Hello Arielle,
Attached is the CILWR agreement for Phases 1-3 of West Side Flats. The agreement not only identifies the CILWR fee for
phases 1-3 but also a rebate amount, to be paid at occupancy, for the instillation of the high efficiency water fixtures
throughout the entirety of the project. The CILWR fee of $98,208 needs to be paid prior to site plan approval for the
phases. Please let me know if the residential unit counts has changed so the agreement can be updated accordingly. Let
me know if you have any questions.
Regards,
City of Bozeman MT
Griffin Nielsen, PE| Engineering Department
D:406.582.2279
C:406.595.1598
gnielsen@bozeman.net
From: Karl A. Johnson <kajohnson@BOZEMAN.NET>
Sent: Monday, March 7, 2022 4:15 PM
To: Arielle Stoness <arielle@jdsarchitectsbozeman.com>
Cc: Jesse Sobrepena <jesse@jdsarchitectsbozeman.com>; Ross Knapper <rknapper@BOZEMAN.NET>; Griffin Nielsen
<GNielsen@BOZEMAN.NET>
Subject: RE: West Side Flats allon Street Phase 1-3
Arielle,
Griffin (CC’d on this email) can help you with the water rights. Griffin, let me know if you need anything from me on that.
Ross, can you please direct them to who they need to talk to for parkland?
Thanks,
Karl Johnson, E.I. | Engineering Department
City of Bozeman | 20 E. Olive St. | Bozeman, MT 59715
C: 406.451.1693
O: 406.582.2281
kajohnson@bozeman.net
From: Arielle Stoness <arielle@jdsarchitectsbozeman.com>
Sent: Friday, March 4, 2022 3:08 PM
To: Karl A. Johnson <kajohnson@BOZEMAN.NET>
2
Cc: Jesse Sobrepena <jesse@jdsarchitectsbozeman.com>
Subject: West Side Flats allon Street Phase 1-3
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the
sender and know the content is safe.
Karl,
Could you please let us know the amounts that need to be paid for the cash-in-lieu water rights for West Side Flats Fallon St Phase 2 &
3? What water and parkland cash-in-lieu payments are required for Phase 1?
Phase 1 application number 20224
Phase 2 & 3 application number 22026
Thank you,
Arielle Stoness
JDS Architects, Inc.
719 West Mendenhall
Bozeman, MT 59715
p 406-556-8080
c 406-600-4961
e-mail: arielle@jdsarchitectsbozeman.com
web: http://jdsarchitectsbozeman.com