conditions.
7.8 Supplementary Conditions.
7.9 Wage Rates.
7.10 Project Specifications.
7.11 Montana Public Works Specifications, Sixth Edition, and City of Bozeman Modifications to
Montana Public Works Standard Specifications Sixth Edition, March 31, 2011 (by
reference).
7.12 Addenda listed on the Bid forms.
7.13 CONTRACTOR'S executed Bid forms.
7.14 Documentation submitted by CONTRACTOR prior to Notice of Award.
7.15 Notice of Award.
7.16 Notice to Proceed.
7.17 Any modification, including Change Orders, duly delivered after execution of Agreement.
7.18 Any Notice of Partial Utilization.
7.19 Notice of Substantial Completion.
7.20 Notices of Final Completion and Acceptance.
7.21 Non-discrimination affirmation form.
7.22 Drawings
There are no Contract Documents other than those listed above in this Article 7. The Contract
Documents may only be altered, amended, or repealed by a modification (as defined in the General
Conditions).
Article 8. MISCELLANEOUS.
8.1 Terms used in this Agreement which are defined in the General Conditions shall have the
meanings indicated in the General Conditions.
8.2 This Agreement and all of the covenants hereof shall inure to the benefit of and be binding
upon the OWNER and the CONTRACTOR respectively and his partners, successors,
assigns, and legal representatives. Neither the OWNER nor the CONTRACTOR shall have
the right to assign, transfer or sublet his interest or obligations hereunder without written
consent of the other party. The OWNER reserves the right to withdraw at any time from any
subcontractor where Work has proven unsatisfactory the right to be engaged in or employed
upon any part of the Work.
8.3 In the event it becomes necessary for either party to this Agreement to retain an attorney to
enforce any of the terms or conditions of this Agreement or to give any notice required
herein, then the prevailing party or the party giving notice shall be entitled to reasonable
attorney's fees and costs.
8.4 Any amendment of modifications of this Agreement or any provisions herein shall be made
in writing and executed in the same manner as this original document and shall after
execution become a part of this Agreement.
IN WITNESS WHEREOF, the parties hereto have executed this Agreement the day and year first
above written.
(CONTRACTOR)
By (SEAL &)
(ATTEST)
Title
(JOINT VENTURE)
By (SEAL &)
(ATTEST)
Title
_____________________________
City of Bozeman
(OWNER)
By _____________________________
(CITY MANAGER)
(SEAL &)
(ATTEST)
_____________________________
APPROVED AS TO FORM:
________________________________
(CITY ATTORNEY)
c:\wpdocs\forms\agreefrm.mrg
6.include testing and start-up; and7.be maintained in effect until final payment is made unless otherwiseagreed to in writing by Owner, Contractor, and Engineer with thirtydays written notice to each other additional insured to whom acertificate of insurance has been issued.B.Contractor shall be responsible for any deductible or self-insured retention.C.The policies of insurance required to be purchased and maintained by Contractorin accordance with this Paragraph SCS.06 shall comply with the requirements ofParagraph 5.06.C of the General Conditions.D.The policies of insurance required to be purchased and maintained by Contractorin accordance with this Article 5.06.A shall comply with the requirements of GC -5.06.C. The qualifications of the insurance company shall comply with therequirements of SC-5.02.A.SC-6.02 Working Hours Add the following to Paragraph 6.02.B: Regular working hours are defined as 8:00 AM. to 5:00 P.M. Emergency work may be done without prior permission. SC-6.09 LAWS AND REGULATIONSAdd the following: The Contractor is responsible for proper disposal of all waste soils, materials, and slurries unless otherwise directed herein. Where waste materials are disposed on private property not owned by the Contractor, evidence of property owner's written permission shall be obtained and provided to the Owner. Contractor shall comply with all Local, State, and Federal laws and regulations pertaining to fill in wetlands and floodplains. The Contractor shall dispose of all refuse and discarded materials in an approved location. If this project is greater than 1.0 acres in area, then a storm water pollution prevention plan (SWPPP) is required to be submitted to the Montana Department of Environmental Quality and the City of Bozeman Stormwater Division. If this project disturbs less than 1.0 acres, a SWPPP is required to be submitted to the City of Bozeman Stormwater Division. Compiling and submitting the SWPPP is the responsibility of the Contractor. Section 00810 -6th Edition Supplementary Conditions to the General Conditions Page 7 of 12
SC-6.04 PROGRESS SCHEDULE Delete Paragraph 6.04.A.1 of the General Conditions in its entirety and replace with the following: 1. Contractor shall submit to Engineer with each application for payment an updated progress schedule reflecting the amount of work completed and adjustments to future work. Such adjustments will be acceptable to Engineer as providing an orderly progression of the Work to completion within any specified milestones and the Contract Time. No progress payment will be made to Contractor until the updated schedules are submitted to and acceptable to Engineer and Owner. Review and acceptance of progress schedules by the Engineer will neither impose on Engineer responsibility for the sequencing, scheduling or progress of the Work, nor interfere with or relieve Contractor from Contractor's full responsibility therefore.
SC-6.13 SAFETY AND PROTECTION Change Supplementary Conditions in paragraph 6.13.C to Special Provisions. Add new paragraphs to the end of paragraph 6.13.F of the General Conditions as follows: G.It is expressly understood by the parties to this Agreement that the Contractor is solely responsible for initiating, maintaining, and supervising safety precautions and programs in connection with the Work. The right of the Owner and Engineer to observe or otherwise review the Work and operations shall not relieve the Contractor from any of his covenants and obligations hereunder. Contractor shall incorporate all safety requirements into his construction progress and work schedules including preconstruction and scheduled monthly safety meetings, posted safety rules, tailgate meetings, and site inspections by safety and other inspectors employed by the Contractor.H.The Contractor shall be responsible for and shall take necessary precautions and provide all material and equipment to protect, shore, brace, support and maintain all underground pipes, conduits, drains, sewers, water mains, gas mains, cables, etc., and other underground construction uncovered in the proximity, or otherwise affected by the construction work performed by him. All pavement, surfacing, driveways, curbs, walks, buildings, grass areas, trees, utility poles or guy wires damaged by the Contractor's operations in the performance of this work shall be repaired and/or replaced to the satisfaction of the Owner, Engineer, and effected property owner at the Contractor's expense. The Contractor shall also be responsible for all damage to streets, roads, highways, shoulders, ditches, embankments, culverts, bridges, or other public or private property or facility, regardless of location or character, which may be caused by moving, hauling, or otherwise transporting equipment, materials, or men to and from the work or any part of site thereof; whether by him or his subcontractors. The Contractor shall make satisfactory and acceptable arrangements with owner of, or the agency or authority having jurisdiction over, the damaged property or facility concerning its repair or replacement or payment of costs incurred in connection with said damage.Section 00810 -6th Edition Supplementary Conditions to the General Conditions Page 8 of 12 This plan must be approved by both the city and/or the Montana DEQ prior to scheduling a preconstruction meeting. No construction activities may take place under this contract until the SWPPP has been approved. Please allow 1 week for the City to review the SWPPP.The Contractor shall exercise all reasonable precautions throughout the life of the project to prevent pollution or siltation of the city stormwater system, rivers, streams or impoundments. Pollutants such as chemicals, slurries, fuels, lubricants, bitumens, raw sewage, and other harmful wastes shall not be discharged into the city stormwater system or into or alongside of rivers, streams, impoundments or into natural or manmade channels leading thereto. In addition, the Contractor shall conduct and schedule his operations to avoid muddying or silting of rivers, streams or impoundments. The Contractor shall meet the requirements of the applicable regulations of the Montana DEQ, Department of Fish, Wildlife and Parks, Department of Health and Environmental Sciences and other State or Federal regulations relating to the prevention or abatement of water pollution and siltation. The Contractor's specific attention is directed to the Montana Water Quality Act and the Montana Stream Preservation Act.The Contractor shall be responsible for obtaining any required discharge permits associated with groundwater de-watering operations and stormwater runoff. All debris or waste materials shall be cleaned up by the end of the work day.
J.Safety provisions must be entirely adequate and meet with City or State andFederal regulations to protect the public on these streets and roads.SC- 6.20 INDEMNIFICATION Add a new paragraph immediately after paragraph 6.20.A. of the General Conditions which is to read as follows: I. The Contractor shall conduct his work so as to interfere as little as possible with public travel, whether vehicular or pedestrian. Whenever it is necessary to cross, obstruct, or close roads, driveways, and walks, whether public or private, the Contractor shall obtain approval from the governing party and shall, at his own expense, provide and maintain suitable and safe bridges, detours, and other temporary expedients for the accommodation of public and private drives before interfering with them. The provisions for temporary expedients will not be required when the Contractor has obtained permission from the owner and tenant of the private property, or from the authority having jurisdiction over public property involved, to obstruct traffic at the designated point.SC-9.03 PROJECT REPRESENTATIVE Refer to the Special Provisions for identification of the responsibilities and authority and limitations of the Engineer's Resident Project Representative (if any). SC-11.01 COST OF THE WORK Delete paragraph 11.01 .A.5 .c of the General Conditions in its entirety and insert the following in its place: 11.01.A.5.c The rental of all construction equipment and machinery and parts thereof whether rented from Contractor or rented from others. The cost shall be calculated as follows and will include the costs of transportation, loading, unloading, assembly, dismantling and removal thereof for equipment involved only in the changed portion of the work covered under the cost of the Work method. Transportation, loading and assembly costs will not be included for equipment already on the site which is being used for other portions of the Work. The cost of any such equipment, machinery, or parts shall cease when the use thereof is no longer necessary for the Work. Hourly equipment and machinery rates shall be calculated from the Rental Rate Blue Book for Construction Equipment, and the Equipment List submitted according to SC 2.05 and SC 2.07, and as follows: 1.For working equipment, the hourly rate shall be the monthly rental ratedivided by 176 hours per month plus the hourly operating cost.2.For equipment on standby, the hourly rate shall be 50% of the monthlyrental rate divided by 176 hours per month, and the hourly operating costshall not be applied.3.For specialized equipment rented for a short duration used for changeorder work or additional work not part of the scope of work bid, theSection 00810 -6th Edition Supplementary Conditions to the General Conditions Page 9 of 12 While Owner and Engineer may have the right under this Contract to observe or otherwise review the work, progress and operations of the Contractor, it is expressly understood and agreed that such observation shall not relieve the Contractor from any of its covenants and obligations hereunder.
Section 00810 – 6th Edition
Supplementary Conditions to the General Conditions
Page 10 of 12
equipment rental rates will be negotiated prior to the work being
performed.
SC-l1.03 UNIT PRICE WORK
2. the total cost of the particular individual item of Unit Price Work amounts to 10% or
more of the Contract Price which is the total sum of all schedules (if any), and
l. the quantity of a particular item of Unit Price Work performed by Contractor differs by
more than 25% from the estimated quantity of such item indicated in the Agreement, and
Delete paragraph 11.03.D.1 and 2 of the General Conditions in its entirety and insert the
following in its place:
Contractor.
4. Each application for progress payment shall be accompanied by Contractor’s
updated progress schedule, shop drawing schedule, procurement schedule, and
other data specified herein or reasonably required by Owner or Engineer. The
Owner reserves the right to require submission of monthly certified payrolls by the
Add a new paragraph after paragraph to 14.02.A.3 to read:
In accordance with state law the Owner may accept deposited securities in lieu of cash
retainage. Retainage may be used by the Owner to offset costs for any of the losses
enumerated in Paragraphs l4.02.B.5.a through 14.02.B.5.d inclusive, 14.02.D.1.a. through
14.02.D.1.d inclusive, or 15.02.C. In addition retainage may be used by the Owner to
protect against loss from failure by the Contractor to complete necessary work and to
offset any liquidated damages due Owner.
Add the following to Paragraph 14.02.A.3:
Payments for materials in storage shall be based only upon the actual cost of the materials
and equipment to Contractor and shall not include any overhead or profit. Bill of Sale,
invoice or other document warranting clear title for materials in storage will be waived
for the material in storage included in the first progress payment application. However,
proof of payment and clear title must be submitted with Application No. 2 for all material
included in Application No. 1. Without such documentation amounts paid for materials in
storage will be deducted from subsequent payments. Beginning with the second
application, all requests for payment for materials in storage shall be accompanied by Bill
of Sale, invoice or other document warranting clear title as required above.
Add the following language at the end of paragraph 14.02.A.1 of the General Conditions:
SC- 14.02.A APPLICATIONS FOR PAYMENTS
SC- 13.07 CORRECTION PERIOD
The correction period for defective work shall be two (2) years following the notice of completion
instead of one (1) year as noted in the General Conditions.
Section 00810 – 6th Edition
Supplementary Conditions to the General Conditions
Page 11 of 12
SC – 14.02.C PAYMENT BECOMES DUE
Delete Paragraph 14.02.C.1 of the General Conditions in its entirety and insert the following in
its place:
1. The Owner will, upon presentation to him of the Contractor’s Application for
Payment with Engineer’s recommendation, review and act upon said payment
request once each month on or about the day of each month stipulated by the
Owner at the preconstruction conference. Payment will become due when Owner
approves the application for payment and when due, will be paid by Owner to
Contractor.
SC- 14.02.D.1.c
Amend the sentence of Paragraph 14.02.D.1.c to read:
…entitling Owner to a set-off against the amount recommended, including liquidated
damages;or...
SC-14.03 CONTRACTORS WARRANTY OF TITLE
Add the following at the end of Paragraph 14.03.A of the General Conditions:
Neither recommendation of any progress payment by Engineer nor payment by the
Owner to Contractor, nor any use or occupancy of the Work or any part thereof will
release the Contractor from complying with the Contract Documents. Specifically the
Contractor shall maintain in accordance with Article 5, property insurance on all Work,
materials, and equipment whether incorporated in the project or not and whether included
in an application for payment or not, for the full insurable value thereof. Passing title to
Owner for materials and equipment included in an application for payment does not
relieve the Contractor of the Contractor’s obligation to provide insurance (including
property insurance) as required in Article 5 of the General Conditions and these
Supplementary Conditions. All insurance shall remain in effect as provided in Article 5.
SC- 14.05 PARTIAL UTILIZATION
Add the following to Paragraph 14.05.A:
Owner has the right to take possession of or use any completed or substantially
completed portions of the work at any time, but such taking possession or use will not be
deemed an acceptance of any work not completed in accordance with the Contract
Documents. Owner’s use of any facilities so identified in the Contract Documents will
not be grounds for extension of the contract time or change in the contract price. Owner’s
use of any facilities not specifically identified in the Contract Documents will be in
Section 00810 – 6th Edition
Supplementary Conditions to the General Conditions
Page 12 of 12
accordance with conditions agreed to prior to such use, and any extra costs or delays in
completion incurred and properly claimed by Contractor will be equitably adjusted with a
Change Order. Facilities substantially completed in accordance with the Contract
Documents which are occupied or used by Owner prior to substantial completion of the
entire work will be done in accordance with General Conditions 14.04. Guarantee
periods for accepted or substantially completed work including mechanical and electrical
equipment will commence upon the start of continuous use by Owner. All tests and
instruction of Owner’s personnel must be satisfactorily completed, and Owner shall
assume responsibility for and operation of all facilities occupied or used except as may
arise through portions of work not yet completed by Contractor If the work has been
substantially completed and the Engineer certifies that full completion thereof is
materially delayed through no fault of the Contractor, the Owner shall, without
terminating the Agreement, make payment of the balance due for the portion of the work
fully completed and accepted.
SC- 14.06 FINAL INSPECTION
Add the following to Paragraph 14.06.A:
After Contractor has remedied all deficiencies to the satisfaction of the Engineer and
delivered all construction records, maintenance and operating instructions, schedules,
guarantees, bonds, certificates of inspection, and other documents (all as required by the
Contract Documents), Owner and Contractor shall be promptly notified in writing by
Engineer that the work is acceptable.
SC- 17.01 GIVING NOTICE
Add the following to Paragraph 17.0l.A:
The mailing address for giving notices to Contractor given in the Agreement is hereby
designated as the place to which all notices, letters, and other communication to
Contractor will be mailed or delivered. The mailing address for giving notices to Owner
given in the Agreement is hereby designated as the place to which all notices, letters, and
other communication to Owner shall be mailed or delivered. Either party may change his
address at any time by an instrument in writing delivered to Engineer and to other party.
END OF SECTION 00810
01010-1
SECTION 01010
SUMMARY OF WORK
PART 1 – GENERAL
1.01 DESCRIPTION OF WORK
A. The Project consists of the installation of new LFG extraction wells and associated buried
piping and valves and fittings at the Story Mill Road Landfill in Bozeman, Montana and
other appurtenances as identified on the plans and herein.
B. The work shall include the installation of three LFG wells, construction of below grade
LFG and leachate/condensate, providing and installing pre-cast vaults, connecting below
grade LFG piping to an existing LFG collection system and all other appurtenant
equipment as shown in the Construction Drawings and as specified herein. The
CONTRACTOR shall replace in kind any existing improvements (drainage channels,
asphalt millings roads, etc.) damaged during the course of construction at no cost to the
City of Bozeman (OWNER).
C. The OWNER may award separate contracts for portions of the Project that are to be
completed simultaneously with the Work. The CONTRACTOR shall cooperate with the
OWNER and other CONTRACTORS so that the OWNER’S work, including landfill and
farming operations, or work by other CONTRACTORS, can be carried out smoothly.
D. No additional and/or extra compensation will be given for all and/any increases to direct
labor costs, subcontract costs, costs of materials and equipment, which includes all fuels.
1.02 WORK HOURS
A. Unless otherwise changed by the OWNER, construction activities and material deliveries
to the Facility shall be limited to the hours of 7AM to 6 PM. No work outside these hours
will be allowed without written approval from the OWNER.
1.03 DISPOSAL OF REFUSE
A. The CONTRACTOR may encounter waste during construction activities on the existing
landfill. All removal and disposal of construction debris or waste generated during
construction is the responsibility of the CONTRACTOR at no additional cost to the
OWNER.
01010-2
1.04 FAMILIARIZATION
A.Prior to implementing any work, the CONTRACTOR shall become thoroughly familiar
with the site, the site conditions, and all portions of the work falling within this Project and
the CQA Plan.
B.Inspection:
1.Prior to implementing any of the work, the CONTRACTOR shall carefully inspect
the site and equipment and verify that the existing piping is complete to the point
where the work may properly commence without adverse impact. This would
include the location and condition of the header pipe daylight.
2.If the CONTRACTOR has any concerns regarding the site, the CONTRACTOR
shall notify the ENGINEER and the OWNER in writing within 48 hours of the site
visit. Failure to notify the OWNER or the ENGINEER prior to installation of all
items shall be construed as CONTRACTOR’S acceptance of the related work of all
other Sections.
3.The CONTRACTOR shall verify as-built conditions prior to placement and/or
excavation of any material.
4.The CONTRACTOR shall be responsible for locating all underground utilities
prior to excavation of any material.
1.05 PRECEDENCE OF DOCUMENTS
A.The Montana Public Works Standard Specifications and Montana Department of
Transportation Specifications will be referenced where applicable. In case there is a
discrepancy or conflict between these specifications and the project specific Construction
Drawings and Project Specifications, the project specific documents will govern.
1.06 CONTRACTOR’S USE OF PREMISES
A.CONTRACTOR shall coordinate use of the premises, for his storage and the operation of
his workmen, with OWNER and utility service companies.
B.The full use of the premises for storage, the operations of workmen and for all other
construction activities will not be available to CONTRACTOR. CONTRACTOR must
operate entirely within the space allowed to him. The Drawings define the area allocated to
CONTRACTOR.
C.CONTRACTOR shall be solely responsible for obtaining and paying all costs in
connection with any additional work area, storage sites, and access to the site or temporary
right-of-way that may be required for proper completion of the Work.
D.It shall be understood that responsibility for protection and safe-keeping of equipment and
materials on or near the site will be entirely that of CONTRACTOR and that no claim shall
be made against the OWNER or his authorized representatives by reason of any act. It shall
01010-3
be further understood that should any occasion arise necessitating access to the sites
occupied by these stored materials or equipment, the ENGINEER shall direct
CONTRACTOR owning or responsible for the stored materials and equipment to
immediately move the same. No materials or equipment may be placed upon the property
of the OWNER, other than in the designated areas as shown on the Drawings, unless the
ENGINEER has agreed to the location contemplated by CONTRACTOR to be used for
storage. All stored materials shall be labeled according to the appropriate CONTRACTOR
or SUBCONTRACTOR with the manufacturer’s label as well. Appropriate material safety
data sheets (e.g., MSDS) shall be provided.
E.CONTRACTOR shall be required to share use of the premises with other
CONTRACTORS whose services the OWNER has obtained or will obtain for construction
of other facilities on the site.
F.The Bozeman Convenience Site must remain open and usable to the public during its
normal business hours (8:00 a.m. to 3:30 p.m. Tuesday through Saturday). Any
construction activities that would obstruct public access (for example trenching and
burying pipe across the entrance) must be done while the Convenience Site is closed.
1.07 AGENCY AND PRIVATE ENTITY COORDINATION & PERMITTING
The work to be performed for this project will require significant planning and coordination with
City, County, and private agencies. The ENGINEER is responsible for obtaining the building
permit. The CONTRACTOR is responsible for obtaining all other permits, payment of fees
and/or coordinating with all involved as needed to perform the construction as indicated on the
project plans.
The following is a list of anticipated public agencies and private entities requiring involvement in
this project:
Montana811
Underground Utility Locator
Dial 811
1.08 PROJECT SCHEDULING
Information pertaining to the preparation and submittal of the construction schedule is contained in
Section 1300. The timing of construction is critical. It is imperative that the collection system downtime
is minimized.. The construction should be substantially complete by June 30, 2023.
1.09 SUBSTANTIAL COMPLETION
A.Substantial Completion means, but is not limited to the completion of the following:
1.Green tag on all electrical work;
2.All systems in place, functional, and displayed to the OWNER or its
representatives;
01010-4
3. Construction Complete;
4. Materials and equipment installed;
5. Punch List items have been identified, itemized, and scheduled for completion;
6. Draft O&M Manuals and record documents reviewed and accepted by the
OWNER;
7. HVAC test and balance completed (provide minimum 30 days prior to projected
substantial completion);
8. Landscaping and site work completed; and
9. Final cleaning.
1.10 FINAL ACCEPTANCE
A. Final Acceptance means the project work is complete; the ENGINEER and the OWNER has
approved and accepted the project work as complete. This shall include, but is not limited to:
1. All punch list items have been completed;
2. All systems reviewed and accepted by the OWNER;
3. Final O&M Manuals and record documents reviewed and accepted by the
OWNER;
4. OWNER’s operation and maintenance training complete
1.11 LIQUIDATED DAMAGES
A. Liquidated damages shall be One Thousand Dollars ($1,000) per day that substantial
completion extends beyond the date determined by the contract time as adjusted.
PART 2 – PRODUCTS
Not Used.
PART 3 – EXECUTION
Not Used.
END OF SECTON
01029-1
SECTION 01029
MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.01 CONTRACT PAY ITEMS
This section includes the items of work and the basis of payment for City of Bozeman
Story Mill Road Landfill Gas (LFG) and Leachate/Condensate System Project. The
CONTRACTOR shall Bid Items 1 through 12 below separately and provide unit prices
and a total sum for all work items. The CONTRACTOR is responsible for supplying all
materials, equipment, and labor necessary for the complete construction and installation
of all work as described in these specifications and as shown on the Construction
Drawings. Payment for each work item will be made on either a unit price or lump sum
basis, and only after that portion of the project has been completed.
1.LFG Drill Rig Mobilization/Demobilization: This task includes any and all temporary
facilities and utilities, safety plans, and construction equipment required for this project.
LFG drilling involves drilling through municipal waste and as such is specialized drilling.
Payment for this work will be made on a lump sum basis. Fifty (50) percent of the lump
sum price bid will be paid with the first payment request following satisfactory evidence
of mobilization of sufficient labor, equipment, and material to adequately progress the
work of this contract. Fifty (50) percent of the lump sum price bid will be paid with the
Final Payment request once drilling has been completed. The price bid in the proposal for
this item shall not exceed ten (10) percent of the drilling total amount.
2.LFG Well Vertical Drilling and Completion: Supply all material, equipment, and labor
necessary for the drilling of approximately 225 vertical feet of LFG wells as shown on
the Construction Drawings. This item shall include all resources necessary to prepare
access roads and drill rig pads, drilling the LFG well borings, and returning the drill
location to its original condition. This item includes the installation of the well casing,
backfill material, and finishing the wellhead. Payment for this item shall be per vertical
foot installed as measured from ground surface down to the bottom of the casing. Excess
drill cuttings consisting of clean soil shall be hauled and disposed by the Contractor to a
location on the Landfill property designated by the Owner. Excess cuttings consisting of municipal waste shall be hauled and disposed of by the Contractor to the Logan Landfill and will be paid separately under Item 6 below.
3.Piping Crew Mobilization and Demobilization: This task includes any and all temporary
facilities and utilities, safety plans, and construction equipment required for this project.
Stormwater pollution prevention permitting is included under this item. Payment for this
work will be made on a lump sum basis. Fifty (50) percent of the lump sum price bid
will be paid with the first payment request following satisfactory evidence of
mobilization of sufficient labor, equipment, and material to adequately progress the
work of this contract. Fifty (50) percent of the lump sum price bid will be paid with the
Final Payment request once all field construction has been completed. The price bid in
the proposal for this item shall not exceed ten (10) percent of the bid amount subtotal for
construction not including LFG well drilling.
4.8” SDR 17 HDPE LFG pipe and fittings: Supply all materials, equipment and labor
for the construction and installation of approximately 880 lineal feet of below
01029-2
grade 8” diameter HDPE SDR 17 piping as shown on the Construction Drawings.
Include all labor and materials for the HDPE pipe, fittings, joining, and necessary
trenching, excavation, shoring, backfill material, backfilling, compaction, and returning
the site to its original condition. Payment for this item shall be per lineal foot
installed along the pipe centerline including the length through vaults. If
municipal solid waste is encountered during excavation for this item, its removal
and disposal is paid for separately. Excess excavation not used in backfill shall be
hauled and disposed by the Contractor to a location on the Landfill property designated
by the Owner. Surveying and staking for pipeline layout is incidental to this item.
5.Corrugated 12” HDPE Sleeve: Supply all materials, equipment, and labor to install
20 lineal feet of 18” HDPE N-12 pipe sleeve with enclosed 8” SDR 17 HDPE pipe, as
shown on the Construction Drawings. Include all labor and materials for the HDPE pipe,
joining, and necessary trenching, excavation, shoring, backfill material, backfilling,
compaction, and returning the site to its original condition. Pavement will be replaced by
the owner. Payment for this item shall be per lineal foot installed. If municipal solid
waste is encountered during excavation for this item, its removal and disposal is paid for
separately. Excess excavation not used in backfill shall be hauled and disposed by the
Contractor to a location on the Landfill property designated by the Owner.
6.Waste Excavation and Disposal. If any municipal solid waste is encountered during
excavation, this item shall include excavating, loading, hauling, and unloading the waste
at the Logan Landfill. This item shall also include tipping fees for the waste. Payment for
this item shall be per ton of waste disposed at the Logan Landfill as measured by the
number of tons documented on weight tickets from the Landfill.
7.Type 2 Pipe Bedding. If municipal solid waste is encountered, supply and install Type 2
pipe bedding and geotextile as shown on the Drawings. Payment for this item shall be by
the lineal foot of trench as measured along the pipe centerline in which Type 2 bedding is
placed.
8.2” diameter SDR 17 HDPE Drainpipe. Supply all materials, equipment and labor for the
construction and installation of approximately 60 lineal feet of below grade 2" diameter
HDPE SDR 17 piping as shown on the Construction Drawings. Include all labor and
materials for the HDPE pipe, fittings, joining, and necessary trenching, excavation,
shoring, backfill material, backfilling, compaction, and returning the site to its original
condition. Payment for this item shall be per lineal foot installed along the pipe centerline
not including the vertical length of pipe in the J-Trap shown on the drawings. If
municipal solid waste is encountered during excavation for this item, its removal and
disposal is paid for separately. Excess excavation not used in backfill shall be hauled
and disposed by the Contractor to a location on the Landfill property designated by
the Owner. Surveying and staking for pipeline layout is incidental to this item.
9.8” diameter SDR 17 HDPE Leachate/Condensate Drainpipe. Supply all materials,
equipment and labor for the construction and installation of approximately 744 lineal feet
of below grade 82" diameter HDPE SDR 17 piping as shown on the Construction
Drawings. Include all labor and materials for the HDPE pipe, fittings, joining, and
necessary trenching, excavation, shoring, backfill material, backfilling, compaction, and
returning the site to its original condition. Payment for this item shall be per lineal foot
01029-3
installed along the pipe centerline including the length through vaults. If municipal solid
waste is encountered during excavation for this item, its removal and disposal is paid for
separately. Excess excavation not used in backfill shall be hauled and disposed by the
Contractor to a location on the Landfill property designated by the Owner. Surveying and staking for pipeline layout is incidental to this item.
10.48” Diameter Manholes. Supply all materials, equipment and labor for the construction
and installation of two (2) standard straight precast manholes with cover slab, casting and
cover, steps and built-in channels. Work includes excavation, backfilling, backfill
material, dust control, gravel, finishing, and returning the site to its original condition.
This item also includes the connection of HDPE pipe to the manholes with a watertight
fitting. Payment for this item shall be per unit installed. Excess excavation not used in
backfill shall be hauled and disposed by the Contractor to a location on the Landfill
property designated by the Owner.
1.02 NON-PAY ITEMS
No separate payment will be made for items not specifically set forth in the bid proposal.
Include costs for such items in prices named in the bid proposal for identified items of
work. Items of work described in Contract Documents, but not listed in the Schedule of
Work items of the bid form are, in general, applicable to more than one listed work item.
Therefore, no separate work item is provided. Include costs of work not listed but
necessary to complete the project per the Contract Document in listed Work items of the
bid form.
1.03 TOTAL COST
Bids for Work are intended to establish a total cost for the work in its entirety. Should the
CONTRACTOR feel that the cost for the Work has not been completely established by
specific items in the bid form, he shall include the cost for that work in some related bid
item so that his bid proposal reflects the total cost for completing the Work in
its entirety.
1.04 QUANTITY OVERRUNS
No payment will be made for quantity overruns unless work is expressly required by the
Contract Documents or authorized in writing by the OWNER or OWNER’S
Representative in advance of the work.
01029-4
1.05 PROGRESS PAYMENTS
Progress payments will be processed monthly as described in the Contract Documents.
PART 2 - PRODUCTS
Not used.
PART 3 - EXECUTION
Not used.
END OF SECTION
SECTION 01410 QUALITY ASSURANCE TESTING, QUALITY CONTROL TESTING
PART 1- GENERAL
1.01 SECTION INCLUDES
A. Construction Quality Assurance (CQA) testing by the ENGINEER.
B. Construction Quality Control (CQC) testing by CONTRACTOR.
C. Certificates of Compliance.
1.02 RELATED SECTIONS
A. Section 01300- Submittals.
1.03 SOURCE OF MATERIALS
A. CONTRACTOR must notify the ENGINEER in writing of the sources from which it proposes to obtain material if different from Drawings and requiring the
ENGINEER approval, certification, or quality assurance testing. Such notification
must be made as soon as possible after award of Contract but no later than 5 days after receipt of the Notice to Proceed. Samples of the proposed material must be provided to the ENGINEER upon request.
1.04 CONSTRUCTION QUALITY ASSURANCE TESTING
A. CQA testing is the testing of materials, before their inclusion in the work, and
materials and workmanship, after their inclusion in the work.
B. CQA testing will be performed by the ENGINEER contracted by the OWNER as a basis for acceptance of the completed work.
C. The ENGINEER will perform CQA testing in accordance with the Specifications.
However, the ENGINEER reserves the option to perform additional CQA testing
at any time to determine conformance of the materials and workmanship in accordance with the Contract Documents.
D. CQA testing performed by the ENGINEER does not relieve the CONTRACTOR
of the obligation to perform and document quality control testing of materials and workmanship.
01410-1
PART 1:
SECTION 01570
CONSTRUCTION TRAFFIC CONTROL
GENERAL
1.1 DESCRIPTION
A. This work is the furnishing of labor, materials and equipment for installing,maintaining and operating traffic control devices to insure the safety of the general public and project personnel.
1.2 REQUIREMENTS
A. Perform work under this section meeting Manual of Uniform Traffic Control Devices (MUTCD) and contract requirements.
1.3 NOTIFICATIONS
A.
B.
C.
PART 2:
Coordinate all construction activities to reduce traffic conflicts at the work site, off-site events or other construction projects.
Furnish the Engineer, for Owner review, the construction traffic control plan at least one week before construction begins or before changes in segments or phases of the work on the project. The Owner will review and approve the Traffic Control Plan considering known off-site activities and may require modification to the plan or construction timing to coordinate events. Work shall not commence until said plan is approved.
For project sites involving a through street, provide the Engineer with a news release. Include in the news release, as a minimum, the work activity and duration. Once approved, furnish the news release to the local media at least three days before starting work. Notify all landowners or residents adjacent to the work of the type and duration of the construction.
PRODUCT
2.1 TRAFFIC CONTROL DEVICES
A. Assure all signs and barricades are reflectorized. Assure all night time trafficcontrol devices meet MUTCD lighting requirements.
B. Use traffic control devices meeting the "Manual of Uniform Traffic Control Devices" and the "Traffic Control Devices Handbook" requirements, availablefrom the Superintendent of Documents, U.S. Government Printing Office,Washington, D.C. 20492.
C. Assure all traffic control devices are clean, legible, reflective for night-time use, and operable.
Section 01570 - 6th Edition CONSTRUCTION TRAFFIC CONTROL Page 1 of3
1.3 STANDARD DRAWINGS
A. Standard Drawings applicable to this section are as follows:
1. Standard Drawing No. 02221-1 - Typical Utility Trench Detail
1.4 TESTING
A. Field Density Testing
1. Meet the quality control and quality assurance testing requirements in
Section 01410, Contractor Quality Control and Owner Quality Assurance.
2. In-place field density tests for quality assurance are at Owner expense
meeting AASHTO T191 (ASTM D1556), Sand Cone Method; or by
AASHTO T310 (ASTM D6938) Nuclear Densometer Methods. Quality
assurance field density testing frequency is at the Engineer's discretion.
3. Re-testing failing areas is at the expense of the Contractor.
4. At the direction of the Engineer, provide necessary equipment and labor
to excavate and replace materials for test holes up to 5 feet deep into the
compacted backfill to allow testing below the surface of any layers
covered without inspection and approval by the Engineer.
B. Laboratory Maximum Density and Optimum Moisture
1. Quality assurance tests will be made by the Engineer for each on-site
natural soil or each source of off-site material, including borrow material,
to determine the laboratory maximum density values and optimum
compaction moisture content according to AASHTO T-99 or ASTM
D698.
C. Material Submittals
1. Submit to the Engineer material quality test results including Type 1
Bedding gradation and plasticity index; and Type 2 Bedding gradation.
2. Submit to the Engineer samples of on-site and off-site borrow soils for
laboratory moisture-density relationship testing by the Engineer.
3. If applicable, submit a blasting plan to the Engineer.
Section 02221 — 6th Edition
TRENCH EXCAVATION AND BACKFILL
FOR PIPELINES & APPURTENANT STRUCTURES
Page 2 of 17
15900-1
SECTION 15900
PRESSURE TESTING OF PIPE
PART 1 - GENERAL
1.01 REQUIREMENTS INCLUDED
A. Leak testing shall be conducted by the Contractor on the following lines:
a. All LFG extraction piping installed by the Contractor.
b. All condensate discharge piping.
B. The procedure and equipment to be used shall be approved by the Engineer prior
to testing any line. Leakage tests shall be performed on all piping after
installation and before backfilling where pipe is buried or encased.
PART 2 - TESTING EQUIPMENT
2.01 GENERAL
The Contractor shall provide necessary piping connections between the section of line
being tested and the nearest available source of air, or test fluid, together with test
pumping equipment, pressure gauge and other equipment, materials and facilities
necessary to make the specified tests. The Contractor shall provide temporary
sectionalizing devices and vents as required for testing. Vents are to be left plugged if
not required for the permanent installation.
PART 3 - EXECUTION
3.01 TESTING PROCEDURE
A. The specified test pressures shall be as measured at the horizontal centerline of
the lowest point of the piping under test.
B. Each pipeline shall be adequately braced and supported before tests are made.
Partial backfilling between joints of pipelines in trenches is permissible to prevent
movement under test pressure, subject to approval by the Engineer.
C. Pipelines that have no valves may be closed with blind flanges or caps on the ends
of the section to be tested. Discrete sections of the system can be pressure tested
separately in order to isolate leaks, however the final pressure test may be
performed on large sections of the system.
15900-2
D. Tests shall be made before the piping has been enclosed in any manner that will
prevent inspection during the test.
E. Leakage testing for the LFG extraction system piping shall be performed by
pressurizing piping to 2 psig and holding for one hour with no more than 0.5 psig
pressure drop within that time frame. Allowable pressure drop may be increased
for pipe sections longer than 600’. A soap and water solution (leak detection
fluid) must be applied to all joints and the joints inspected for leakage by the
formation of bubbles at the point of leakage. Any leaks detected must be repaired
even if the test meets the set requirements. All of these lines, either individually
or in common, are to be pressurized to 2 psig. All joints and connections shall be
visually inspected for leaks after applying the leakage detecting fluid.
F. Leakage testing for the condensate system piping shall be performed by
pressurizing piping to 125 psig and holding for one hour with no drop in pressure.
A soap and water solution (leak detection fluid) must be applied to all joints and
the joints inspected for leakage by the formation of bubbles at the point of
leakage. Any leaks detected must be repaired even if the test meets the set
requirements. All of these lines, either individually or in common, are to be
pressurized to 125 psig. All joints and connections shall be visually inspected for
leaks after applying the leakage detecting fluid.
G. The Contractor, at his own expense, shall make necessary repairs or replacements
in accordance with the Specifications. Repairing and testing shall be repeated
until the pipeline installation conforms to the specified requirements and is
acceptable to the Engineer.
H. After the test has been concluded, the pipeline shall be restored to a condition
satisfactory to the Engineer.
I. It is intended that piping, whether tested after installation or not, shall be air-tight
and free from visible leaks. Each leak which is discovered within one year after
final acceptance of the work by the COP shall be repaired by and at the expense
of the Contractor.
J. Pumps, air compressors, instrumentation and similar equipment shall not be
subjected to the pressure tests.
15900-3
K. All pressure testing performed shall be witnessed by the Engineer. The
Contractor shall maintain a record of all pressure tested components. Each line
item of the record shall be accepted by the Engineer. Acceptance of the pressure
test by the Engineer shall not release the Contractor from its warranties.
END OF SECTION
JANUARY 2023
BOZEMAN LANDFILL
CONSTRUCTION PLANS
BOZEMAN, MONTANA
INDEX OF DRAWINGS
LFG AND LEACHATE/ CONDENSATE SYSTEM IMPROVEMENTS REBID
LOCATION MAP
N.T.S.
VICINITY MAP
N.T.S.
SITE ADDRESS: 2143
STORY MILL ROAD
BOZEMAN, MONTANA
SITE LOCATION
VAULT (EXISTING)
AI WELL (EXISTING)
SVE WELL (EXISTING)
LEGEND
MAJOR CONTOUR (EXISTING)
MINOR CONTOUR (EXISTING)
SVE PIPELINE (EXISTING)
AIR LINE (EXISTING)A
METHANE WELL (EXISTING)
TREE
BUSH
METHANE PIPELINE (EXISTING)
SVE PIPELINE (PROPOSED)
SVE PIPELINE ROAD CROSSING (PROPOSED)
SVE WELL (PROPOSED)
G-001 COVER SHEET (THIS SHEET)
G-002 EXISTING CONDITIONS
P-101 LFG EXTRACTION SYSTEM
PLAN AND PROFILE
P-102 LEACHATE/ CONDENSATE PIPELINE
PLAN AND PROFILE
D-101 LFG EXTRACTION SYSTEM DETAILS
D-102 LFG EXTRACTION SYSTEM DETAILS
MARK DATE DESCRIPTION BY
Checked By:
Drawn By:
Project No.:
Designed By:
www.tetratech.com
1/10/2023 8:22 AM - O:\A-G\BOZEMAN CITY OF\114-560487E - 2020-2021 REMEDIATION SYSTEMS\07-CAD\SHEETFILES\LFG PLANS\G-001 COVER SHEET.DWG1
A
2 3 4 5 6 7
B
C
D
E
F
Bar Measures 1 inch
114-560487E
JSS
LC
G-001
Copyright Tetra TechBOZEMAN, MONTANA
2023 LFG AND EACHATE/ CONDENSATE SYSTEM IMPROVEMENTS REBID
BOZEMAN LANDFILL
COVER SHEET825 W. Custer Ave.
Helena, Montana 59602
PHONE: 406-443-5210 FAX: 406-442-7182
ISSUED FOR REBID1/23 LC
4750
4760
4770
4780
4790
4800
4810
4820
4830
4840
G
G
Flare
Station
G
G G
G
GGG
G
G
GGGG
G GGGGOHPOHPOHPOHPOHPOHPSSUGT
SSSSSSSSSSSS
S
SSS
S
SS
S
S
S
S
S
S
SS
UGP
UGP
P
EXISTING
LYSIMETER
LANDFILL
OFFICES &
SHOP
EXISTING LEACHATE UST
MCLLHATTAN ROADSTORY MILL ROADLANDFILL
CONVENIENCE
EXISTIN
G
U
N
L
I
N
E
D
C
E
L
L
WITH LF
G
C
O
L
L
E
C
T
I
O
N
S
Y
S
T
E
M
4790480048104820483048404850ASBESTOS WASTE AREAEXISTING LFG HANDLING
SYSTEM & FLARE
CELL BOUNDARY
CELL BOUNDARY
S
T
O
R
M
W
A
T
E
R
P
O
N
D
CONTR
A
C
T
O
R
A
C
C
E
S
S
CONTRACTOR A
C
C
E
S
S
CONTRACTOR
ACCESS
CONTRACTOR
ACCESS
EXISTING
LINED CELL
CONTR
A
C
T
O
R
A
C
C
E
S
S
4
7
5
0
4760
4770
4780
4790
4800
4810
482
0
4830
4740
4740
4750
4760 4750
4760
4770
4780
4
7
2
0 47304860487048804890N
0
SCALE:
50 100 200
1" = 100'
MARK DATE DESCRIPTION BY
Checked By:
Drawn By:
Project No.:
Designed By:
www.tetratech.com
1/10/2023 8:23 AM - O:\A-G\BOZEMAN CITY OF\114-560487E - 2020-2021 REMEDIATION SYSTEMS\07-CAD\SHEETFILES\LFG PLANS\G-002 EXISTING CONDITIONS.DWG1
A
2 3 4 5 6 7
B
C
D
E
F
Bar Measures 1 inch
114-560487E
JSS
LC
G-002
Copyright Tetra TechBOZEMAN, MONTANA
2023 LFG AND LEACHATE/ CONDENSATE SYSTEM IMPROVEMENTS REBID
BOZEMAN LANDFILL
EXISTING CONDITIONS825 W. Custer Ave.
Helena, Montana 59602
PHONE: 406-443-5210 FAX: 406-442-7182
ISSUED FOR REBID1/23 LC
4
D-102
3
D-102
3
D-102
3
D-102
6
D-102
PROPOSED LFG WELL #1
SEE DETAIL
TIE-IN TO EXISTING LFG PIPELINE
8" SDR17 LFG
PIPELINE
PRESERVE &
PROTECT EXISTING
LYSIMETER
PROPOSED LFG WELL #2
SEE DETAIL
PROPOSED LFG WELL #3
SEE DETAIL
CELL BOUNDARY
PIPELINE TRENCH
SEE DETAIL
J-TRAP
SEE DETAIL
4840GGGG
G GGGGGOHPOHPOHPOHPOHPOHPOHPOHPOHPOHP479
0
480
0
481
0
482
0
+0 00
+1
00
+
2
00
+3 00
+4 00
+5
00
+
6
00
+
7
0
0 +800+8844
7
9
0
4
8
0
0
48
1
0
48
2
0
48
3
0
48
4
0
475
0
4760
2" Ø SDR17 CONDENSATE PIPELINE
EXISTING LEACHATE UST
ROAD CROSSING
(APPROX. 30')
5
D-102
1
D-102
CONNECT TO EXISTING LEACHATE UST
SEE DETAIL
MIN 4' BURY DEPTH
W/ MIN 0.2% GRADE
TO LOW POINT
MIN 4' BURY DEPTH
W/ MIN 0.2% GRADE
TO LOW POINT
CONNECT TO EXISTING HDPE W/ 8"x8"x8" TEE
ELEV. 4774 APPROXIMATE ONLY,
CONTRACTOR TO VERIFY.
4750
4760
4770
4780
4790
4800
4810
4820
4830
4840
4850
4750
4760
4770
4780
4790
4800
4810
4820
4830
4840
4850
0+00 0+50 1+00 1+50 2+00 2+50 3+00 3+50 4+00 4+50 5+00 5+50 6+00 6+50 7+00 7+50 8+00 8+50 8+84
STA:0+80.65
ELEV:4840.00
STA:2+09.37
ELEV:4839.50
STA:0+05.83
ELEV:4840.50
STA:5+65.41
ELEV:4772.50
STA:6+27.57
ELEV:4772.30 LOW POINT
8"x8"x2" TEE
TO CONDENSATE
PIPELINE
STA:7+77.20
ELEV:4758.78
STA:3+28.81
ELEV:4800.30
EXISTING GRADE
N0
SCALE:
30'60'120'
1'' = 60'
MARK DATE DESCRIPTION BY
Checked By:
Drawn By:
Project No.:
Designed By:
www.tetratech.com
1/10/2023 8:23 AM - O:\A-G\BOZEMAN CITY OF\114-560487E - 2020-2021 REMEDIATION SYSTEMS\07-CAD\SHEETFILES\LFG PLANS\P-101 - LFG PLAN.DWG1
A
2 3 4 5 6 7
B
C
D
E
F
Bar Measures 1 inch
114-560487E
JSS
LC
P-101
Copyright Tetra TechBOZEMAN, MONTANA
2023 LFG AND LEACHATE/ CONDENSATE SYSTEM IMPROVEMENTS REBID
BOZEMAN LANDFILL
LANDFILL GAS EXTRACTION SYSTEM
PLAN AND PROFILE
825 W. Custer Ave.
Helena, Montana 59602
PHONE: 406-443-5210 FAX: 406-442-7182
ISSUED FOR REBID1/23 LC
GGGGGOHPOHPOHPOHPOHPSSS
SS
S
S
S
S
SSS
S
S
S
S
S
S
S
SS
SS
+0 00
+1 00
+2 00
+3 00
+4 00
+5 00
+600+7 00 +744MH 3
STA: 5+57.59
4740
4740
4745
4745
4750
4750
4755
4755
4760
4760
4765
4770
4775
4780
4785
4790
4795
4800
4730
473
5
4740
4745
4750
4765
4770477547804785479047954800480547
5
0
47
5
5
47
6
0
4745
4750
4755
4745
4750
4755
4760
4765
4770
4775
478
0
4785
4790
4795
4800
4805
4810
4815
4
7
2
0 4725473047354740474547504755476047654770EXISTING VAULT
LOCATION
EXISTING LINED CELL
EXISTING MH 1
STA: 0+00.00
175.45 LF 8" HDPE
557.58 LF OF 8" HDPE
MH 2
STA: 3+00.00
4710
4720
4730
4740
4750
4760
4770
4710
4720
4730
4740
4750
4760
4770
0+00 0+50 1+00 1+50 2+00 2+50 3+00 3+50 4+00 4+50 5+00 5+50 6+00 6+50 7+00 7+44
0+00 0+50 1+00 1+50 2+00 2+50 3+00 3+50 4+00 4+50 5+00 5+50 6+00 6+50 7+00 7+44
EXST
GRADE
CONNECT TO EXISTING
4" HDPE DRAIN LINE.
ELEVATION UNKNOWN.
CONTRACTOR TO FIELD
VERIFY SEE D-101.EXISTING MH 1RIM = 4734.5±INV IN = 4727.06' MIN BURY DEPTH
8" HDP
E
8
.
2
%
8" HDPE 1.53%INV OUT = 4735.51'INV IN = 4736.84'MH 3RIM = 4744.04'INV OUT = 4731.58'INV IN = 4731.68'MH 2RIM = 4740.12'MARK DATE DESCRIPTION BY
Checked By:
Drawn By:
Project No.:
Designed By:
www.tetratech.com
1/10/2023 8:24 AM - O:\A-G\BOZEMAN CITY OF\114-560487E - 2020-2021 REMEDIATION SYSTEMS\07-CAD\SHEETFILES\LFG PLANS\P-102 - LFG PLAN.DWG1
A
2 3 4 5 6 7
B
C
D
E
F
Bar Measures 1 inch
114-560487E
JSS
LC
P-102
Copyright Tetra TechBOZEMAN, MONTANA
2023 LFG AND LEACHATE/ CONDENSATE SYSTEM IMPROVEMENTS REBID
BOZEMAN LANDFILL
LEACHATE/ CONDENSATE PIPELINE
PLAN AND PROFILE
825 W. Custer Ave.
Helena, Montana 59602
PHONE: 406-443-5210 FAX: 406-442-7182
LEACHATE/ CONDENSATE PROFILE
SCALE: 1" = 50'NOTES
1.LOCATION OF UTILITIES SHOWN ARE TO BE CONSIDERED
APPROXIMATE. CONTRACTOR TO VERIFY UTILITIES AND
THEIR LOCATION PRIOR TO EXCAVATION.
2.EXISTING MANHOLE 1 IS A HDPE MANHOLE. MINIMIZE
DAMAGE TO HDPE LADDER WITH NEW INLET.
3.MANHOLE 2 & 3 TO CONSIST OF 48" DIA. STANDARD
STRAIGHT PRECAST MANHOLES (SEE STANDARD DWG.
02720-4) WITH COVER SLAB, CASTING & COVER, STEPS &
BUILT IN CHANNEL.
0
SCALE:
25'50'100'
1'' = 50'
N
LEACHATE/ CONDENSATE PLAN
SCALE: 1" = 50'
ISSUED FOR REBID1/23 LC
PRESERVE & PROTECT
ALL VALVE & PIPE IN THIS
AREA
EXISTING ABOVE GROUND 4" HDPE
FLANGE ADAPTER WITH BLIND FLANGE
INSTALL 2" HDPE FLANGE ADAPTERS, 2 SS BACK0UP RINGS,
BOLT & GASKET KIT, 2" C.I. BUTTERFLY VALVE WITH SS DISK & STEM,
VALVE EXTENSION WITH GEAR OPERATOR, AND CSP VAULT WITH
ACCESS LID, INSTALL CEMENT SLURRY WITH 20% BENTONITE IN VAULT
IF LOCATED IN WASTE, LABEL VAULT "CONDENSATE FROM LINED CELL"
2" Ø SDR11 HPDE CONDENSATE PIPELINE
REMOVE AND DISPOSE
EXISTING LEVEL
FLOAT SWITCH
WITH CSP VAULT
REMOVE AND DISPOSE
EXISTING ABOVE GROUND
8" THK, CONCRETE PAD
EXISTING ABOVE GROUND
ELECTRICAL PANELS
INSTALL 8"x2" HDPE TEE
EXISTING 4" HDPE TO J-TRAP
EXSTING 2" HDPE CONDENSATE LINE
FROM FIELD/TREATMENT FACILITY
EXISTING 2" HDPE CONDENSATE LINE
FROM SUMP #2
TANK AREA PLAN1
_N.T.S
7.50'
INSTALL 8"x4" HDPE REDUCER
INSTALL 8" CONDENSATE
DRAIN LINE
NOTES:
1.EXISTING ABOVE GROUND ELECTRICAL PANELS ARE
DE-ENERGIZED AND NOT FUNCTIONING.
2.CONTRACTOR TO CLOSE VALVES OR INSERT TEMPORARY
PLUGS TO PREVENT CONDENSATE/ LEACHATE DRAINAGE
DURING CONSTRUCTION.
3.CONTRACTOR TO MINIMIZE TIME WHEN LEACHATE/
CONDENSATE IS NOT DRAINING BY CONSTRUCTING
DOWNSTREAM 8" CONDENSATE DRAIN LINE PRIOR TO TANK
REMOVAL.
A
-
EXISTING ABOVE GROUND PAD AND BOLLARDS
PRESERVE AND PROTECT
EXISTING CONDENSATE TANK
PRESERVE AND PROTECT
INSTALL 8"x4"
HDPE REDUCER
EXISTING 4" DRAIN LINE
ELEVATION UNKNOWN.
CONTRACTOR TO FIELD VERIFY
INSTALL
8"x2" HDPE TEE
6' DIA. STEEL UST
PRESERVE AND PROTECT
MIN. 3%
8' CONDENSATE DRAIN LINE
EXISTING 4"
HDPE TO J-TRAP
CROSS SECTION A
N.T.S
REMOVE & DISPOSE
8" THK CONCRETE PAD
EXISTING GROUND
VARIES 4760-4762±
MARK DATE DESCRIPTION BY
Checked By:
Drawn By:
Project No.:
Designed By:
www.tetratech.com
1/10/2023 8:36 AM - O:\A-G\BOZEMAN CITY OF\114-560487E - 2020-2021 REMEDIATION SYSTEMS\07-CAD\SHEETFILES\LFG PLANS\D-101 - LFG DETAIL.DWG1
A
2 3 4 5 6 7
B
C
D
E
F
Bar Measures 1 inch
114-560487E
JSS
LC
D-101
Copyright Tetra TechBOZEMAN, MONTANA
2023 LFG AND LEACHATE/ CONDENSATE SYSTEM IMPROVEMENTS REBID
BOZEMAN LANDFILL
LANDFILL GAS EXTRACTION SYSTEM
DETAILS
825 W. Custer Ave.
Helena, Montana 59602
PHONE: 406-443-5210 FAX: 406-442-7182
ISSUED FOR REBID1/23 LC
2.00'8.00' (MIN)3' ±18"SLOTTED CASINGSOLID CASINGCEMENT GROUT WITH
20% BENTONITE POWDER
6" Ø SCH 80 CPVC WITH 3 ROWS
OF 0.040" SLOTS
3/8" MINUS WASHED GRAVEL
SALVAGED LOCAL
TOPSOIL
6" Ø SCH 80 CPVC
SOLID CASING
ORP 35 WELLHEAD
WITH 1
4" SAMPLE BARBS
ENDCAP
1' (MIN) CLEAN SOIL
TO EXISTING LFG COLLECTION
SYSTEM
GEOTEXTILE DONUT
HEAT BONDED TO PIPE
1'2.00'QED
QED
QED
QED FINE TUNE
CONTROL VALVE QED QWC 6284 DUAL EXTRACTION
WELL CAP3' ±QED
QED
QED
QED 2" Ø SOLARGUARD
FLEX HOSE
2'-3'
2" QED WELLHEAD ASSEMBLY,
6"x2" DUAL EXTRACTION
WELL CAP
TYPICAL WELLHEAD INSTALLATION2
_N.T.S
WELL I.D. TAG
6"x2" COUPLE/REDUCER
8" Ø SDR17 HDPE
SEE P-101
8" x 6" SDR11 TEE
PROPOSED 6" Ø LFG WELL
SEE DETAIL3
_
EXISTING GRADE
TYPICAL LFG WELL INSTALLATION3
_N.T.S
6" Ø SDR17 HDPE
62
62
62
MARKER TAPE WITH TRACER
WIRE "CAUTION GAS LINE"
(12" BELOW GRADE)
EXISTING GRADE
SEE P-101 & P 102HDPE PIPE
(PER PLAN)
TYPE C COMPACTED
SOIL BACKFILL
2.5' TYPICAL
TRENCH DETAIL (TYP.)4
_N.T.S6' FOR 2" DIA DRAINSEE ALSO
STANDARD DWG. 02221-1
TYPE 2 PIPE BEDDING
SURROUNDED BY GEOTEXTILE
WHERE WASTE IS ENCOUNTERED
6' TYPICALROAD CROSSING DETAIL5
_N.T.S
8" SDR17 HDPE PIPE
18" CORRUGATED HDPE
SLEEVE
TYPE A COMPACTED
SOIL BACKFILL
MARKER TAPE WITH TRACER
WIRE "CAUTION GAS LINE"
(12" BELOW GRADE)
EXISTING ROAD GRADE
REPLACE EXISTING ROAD
SURFACE AND BASE TO
ORIGINAL CONDITION
CUT EXISTING
PAVEMENT CLEANLY
SALVAGE & REPLACE ROAD BASE
OWNER TO REPLACE PAVEMENT
SEE ALSO
STANDARD DWG 02221-1 6.00'J-TRAP DETAIL6
_N.T.S
FROM 8" GAS LINE
TO EXISTING
LEACHATE
CONDENSATE
DRAIN
2" SDR17 CONDENSATE
PIPELINE
THOROUGHLY COMPACT
SOIL OR PEA GRAVEL
IN BORING EXCAVATION
CONTRACTOR TO FILL
J-TRAP WITH CLEAN
WATER. ENGINEER TO VERIFY.6.00'MARK DATE DESCRIPTION BY
Checked By:
Drawn By:
Project No.:
Designed By:
www.tetratech.com
1/10/2023 8:37 AM - O:\A-G\BOZEMAN CITY OF\114-560487E - 2020-2021 REMEDIATION SYSTEMS\07-CAD\SHEETFILES\LFG PLANS\D-101 - LFG DETAIL.DWG1
A
2 3 4 5 6 7
B
C
D
E
F
Bar Measures 1 inch
114-560487E
JSS
LC
D-102
Copyright Tetra TechBOZEMAN, MONTANA
2023 LFG AND LEACHATE AND CONDENSATE SYSTEM IMPROVEMENTS REBID
BOZEMAN LANDFILL
LANDFILL GAS EXTRACTION SYSTEM
DETAILS
825 W. Custer Ave.
Helena, Montana 59602
PHONE: 406-443-5210 FAX: 406-442-7182
ISSUED FOR REBID1/23 LC