HomeMy WebLinkAboutSoils Investigation Report 1091 Stoneridge Drive • Bozeman, Montana • Phone (406) 587-1115 • Fax (406) 587-9768 www.chengineers.com • E-Mail: info@chengineers.com August 25, 2021 Easton Concrete, Inc. Attn: Mark Easton E-amil: mark@eastoncompanies.com RE: Soils Investigation – 5153, 5155, 5157, 5161, 5163, 5167, 5171, 5173 & 5177 Fallon Street, Lot R-2, J&D Family Subdivision Phase 2; Bozeman, Montana (210909) Dear Mark, Per your request, C&H Engineering and Surveying Inc. (C&H Engineering) has conducted a subsurface soils investigation on the above referenced property. The subject property is found in the Southeast Quarter of Section 9, Township 2 South, Range 5 East in Gallatin County, Montana. The scope of services was to conduct a subsurface investigation and provide a soils investigation report. The report documents the sites’ soil and groundwater conditions, subsurface soil properties, and provides foundation design and general earthwork recommendations for the pavements and structures within the proposed development. Proposed Construction The proposed West Side Flats Development is a residential multi-family development that will consist of five 12-plex units and four 16-plex units. The proposed development is on a relatively flat 14.02 acres North of Fallon Street and South of West Babcock Street. Subsurface Soil and Conditions On August 11, 2021 Noah J. Schaible, E.I. of C&H Engineering visited the site to conduct a subsurface soils investigation. The subsurface soils investigation consisted of examining thirteen exploratory test pit excavations. The exploratory test pits were excavated with a CAT 305.5 mini tracked excavator provided by Grade A Site Works. The soil profiles revealed by the excavations were logged and visually classified according to ASTM D 2488, which utilizes the nomenclature of the Unified Soil Classification System (USCS). Representative samples of each soil layer were collected from the trench sidewalls at varying depths for further classification in the lab. The relative density of each soil layer was estimated based on probing of the excavation sidewalls with a rock hammer, penetration tests performed with a static cone penetrometer and the overall stability of the excavation. Any evidence of seepage or other groundwater conditions were also noted. The locations of the test pits are shown on the included Test Pit Location Map. The test pits (TP) excavated for the field investigation exhibited very similar soil profiles. The SOILS INVESTIGATION REPORT #210909 – WEST SIDE FLATS, LOT R-2, J&D FAMILY SUBDIVISION PHASE 2; BOZEMAN, MONTANA 2 following paragraphs briefly summarize the subsurface soils and conditions observed in the test pits excavated for the field investigation. The soil horizons are described as they were encountered in the test pit excavations, starting with the horizon nearest the surface and proceeding with each additional horizon encountered with depth. The first soil horizon encountered in each exploratory test pit was a Silty Clay Organic Soil of low plasticity (OL). This material was black in color, moist, and soft. This material was encountered to depths ranging from approximately 1.0 to 1.5 feet below grounds surface (bgs). Organic soils are highly compressible and are not suitable for foundation support. This material must also be removed from beneath all interior and exterior slabs as well as beneath all asphalt and/or concrete paving improvements. This material may be stockpiled onsite and used for final site grading purposes. The second soil horizon encountered in each exploratory excavation was Lean Clay with Sand (CL). This material was yellowish brown to black in color, was very soft to soft in consistency, and estimated to contain approximately 85 percent fines with medium plasticity, and approximately 15 percent coarse to fine grained sand. Trace gravels were encountered with depth. This material was encountered to depths varying from 2.67 to 6.25 feet bgs. Penetration test performed on this material with a static cone penetrometer indicate that this material is compressible and not suitable for foundation support. The third soil horizon encountered in each exploratory excavation was a Poorly Graded Gravel with Sand and Cobbles (GP), known locally as “pit-run” gravel. This material was grayish brown in color, loose to medium dense, and estimated to contain approximately 40 percent coarse to fine grained sand, and approximately 60 percent gravels and cobbles. Trace boulders were encountered. This material was present to the end of each excavation, varying in depth from approximately 4.0 to 6.5 feet bgs. The groundwater table was encountered at the bottom of each exploratory excavation within this material. Based on the subsurface investigation, it is recommended that the excavation for each structure’s foundation footprint continue down to the Poorly Graded Gravel with Sand and Cobbles and structural fill be used to achieve the desired bottom of footing elevations if necessary. Dewatering of the site will likely be necessary to complete the over-excavation and structural fill placement. It should be noted that a significant amount of groundwater was encountered in each excavation and it is likely that multiple dewatering pumps will be required to adequately dewater the site. It is recommended that dewatering pumps be installed as far ahead of the date of the excavation as possible, preferably one week or more. Dewatering well before the excavation will lower the groundwater table and allow the subsurface soils to dry out which will increase the overall stability of the excavation sidewalls. If the excavated soils have a high moisture content, it is expected that significant caving of the excavation side walls will occur, especially when exposed to vibrations induced by the compaction equipment. It is required that the excavation for any structure be observed by a licensed geotechnical engineer to verify that the proper foundation subgrade material has been reached prior to the forming or casting of any foundation elements or the placement and compaction of any required SOILS INVESTIGATION REPORT #210909 – WEST SIDE FLATS, LOT R-2, J&D FAMILY SUBDIVISION PHASE 2; BOZEMAN, MONTANA 3 structural fill. Groundwater Groundwater was encountered within the depth of each excavation at depths varying from approximately 3.0 feet bgs to 5.5 feet bgs. Signs of seasonally high groundwater such as gleying of the soils were also observed within each excavation at depths varying from approximately 2.0 feet bgs to 3.0 feet bgs. Please note that once the low permeability clay layer is removed the water table may rise higher than the indicators suggest. Please note that our subsurface investigation is not a detailed groundwater study, and groundwater conditions may change dramatically due to conditions that are out of our control, as mentioned previously. Our assessment of the groundwater conditions is based on the conditions observed within the exploratory test pits on the day of the excavation, our general experience in the project area, and any available literature regarding groundwater conditions in the vicinity of the subject property. If more detailed knowledge of the seasonally high groundwater elevation across the subject property is desired, it is recommended that groundwater monitoring wells be installed and checked weekly from the early spring to late summer months in order to determine the peak seasonally high groundwater elevation. Given the shallow depth to groundwater across the site, basement and crawl space foundations are not feasible. It is recommended that slab-on-grade with stem wall foundations be utilized within the development. Foundation Recommendations Based on the subsurface soils and conditions encountered in the exploratory excavations, it will be acceptable to utilize a slab-on-grade with stem wall foundation across the entire development. Basement and crawl space foundations are not recommended due to high groundwater. Please find the following as general recommendations for all foundation elements:  In order to keep the footing out of the active frost zone it is recommended that the bottom of all footing elevation be located a minimum of 4 feet below finished grade.  It is recommended that typical strip footings for these structures have a minimum width of 16 inches and column footings should have a minimum width of 24 inches, provided the soils allowable bearing capacity is not exceeded.  All foundation elements are to bear on the Poorly Graded Gravel with Sand, and Cobbles, or on properly placed and compacted structural fill overlying this material.  The subgrade must remain in a dry condition throughout construction of the foundation elements.  If groundwater is encountered, the excavation will need to be dewatered to allow for the proper placement and compaction of any required structural fill. SOILS INVESTIGATION REPORT #210909 – WEST SIDE FLATS, LOT R-2, J&D FAMILY SUBDIVISION PHASE 2; BOZEMAN, MONTANA 4  If construction takes place during the colder months of the year, the subgrade must be protected from freezing. This may require the use of insulating blankets and/or ground heaters.  It is required that the excavation for any structure be observed by a licensed geotechnical engineer to verify that the proper foundation subgrade material has been reached prior to the forming or casting of any foundation elements or the placement and compaction of any required structural fill. Allowable Bearing Capacity & Settlement The bearing capacity of a soil is defined as the ultimate pressure per unit area by the foundation load that can be supported by the soil in excess of the pressure caused by the surrounding soil at the footing level. Bearing capacity is determined by the physical and chemical properties of the soil located beneath the proposed structures footings. It is recommended that all foundation footings bear on the Poorly Graded Gravel with Sand and Cobbles, or on properly placed and compacted structural fill overlying this material. For this scenario it is recommended that an allowable bearing capacity of 2,500 pounds per square foot be used to dimension all foundation footings. Settlement and differential settlement were estimated using conservative soil parameters. Based on conservative soil parameter estimates, the recommended bearing capacity, and the assumption that all recommendations made in this report will be properly implemented, it is expected that total and differential settlement will be ½-inch or less. Typical wood framed structures with reinforced concrete foundations can generally tolerate settlements of this magnitude, however, this should be checked by a structural engineer to determine if it is acceptable. The allowable bearing capacity may be increased by one third for short term loading conditions such as those from wind or seismic forces. Subgrade Preparation and Structural Fill In general, the excavation for the foundation footprint must be level and uniform and continue down to the Poorly Graded Gravel with Sand and Cobbles or to the bottom of footing elevation, whichever is deeper. If any soft spots, or boulders are encountered, they will need to be removed and backfilled with structural fill. The excavation width must extend a minimum of one footing width from the outer edges of the footings, or to a distance equal to ½ the height of the required structural fill, whichever is greater. For example, if 6 feet of structural fill is required, the width of the excavation must extend out a distance of 3 feet on either side of the foundation footings. Once the excavation is complete, the native subgrade shall be proof rolled with a large vibrating compactor to an unyielding condition. Any areas that are found to be pumping or rutting shall be sub-excavated and replaced with structural fill. SOILS INVESTIGATION REPORT #210909 – WEST SIDE FLATS, LOT R-2, J&D FAMILY SUBDIVISION PHASE 2; BOZEMAN, MONTANA 5 Structural fill is defined as all fill that will ultimately be subjected to structural loadings, such as those imposed by footings, floor slabs, pavements, etc. None of the soils encountered in the exploratory excavations are suitable for use as structural fill. Structural fill will need to be imported for this project. Imported structural fill is recommended to be a well graded gravel with sand that contains less than 15 percent of material that will pass a No. 200 sieve and that has a maximum particle size of 3 inches. Also, the fraction of material passing the No. 40 sieve shall have a liquid limit not exceeding 25 and a plasticity index not exceeding 6. The gravel and sand particles also need to be made up of durable rock materials that will not degrade when compacted; no shale or mudstone fragments should be present. Structural fill must be placed in lifts no greater than 12 inches (uncompacted thickness) and be uniformly compacted to a minimum of 97 percent of its maximum dry density, as determined by ASTM D698. Typically, the structural fill must be moisture conditioned to within + 2 percent of the materials optimum moisture content to achieve the required density. It is recommended that the structural fill be compacted with a large vibrating smooth drum roller. Please note that if a moisture-density relationship test (commonly referred to as a proctor) needs to be performed for a proposed structural fill material to determine its maximum dry density in accordance with ASTM D698, a sample of the material must be delivered to this office a minimum of three full working days prior to beginning placement of the structural fill. At no time should surface water runoff be allowed to flow into and accumulate within the excavation for the foundation elements. If necessary, a swale or berm should be temporarily constructed to reroute all surface water runoff away from the excavation. Excavation should not proceed during large precipitation events. If any of the foundation footings are found to be located on a test pit, the area will need to be excavated down to the full depth of the test pit and structural fill be placed and compacted in lifts to bring the area back up to the desired grade. Foundation Wall Backfill Approved backfill material should be placed and compacted between the foundation wall and the edge of the excavation. The native soils, with the exception of the organic soils, may be used as backfill along the exterior of the foundation, provided they are not too moist. Based on our observations on the day of the site visit, the onsite soils were too wet to be utilized as foundation wall backfill. The onsite soils will need to be stockpiled and properly dried prior to being utilized as foundation wall backfill. It is recommended that structural fill be used as backfill in all areas that will support concrete slabs-on-grade or asphalt paving improvements. Foundation wall backfill may also be imported, imported foundation wall backfill is recommended to be a well- draining granular material. The foundation wall backfill will need to be compacted with either walk behind compaction equipment or hand operated compaction equipment in order to avoid damaging the foundation walls. If walk behind compaction equipment is used lifts should not exceed 8-inches (loose thickness) and if hand operated compaction equipment is used lifts should not exceed 4-inches (loose thickness). SOILS INVESTIGATION REPORT #210909 – WEST SIDE FLATS, LOT R-2, J&D FAMILY SUBDIVISION PHASE 2; BOZEMAN, MONTANA 6 Site Grading Surface water should not be allowed to accumulate and infiltrate the soil near the foundation. Proper site grading will ensure surface water runoff is directed away from the foundation elements and will aid in the mitigation of excessive settlement. Please find the following as general site grading recommendations:  Finished grade must slope away from the building a minimum of 5 percent within the first 10 feet, in order to quickly drain ground surface and roof runoff away from the foundation walls. Please note that in order to maintain this slope; it is imperative that any backfill placed against the foundation walls be compacted properly. If the backfill is not compacted properly, it will settle and positive drainage away from the structure will not be maintained.  Permanent sprinkler heads for lawn care should be located a sufficient distance from the structure to prevent water from draining toward the foundation or saturating the soils adjacent to the foundation.  Rain gutter down spouts are to be placed in such a manner that surface water runoff drains away from the structure.  All roads, walkways, and architectural land features must properly drain away from all structures. Special attention should be made during the design of these features to not create any drainage obstructions that may direct water towards or trap water near the foundation. Interior Slabs-on-Grade Due to depth of the organic soil and the very low sheer strength of the Lean Clay with Sand, it is recommended the building footprint continue down to the hard gravel layer. Structural fill can then be placed and compacted to 6 inches below the bottom of slab elevation. For all interior concrete slabs-on-grade, preventative measures must be taken to stop moisture from migrating upwards through the slab. Moisture that migrates upwards through the concrete slab can damage floor coverings such as carpet, hardwood and vinyl, in addition to causing musty odors and mildew growth. Moisture barriers will need to be installed to prevent water vapor migration and capillary rise through the concrete slab. In order to prevent capillary rise through the concrete slab-on-grade it is recommended that 6 inches of ¾-inch washed rock (containing less than 10 percent fines) be placed and compacted once the excavation for the slab is complete. The washed rock has large pore spaces between soil particles and will act as a capillary break, preventing groundwater from migrating upwards towards the bottom of the slab. In order to prevent the upward migration of water vapor through the slab, it is recommended that a 15-mil extruded polyolefin plastic that complies with ASTM E1745 (such as a Stego Wrap 15- SOILS INVESTIGATION REPORT #210909 – WEST SIDE FLATS, LOT R-2, J&D FAMILY SUBDIVISION PHASE 2; BOZEMAN, MONTANA 7 mil Vapor Barrier) be installed. The vapor barrier should be pulled up at the sides and secured to the foundation wall or footing. Care must be taken during and after the installation of the vapor barrier to avoid puncturing the material, and all joints are to be sealed per the manufacture’s recommendations. Once the excavation for the interior slab-on-grade is completed as described in the first paragraph of this section, and the ¾ inch washed rock and moisture barriers have been properly installed, it will be acceptable to form and cast the steel reinforced concrete slab. It is recommended that interior concrete slabs-on-grade have a minimum thickness of 4 inches, unless the slab will be supporting vehicles, in which case the slab shall have a minimum thickness of 6 inches. Exterior Slabs-on-Grade For exterior areas to be paved with concrete slabs, it is recommended that, at a minimum, the organic soil be removed. The subgrade then needs to be compacted to an unyielding condition. Then for non-vehicular traffic areas, a minimum of 12 inches of ¾-inch minus rock needs to be placed, and 4 inches of 4000 pounds per square inch (psi) concrete placed over the ¾-inch minus rock. Exterior slabs that will be located adjacent to the foundation walls need to slope away from the structure at a minimum grade of 2 percent and should not be physically connected to the foundation walls. If they are connected, any movement of the exterior slab will be transmitted to the foundation wall, which may result in damage to the structure. Private Asphalt Paving Improvements For areas to be paved with asphalt, it is recommended that, as a minimum, the topsoil and any organics be removed. The native subgrade shall be smooth and rut free. Following removal of the organic soil or excavation to the desired subgrade elevation, the native subgrade shall be compacted to a minimum of 95 percent of its maximum dry density. If the native subgrade is able to be compacted to the specified density, a layer of Mirafi 160N geotextile fabric shall be installed, followed by a layer of Tensar TX5 Triaxial Geogrid. Next 12 inches of 3-inch minus “pit-run” gravel (subbase course) shall be installed, followed by 6 inches of 1.5-inch minus road mix (base course). Both of these gravel layers must be compacted to a minimum of 95 percent of their maximum dry density, as determined by ASTM D698. A three-inch-thick layer of Asphalt can then be placed over this cross section. In the event the native subgrade cannot be compacted to 95 percent of its maximum dry density, the excavation must continue down an additional 12 inches, a layer of Mirafi 160N geotextile fabric shall be installed, followed by a layer of Tensar TX5 Triaxial Geogrid, followed by a single 24-inch thick lift of 3-inch minus “pit-run” gravel and a 6-inch thick lift of 1.5-inch minus road mix. A three-inch-thick layer of Asphalt can then be placed over this cross section. If asphalt paving is to be placed on foundation wall backfill, the backfill must be compacted to a minimum of 95 percent of its maximum dry density, as determined by ASTM D698. It is SOILS INVESTIGATION REPORT #210909 – WEST SIDE FLATS, LOT R-2, J&D FAMILY SUBDIVISION PHASE 2; BOZEMAN, MONTANA 8 recommended the backfill be placed in uniform lifts and be compacted to an unyielding condition as described in the section “Foundation Wall Backfill”. Construction Administration The foundation is a vital element of a structure; it transfers all of the structure’s dead and live loads to the native soil. It is imperative that the recommendations made in this report are properly adhered to. A representative from C&H Engineering should observe the construction of any foundation or drainage elements recommended in this report. The recommendations made in this report are contingent upon our involvement. If the soils encountered during the excavation differ than those described in this report or any unusual conditions are encountered, our office should be contacted immediately to examine the conditions, re-evaluate our recommendations and provide a written response. If construction and site grading take place during cold weather, it is recommended that approved winter construction practices be observed. All snow and ice shall be removed from cut and fill areas prior to site grading taking place. No fill should be placed on soils that are frozen or contain frozen material. No frozen soils can be used as fill under any circumstances. Additionally, Concrete should not be placed on frozen soils and should meet the temperature requirements of ASTM C 94. Any concrete placed during cold weather conditions shall be protected from freezing until the necessary compressive strength has been attained. Once the footings are placed, frost shall not be permitted to extend below the foundation footings, as this could heave and crack the foundation footings and/or foundation walls. It is the responsibility of the contractor to provide a safe working environment with regards to excavations on the site. All excavations should be sloped or shored in the interest of safety and in accordance with local and federal regulations, including the excavation and trench safety standards provided by the Occupational Safety and Health Administration (OSHA). Report Limitations The recommendations made in this report are based on information obtained from the test pits excavated at the locations shown on the included Test Pit Location Map. It is not uncommon for variations to occur between these points, the nature and extend of which do not become evident until additional exploration or construction is conducted. The variations may result in additional construction costs, and it is suggested that a contingency be provided for this purpose. This report is for the exclusive use of Easton Concrete Inc. In the absence of our written approval, we make no representation and assume no responsibility to other parties regarding the use of this report. These recommendations are applicable to the subject property only and are not applicable to other construction sites. Under no circumstances shall a portion of this report be removed or be used independently of the rest of the document, this report is applicable as a full document only. Services performed by C&H Engineering and Surveying, Inc. for this project have been OL CL GP 1.0 5.0 6.0 0 TO 1 FEET: SILTY CLAY ORGANIC SOIL; (OL); black; moist; soft. 1 TO 5 FEET: LEAN CLAY WITH SAND; (CL); yellowish brown to black; moist to saturated; medium plasticity; very soft to soft; approximately 15 percent fine to coarse grain sand; approximately 85 percent clayey fines. 5 TO 6 FEET: POORLY GRADED GRAVEL WITH SAND AND COBBLES; (GP); grayish brown; moist to saturated; medium dense; approximately 60 percent subrounded gravels; approximately 40 percent fine to coarse grain sand. Bottom of test pit at 6.0 feet. NOTES GROUND ELEVATION LOGGED BY Noah J. Schaible, E.I. EXCAVATION METHOD CAT 305 Mini Tracked Excavator EXCAVATION CONTRACTOR Grade A Site Works GROUND WATER LEVELS: DATE STARTED 8/11/21 COMPLETED 8/11/21 AT TIME OF EXCAVATION 5.50 ft AFTER EXCAVATION --- AT END OF EXCAVATION ---DEPTH(ft)0.0 2.5 5.0 SAMPLE TYPENUMBERPAGE 1 OF 1 TEST PIT NUMBER TP1 PROJECT NUMBER 210909 CLIENT Easton Concrete, Inc. PROJECT LOCATION West Side Flats PROJECT NAME Soils Investigation GENERAL BH / TP / WELL - GINT STD US.GDT - 8/25/21 10:49 - G:\C&H\21\210909\REPORT DOCUMENTS\TEST PIT LOGS (210909).GPJU.S.C.S.GRAPHICLOGMATERIAL DESCRIPTION OL CL GP 1.0 4.0 4.5 0 TO 1 FEET: SILTY CLAY ORGANIC SOIL; (OL); black; moist; soft. 1 TO 4 FEET: LEAN CLAY WITH SAND; (CL); yellowish brown to black; moist to saturated; medium plasticity; very soft to soft; approximately 15 percent fine to coarse grain sand; approximately 85 percent clayey fines. 4 TO 4.5 FEET: POORLY GRADED GRAVEL WITH SAND AND COBBLES; (GP); grayish brown; moist to saturated; medium dense; approximately 60 percent subrounded gravels; approximately 40 percent fine to coarse grain sand. Bottom of test pit at 4.5 feet. NOTES GROUND ELEVATION LOGGED BY Noah J. Schaible, E.I. EXCAVATION METHOD CAT 305 Mini Tracked Excavator EXCAVATION CONTRACTOR Grade A Site Works GROUND WATER LEVELS: DATE STARTED 8/11/21 COMPLETED 8/11/21 AT TIME OF EXCAVATION 4.00 ft AFTER EXCAVATION --- AT END OF EXCAVATION ---DEPTH(ft)0.0 2.5 SAMPLE TYPENUMBERPAGE 1 OF 1 TEST PIT NUMBER TP2 PROJECT NUMBER 210909 CLIENT Easton Concrete, Inc. PROJECT LOCATION West Side Flats PROJECT NAME Soils Investigation GENERAL BH / TP / WELL - GINT STD US.GDT - 8/25/21 10:49 - G:\C&H\21\210909\REPORT DOCUMENTS\TEST PIT LOGS (210909).GPJU.S.C.S.GRAPHICLOGMATERIAL DESCRIPTION OL CL CL GP 1.0 4.0 6.3 6.5 0 TO 1 FEET: SILTY CLAY ORGANIC SOIL; (OL); black; moist; soft. 1 TO 4 FEET: LEAN CLAY WITH SAND; (CL); black; moist to saturated; medium plasticity; very soft to soft; approximately 15 percent fine to coarse grain sand; approximately 85 percent clayey fines. 4 TO 6.25 FEET: LEAN CLAY WITH SAND; (CL); yellowish brown; moist to saturated; medium plasticity; very soft to soft; approximately 15 percent fine to coarse grain sand; approximately 85 percent clayey fines. 6.25 TO 6.5 FEET: POORLY GRADED GRAVEL WITH SAND AND COBBLES; (GP); grayish brown; moist to saturated; medium dense; approximately 60 percent subroundedgravels; approximately 40 percent fine to coarse grain sand. Bottom of test pit at 6.5 feet. NOTES GROUND ELEVATION LOGGED BY Noah J. Schaible, E.I. EXCAVATION METHOD CAT 305 Mini Tracked Excavator EXCAVATION CONTRACTOR Grade A Site Works GROUND WATER LEVELS: DATE STARTED 8/11/21 COMPLETED 8/11/21 AT TIME OF EXCAVATION 4.00 ft AFTER EXCAVATION --- AT END OF EXCAVATION ---DEPTH(ft)0.0 2.5 5.0 SAMPLE TYPENUMBERPAGE 1 OF 1 TEST PIT NUMBER TP3 PROJECT NUMBER 210909 CLIENT Easton Concrete, Inc. PROJECT LOCATION West Side Flats PROJECT NAME Soils Investigation GENERAL BH / TP / WELL - GINT STD US.GDT - 8/25/21 10:49 - G:\C&H\21\210909\REPORT DOCUMENTS\TEST PIT LOGS (210909).GPJU.S.C.S.GRAPHICLOGMATERIAL DESCRIPTION OL CL GP 1.0 4.0 6.0 0 TO 1 FEET: SILTY CLAY ORGANIC SOIL; (OL); black; moist; soft. 1 TO 4 FEET: LEAN CLAY WITH SAND; (CL); yellowish brown to black; moist to saturated; medium plasticity; very soft to soft; approximately 15 percent fine to coarse grain sand; approximately 85 percent clayey fines. 4 TO 6 FEET: POORLY GRADED GRAVEL WITH SAND AND COBBLES; (GP); grayish brown; moist to saturated; medium dense; approximately 60 percent subrounded gravels; approximately 40 percent fine to coarse grain sand. Bottom of test pit at 6.0 feet. NOTES GROUND ELEVATION LOGGED BY Noah J. Schaible, E.I. EXCAVATION METHOD CAT 305 Mini Tracked Excavator EXCAVATION CONTRACTOR Grade A Site Works GROUND WATER LEVELS: DATE STARTED 8/11/21 COMPLETED 8/11/21 AT TIME OF EXCAVATION 5.50 ft AFTER EXCAVATION --- AT END OF EXCAVATION ---DEPTH(ft)0.0 2.5 5.0 SAMPLE TYPENUMBERPAGE 1 OF 1 TEST PIT NUMBER TP4 PROJECT NUMBER 210909 CLIENT Easton Concrete, Inc. PROJECT LOCATION West Side Flats PROJECT NAME Soils Investigation GENERAL BH / TP / WELL - GINT STD US.GDT - 8/25/21 10:49 - G:\C&H\21\210909\REPORT DOCUMENTS\TEST PIT LOGS (210909).GPJU.S.C.S.GRAPHICLOGMATERIAL DESCRIPTION OL CL GP 1.0 5.0 6.0 0 TO 1 FEET: SILTY CLAY ORGANIC SOIL; (OL); black; moist; soft. 1 TO 5 FEET: LEAN CLAY WITH SAND; (CL); yellowish brown to black; moist to saturated; medium plasticity; very soft to soft; approximately 15 percent fine to coarse grain sand; approximately 85 percent clayey fines. 5 TO 6 FEET: POORLY GRADED GRAVEL WITH SAND AND COBBLES; (GP); grayish brown; moist to saturated; medium dense; approximately 60 percent subrounded gravels; approximately 40 percent fine to coarse grain sand. Bottom of test pit at 6.0 feet. NOTES GROUND ELEVATION LOGGED BY Noah J. Schaible, E.I. EXCAVATION METHOD CAT 305 Mini Tracked Excavator EXCAVATION CONTRACTOR Grade A Site Works GROUND WATER LEVELS: DATE STARTED 8/11/21 COMPLETED 8/11/21 AT TIME OF EXCAVATION 5.00 ft AFTER EXCAVATION --- AT END OF EXCAVATION ---DEPTH(ft)0.0 2.5 5.0 SAMPLE TYPENUMBERPAGE 1 OF 1 TEST PIT NUMBER TP5 PROJECT NUMBER 210909 CLIENT Easton Concrete, Inc. PROJECT LOCATION West Side Flats PROJECT NAME Soils Investigation GENERAL BH / TP / WELL - GINT STD US.GDT - 8/25/21 10:49 - G:\C&H\21\210909\REPORT DOCUMENTS\TEST PIT LOGS (210909).GPJU.S.C.S.GRAPHICLOGMATERIAL DESCRIPTION OL CL GP 1.0 4.5 5.0 0 TO 1 FEET: SILTY CLAY ORGANIC SOIL; (OL); black; moist; soft. 1 TO 4.5 FEET: LEAN CLAY WITH SAND; (CL); yellowish brown to black; moist to saturated; medium plasticity; very soft to soft; approximately 15 percent fine to coarse grain sand; approximately 85 percent clayey fines. 4.5 TO 5 FEET: POORLY GRADED GRAVEL WITH SAND AND COBBLES; (GP); grayish brown; moist to saturated; medium dense; approximately 60 percent subrounded gravels;approximately 40 percent fine to coarse grain sand. Bottom of test pit at 5.0 feet. NOTES GROUND ELEVATION LOGGED BY Noah J. Schaible, E.I. EXCAVATION METHOD CAT 305 Mini Tracked Excavator EXCAVATION CONTRACTOR Grade A Site Works GROUND WATER LEVELS: DATE STARTED 8/11/21 COMPLETED 8/11/21 AT TIME OF EXCAVATION 4.00 ft AFTER EXCAVATION --- AT END OF EXCAVATION ---DEPTH(ft)0.0 2.5 5.0 SAMPLE TYPENUMBERPAGE 1 OF 1 TEST PIT NUMBER TP6 PROJECT NUMBER 210909 CLIENT Easton Concrete, Inc. PROJECT LOCATION West Side Flats PROJECT NAME Soils Investigation GENERAL BH / TP / WELL - GINT STD US.GDT - 8/25/21 10:49 - G:\C&H\21\210909\REPORT DOCUMENTS\TEST PIT LOGS (210909).GPJU.S.C.S.GRAPHICLOGMATERIAL DESCRIPTION OL CL GP 1.3 3.0 5.4 0 TO 1.33 FEET: SILTY CLAY ORGANIC SOIL; (OL); black; moist; soft. 1.33 TO 3 FEET: LEAN CLAY WITH SAND; (CL); yellowish brown to black; moist to saturated; medium plasticity; very soft to soft; approximately 15 percent fine to coarse grain sand; approximately 85 percent clayey fines. 3 TO 5.42 FEET: POORLY GRADED GRAVEL WITH SAND AND COBBLES; (GP); grayish brown; moist to saturated; medium dense; approximately 60 percent subrounded gravels; approximately 40 percent fine to coarse grain sand. Bottom of test pit at 5.4 feet. NOTES GROUND ELEVATION LOGGED BY Noah J. Schaible, E.I. EXCAVATION METHOD CAT 305 Mini Tracked Excavator EXCAVATION CONTRACTOR Grade A Site Works GROUND WATER LEVELS: DATE STARTED 8/11/21 COMPLETED 8/11/21 AT TIME OF EXCAVATION 5.25 ft AFTER EXCAVATION --- AT END OF EXCAVATION ---DEPTH(ft)0.0 2.5 5.0 SAMPLE TYPENUMBERPAGE 1 OF 1 TEST PIT NUMBER TP7 PROJECT NUMBER 210909 CLIENT Easton Concrete, Inc. PROJECT LOCATION West Side Flats PROJECT NAME Soils Investigation GENERAL BH / TP / WELL - GINT STD US.GDT - 8/25/21 10:49 - G:\C&H\21\210909\REPORT DOCUMENTS\TEST PIT LOGS (210909).GPJU.S.C.S.GRAPHICLOGMATERIAL DESCRIPTION OL GC GP 1.0 2.8 5.0 0 TO 1 FEET: SILTY CLAY ORGANIC SOIL; (OL); black; moist; soft. 1 TO 2.75 FEET: CLAYEY GRAVEL WITH SAND AND COBBLES; (GC); grayish brown to brown; moist to saturated; medium plasticity; loose to medium dense; approximately 50 percent subrounded gravels; approximately 30 percent fine to coarse grain sand; approximately 20 percent clayey fines. 2.75 TO 5 FEET: POORLY GRADED GRAVEL WITH SAND AND COBBLES; (GP); grayishbrown; moist to saturated; medium dense; approximately 60 percent subrounded gravels; approximately 40 percent fine to coarse grain sand. Bottom of test pit at 5.0 feet. NOTES GROUND ELEVATION LOGGED BY Noah J. Schaible, E.I. EXCAVATION METHOD CAT 305 Mini Tracked Excavator EXCAVATION CONTRACTOR Grade A Site Works GROUND WATER LEVELS: DATE STARTED 8/11/21 COMPLETED 8/11/21 AT TIME OF EXCAVATION 5.00 ft AFTER EXCAVATION --- AT END OF EXCAVATION ---DEPTH(ft)0.0 2.5 5.0 SAMPLE TYPENUMBERPAGE 1 OF 1 TEST PIT NUMBER TP8 PROJECT NUMBER 210909 CLIENT Easton Concrete, Inc. PROJECT LOCATION West Side Flats PROJECT NAME Soils Investigation GENERAL BH / TP / WELL - GINT STD US.GDT - 8/25/21 10:49 - G:\C&H\21\210909\REPORT DOCUMENTS\TEST PIT LOGS (210909).GPJU.S.C.S.GRAPHICLOGMATERIAL DESCRIPTION OL GC GP 1.5 2.5 5.0 0 TO 1.5 FEET: SILTY CLAY ORGANIC SOIL; (OL); black; moist; soft. 1.5 TO 2.5 FEET: CLAYEY GRAVEL WITH SAND AND COBBLES; (GC); grayish brown to brown; moist to saturated; medium plasticity; loose to medium dense; approximately 50percent subrounded gravels; approximately 30 percent fine to coarse grain sand; approximately 20 percent clayey fines. 2.5 TO 5 FEET: POORLY GRADED GRAVEL WITH SAND AND COBBLES; (GP); grayish brown; moist to saturated; medium dense; approximately 60 percent subrounded gravels;approximately 40 percent fine to coarse grain sand. Bottom of test pit at 5.0 feet. NOTES GROUND ELEVATION LOGGED BY Noah J. Schaible, E.I. EXCAVATION METHOD CAT 305 Mini Tracked Excavator EXCAVATION CONTRACTOR Grade A Site Works GROUND WATER LEVELS: DATE STARTED 8/11/21 COMPLETED 8/11/21 AT TIME OF EXCAVATION 5.00 ft AFTER EXCAVATION --- AT END OF EXCAVATION ---DEPTH(ft)0.0 2.5 5.0 SAMPLE TYPENUMBERPAGE 1 OF 1 TEST PIT NUMBER TP9 PROJECT NUMBER 210909 CLIENT Easton Concrete, Inc. PROJECT LOCATION West Side Flats PROJECT NAME Soils Investigation GENERAL BH / TP / WELL - GINT STD US.GDT - 8/25/21 10:49 - G:\C&H\21\210909\REPORT DOCUMENTS\TEST PIT LOGS (210909).GPJU.S.C.S.GRAPHICLOGMATERIAL DESCRIPTION OL CL GP 1.0 3.0 6.0 0 TO 1 FEET: SILTY CLAY ORGANIC SOIL; (OL); black; moist; soft. 1 TO 3 FEET: LEAN CLAY WITH SAND; (CL); yellowish brown to black; moist to saturated; medium plasticity; very soft to soft; approximately 15 percent fine to coarse grain sand; approximately 85 percent clayey fines. 3 TO 6 FEET: POORLY GRADED GRAVEL WITH SAND AND COBBLES; (GP); grayish brown; moist to saturated; medium dense; approximately 60 percent subrounded gravels; approximately 40 percent fine to coarse grain sand. Bottom of test pit at 6.0 feet. NOTES GROUND ELEVATION LOGGED BY Noah J. Schaible, E.I. EXCAVATION METHOD CAT 305 Mini Tracked Excavator EXCAVATION CONTRACTOR Grade A Site Works GROUND WATER LEVELS: DATE STARTED 8/11/21 COMPLETED 8/11/21 AT TIME OF EXCAVATION 5.00 ft AFTER EXCAVATION --- AT END OF EXCAVATION ---DEPTH(ft)0.0 2.5 5.0 SAMPLE TYPENUMBERPAGE 1 OF 1 TEST PIT NUMBER TP 10 PROJECT NUMBER 210909 CLIENT Easton Concrete, Inc. PROJECT LOCATION West Side Flats PROJECT NAME Soils Investigation GENERAL BH / TP / WELL - GINT STD US.GDT - 8/25/21 10:49 - G:\C&H\21\210909\REPORT DOCUMENTS\TEST PIT LOGS (210909).GPJU.S.C.S.GRAPHICLOGMATERIAL DESCRIPTION OL CL GC GP 1.0 2.7 4.3 5.5 0 TO 1 FEET: SILTY CLAY ORGANIC SOIL; (OL); black; moist; soft. 1 TO 2.67 FEET: LEAN CLAY WITH SAND; (CL); yellowish brown to black; moist to saturated; medium plasticity; very soft to soft; approximately 15 percent fine to coarse grain sand; approximately 85 percent clayey fines. 2.67 TO 4.33 FEET: CLAYEY GRAVEL WITH SAND AND COBBLES; (GC); grayish brownto brown; moist to saturated; medium plasticity; loose to medium dense; approximately 50 percent subrounded gravels; approximately 30 percent fine to coarse grain sand; approximately 20 percent clayey fines. 4.33 TO 5.5 FEET: POORLY GRADED GRAVEL WITH SAND AND COBBLES; (GP); grayish brown; moist to saturated; medium dense; approximately 60 percent subrounded gravels; approximately 40 percent fine to coarse grain sand. Bottom of test pit at 5.5 feet. NOTES GROUND ELEVATION LOGGED BY Noah J. Schaible, E.I. EXCAVATION METHOD CAT 305 Mini Tracked Excavator EXCAVATION CONTRACTOR Grade A Site Works GROUND WATER LEVELS: DATE STARTED 8/11/21 COMPLETED 8/11/21 AT TIME OF EXCAVATION 5.00 ft AFTER EXCAVATION --- AT END OF EXCAVATION ---DEPTH(ft)0.0 2.5 5.0 SAMPLE TYPENUMBERPAGE 1 OF 1 TEST PIT NUMBER TP 11 PROJECT NUMBER 210909 CLIENT Easton Concrete, Inc. PROJECT LOCATION West Side Flats PROJECT NAME Soils Investigation GENERAL BH / TP / WELL - GINT STD US.GDT - 8/25/21 10:49 - G:\C&H\21\210909\REPORT DOCUMENTS\TEST PIT LOGS (210909).GPJU.S.C.S.GRAPHICLOGMATERIAL DESCRIPTION OL CL CL GP 1.0 2.0 5.0 6.0 0 TO 1 FEET: SILTY CLAY ORGANIC SOIL; (OL); black; moist; soft. 1 TO 2 FEET: LEAN CLAY WITH SAND; (CL); black; moist to saturated; medium plasticity; very soft to soft; approximately 15 percent fine to coarse grain sand; approximately 85 percent clayey fines. 2 TO 5 FEET: LEAN CLAY WITH SAND; (CL); yellowish brown; moist to saturated; medium plasticity; very soft to soft; approximately 15 percent fine to coarse grain sand; approximately 85 percent clayey fines. 5 TO 6 FEET: POORLY GRADED GRAVEL WITH SAND AND COBBLES; (GP); grayish brown; moist to saturated; medium dense; approximately 60 percent subrounded gravels; approximately 40 percent fine to coarse grain sand. Bottom of test pit at 6.0 feet. NOTES GROUND ELEVATION LOGGED BY Noah J. Schaible, E.I. EXCAVATION METHOD CAT 305 Mini Tracked Excavator EXCAVATION CONTRACTOR Grade A Site Works GROUND WATER LEVELS: DATE STARTED 8/11/21 COMPLETED 8/11/21 AT TIME OF EXCAVATION 5.00 ft AFTER EXCAVATION --- AT END OF EXCAVATION ---DEPTH(ft)0.0 2.5 5.0 SAMPLE TYPENUMBERPAGE 1 OF 1 TEST PIT NUMBER TP 12 PROJECT NUMBER 210909 CLIENT Easton Concrete, Inc. PROJECT LOCATION West Side Flats PROJECT NAME Soils Investigation GENERAL BH / TP / WELL - GINT STD US.GDT - 8/25/21 10:49 - G:\C&H\21\210909\REPORT DOCUMENTS\TEST PIT LOGS (210909).GPJU.S.C.S.GRAPHICLOGMATERIAL DESCRIPTION OL CL GP 1.0 5.0 5.5 0 TO 1 FEET: SILTY CLAY ORGANIC SOIL; (OL); black; moist; soft. 1 TO 5 FEET: LEAN CLAY WITH SAND; (CL); yellowish brown to black; moist to saturated; medium plasticity; very soft to soft; approximately 15 percent fine to coarse grain sand; approximately 85 percent clayey fines. 5 TO 5.5 FEET: POORLY GRADED GRAVEL WITH SAND AND COBBLES; (GP); grayish brown; moist to saturated; medium dense; approximately 60 percent subrounded gravels; approximately 40 percent fine to coarse grain sand. Bottom of test pit at 5.5 feet. NOTES GROUND ELEVATION LOGGED BY Noah J. Schaible, E.I. EXCAVATION METHOD CAT 305 Mini Tracked Excavator EXCAVATION CONTRACTOR Grade A Site Works GROUND WATER LEVELS: DATE STARTED 8/11/21 COMPLETED 8/11/21 AT TIME OF EXCAVATION 3.00 ft AFTER EXCAVATION --- AT END OF EXCAVATION ---DEPTH(ft)0.0 2.5 5.0 SAMPLE TYPENUMBERPAGE 1 OF 1 TEST PIT NUMBER TP 13 PROJECT NUMBER 210909 CLIENT Easton Concrete, Inc. PROJECT LOCATION West Side Flats PROJECT NAME Soils Investigation GENERAL BH / TP / WELL - GINT STD US.GDT - 8/25/21 10:49 - G:\C&H\21\210909\REPORT DOCUMENTS\TEST PIT LOGS (210909).GPJU.S.C.S.GRAPHICLOGMATERIAL DESCRIPTION